[00:00:04]

ALL SORRY FOR THE DELAY.

WE'LL GO AHEAD AND GET STARTED.

UH, CAN SOMEONE ON THE WEBEX CONFIRM THEY CAN SEE THE SCREEN AND HEAR MY VOICE? SOMEONE ON THE WEBEX.

CHIME IN.

ALRIGHT, CAN SOMEONE ON THE WEBEX CONFIRM THEY CAN HEAR ME AND SEE THE SLOT, SEE THE WEBPAGE FOR TODAY? WE GOT YOU.

VERY GOOD.

ALL RIGHT.

ALRIGHT, WELL GOOD MORNING.

WELCOME TO WORKSHOP NUMBER FOUR.

UH, WE GOT A LOT TO COVER TODAY.

I GUESS JUST TO KICK IT OFF, UM, ERCOT, UH, DID KIND OF THE LONG HAUL ON GETTING A VERY LARGE, UH, PLANNING GUIDE REVISION OUT THE DOOR LAST WEEK.

I WILL ACCEPT RESPONSIBILITY FOR AS THE LATE NIGHT POSTINGS LAST NIGHT GOT OUT.

UM, OUR FOCUS IS DEFINITELY ON THE REVISION REQUESTS RATHER THAN ALL THE HOW'S AND WHAT'S BEHIND IT.

AND, UH, I, MY INTENTION WAS AND IS TO USUALLY POST MATERIALS AT LEAST A DAY BEFORE.

SO, YOU KNOW, AS WE CYCLE THROUGH THESE WORKSHOPS EVERY SEVEN OR 14 DAYS, DAY BEFORE, WE'LL BE THE MARK THAT WE'RE TRYING TO HIT.

AND I JUST WANTED TO APOLOGIZE FOR THAT.

SO JUST WANTED TO, UM, UPFRONT, THAT'S NOT GOOD FORM WHEN WE'RE IN A LARGE STAKEHOLDER COMMUNITY WITH ALL THE OTHER WORKSHOPS GOING ON.

SO DEFINITELY ERCOT IS NOT BLIND TO HOW MUCH YOU'RE HAVING TO CARRY, UH, IN PARTNERSHIP WITH US.

SO, UH,

[1. Antitrust Admonition]

SO LET ME GO AHEAD AND GET THE ANTITRUST ADMONITION ON THE SCREEN FOR A SECOND.

YOU WANNA TAKE A SECOND TO READ THAT.

AND THE WAY WE'RE LOOKING TO UNPACK AT THE WORKSHOP, I EMAILED THIS OUT TO TAC AND THE LLWG, WAS THAT WE'RE GONNA GO THROUGH A KIND OF A 10 MINUTE RECAP OF WHY WE'RE HERE, WHAT'S THE SCOPE, WHAT'S OUTTA SCOPE, AND THEN WE'RE GONNA GO THROUGH THE STAKEHOLDER FEEDBACK IN FAQ, UM, IN A DRY RUN YESTERDAY.

THIS WILL TAKE MORE LIKE 40 MINUTES WITHOUT QUESTIONS.

WHAT WE REALLY WANT TO DO IS TO BE ABLE TO SAY, WE'VE HEARD THE QUESTIONS.

HERE'S WHAT WE THINK ARE SOME BASIC RESPONSES, LIKE WE HAVE 70 SLIDES TO HIT TODAY.

WE JUST WANTED TO PAUSE AND KIND OF WALK THROUGH THREE SLIDES THAT ARE KIND OF FUNDAMENTAL PRINCIPLES IN ALIGNMENT WITH THE DIRECTION WE'RE HEADED.

NOT THAT THAT'S THE END GAME, BUT WHY WE'RE HEADED WHERE WE ARE.

SO THOSE FAQ SLIDES WILL BE SOMETHING WE HIT.

AND THEN ALSO THE RESULTS OF THE SURVEY.

SO WE HAD THROWN OUT THE SURVEY AND I THINK 80 PLUS OF Y'ALL RESPONDED BACK.

UM, A LOT OF WHAT ERCOT PROPOSED LAST TIME HAD FILL IN THE BLANKS ON DATES.

YOU KNOW, SO WHAT DATES IS THE MARKET THINKING ON CUTOFFS AND TIMELINES, OR WHAT KIND OF COGEN ARRANGEMENTS DO WE WANT? SO WE'LL START TO WALK THROUGH THOSE AS PART OF THE FAQ.

BUT MY INTENT IS TO NOT HAVE A QUEUE AND MUSCLE THROUGH THAT BECAUSE IF WE STOP FOR QUESTIONS IN THE FIRST 20 SLIDES, WE'RE NOT GONNA MAKE IT THROUGH THE REST OF THE MATERIALS.

AND WE'RE WELCOME TO AT THE END OF THE AGENDA, COME BACK AROUND TO THIS AND GO TOP TO BOTTOM AGAIN.

BUT, UM, MY, MY HOPE IS TO SPEND MAYBE 45 MINUTES SETTING THE STAGE FOR, FOR TODAY.

AND THEN WE'RE GONNA HAVE JEFF WALK THROUGH THE BATCH ZERO.

UH, THE IDEA IS THERE'S PRESENTATION MATERIALS.

UH, YOU'LL NOTICE IF YOU HAPPEN TO HAVE HAD TIME TO OPEN THE PRESENTATION, IT'S UNIQUE.

WHAT WE'VE DONE IS FROM WHAT WE COMMUNICATED THE LAST WORKSHOP TO WHAT'S CHANGED FOR NOW, WE'VE ACTUALLY INTRODUCED SOME RED LINES, LIKE WHAT'S BEEN INTRODUCED CONCEPTUALLY, AND THEN THAT HAS A FOOTER ON THAT SLIDE THAT POINTS OVER TO THE BIGGER LANGUAGE THAT SAYS THIS IS SECTION XXX.

SO IT'S THE HOW AND WHY WE'RE DOING IT.

CONTEXT THAT POINTS YOU OVER TO THE LANGUAGE.

AND WE'LL JUST HAVE TO SEE HOW JEFF WANTS TO NAVIGATE THE IDEA OF SHOWING SLIDES AND THEN ALTERNATING IN AND OUTTA THE REVISION REQUESTS.

I KNOW THIS WILL TAKE US TO LUNCH AND MAYBE A LITTLE AFTER LUNCH.

AND THEN AT THAT TIME, WE'VE HAD FOUR SETS OF MARKET COMMENTS COME IN.

SO WE'LL GIVE EACH, UH, MARKET COMMENTER.

I'VE EMAILED THEM.

WE HAVE AN ORDER.

UH, THEY'LL EACH GET 15 MINUTES TO UNPACK THEIR CONCERNS OR QUESTIONS.

SO THAT'S THE FORMAL, UH, FEEDBACK FROM THEM.

AND THEN WE WILL BE HOPING TO, AND I THINK WE'LL HAVE TIME FOR DISCUSSION OF THE, UH, BRING YOUR OWN GEN AND INITIAL CONTROLLABLE LOAD RESOURCE CONCEPT.

SO I KNOW THAT'S A, UH, TOPIC THAT PEOPLE WANT ERCOT TO START HELPING WITH AND TO GET SOMETHING OUT THERE.

AND THE IDEA IS WE WILL HAVE ANOTHER TIME SLOT AT LLWG ON FRIDAY.

THAT'S ONLY AN HOUR.

SO IT'S NOT THAT WE'RE GONNA SAY HAVE A WHOLE NOTHER WORKSHOP, BUT IT WILL GIVE PEOPLE, UH, SOME TIME AND SPACE FOR QUESTIONS THERE TOO.

AND I'M ESTIMATING WE END AT FOUR 30.

I THINK IT'S A REASONABLE TIME TO CUT OFF.

UM, AND THEN BE READY FOR OUR NEXT WORKSHOP AFTER THAT, UH, TUESDAY AFTER NEXT.

SO WITH THAT, LEMME GO AHEAD AND GET US GOING ON THE SLIDES.

OH, OH, ALSO, WE DON'T HAVE COREY HERE RUNNING.

SO JANICE HAS KINDLY STEPPED IN TO RUN THE QUEUE.

GOD BLESS HER.

SHE IS GOING TO HELP NAVIGATE THE QUESTIONS AS THEY COME IN.

UH, WE ALSO RECOGNIZE IF YOU HAVE A QUESTION TO GET IN THE QUEUE, SAY PUT ME IN THE QUEUE OR A QUESTION.

BUT IF YOU'RE JUST MAKING QUESTIONS OR COMMENTS, EXT, WHATEVER THAT WORD EX

[00:05:01]

EX, IF YOU'RE JUST SAYING EXT, WHAT IS THE WORD? EXTEMPORANEOUSLY? EXTEMPORANEOUSLY.

WE'RE NOT GONNA PUT YOU IN THE QUEUE.

I SHOULDN'T EVEN TRY THAT WORD.

ESPECIALLY ON A DAY.

LIKE, YEAH, I'VE HAD ENOUGH ISSUES GETTING THE SLIDES POSTED ON TIME.

UM, ENGINEER IN ENGLISH.

OKAY.

ALRIGHT, HERE WE GO.

BY THE WAY, MY NAME'S MATT MARINAS, IF YOU'RE KEEPING TRACK OF WHO THIS GOOFBALL IS.

ALRIGHT.

OKAY.

IF I HAVE NOTHING ELSE, I HAVE HUMOR.

OKIE DOKE.

ALRIGHT, THANK YOU FOR YOUR PATIENCE.

[2. Timeline and governance recap (10 mins)]

OKAY, WE JUST TALKED ABOUT ALL THIS.

THIS IS HOW WE'RE GONNA ROLL.

OKAY, JUST A FEW SLIDES.

YOU'VE SEEN THESE BEFORE.

THIS IS THE MARCH TO THE FINISH LINE, WHICH IS THE JUNE BOARD.

UH, WE HAVE THESE, UH, WE'RE ON WORKSHOP NUMBER FOUR OF SEVEN WORKSHOPS AFTER SEVEN WORKSHOPS.

THE IDEA IS TO TRANSITION TO AS NEEDED PRS AND ROS MEETINGS.

UH, SANDEEP BOKAR IS ALREADY REACHING OUT TO SEE WHETHER OR NOT TO PUT ONE OR TWO SPECIAL ROS MEETINGS IN MID TO LATE APRIL.

UH, THAT IS TO THEN SET THE STAGE FOR GETTING TO TECH, WHICH HAS EXTRA MEETINGS POSSIBLY IN THE TWO DAY MEETING HERE ON THE CALENDAR TO GET TO THE BOARD.

SO IT IS A, UM, THERE'S A LOT MORE WORK COMING.

UH, WHAT WE HAVE ADDED HERE IS A TARGET, WHICH IS FOR ERCOT TO FILE THE NECESSARY REVISION REQUEST TO CON, UM, TO SUPPORT THE CONTROLLABLE LOAD RESOURCE AND BRING YOUR OWN GEN.

UH, SO WHAT THAT LOOKS LIKE, AND WE'LL TALK MORE ABOUT THAT IN THE MEETING, IS THAT TODAY'S MEETING IS THAT INITIAL VERY HIGH LEVEL.

HERE'S THE TYPES OF CONFIGURATIONS WE'RE THINKING ABOUT.

WE'LL HAVE MORE DETAILS AT THE 24TH WORKSHOP, AND THEN HOPEFULLY BY MARCH 30TH WE HAVE DRAFT LANGUAGE OR CONCEPTS THAT WE'LL RELEASE IN AN NPR AND OR OPERATING GUIDE REVISION AND OR OUR PLANNING GUIDE REVISION TO THEN HIT THAT NEXT WORKSHOP SEVEN.

UH, AND AGAIN, IF WE NEED AN EXTRA WORKSHOP, WE CAN, OR IF WE JUST ROLL RIGHT INTO THE ROS UM, PIECE.

SO AGAIN, THERE'S MORE COMING ON THIS.

SO IN TERMS OF HOW DO WE GET FEEDBACK, UM, I, I'LL JUST PAUSE.

WHAT I THINK IS GONNA HELP IS TO FORMALLY FILE COMMENTS, UH, ESPECIALLY TO THE PICKER IN THIS CASE FOR THE BATCH ZERO PROCESS.

UH, THE FORMAL FILING IS NOTICED TO EVERYONE AT THE SAME TIME.

SO IRRESPECTIVE OF WHAT THE, UM, HOST DOES, EVERYTHING IS ON THE RECORD WITH THE COMPANY.

YOUR PRESENTATION COULD BE CLIP TO IT.

AND I'LL ENSURE THAT EVERY MEETING WE HAVE IS THAT THOSE ARE THE FIRST IN LINE TO WALK THROUGH THEIR COMMENT.

SO YOU'LL HAVE A TIME AND SPACE TO SHARE YOUR COMMENTS.

UM, AGAIN, IT'S NOT JUST ABOUT SAYING THAT'S WRONG, IT'S ABOUT TELL US WHAT THE RIGHT ANSWER IS.

SO AS ERCOT, WE'D REALLY LIKE TO KNOW, UM, WHAT THE COUNTER PROPOSAL IS TO GET US INTO A BETTER SPOT, UM, FOR ADOPTION.

UH, AGAIN, THE PIGGER UH, THAT PLANNING GUIDE REVISION GOES FROM THIS LARGE LOAD WORKSHOP INTO ROS THAT WE TALKED ABOUT.

SO THAT'S THE LARGE REVISION REQUEST THAT GOES TO TACK ON THE BOARD AND THE PUC.

AND IF YOU WANT TO FILL OUT A FORM FOR THE PIGGER, IT'S CLICKING HERE AND THAT'S HOW YOU CAN GET A BLANK FORM.

AND FOR THE NPR IS THERE.

AND THEN THIS IS THE SAME SLIDE AS LAST TIME.

JUST A REMINDER THAT THE, UH, 58 40 LOAD FORECASTING RULE FOR LARGE LOADS IS, UM, HAS BEEN ADOPTED AND IN EFFECT.

AND THAT 5 8 4 8 1 IS NOT YET ADOPTED AND IS IN FLIGHT.

AND, UM, THAT IS THE FRAMEWORK THAT WE'VE KIND OF LIFTED INTO THE CURRENT PROPOSAL.

UM, ASSUMING THAT THOSE ARE HOW THESE MARRY TOGETHER FOR BATCH ZERO, WHETHER THAT'S APPROPRIATE OR NOT, THAT'S UP FOR DEBATE LATER TODAY.

AND IN TERMS OF REMINDER OF THE SCOPE, SO EVERYTHING ABOUT THAT JUNE 1ST MEETING IS BATCH ZERO.

EVERYTHING ELSE AFTER THAT IS A STRETCH GOAL THAT WE ALL WANNA PARTNER WITH AND TRY TO GET TO, WHICH IS THE CLR AND BRING YOUR OWN GEN.

UH, AGAIN, WE USE THE SURVEY, OTHER TOOLS TO TRY AND GET THIS, UM, FEEDBACK LOOP TIGHT AND RAPID AND THE, BUT THE LONG TERM BATCH PROCESS OF WHAT DO WE DO AFTER FIRST BATCH, THAT'S REALLY, WE'RE GOING TO SET THAT TO THE SIDE AS QUICKLY AS WE CAN IN THE CONTEXT OF THESE MEETINGS.

SO WE CAN HAVE A SIDE NOTES OF THINGS TO REMEMBER TO COME BACK TO, BUT IT'S NOT TO SOLVE TODAY.

[3. Stakeholder Survey Feedback and FAQ (20 mins)]

OKAY.

SO IN TERMS OF THE FAQS, THIS IS A LOT OF WORDS, BUT AGAIN, SINCE WE RELEASED IT LAST NIGHT, I'M JUST GONNA KIND OF SLOW DOWN AND WALK THROUGH 'EM.

AND JEFF, IF YOU WANT TO CHIME IN ON ANY OF THEM FOR CONTEXT, YOU'RE WELCOME TO.

SO WE THEME THIS INTO THE BATCH ZERO PROCESS, TIMELINE AND DECISION POINTS IS KIND OF THE TOPIC.

UH, THESE ARE THE QUESTIONS THAT WE'VE HEARD KIND OF ECHOING THROUGH EITHER IN THE SURVEY OR IN THE WORKSHOPS.

IS IT POSSIBLE TO INCLUDE A SECOND POST REFINEMENT DECISION POINT FOR MARKET PARTICIPANTS TO OPT OUT? AND THE ANSWER IS NO.

ERCOT IS DESIGNED.

BATCH ZERO IS A ONE BINDING COMMITMENT.

YOU KNOW, WE RUN THE PROCESS AND THEN THERE'S THAT 30 DAY WINDOW FOR THAT COMMITMENT.

THE REFINEMENT, UM, DOES NOT CHANGE THE COMMITTED RAMP AND IT'S NOT INTENDED TO INCREASE COST.

YOU WOULDN'T HAVE TO SECURITIZE ADDITIONAL MEGAWATTS 'CAUSE THERE ARE NO ADDITIONAL MEGAWATTS.

IT ONLY FINALIZES

[00:10:01]

A TRANSMISSION SOLUTION.

UH, AND THEN A SECOND OPT OUT TO DO THAT REINTRODUCES THE LOOP, UH, STUDY RISK THAT WE'RE ALREADY IN.

SO JUST A REMINDER OF THAT ONE.

NEXT, WHAT WILL THE BATCH ZERO STUDY ALLOCATIONS, UH, BE FINALIZED AND COMMUNICATED? ALLOCATION TIMING IS TIED TO THE COMPLETION OF THE BATCH ZERO STUDY PHASE UNDER THE DRAFT.

FIGURE 1 45 TIMELINE ALLOCATION RESULTS WILL BE ISSUED IN THE JANUARY 20, 27.

UH, AND FINAL DATES WILL BE CONFIRMED FINAL IN THE FINALIZATION OF P 1 45.

SO AS PROPOSED AS JANUARY, 2027.

BUT WHATEVER'S ADOPTED WILL BE THAT DATE.

CAN THE 30 DAY COMMITMENT WINDOW BE EXTENDED? UH, ERCOT INTENDS TO MAINTAIN THE 30 DAY COMMITMENT WINDOW CONSISTENT WITH THE DRAFT, UH, PC PROJECT.

UM, 5 8 4 8 1.

THE FULL BATCH ZERO SCHEDULE, INCLUDING THE COMMITMENT DEADLINE WILL BE PUBLISHED IN ADVANCE.

AND THEN WHAT IS THE DATE FOR MEETING COMMITMENT CRITERIA? THE DATE FOR MEETING CRITERIA IS PROPOSED IS MARCH 1ST, 2027 IN PICKER 1 45.

AND WHAT GETS TO THE BATCH ZERO PLANNING? UM, BATCH ZERO PLANNING INTEGRATION.

HOW CAN BATCH ONE PROCEED BEFORE BATCH ZERO YEAR SIX? TRANSMISSION SOLUTIONS ARE FULLY IDENTIFIED.

THIS IS THAT IDEA.

WE'RE ONLY STUDYING YEARS ONE THROUGH FIVE.

WHAT ABOUT THE YEAR SIX? SO UNDER A SIX MONTH CADEN, EACH BATCH PROCESS WOULD BE ACTIONABLE RESULTS FOR YEAR ONE THROUGH FIVE.

WHILE THE YEAR SIX TRANSMISSION SOLUTIONS MAY CONTINUE THROUGH THE R-T-P-R-P-G PROCESS, THAT REFLECTS THE TRADE OFF BETWEEN SPEED AND THE FULL TRANSMISSION VETTING.

IF WE WANTED TO GET ALL THE YEAR SIX, ALL THE DETAILS OF THOSE LONG TERM PROJECTS, WE'D BE OUTTA THAT WINDOW.

SO THAT'S THE GIVE AND TAKE OF THIS DESIGN.

NEXT SLIDE.

UH, BATCH ZERO PLANNING AND INTEGRATION.

HOW ARE THE IN-FLIGHT RPG PROJECTS INCORPORATED INTO BATCH ZERO? PROJECTS THAT HAVE PROGRESSED THROUGH RPG AND RECEIVED ENDORSEMENT AT THE START OF BATCH ZERO WILL BE TREATED CONSISTENT WITH THE ESTABLISHED PLANNING PRACTICES AND BE INCORPORATED INTO THE BATCH ZERO STUDY.

HOW DOES BATCH ZERO INTERACT WITH THE 2026 AND 2027 RTP BASED ON THE CURRENT SEQUENCING, BATCH ZERO WILL NOT AFFECT THE 2026 RTP BECAUSE COMMITMENT OCCURS AFTER THE 2026 RTP MODELING CYCLE IS COMPLETE.

UH, LOADS THAT MEET COMMITMENT MILESTONES IN MARCH, 2027 MAY BE INCORPORATED INTO THE 2027 RTP AND THE FINAL TIMING ALIGNS DEPENDING ON THE FINALIZATION OF PICKER 1 45 AND PUBLICATION OF BATCH ZERO SCHEDULE.

OKAY, IN TERMS OF TRANSMISSION UPGRADES, HOW ARE MULTI-YEAR YEAR SIX UPGRADES, UH, AND BASE CASES HANDLED? ERCOT RECOGNIZES THE YEAR SIX SOLUTIONS MAY INVOLVE COMPLEX MULTI-YEAR TRANSMISSION UPGRADES.

BATCH BATCH ZERO ESTABLISHES A COMMITTED LOAD BASELINE AND PROVIDES EARLIER CLARITY ON REQUIRED IMPROVEMENTS.

LONG DURATION UPGRADES WILL CONTINUE TO PROCEED THROUGH ESTABLISHED TRANSMISSION PLANNING PROCESSES, INCLUDING RTP AND RPG PATHWAYS.

UH, NEXT QUESTION.

IF NO RELIABLE TRANSMISSION SOLUTION EXISTS WITHIN THE STUDY HORIZON, HOW WILL THE ALLOCATED MEGAWATTS BE HANDLED? UH, WITHIN YEARS ONE THROUGH FIVE, ERCOT WILL ALLOCATE THE MEGAWATTS THAT CAN BE RELIABLY SERVED BASED ON EXISTING SYSTEM CAPABILITY.

PROJECTS MAY RECEIVE PARTIAL ALLOCATIONS DURING THIS PERIOD.

IF CONSTRAINTS EXIST BY YEAR SIX, THE ASSUMPTIONS THAT THE RTP PROCESS WILL IDENTIFY UPGRADES NECESSARY TO SERVE FULL COMMITTED LOAD ACCORDINGLY.

YEAR SIX REFLECTS FULL A HUNDRED PERCENT SERVICE OF THE COMMITTED MEGAWATTS.

AND THE LAST ONE OF THESE, UH, ALLOCATION OUTCOMES AND RAMP SCHEDULES.

CAN ERCOT CHANGE THE MEGAWATT ALLOCATIONS AFTER COMMITMENT? NO.

FOR BATCH ZERO AFTER THE COMMITMENT POINT, THE MEGAWATT ALLOCATION BY YEAR IS LOCKED.

THE REFINEMENT PHASE IS INTENDED ONLY TO FINALIZE THE TRANSMISSION PLAN, NOT REDUCE MEGAWATTS OR DELAYED DELIVERY YEARS FOR COMMITTED MEGAWATTS.

IF A PROJECT DROPS OUT, ARE THE MEGAWATTS REALLOCATED WITHIN THE SAME BATCH? WE'VE PROBABLY HAD THIS QUESTION 20 TIMES.

NO.

ERCOT IS NOT PLANNING TO REALLOCATE THE MEGAWATTS WITHIN THE BATCH ZERO AFTER COMMITMENT BECAUSE IT CREATES COMPLEXITY AND REOPENS TUDY CASES.

ADDITIONAL MEGAWATTS WOULD GENERALLY BE ADDRESSED IN THE SUBSEQUENT BATCHES MAINTAINING THE PROCESS OF STABILITY AND SCHEDULE CERTAINTY.

SO THE IDEA IS YOU KEEP ROLLING ON THIS CADENCE AS QUICKLY AS POSSIBLE TO GET THAT EXCESS CAPACITY.

UH, FINANCIAL SECURITY AND COST RESPONSIBILITY.

OUR FINANCIAL OBLIGATIONS, INCLUDING KAYAK AND SECURITY, LOCKED A COMMITMENT BASED ON THE DRAFT PF UH, PFP FOR THE PC PROJECT 5 8 4 81.

ERCOT IS PROPOSING THAT THE FINANCIAL OBLIGATIONS ARE ESTABLISHED AND LOCKED AT THE COMMITMENT POINT.

THE REFINEMENT PHASE MAY ADJUST TRANSMISSION SOLUTIONS, BUT IT IS NOT INTENDED TO REPRICE COMMITMENTS OR INTRODUCE POST COMMITMENT TRUE UP COSTS.

THIS HAS COME UP QUITE A BIT TOO.

THE PROCESS IS DESIGNED TO PROVIDE COST CERTAINTY AND AVOID REOPENING FINANCIAL OBLIGATIONS AND SUBSEQUENT PLANNING STEPS.

OKAY, SECOND TO LAST.

HOW WILL ADDITIONAL GENERATION BE MODELED IN BATCH ZERO? ERCOT WILL APPLY THE METHODOLOGY ESTABLISHED IN PICKER 1 27 WHEN MODELING ADDITIONAL GENERATION IN BATCH ZERO.

UH, THE MODELING APPROACH AND ASSOCIATED ASSUMPTIONS WILL BE DOCUMENTED

[00:15:01]

IN THE PUBLISHED CASE ASSUMPTIONS TO ENSURE TRANSPARENCY AND CONSISTENCY.

UH, DOES BATCH ZERO INCLUDE A LOW SOLAR SCENARIO? THE BATCH ZERO DOES INCLUDE A NULL SOLAR SCENARIO INTENDED TO REFLECT STRESSED CONDITIONS.

OKAY, SO AGAIN, YOU MAY NOT AGREE WITH EVERYTHING WE JUST SAID, BUT THIS IS SETTING THE TRAJECTORY FOR WHAT IS BEING PROPOSED.

AND ALL OF THAT IS, UM, UP FOR DEBATE, BUT THOSE ARE, WE HOPE ARE KIND OF CHEAT SHEETS TO GO BACK TO.

AND WHY DID THEY SAY THAT? UM, WHAT'S THE APPROACH? SO NOW WE'RE GONNA GET BACK, UM, AND PLAY BACK TO YOU WHAT YOU HEARD.

LET ME FLIP DOWN REAL QUICK HERE.

OKAY, SO THE SURVEY, UH, FOR THOSE OF YOU THAT COMPLETED, YOU'LL NOTICE IT WAS 20 QUESTIONS IN TERMS OF, UM, THE THINGS THAT WE HAD THE COMEBACK FEED ON WHERE IT WAS ELIGIBILITY AND SCREENING HAD TWO MULTIPLE CHOICES, THREE FREE RESPONSES.

THE DESIGN OF BATCH ZERO HAD MULTIPLE CHOICES.

COMMITMENT, REALLOCATION CONFIDENTIALITY AND TRANSPARENCY.

THAT WAS AN INTERESTING ONE.

JUST ONE MULTIPLE CHOICE QUESTION.

AND THEN CLR AND BYOG.

SO, UM, GOSH, I'LL TRY TO READ THIS QUICKLY, BUT EACH ONE OF THESE HAS A SLIDE.

SO AGAIN, I DON'T WANT TO GET LOST IN THIS, BUT I THOUGHT IT WAS FAIR FOR EVERYONE TO KIND OF SEE AND SOAK IN WHAT WE'RE SAYING AND NOT JUST BORE YOU TO DEATH.

SO, UH, NUMBER ONE.

QUESTION NUMBER ONE WAS RELATED TO DEVELOPMENT ACTIVITY CUTOFF.

UH, STAKEHOLDERS SHOWED A PREFERENCE FOR DECEMBER 27 AS THE LATEST IN-SERVICE DATE TO DEMONSTRATE DEVELOPMENT ACTIVITY.

SO WE'LL SHOW YOU NUMBERS IN A MINUTE, BUT THAT WAS THE SWEET SPOT ON.

UM, STAKEHOLDER PREFERENCE.

HOW ABOUT THE PARTIALLY COMPLETE STUDY DATE CUTOFF? UH, STAKEHOLDERS SHOW A CLEAR PREFERENCE FOR A JUNE, 2026 CUTOFF DATE, AND THAT'S TO DETERMINE BATCH ZERO ELIGIBILITY FOR PARTIALLY COMPLETE STUDIES.

UH, HOW ABOUT THE INTERMEDIATE AGREEMENT INTERCONNECTION AGREEMENT CRITERIA? CUTOFFS, UH, STAKEHOLDERS SHOWED STRONGEST PREFERENCE FOR JULY, 2026, DEADLINE TO MEET AGREEMENT CRITERIA FOR BATCH ZERO INCLUSION DEVELOPMENT ACTIVITY.

AND THAT WAS DIFFERENT TYPES OF DEVELOPMENT ACTIVITY.

STAKEHOLDERS STRONGLY FAVOR SITE PREPARATION AND CONSTRUCTION AS PROOF OF DEVELOPMENT ACTIVITY WITH ADDITIONAL EMPHASIS ON CAPITAL COMMITMENT, SITE CONTROL AND INTERCONNECTION READINESS.

AND THEN SITE PREP AND CONSTRUCTION STAKEHOLDERS STRONGLY FAVOR DEFINING SITE PREP AND CONSTRUCTION THROUGH SITE CONTROL AND POSTED FINANCIAL SECURITY, ALSO SUPPORTING STAGED ENGINEERING PERMITTING AND EQUIPMENT DEPOSITS.

NOW IN TERMS OF THE DESIGN OF THE BATCH ZERO, THE FUNDAMENTAL PRINCIPLES STAKEHOLDERS SHOW SUPPORT OF ERCOT BATCH ZERO PRINCIPLES.

UH, THOUGH IT'S RELATIVELY CLOSE SPLIT INDICATES MEANINGFUL STAKEHOLDER SENSITIVITY AS TO HOW THE FRAMEWORK IS IMPLEMENTED.

WHEN I SHOW YOU THE DATA, YOU'LL SEE WHAT THOSE WORDS KIND OF MEAN.

UH, THE REFINEMENT STUDY APPROACH.

THIS IS THE IDEA THOSE MONTHS AFTER THE COMMITMENT.

UH, STAKEHOLDERS BROADLY SUPPORT THE PROPOSED REFINEMENT STUDY APPROACH, THOUGH MINORITY SIGNALS, UH, SENSITIVITY TO THE IMPLEMENTATION DETAILS AROUND THAT.

UH, TRANSMISSION UPGRADE AND PROCESS DESIGN STAKEHOLDERS OVERWHELMINGLY FAVOR A SHORTER SIX MONTH BATCH STUDY TIMELINE SIGNALING A STRONG PREFERENCE FOR SPEED AND PROCESS EFFICIENCY OVER LONG STUDY DURATION.

UH, THERE IS STILL A 12 MONTH CAMP, AND WE'LL TALK ABOUT THAT IN A MINUTE.

UH, AND THEN ALSO A FINAL COMMITMENT PERIOD.

STAKEHOLDERS BROADLY FAVOR PRESERVING FLEXIBILITY AND LOAD RAMP AND FINANCIAL COMMITMENTS AS COST ESTIMATES EVOLVE WITH LIMITED SUPPORT, UH, FOR RIGID OR FULLY REOPENED ALLOCATION APPROACHES.

AND THEN PUBLICLY DISCLOSED INFORMATION, UH, THAT'S COME UP A FEW TIMES HERE, WHICH IS, WHY DON'T WE JUST POST ALL THIS STUFF PUBLICLY.

SO THIS IS TRYING TO FIND, WELL, WHAT DO WE WANNA PUBLISH PUBLICLY? SO STAKEHOLDERS STRONGLY SUPPORT PROTECTING CUSTOMER IDENTITY AND COMMERCIALLY SENSITIVE PROJECT DATA, UH, SIGNALING A PREFERENCE FOR TRANSPARENCY AT THE SYSTEM LEVEL RATHER THAN BY COMPANY.

SO I'LL JUST MARCH THROUGH THIS B ONE THROUGH E ONE SLIDES.

UH, SO HERE IS THAT, UM, IN TERMS OF THE DEVELOPMENT ACTIVITY CUTOFF DATE, THIS IS HOW THE DATES CAME OUT TO DECEMBER, 2027.

UH, YOU CAN SEE SOME WENT ALL THE WAY OUT MUCH FURTHER INTO THE FUTURE.

UH, SOME WENT BACK INTO MAY, 2026.

I'LL LEAVE IT AT THAT.

YOU CAN TRY TO REMEMBER WHAT YOU PUT IN THE BLANK.

.

ALL RIGHT.

AND THEN THIS ONE'S A LITTLE MORE TIED.

THIS ELIGIBILITY AND SCREENING, PARTIALLY COMPLETE STUDY CUTOFF DATES.

UH, AGAIN, MOST FAVORED THE JUNE, 2026.

YOU KNOW, YOU CAN SEE SOME INTO THE JULY AND THEN MAY, BUT MOST OF THEM ARE IN THIS, UH, THOSE THREE MONTH PERIODS.

I HAVE A COUPLE WAY OUT HERE.

AND THEN ELIGIBILITY AND SCREENING.

THE IDEA OF THE INTERMEDIATE OR INTERCONNECTION AGREEMENT CRITERIA, CUTOFF DATES, UH, THE LION'S SHARE IS HONING IN ON THE MAY, JUNE, JULY WITH JULY, 2026 BEING THE MOST FAVORED VIEW.

UM, OH, AND BEFORE I GO TOO FAR, MY APOLOGIES.

UH, WE DID TWEAK THE KEY ON HERE, UM, FROM

[00:20:01]

THE PREVIOUS ONE, WHICH IS WE TEASE OUT THE GENERATORS SEPARATELY.

THEY'RE MIXED IN WITH THE OTHERS BEFORE.

SO IT'S WIRES, COMPANIES, LARGE LOADS, OTHERS, AND THEN GENERATORS.

ELIGIBILITY AND SCREENING.

IN TERMS OF DEVELOPMENT ACTIVITY, WHAT INFORMATION SHOULD BE REQUIRED FOR PROJECTS TO DEMONSTRATE DEVELOPMENT ACTIVITY? SITE PREPARATION IS THE MIDDLE ONE.

HERE IS THE IN CONSTRUCTION.

UH, THE NEXT MOST WAS THE, THIS OTHER, AND WE'LL TALK OVER HERE TO THE RIGHT.

ALSO, WHETHER OR NOT HAVING PURCHASED ALL THE NECESSARILY CUSTOMER OWNED HIGH VOLTAGE TRANSFORMERS AND CIRCUIT BREAKERS WITH DELIVERY BY PROJECT IN SERVICE STATE.

THAT'S THE LONG LEAD TIME ON CRITICAL EQUIPMENT THAT WE'VE TALKED ABOUT HERE BEFORE.

AND INCLUSION IN A QUARTERLY STABILITY ASSESSMENT.

SO IN TERMS OF THE OTHER CRITERIA, SUGGESTED, UH, EVIDENCE OF FINANCIAL COMMITMENT, UM, IS OTHER, AGAIN, WHAT'S IN THIS 49% BECAUSE OTHER IS JUST A WORD.

FINANCIAL COMMITMENT WAS A LEADING PIECE OF IT.

UH, EQUIPMENT ORDERS PLACED SECURITY PROVIDED, UH, VERSUS FULL EQUIPMENT PURCHASE.

UH, DEMONSTRATING SITE CONTROL, ZONING APPROVALS, PERMITS, UH, ENGINEERING AND ERROR, CONNECTION READINESS, MILESTONES, EXECUTE AGREEMENTS, MODELING DATA SUBMITTED.

AND I'M NOT SURE WHAT EPC CONTRACTS ARE, BUT EPC CONTRACTS AND COMMERCIAL FIRMNESS INDICATORS SUCH AS POWER PURCHASE AGREEMENT.

CAN ANYONE TELL ME WHAT AN EPC IS? ENGINEERING PROCUREMENT CONSTRUCTION CONTRACT.

THANK YOU.

ALRIGHT.

ALRIGHT.

THE NEXT ONE WAS SITE PREP AND CONSTRUCTION.

UM, AGAIN, MAJORITY WERE FAVORING THE SITE CONTROL, EITHER OWNED OR LONG, LONG TERM LEASED LAND.

UH, AND THEN FINANCIAL SECURITY.

AND THEN THEY EXECUTED INTERCONNECTION AGREEMENT BREAKER, MAJOR ELECTRICAL EQUIPMENT, DEPOSITS, ENGINEERING, THE DESIGN, HIGH VOLTAGE TRANSFORMER.

SO THERE'S THE DISTRIBUTION.

UH, SO CAN, TO SUMMARIZE, THIS ONE'S HARD 'CAUSE THERE'S A LOT GOING ON, BUT STRONG MAJORITY OF RESPONDENTS WERE IN FAVOR OF DEFINING SITE PREP AND CONSTRUCTION TO INCLUDE POSTED FINANCIAL SECURITY DEPOSITS AND DEMONSTRATED SITE CONTROL WITH SUPPORT FOR SOME OF THESE OTHER AREAS, INCLUDING BREAKER, MAJOR ELECTRICAL EQUIPMENT, INTERCONNECTION AGREEMENTS, AND HIGH VOLTAGE TRANSFORMERS.

ALRIGHT, AND THEN THE NEXT ONE, C ONE FUNDAMENTAL PRINCIPLES.

DO YOU AGREE WITH ERCOT FUNDAMENTAL PRINCIPLES FOR BATCH ZERO? AND IT'S KIND OF A 50 50 SPLIT? YES AND NO.

SO IT'S A MAJORITY RESPONDENTS AGREE WITH ERCOT.

I WOULD SAY A NARROW MAJORITY AGREE WITH THE PRINCIPLES OF BATCH ZERO.

UH, MIXED STAKEHOLDER ALIGNMENT, TSPS AND GENERATORS STAKEHOLDERS SHOW CLEAR MAJORITY SUPPORT FOR PROPOSED FUNDAMENTAL PRINCIPLES.

LARGE LOW CUSTOMERS ARE AMBIVALENT WHILE OTHERS ARE OPPOSED.

UH, REASONS FOR OPPOSITION CONCERN OVER RETROACTIVE APPLICATION OF PROPOSED 5 8 4 8 1 RULES AND POTENTIAL INVALIDATION OF PREVIOUSLY APPROVED STUDIES OR ALLOCATED MEGAWATTS OBJECTION TO REALLOCATION OF NON UTILIZED CAPACITY IN THE A HUNDRED THOUSAND DOLLARS PER MEGAWATT FINANCIAL SECURITY REQUIREMENT VIEWS AS VIEWED AS ECONOMICALLY HAR, HARMFUL AND PREMATURE.

UH, THE RISK OF INEQUITABLE TREATMENT DURING DUE TO TSP DRIVEN DELAYS, POTENTIALLY DISADVANTAGING PROJECTS THROUGH NO FAULT OF DEVELOPERS AND THE NEED FOR CLEAR ALIGNMENT WITH SENATE BILL SIX AND FINAL PC GATING RULES BEFORE IMPLEMENTING BATCH ZERO CRITERIA.

SO THAT'S WHERE WE ARE.

WE'LL SEE HOW THE DISCUSSION GOES TODAY.

OKAY, REFINEMENT STUDY APPROACH.

UH, STRONG MAJORITY OF RESPONDENTS ARE AGREE WITH THIS REFINEMENT SITE.

SO IF YOU REMEMBER THE LAST WORKSHOP, THAT'S WHERE BROUGHT ERCOT BROUGHT FORWARD THAT NEW CONCEPT, UH, THAT'S BEING WELL RECEIVED, UH, BY THE WIRES COMPANIES, LARGE LOAD CUSTOMERS ACROSS THE BOARD.

UH, THERE ARE CONCERNS OVER THE REFINEMENT STUDY COULD DELAY PROJECTS OR OVERLAP WITH SUBSEQUENT BATCHES, CREATING INEFFICIENCIES RE STUDIES OR UNCERTAINTY NEED FOR CLEAR CRITERIA SEQUENCING OR OPERATIONAL AND OPERATIONAL TRANSPARENCY RISKS THAT THE PROCESS COULD REOPEN OR EFFECTIVELY UDDY PREVIOUSLY APPROVED PROJECTS, PENALIZING INVESTMENTS MADE EARLIER, UNDER EARLIER ASSUMPTIONS.

UH, AND THEN REQUIREMENTS TO ENSURE ALIGNMENT WITH STATUTORY TIMELINES, THE PURE ONE 20 DAY RULE AND AVOID CONFLICTS WITH SENATE BILL SIX NET METERING REVIEWS.

UH, AND THEN OBJECTIONS TO CERTAIN IMPLEMENTATION ELEMENTS, INCLUDING THE A HUNDRED THOUSAND, UH, PER MEGAWATT SECURITY REQUIREMENT AND EXTENDING GOVERNANCE APPROVAL, TIMELINES, TRANSMISSION UPGRADE AND DESIGN PROCESS AND DESIGN.

UH, WHICH TRANSMISSION UPGRADE BATCH PROCESS WOULD YOU PREFER? SO, SIX MONTH VERSUS THE 12 MONTH.

SO HERE'S THE DATA OR THE, YOU KNOW, THE DATA WITHIN THE DATA.

UM, THE MOST OF THE LARGE, UH, TSPS WE'RE IN FAVOR OF THE 12 MONTH PROCESS.

UH, A LOT OF THAT IS AROUND THE ALIGNMENT WITH EXISTING R-P-G-R-T-P PROCESSES AND HOW DO YOU GET THIS TOGETHER INTO A SINGLE PUT TOGETHER FINAL STUDY RATHER THAN ONE FEEDING INTO THE OTHER.

SO I, I WON'T SAY MUCH MORE THAN THAT, OR I SAW JEFF COME OFF AS COME OFF MUTE.

GO AHEAD.

YEAH, MATT, JUST YOU WANNA ADD TO THAT? YOU KNOW, I THOUGHT THAT WAS INTERESTING DATA.

WHILE, WHILE THERE IS A STRONG MAJORITY THAT FAVORS THE SIX MONTH PROCESS,

[00:25:01]

UM, AS MATT SAID, NOT ALL OF THE LARGER TSPS, BUT, UM, UH, I WOULD SAY MOST OF THE LARGE TSPS FAVOR THE 12 MONTH.

AND, AND I, YOU KNOW, THAT THAT REPRESENTS A SIGNI SIGNIFICANT, UM, NUMBER OF MILES OF TRANSMISSION IN THE STATE.

UM, AND SO I THINK THAT THAT, UH, HAS SOME WEIGHT TO IT.

UM, AND SO WE'RE STILL THINKING ABOUT ABOUT THAT.

UM, AND, AND I'LL SAY WE'RE, WE'RE TRYING TO THREAD THIS NEEDLE.

UM, I, I THINK BATCH ZERO, WE, WE FEEL WE, WE SHOULD STICK WITH THE, THE PROCESS WE'VE LAID OUT IN THE PICKER, BUT ONGOING BATCH.

UM, WE WE'RE, WE'RE THINKING ABOUT HOW TO TAKE THAT FEEDBACK AND AGAIN, TRYING TO SEE IF WE CAN THREAD THAT NEEDLE.

IT, IT'S, IT'S A TRICKY SITUATION, UM, YOU KNOW, TRYING TO, UH, FIND THAT, THAT BALANCE IN, IN THE TRADE OFFS.

BUT, UH, BUT WE, WE ARE TAKING THIS FEEDBACK VERY SERIOUSLY AND, AND ARE CONTINUING TO CHURN INTERNALLY ON THAT, UH, PARTICULARLY WITH THE, THE ONGOING AS WE'RE THINKING ABOUT THE ONGOING BATCH PROCESS.

ALRIGHT, THANK YOU JEFF.

AND WE'RE ALMOST DONE HERE.

AND THEN WE'LL TAKE A PAUSE FOR, UH, OPENING THE QUEUE HERE IN A SECOND, UH, COMMITMENT ALLOCATION, FINAL, UH, COMMITMENT PERIOD.

SO SOME PARTICIPANTS WERE CONSIDERING A FINAL COMMITMENT PERIOD AFTER THE REFINEMENT STUDY.

IN THIS CASE, HOW SHOULD COST AND LOAD RAMP DIFFERENCES DURING THE SUBSEQUENT STUDY REFINEMENTS OCCUR? SO THIS IS THE IDEA OF, WE SAID IT'S A SINGLE COMMITMENT.

THIS IS IN THE EVENT THAT THERE'S A SECOND COMMITMENT AFTER THE REFINEMENT PROCESS.

UM, SO THERE IS MAJORITY RESPONDENTS WERE FAVORED ADJUSTING THE LOAD RAMP IN FINANCIAL SECURITY UPWARD OR DOWNWARD BASED ON THOSE CHANGED IN COST ESTIMATES.

ON THE THEORY OF A SECOND, UH, COMMITMENT, A MIXED STAKEHOLDER ALIGNMENT, TDS PS LARGE OLD CUSTOMERS AND OTHER STAKEHOLDERS ARE ALIGNED, UM, ALLOWING FLEXIBILITY TO ADJUST COMMITMENTS WHILE GENERATORS ARE COMPARATIVELY STRONGER FOR LOCKING THE ORIGINAL LOAD RAMP AND FINANCIAL COMMITMENT.

SO HERE'S THE CONFIDENTIALITY AND TRANSPARENCY, AND I WILL SAY THIS IS SOMETHING WE DON'T HAVE TO SOLVE TODAY, BUT I THINK THIS IS GOOD STEP FORWARD IN UNDERSTANDING WHERE PEOPLE BELIEVE.

UM, SO THERE'S A STRONG PREFERENCE.

WHAT SHOULD REMAIN CONFIDENTIAL, FIRST AND FOREMOST IS THE CUSTOMER IDENTITY.

UM, AND THEN WHEN IT COMES TO EVERYTHING ELSE IS KIND OF A DISTANCE SECOND OF WHETHER OR NOT WE SHOULD BE ABLE TO PUBLISH A TABLE OF STUFF, WHETHER IT'S, YOU KNOW, BY THE LL YOU KNOW, THE LOAD, LARGE LOAD ID OR WHETHER IT'S SYSTEM WIDE.

BUT THERE'S THE IDEA OF WHAT DOES IT MEAN TO START PUBLISHING AND SHARING SOME OF THIS INFORMATION WHEN IT COMES TO, YOU KNOW, WHERE IS IT POINT OF INTERCONNECTION REQUESTED MEGAWATTS, AWARD AND MEGAWATTS TRANSMISSION UPGRADES, UH, COST ESTIMATES, FINANCIAL COMMITMENTS, RAMP SCHEDULE, STEADY RESULTS.

SO WE'RE NOT, WE DON'T HAVE LANGUAGE FOR THIS TODAY, BUT THIS IS, WHAT DOES IT MEAN TO START HAVING TRANSPARENCY ON RESULTS OR THE LARGE LOADS IN GENERAL.

ALRIGHT, SO WITH THAT, UM, WE'LL OPEN UP THE QUEUE AND I, WHAT I WANNA STAY WITH IS MAYBE SOME CLARIFYING QUESTIONS.

UH, AND WE'LL JUST GIVE THIS 20 MINUTES TO SEE WHERE IT GOES.

UH, THERE MAY BE A POINT AT WHICH I RUDELY INTERVENE AND JUST CUT OFF THE QUESTION AND SAY, WE'VE GOTTA GET JEFF UP HERE TO START RUNNING THROUGH, UH, THE MEAT OF THE MEETING.

SO JANICE, IF YOU WANT, I CAN START TO FIGURE OUT WHEN THINGS STARTED.

HERE'S WHAT I DON'T WANNA DO IS TO GO BACK 20 MINUTES AGO.

I WANTED TO GET ALL THIS INFORMATION OUT.

UM, SO JANICE, DO YOU HAVE A NATURAL CUT POINT TO CHOOSE FROM OR DO YOU WANT ME TO PICK IT FOR YOU? SHE UPDATED, PUT THERE.

OKAY.

OKAY.

YEAH, I, I CAN, IF YOU CAN'T SEE THE CUBE IN, I CAN.

I THINK PRASHANT IS FIRST.

YEP.

PRASHAN, GO AHEAD.

HEY, UH, THIS IS PRASHANT FROM BLACK MOUNTAIN.

QUICK QUESTION ON SLIDE 10.

SLIDE 10, UM, YES, UH, ON THE RTP VERSUS BATCH ZERO, UH, MY QUESTION IS, IF A LOAD GETS INCLUDED IN THIS 2026 RTP, UH, WOULD THAT BE AUTOMATICALLY INCLUDED IN THE BATCH ZERO? UH, SO THE ANSWER TO THAT PRASHANT IS, UH, WE WILL LOOK AT, UH, WE'RE BATCH ZERO, WE'RE, WE'RE GONNA FOLLOW WHAT IS IN, UH, PICKER 1 45, WHICH, UM, I THINK RIGHT NOW DOES NOT, UH, AS, AS DRAFTED, UH, DOES NOT INCLUDE A, UH, 2026 RTP CONSIDERATION.

ALRIGHT, THANK YOU.

OKAY, NEXT UP IN THE QUEUE.

UH, BILL BARNES.

HEY MATT, CAN YOU GUYS HEAR ME OKAY? YES, GO AHEAD.

THANK YOU.

SLIDE 23, PLEASE.

THIS IS RELATED TO THE SURVEY QUESTION ON A SIX MONTH VERSUS AN ANNUAL CADENCE, AND I'LL JUST, I'LL KIND OF SPEAK TO OUR

[00:30:01]

RESPONSE, WHICH IS REALLY CONDITIONED ON THE EXPECTATION THAT A SIX MONTH PROCESS WOULD BE FASTER OVERALL IN TERMS OF COMPLETING THE STUDIES AND THEN, UH, GETTING THE, THE DETERMINATION THROUGH THE TRANSMISSION PLANNING PROCESS, RTP AND HAVING LINE OF SIGHT TO NEW TRANSMISSION PROJECTS.

I WOULD SAY THAT IF THE 12 MONTH PROCESS, WHICH INCLUDE WHICH COULD POTENTIALLY INCORPORATE THE BATCH STUDY AND WHAT WOULD BE INCLUDED IN RTP, IF THAT OVERALL GETS YOU TO A FASTER OUTCOME, THEN I THINK A LOT OF RESPONDENTS FOR THE SIX MONTH PROCESS WOULD CHANGE THEIR ANSWER TO 12 MONTHS.

I KNOW WE WOULD.

SO I, I THINK THAT'S, UM, KIND OF WORTH DIGGING IN OR CLARIFYING.

'CAUSE A SIX MONTH BATH BATCH PROCESS, WHICH THEN HAS TO WAIT ON AN RTP IS PROBABLY NOT FASTER OVERALL THAN A 12 MONTH BATCH STUDY THAT INCORPORATES BOTH.

BUT I WOULD LOVE TO HEAR, UH, T'S RESPONSE TO THAT, IF THAT IS A POSSIBILITY.

THANKS.

YEAH, SO I, I THINK THE, UM, IT IS A LITTLE HARD TO HEAR IN THE ROOM, BUT I, I THINK THE MAYBE COMMENT OR QUESTION WAS, UH, WE, UH, VOTED FOR A SIX MONTH PROCESS, BUT WE'D BE, UH, MAYBE WOULD PREFER A 12 MONTH IF THAT RESULTS IN, UM, NOT HAVING TO WAIT FOR THE RTP TO IDENTIFY WHAT, WHAT THE FULL SET OF SOLUTIONS ARE.

AND I, I'LL SAY I APPRECIATE THE COMMENT, WE'RE STILL THINKING ABOUT THAT LONG TERM.

OKAY, THANKS JEFF.

THAT WAS EXACTLY, UH, THE COMMENT.

THANKS.

ALRIGHT, THANK YOU BILL.

THANK YOU JEFF.

SHANNON CARAWAY, SLIDE 10 PLEASE.

YEP.

THE SECOND QUESTION THERE, THE, HOW DOES BATCH ZERO INTERACT WITH 20 26 20 27 RTP? YOUR FIRST SENTENCE SAYS, BASED ON THE CURRENT SEQUENCING, BATCH ZERO WILL NOT AFFECT THE 2026 RTP BECAUSE COMMITMENT OCCURS AFTER THE 2026 MODELING CYCLE IS COMPLETE.

THE, MY QUESTION IS, IS WHY IS THE REVERSE NOT TRUE WHERE YOU WERE TAKING THE 2026 RTP? YOU KNOW, IF WE LOOK AT YOUR FEBRUARY 3RD PRESENTATION WHERE Y'ALL WERE TAKING THE RTP INTO ACCOUNT, GIVEN THAT THESE CYCLES ARE ALIGNED DIFFERENTLY AND THAT WE HAVE THE RTP, THEY'LL HAVE THE APRIL 1ST DEADLINE AND WE HAVE THE 58,480 RULE THAT, UH, MAKES IT WHERE THE COMMITMENT CRITERIA IS ESSENTIALLY ALIGNED, WHY ARE YOU NOT INCLUDING THE 2026 RTP? BECAUSE OTHERWISE YOU'RE JUST MISSING A WHOLE YEAR AGAIN OF, UM, OF RTP? SO THAT'S MY FIRST QUESTION.

I'LL PAUSE.

I THINK THAT THE CHALLENGE WITH THAT IS THAT THE, UM, THE COMMITMENT CRITERIA FOR 2026 RTP, UH, IS, UM, UH, POTENTIALLY DIFFERENT FROM WHAT THE COMMITMENT CRITERIA WILL BE COMING OUT AT 58 4 81.

AND SO THE TRANSMISSION PLAN THAT COMES OUT OF BATCH STUDY, WE, WE WANT THAT TO BE CONSISTENT WITH WHAT WE THINK THE COMMITMENT CRITERIA WILL BE COMING OUT OF 58 41, WHICH MAY ALIGN, MAY NOT ALIGN WITH 2026 RTP.

DOESN'T THE 58 4 80 RULE ACTUALLY SAY THE WHOLE PURPOSE OF IT IS TO ALIGN IT WITH WHAT WAS GONNA COME OUT OF 50 AS BEST AS THEY KNEW AT THE TIME 58 41.

I THOUGHT I READ THAT IN THERE AND, UM, YEAH, I DON'T, I DON'T WANT TO SPEAK, I DON'T, I DON'T WANNA SPEAK FOR, UH, COMMISSION ON THIS, BUT I, I, UM, THE, THE 58 4 80 HAS IT, IT POINTS TO 58 41.

YEP.

BUT HAS THIS BE, BECAUSE 58 41 IS NOT COMPLETE, HA HAS THIS SORT OF SPECIAL RULE FOR 2026.

YEP.

BUT, UM, I THINK OUR, OUR READING OF THAT IS THAT THAT MAY NOT ALIGN.

THAT THE SPECIAL 2026 RULE MAY NOT ALIGN WITH THE FOREVER RULE.

THAT WILL BE IN 58 4 81, UH, IT AND THEREFORE IF, IF THE TRANSMISSION PLAN THAT WE WILL BE ENDORSING OUT OF BATCH ZERO, IF, IF THAT TIMING IS 2027 IS WHEN WE THINK THAT'LL OCCUR, WE, WE WANT TO NOT LOOK AT THE SPECIAL 2026 RULE.

WE WANT TO LOOK FORWARD TO WHAT WE THINK THE RULE WILL BE IN 2027.

'CAUSE THAT, THAT, THAT IS WHAT THAT TRANSMISSION PLAN WILL BE ENDORSED UPON BASED UPON, I THINK FOR BATCH ONE.

THAT MAKES COMPLETE SENSE.

BUT LET ME TAKE WHAT YOU JUST SAID AND ASK THE QUESTION IN REVERSE FOR YOUR 2026 RTP IF YOU HAVE THE CONCERNS.

YOU JUST STATED THAT THE BATCH ZERO COULD BE

[00:35:01]

A DIFFERENT SET OF CRITERIA.

WHAT'S THE PURPOSE OF DOING THE 2026 RTP AT ALL? IF YOU THINK THAT YOU COULD WIND UP WITH A MORE RE IT'S ONLY IF YOU WOULD WIND UP WITH A MORE RESTRICTIVE BATCH ZERO CRITERIA THAT YOUR CONCERN WOULD BE VALID.

AND SO IF THAT'S YOUR REAL CONCERN, THEN WHY, WHY EVEN GO THROUGH THE EFFORT OF DOING A 2026 RTP? BECAUSE IF YOU, WHEN YOU'RE FINISHED, HOW ARE YOU GONNA BE ABLE TO TAKE ANY BOARD ACTION ON ANYTHING IF YOU'VE TAKEN THE POSITION THAT, WELL, THE, THE CRITERIA IS DIFFERENT.

SO, YOU KNOW, THERE'S A GOOD EXERCISE, UH, PLUS PAT HERSELF ON THE BACK AND COME BACK NEXT YEAR.

IT SEEMS LIKE THE INTENT OF THE 58,480 WAS TO COMMISSION TO DO THE VERY BEST THEY COULD.

THE COMMISSIONERS WITH WHAT WAS KNOWN THEN TO GET THAT REFLECTED IN, UH, IN THE, UH, 2026 RTP AND 2026 RTP NEEDS TO BE USEFUL WHEN IT'S FINISHED ACTION NEEDS TO BE TAKEN ON IT OR OTHERWISE WE'VE WASTED ANOTHER YEAR.

YEAH.

AND, AND I'LL I'LL SAY, UM, SO I, UM, I UNDERSTAND THE TIE IN NOT NOT TRYING TO MAKE THIS AN RPG UH, MEETING, BUT, UM, SO, SO I, I DON'T WANNA GO TOO FAR INTO 2026 RTP, BUT I THINK PROBABLY WE MAY WANNA, YOU KNOW, GIVE AN ANSWER ON THAT.

YEAH.

UH, GOOD MORNING, THIS .

SO THERE, THERE ARE A NUMBER OF REASONS WHY WE HAVE TO DO THE RTP.

UH, ONE IS OF COURSE THE FUNDAMENTAL DRIVER IS THE NERC TPL CRITERIA, WHICH REQUIRES YOU TO DO THE PLANNING ASSESSMENT, LOOKING AT BOTH NEAR TERM AND LONG TERM.

AND NUMBER TWO, THE WAY THIS BATCH STUDY IS SCOPED IS IT'S FOCUSES ON ALL LARGE LOADS.

THAT'S NOT THE ONLY LOAD THAT CONNECTS TO THE SYSTEM.

THERE IS A LOT OF, UH, YOU KNOW, OTHER LOAD GROWTH AND PROJECTS.

AND THE WAY THE BATCH STUDY IS LAID OUT IS LIKE THE, WHEN YOU GO TO YEAR FIVE AND SIX, THERE ARE GONNA BE LARGER PROJECTS THAT'S GONNA COME OUT OF THE RTP.

AND, UH, YOU KNOW, THE CURRENT PLANNING CYCLE IS, YEAH, WE NEED TO DO THE RTP, JUST BOTH FOR NERC AND THE PLANNING CRITERIA.

THERE ARE PARTS OF STUDIES WHICH, YOU KNOW, SPECIFIC TO PLANNING, UM, SPECIFIC TO OR CUT REGION THAT'S LAID OUT IN THE PLANNING GUIDES.

THOSE ARE NOT COVERED IN THE BATCH STUDY EITHER.

SO I THINK THERE ARE A NUMBER OF DRIVERS FOR DOING THE RTP AND THE RTP IS THE TRANSMISSION PLANNING ASSESSMENT, UH, FOR THEIR CUT REGION.

TO BE CLEAR, I WAS BEING SARCASTIC WITH WHY ARE WE DOING IT? I'M ACTUALLY POINTING OUT THE, WE ABSOLUTELY NEED TO DO THE 2026 RTP.

JUST WANNA BE CLEAR THAT THAT'S WHAT I BELIEVE, BUT TO NOT, BUT TO THEN WORRY THAT BATCH ZERO CAN'T HAVE USED IT AS YOU PREVIOUSLY PROPOSED BACK ON YOUR FEBRUARY 3RD PRESENTATION THAT YOU WOULD, SEEMS ILLOGICAL.

UH, IT SEEMS LIKE YOU'RE MORE WORRIED THAT 58 41 TURNS OUT DIFFERENT.

OKAY, GREAT.

THAT SHOULD APPLY TO THINGS THAT, THAT ARE COMING ALONG NEW AFTER THAT THAT APPLIES.

AND THAT'S THE NEW LAW OF THE LAND.

BUT IT ISN'T THAT COMMISSION INTENT OF, UH, COMMISSIONER INTENT OF, UH, 58,480 SHOULD JUST BE IGNORED.

UH, OTHERWISE WHAT WAS THE PURPOSE OF THAT RULE? SO I WOULD JUST ASK YOU TO RECONSIDER THAT AND, AND MOVE TO USING IT AS YOU WERE PREVIOUSLY PROPOSING TO USE IT BACK ON THE FEBRUARY 3RD ONE.

ALRIGHT, SO THAT'S R-T-P-R-P-G ON THE, HEY SHANNON, YOU HAD THE FLOOR FOR A BIT.

UH, YOU WANNA TAKE ONE MORE AND THEN WE'RE GONNA NEED, WE HAVE A QUEUE BEHIND YOU.

SURE.

ALRIGHT.

UH, RPG.

YES.

IN YOUR PRESENT, UH, YOUR, UH, FIGURE YOU PUT OUT, I THINK Y'ALL TIED THAT TO DECEMBER 15TH FILING QUESTION FOR YOU THERE IS, WHAT'S THE LOGIC IN MAKING THAT RETROACTIVE BACK TO THE 15TH? IT SEEMS LIKE TO ME THAT OUGHT TO BE, YOU KNOW, THE MOST LOGICAL ONE IS WHEN THE RULE IS PASSED, THEN THAT BECOMES THE NEW EFFECT.

OTHERWISE, YOU'RE, YOU'RE ONCE AGAIN, TAKING THE EXISTING PLANNING PROCESS THAT DOES WORK AND YOU'RE IMPAIRING IT BY MAKING IT ONE TO WHERE THANK YOU TSPS FOR YOUR WORK, BUT WE'RE GONNA TOSS IT IN THE TRASH.

UH, I WHY, WHY WOULD THAT NOT BE UP THROUGH THE DATE OF THE RULE ADOPTION BE YOUR CUTOFF.

YEAH, IT, I THINK MAYBE BETTER TO ADDRESS THAT WHEN WE GET TO THAT POINT IN THAT PRESENTATION.

SHANNON, THANKS.

ALRIGHT.

AND I SEE CINDY BOKAR, WE'LL LET YOU BE THE LAST ONE IN THE QUEUE AND WE'RE GONNA CUT THE QUEUE OFF AT THAT POINT AND SEE HOW FAR WE CAN GET THE NEXT 20 MINUTES ON THE, UH, EIGHT PEOPLE HERE.

SO ERIC GOFF, YOU'RE NEXT.

[00:40:05]

UM, VERY BRIEFLY, I THINK BILL BARNES MADE SOME EXCELLENT POINTS ABOUT THE SIX MONTH VERSUS TRADE MONTH, SIX MONTH VERSUS 12 MONTH TRADE OFFS.

AND I THINK THAT THE REASON YOU GOT THE ANSWERS THAT YOU GOT IS BECAUSE THE QUESTION WASN'T, YOU KNOW, WELL WORDED.

OF COURSE PEOPLE WANT A SHORTER PROCESS, RIGHT.

BUT TO THE EXTENT THAT THE 12 MONTH PROCESS GETS YOU WHAT YOU WANT AND THE SIX MONTH PROCESS DOESN'T, IT'S NOT A GOOD QUESTION.

AND SO I THINK WE NEED TO RE-ASK THESE QUESTIONS TO GET AT THE POINTS THAT BILL AND I ARE RAISING.

THANKS.

IF YOU WANT TO EMAIL ME THE QUESTION, THAT WOULD BE GREAT.

NO, SERIOUSLY.

I COULD USE SOME HELP.

LIKE HOW DO WE YEAH.

RUN THAT DECISION TREE THROUGH THE RIGHT QUESTIONS? UH, THAT SOUNDS GOOD.

UM, I, I, I'LL BE HAPPY TO DO THAT, BUT SPECIFICALLY I THINK IT'S WORTH A DISCUSSION ABOUT WHETHER OR NOT THE, UH, YOU'RE GETTING MORE FROM THE 12 MONTH PROCESS THAT YOU'RE NOT GETTING THE SIX MONTH PROCESS.

AND I THINK WE HAVEN'T REALLY TALKED ABOUT THE, THE TRADE OFFS ENOUGH.

GOTCHA.

I, I, AND I WONDER IF, IF WHAT PEOPLE WANT IS A TRANSMISSION PLAN AND YOU'RE NOT GETTING IT FROM THE SIX MONTH PLAN, WHY WE'RE DOING IT.

OKAY.

SO I HEAR YOU'RE SAYING IS YOU MAY NEED TO SEE THOSE TRADE OFFS TO THEN KIND OF ASK THE RIGHT QUESTION.

THAT'S RIGHT.

OKAY, COOL.

THANKS ERIC.

ALRIGHT, NEXT, UH, KEVIN HANSEN.

YEAH, KEVIN HANSEN AND VERJEE, MY QUESTION IS, WILL WE KNOW BY THE START OF BATCH ZERO HOW RPG PROJECTS IDENTIFIED BY THE BATCH PROCESS WILL BE PAID FOR, WILL BE TCOS OR ALLOCATE TO LARGE LOADS? BUT WE KNOW THAT I ANSWER BEFORE IT KICKS OFF.

I, UH, I I THINK THAT THAT IS ULTIMATELY A, UM, I THINK THAT'S 58 41 QUESTION.

YEP.

UM, THIS IS BARKSDALE WITH THE COMMISSION AND KEVIN, YOU AND I TALKED ABOUT THIS PRETTY EXTENSIVELY BEFORE THE MEETING.

SO, UM, JUST TO REITERATE WHAT I SAID.

UH, THE RULE MAKING FOR THE INTERCONNECTION STANDARDS IN PROJECT NUMBER 5 8 4 8 1 DIRECTLY ADDRESSES DIRECT COST TO INTERCONNECT AND THAT THOSE ARE PAID FOR BY THE LARGE LOAD.

THERE IS IN THE DRAFT RULE THAT IS UP FOR THE COMMISSIONER'S CONSIDERATION ON THURSDAY PROVISIONS DEALING WITH SYSTEM UPGRADES.

SO THE, BUT FOR COSTS TO IMPROVE THE SYSTEM IN ORDER TO HANDLE A LARGE LOAD IN A PARTICULAR GEOGRAPHIC AREA, THERE ARE PROVISIONS IN THERE THAT WOULD ALSO COVER FOR THE LARGE LOAD PAYING FOR THOSE AS WELL.

UM, I WILL BE QUITE CANDID AND SAY THAT THERE'S A LOT OF DEBATE AROUND THAT AND HOW THE COMMISSIONERS CHOOSE TO HANDLE THAT ON THURSDAY.

WE WILL SEE, UM, AND WE WILL LOOK FORWARD TO RECEIVING FORMAL STAKEHOLDER COMMENTS IN THE COMMENT PERIOD ON THAT RULEMAKING.

UM, SO I THINK THAT SHOULD ANSWER YOUR QUESTION, UM, ABOUT WHO IS PAYING FOR THE COST TO INTERCONNECT.

SO THE, THE AMOUNT OF THE COST THOUGH, YOU WILL NOT KNOW UNTIL THE RPG PROJECTS ARE COMPLETED.

SO THEREFORE, THEORETICALLY, IF IT'S A BILLION DOLLAR TRANSMISSION PROJECT FOR A LARGE LOAD, THEORETICALLY YOU CAN HAVE YOUR, IF IT'S HUNDRED THOUSAND DOLLARS TWICE, SO IT'S FOR SAY FOR A GIGAWATT LOAD, YOU'RE WRITING A CHECK FOR A HUNDRED MILLION DOLLARS, THEN ON TOP OF THAT YOU MAY HAVE AN ADDITIONAL BILL OF A BILLION DOLLARS FOR AN RRP G PROJECT THAT WE DON'T KNOW YET THE RULES OF THE GAME.

I THINK, I THINK THE RULES OF THE GAME ARE QUITE CLEAR.

THE ACTUAL NOMINAL DOLLAR AMOUNT IS SOMETHING THAT YOU WOULD NEVER KNOW UNTIL THE ACTUAL PROJECT HAS BEEN DEVELOPED.

SO I THINK THE RULES ARE QUITE CLEAR THOUGH, BUT THE LOADS COULD NOT, SO WE NEED TO MAKE SURE WE UNDERSTAND THE RULES.

AGAIN, WHAT YOU'RE WALKING AWAY FROM.

IF YOU HAVE A NUMBER YOU DON'T LIKE, UH, FROM THE RRP G PROJECT IN THE FUTURE, I THINK YOU AND YOUR INTERCONNECTING UTILITY HAVE TO HAVE CONVERSATIONS ABOUT, UM, THE TYPE OF PROJECTS THAT MIGHT BE NEEDED IN ORDER TO CONNECT THE LOAD.

AND YOU MIGHT HAVE A BETTER INDICATION THROUGH THOSE PRIVATE ONE-ON-ONE CONVERSATIONS ABOUT THE SCALE OF THOSE NECESSARY UPGRADES IN ORDER TO ACCOMMODATE THE LOAD.

OKAY, THANK YOU.

ALRIGHT, WE'RE DOWN TO THE LAST SIX QUESTIONS HERE.

BOB WHITMEYER, UH, SLIDE 25 PLEASE.

SO THE, THE FIRST BULLET OVER THERE IS THE L-I-L-L-I-S NUMBER CONFIDENTIAL.

IT WOULD HELP ERCOT TREMENDOUSLY IF YOU COULD PUBLISH THE LIST JUST OF LLI NUMBERS

[00:45:01]

AND WHAT THEY HAVE COMPLETED IN ERCO T'S MIND BECAUSE THERE'S A LOT OF, A LOT OF MISCOMMUNICATION.

OBVIOUSLY THERE'S NO DIRECT COMMUNICATION BETWEEN ERCOT AND LARGE LOADS.

I WOULD PREFER TO HAVE A ALLELE, A LARGE LOAD, INTERCONNECTED ONGOING OPERATION.

BUT SHORT OF THAT, IF YOU COULD JUST TELL THESE LOADS, 'CAUSE THEY ALL KNOW THEIR NUMBERS.

IF THEY COULD JUST SEE WHERE THEY ARE IN THE PROCESS, I THINK THAT WOULD BE EXTREMELY HELPFUL.

THANK YOU.

SO MORE OR LESS A CHECKLIST STATUS REPORT? YEP.

GOT IT.

SO, HEY, HEY BOB.

UH, COUPLE THOUGHTS, QUICK THOUGHTS ON THAT.

SO, UM, WE, WE HAVE GIVEN THAT INFORMATION TO THE, UH, TSPS, UH, I THINK WE ARE HESITANT TO PUBLICLY POST THAT.

AND, UH, AND THAT'S BECAUSE WE'VE GOTTEN FEEDBACK THAT IT, IT, UM, FOR, UH, SOME LARGE LOAD PROJECTS, THOSE PROJECTS HAVE BEEN SOLD TO OTHER DEVELOPERS.

UH, AND, AND SO YOU MAY KNOW, UH, YOU, YOU MAY KNOW A, A, UH, A LLI NUMBER THAT IS NOT YOUR PROJECT ANYMORE.

AND BY KNOWING THE STATUS OF THAT, THEN THAT GIVES YOU SOME COMPETITIVE INFORMATION THAT, THAT YOU SHOULDN'T HAVE.

AND SO THAT, I THINK THAT'S THE DIFFICULTY WITH WHERE WE'RE AT TODAY.

BUT I THINK WE'RE, WHAT WE'RE TRYING TO TEASE OUT IN THIS IS, UH, SHOULD WE WRITE DIFFERENT RULES AROUND THAT GOING FORWARD? AND, AND JEFF, I I COMPLETELY AGREE, YOU NEED TO BE VERY CAREFUL WITH THAT, BUT I WOULD ALSO LIKE YOU TO RECOGNIZE THAT I THINK IT WOULD TAKE A LOT OFF ERCOT PLATE IF SUCH A SYSTEM EXISTED, BUT YOU'RE, YOU'RE RIGHT TO BE CONCERNED ABOUT EXPOSING THAT INFORMATION.

THANK YOU.

OKAY, THANKS.

ALL RIGHT.

NEXT QUESTION.

UM, OOPS, JUST MOVED ON ME, UH, GODFRIED ARTHUR OR ARTHUR? YEAH.

HELLO, CAN YOU HEAR ME? GOOD? YES, GO AHEAD.

ALRIGHT, QUICK ONE.

SO, UM, FOR BADGE ZERO, WHAT DOES THE INTERMEDIATE CRITERIA LOOK LIKE FOR LOAD WITH INTERCONNECTION STUDIES SPECIALLY COMPLETE? SO LIKE, ARE THEY ALSO SUBJECT TO THE HUNDRED THOUSAND, UM, DOLLARS PER MEGAWATTS FINANCIAL SECURITY? YEAH, I, I, I THINK WE'LL GET TO THAT LATER IN THAT PRESENTATION.

OKAY.

ALRIGHT.

THANK YOU SIR.

UH, NEXT CHRIS MATTIS, WELL, I, OKAY, IT STILL WORKS WIRELESSLY, UM, .

SO ON TO, TO ECHO, I THINK ERIC AND, AND BILL'S POINT AND JUST TRANSPARENTLY ON SLIDE 23, I ACTUALLY VOTED FOR A 12 MONTH PERIOD OR, OR PASSWORD 12 MONTH PERIOD, BUT THAT WOULD ALSO BE IN LINE WITH GOOGLE AND LAN'S COMMENTS OF CLEAR DELIVERABLES COMING OUT OF IT.

SO, AND WE'VE KIND OF REITERATED THIS A FEW TIMES THROUGHOUT THE PROCESS, THAT IF YOU'RE GOING TO POSE QUESTIONS LIKE THIS, WHAT ARE THE CLEAR DELIVERABLES THAT COME OUT OF A SIX MONTH PROCESS AND NINE MONTH PROCESS OR A 12 MONTH PROCESS AND GIVE STAKEHOLDERS, WELL, HONESTLY JUST COMMITMENTS FROM BOTH SIDES.

IF THE EXPECTATION OUT OF THIS IS FINANCIAL COMMITMENTS TO JUSTIFY THE LOAD, THEN THOSE LOADS SHOULD KNOW WHAT THEY ARE GETTING OUT OF A PROCESS IN IT.

AND IT IS NOT FIRM TRANSMISSION UPGRADES, AND I'VE EXPRESSED THIS IN THE CURRENT WAY, SECURITIES ARE PROPOSED THAT CAN LEAVE LARGE LOADS ON THE HOOK FOR HUNDREDS OF MILLIONS OF DOLLARS THAT ARE NON-REFUNDABLE FOR TIMELINES THAT ARE UNCLEAR ON THE DELIVERY, WHICH IS A REALLY UNFAIR RISK TO THE LOAD.

SO I DON'T WANT TO REVISIT THIS QUESTION AS SIMPLY AS THIS, I WANT TO REVISIT THIS QUESTION AND I, I THINK ERCOT PERSPECTIVE IS ACTUALLY REALLY WHAT'S IMPORTANT HERE.

WHAT CAN YOU DO IN SIX MONTHS? WHAT CAN YOU DO IN NINE MONTHS AND WHAT CAN YOU DO IN 12 MONTHS AND SET THE STAGE FOR US TO DECIDE ON THAT.

LIKE, I'M INTERESTED TO KNOW AND, AND THAT WOULD BE REALLY HELPFUL FOR THIS, THIS QUESTION.

UM, AND THEN ON THE LLI AND POINT THAT BOB BROUGHT UP, I'M WONDERING WHY CAN'T WE JUST REASSIGN THOSE WHEN THEY ARE TRANSACTED UPON OR, OR GIVEN A NEW NUMBER? YEAH, SO I THINK WE'RE OPEN TO THAT GOING FORWARD.

I, I, THE, THE QUESTION IS RIGHT NOW, UM, THAT I THINK WE, WE DON'T HAVE A SYSTEM TO DO THAT TODAY.

SO WHAT, WHAT DO WE DO IN FIRST AND SECOND QUARTER OF 2026 IS, I THINK WE HAVE THE SYSTEMS THAT WE HAVE AND, AND THE, THE RULES THAT WE HAVE.

BUT GOING FORWARD, I THINK WE'RE DEFINITELY OPEN TO CHANGING THAT.

OKAY.

AND THIS IS GONNA GET TO MY OTHER POINT FROM LAST TIME, WHICH IS WHAT ARE THE ADMINISTRATIVE GAPS WE CAN ALREADY START ADDRESSING?

[00:50:01]

SO THAT WAY WHEN WE HAVE THE BATCH PROCESS STARTING IN, YOU KNOW, A PROPOSED AUGUST SEPTEMBER TIMELINE, WE'RE, WE'RE KIND OF READY FOR THAT.

AND I, I REALLY THINK A CENTRAL MANAGEMENT SYSTEM OF JUST LIKE INFORMATION SUBMITTED IS REALLY, REALLY CORE TO THE SUCCESS OF THIS.

AND WE NEED TO HAVE THAT CONVERSATION NOW.

EVEN IF ALL THAT BEING, EVEN IF WE HAVEN'T FULLY FINISHED THIS PROCESS, AT THE VERY LEAST WE'RE GETTING TO A CENTRALIZED UNDERSTANDING OF HOW INFORMATION IS, IS GOING TO BE SUBMITTED FROM TSP TO TSP TO ERCOT.

AND THEN WE CAN, I THINK WITHIN THAT, FIGURE OUT HOW THE LOADS WILL OR WILL NOT BE INVOLVED STILL, STILL IN THIS PROCESS WITHOUT, I DON'T, I DON'T THINK THAT CAN'T START WITHOUT THIS BEING DONE OR THAT CAN START WITHOUT THIS BEING DONE.

I GUESS THAT'S REALLY WHAT I'M SAYING.

BUT THANK YOU.

THANK YOU.

ALRIGHT, NEXT JENNY.

THANK YOU.

UM, THIS IS JENNY, SHE FROM SAUNA.

JUST A QUICK QUESTION THAT IF ONE INTERCONNECTION REQUEST THAT WAS SUBMITTED TO THE INTERCONNECTING UTILITY LAST YEAR FOR 100 MEGAWATT, BUT WE HAVE SINCE THEN REDUCED THE CAPACITY TO 74 MEGAWATT THIS YEAR AND THIS REDUCTION HAS JUST BEEN APPROVED BY THE INTERCONNECTING UTILITY.

BASED ON THIS CHANGE, WILL THIS PROJECT BE INCLUDED AS BASE LOAD OR STUDIED LOAD IN THE BATCH ZERO PROCESS? I MIGHT NEED TO PHONE A FRIEND ON THAT DON'T OFF ANY OF THE LARGE LOAD, UH, INTERCONNECTION TEAM IS ONLINE AND CAN ANSWER THAT.

YEAH, IT, IT, UM, IT, IF NOT MAYBE, UM, SEND US AN EMAIL ON THAT AND WE'LL WE'LL TRY TO ANSWER, UM, QUESTIONS ON ANY SPECIFIC PROJECTS.

GOT IT.

SOUNDS GOOD.

THANK YOU.

ALRIGHT, THANK YOU.

DOWN THE LAST TWO HERE CHRIS, AND THEN SANDEEP.

GO AHEAD.

CHRIS HENDRICK, UH, CHRIS HENDRICKS FOR SWITCH.

UM, MY QUESTION OR REALLY A SUGGESTION ON THE CONFIDENTIALITY ON PAGE 25 IS FOR THE NEXT WORKSHOP IF WE COULD GET A COMPARISON BETWEEN WHAT THE GENERATORS ARE ALL ALLOWED OR WHAT YOU PRODUCE FOR THE GENERATORS, WE COULD KIND OF COMPARE THAT TO THE LARGE LOAD AND SEE WHAT WE CAN AGREE WITH AND WHAT WE CAN'T AGREE WITH.

AND I THINK THAT WOULD BE HELPFUL.

I AGREE.

OKAY.

GOOD FEEDBACK.

SO A COMPARISON OF DISCLOSURES.

YEP.

ALRIGHT, THANKS.

ALRIGHT.

AND LAST ONE, SANDEEP BOKAR, LCRA ON THE QUESTION ON THE IN-FLIGHT RPG PROJECTS, UH, I I TAKE THAT THAT'S MORE FOR THE, WELL DEFINITELY FOR THE UPGRADES, THE STANDARD PRACTICES RPG APPROVED PROJECTS YOU INCLUDE IN THE BASE CASES.

SO ONE QUESTION IS, UH, WHEN WE SAY THEY, THEY'VE RECEIVED ENDORSEMENT, IS THAT ER CARD BOARD APPROVED? BECAUSE THAT PUSHES SOME OF THE PROJECTS FURTHER DOWN THE ROAD VERSUS THAT AT, AT THE RPG PRESENTATION, ER CARD HAS CONCLUDED THE, UH, THE, THE WORK AND HAS PRESENTED AT THIS IS THE RECOMMENDED OPTION, WHICH DID, BECAUSE THAT WILL MATTER DEPENDING ON, 'CAUSE THERE ARE SOME OF BIG PROJECTS GOING THROUGH RIGHT NOW, UH, IN THE PROCESS AND CURIOUS WHICH ONE IS USED.

UM, I MIGHT NEED, UH, HELP FROM MY TRANSMISSION PLANNING FRIENDS, BUT I THINK THE CURRENT PRACTICE IS, IT, IT'S WHENEVER THE PROJECT IS ENDORSED BY ORCO, WHICH WOULD, FOR TIER ONE PROJECTS WOULD BE BOARD OF DIRECTOR AND, AND, UH, ENDORSEMENT TIER TWO, IT WOULD BE ERCOT INDEPENDENT REVIEW AND TIER THREE IT WOULD BE WHEN IT'S RECEIVED RPG APPROVAL.

GOT IT.

YEAH, I THINK GIVEN THE, THE FACT THAT WE NEED A LOT OF TRANSMISSION UPGRADES FOR THIS WORK, I WOULD ENCOURAGE WE, WE HAVE THAT EXCEPTION AS PART OF THIS PROCESS.

UH, UM, USE THE EARLIER ENDORSEMENT, UH, AS A, AS, AS A, AS A SLICE IN TIME.

AND THE SECOND QUESTION ON THAT ONE WAS, UH, THAT WAS ABOUT THE UPGRADES.

UH, IS THAT ALSO TRUE ABOUT THE LOADS THEN IF THE LARGE LOADS THAT WERE INCLUDED IN THE STUDY ALSO FALL INTO THE SAME CATEGORY THAT THEY ARE INCLUDED AS WELL ALONG WITH IT? UM, YEAH, SO WE WOULD, UM, IT'S UH, I THINK IT'S COMPLEX.

UH, IT'S, IT'S LAID OUT IN 1 45.

I THINK IF, IF Y'ALL, UH, BEAR WITH US, THEN WE'LL WE'LL WALK THROUGH THAT HERE IN A LITTLE BIT.

GOOD DEAL.

AND THE LAST COMMENT WAS ABOUT THE SIX MONTH VERSUS THIS 12 MONTH.

UH, I THINK WE WERE ALSO ONE OF THOSE WHO SUPPORTED THE 12.

UH, THE LOGIC THERE WAS, ESPECIALLY FOR THE BATCH ZERO, IT IS GOING TO BE A LOT OF WORK.

I KNOW EVERYONE IS ASKING ABOUT SIX MONTHS.

IT'S JUST A LOT OF CASES AND, UH, LOT OF PROJECTS WILL BE CLEARED AS PART OF THIS.

[00:55:01]

SO MORE TIME WE SPEND AND GET IT RIGHT ON THE FIRST ATTEMPT WOULD BE NICE TO BATCH ONE AND, AND ONWARDS MAYBE A SIX OR NINE MONTH MAY.

UH, MAYBE, UH, SOMETHING WE CAN, UH, LOOK AT.

BUT FIRST ONE, THINK IT'S IMPORTANT THAT WE GET IT RIGHT AND UH, WE HAVE THE UPGRADES LINED UP TO FOLLOW.

THANK YOU, SIR.

OKAY, PERFECT.

ALRIGHT.

OKAY.

SO AT THIS POINT I THINK WE'RE GONNA TRANSITION TO JEFF, THANK YOU FOR THE, UH, THE QUEUE MANAGEMENT HERE, JANICE.

AND AT THIS POINT WE'RE GONNA

[4. Batch Zero NPRR/PGRR Walk-through (most of meeting)]

KIND OF STOP THE QUEUE AGAIN AND LET JEFF GET THROUGH.

HE'S GONNA DO A WALKTHROUGH.

UM, AND JEFF, IF YOU WANNA KIND OF BE THINKING ABOUT HOW TO GO THROUGH THIS.

SO WE HAVE THE PRESENTATIONS UP, YOU HAVE DIFFERENT SECTIONS TO WALK THROUGH IN THE BIGGERS ON, UM, IN THE BACKGROUND.

SO LET, LETS GO.

THANK YOU, SIR.

OKAY.

YEAH, AND I'M JUST, TO BE HONEST, I'M NOT, UM, SURE HOW I'M GONNA DO THIS.

I I THINK I'M GOING TO WALK THROUGH THE PRESENTATION, BUT AS WE NEED TO, UH, GO OVER TO THE LANGUAGE, THEN WE WILL, UM, DO THAT.

UH, ALSO TO, UM, START WITH I'VE HAD, UH, A LOT OF, UM, KUDOS ON, UH, GETTING THE LANGUAGE OUT.

I KNOW, UM, THAT THERE'S, UH, THAT'S OFTEN ACCOMPANIED WITH, BUT WE DISAGREE WITH THIS SECTION OR WE DISAGREE WITH THIS LANGUAGE.

BUT, UH, BUT, YOU KNOW, WE'VE UH, HEARD A LOT OF APPRECIATION FOR GETTING THAT OUT.

AND I WOULD BE REMISS IF I DIDN'T ACKNOWLEDGE THAT THERE WAS A WHOLE TEAM OF FOLKS THAT, THAT WORKED ON THIS, UM, AT, AT ERCOT.

AND, UM, AND, UH, THREE INDIVIDUALS IN PARTICULAR, UH, AG SPRINGER, CHRISTINA SWITZER, AND EVAN ROWE, WHO, UH, HAD, UH, SPENT A LOT OF HOURS OVER WEEKENDS, UH, SOME REALLY LATE NIGHTS.

UH, THERE, THERE WERE TIMES WHERE I WOULD, UH, GO TO BED AND, YOU KNOW, THEY'D ASK ME BE ASKED QUESTIONS AND I'D GO TO BED AND, UH, I'D WAKE UP AND, YOU KNOW, THEY'D SENT THE LATEST VERSION, UH, THAT THEY'D WORKED ON UNTIL MIDNIGHT.

SO, UH, JUST WANTED TO, UH, YOU KNOW, IT IS THE KUDOS THAT WE'VE GOTTEN.

I WANTED TO EXTEND THAT AND MAKE SURE THAT, THAT THE TEAM WAS RECOGNIZED FOR THEIR HARD WORK.

OKAY.

SO, UM, WITH THAT, UM, AND ONE OTHER, UM, KIND OF UPFRONT COMMENT I WANNA MAKE IS THAT, UH, UH, I THINK MATT KIND OF ALLUDED TO THIS, BUT YOU KNOW, THIS IS A, UM, THIS IS A PROCESS.

SO WHAT WE HAVE POSTED THAT IS LIKELY NOT THE FINAL VERSION, UH, THAT YOUR, YOUR COMMENTS, NOT JUST, UH, HEY, YOU GOT IT WRONG OR CAUGHT, BUT YOU KNOW, HERE HERE'S ALTERNATIVE LANGUAGE THAT WE THINK WORKS BETTER.

UH, THAT I THINK THAT THAT IS HELPFUL.

UH, WE, WE'VE TRIED TO TAKE THAT FEEDBACK, UH, THAT WE'VE GOTTEN ALONG THE WAY.

SO I'VE ALREADY HEARD COMMENTS TODAY OF, HEY, YOU, YOU SAID SOMETHING DIFFERENT, UH, AT A PREVIOUS WORKSHOP AND WHY, WHY DID YOU CHANGE? AND THAT CHANGE HAS BEEN BECAUSE OF THE, UH, THE FEEDBACK THAT WE'VE GOTTEN.

AND SO THIS IS, YOU KNOW, STILL A PROCESS WHERE WE ARE ASKING FOR THAT, THAT FEEDBACK.

UM, OKAY.

SO WITH THAT, UH, I WANTED TO START HERE AGAIN THAT THIS WAS, UM, A, UH, SLIDE THAT AG PUT TOGETHER FOR THE LAST WORKSHOP THAT, UH, I THINK GOT A LOT OF, UH, GOOD, UH, COMMENTS AND, AND FEEDBACK AND WAS HELPFUL FOR THE DISCUSSION.

SO I WANTED TO START HERE.

UH, SO WE'RE, WE'RE GONNA START WITH THE, THE STUDY PROCESS.

SO MATT, I THINK WE'RE, WE'LL TRY TO GO THROUGH SLIDE 42 IF WE CAN, UH, ACHIEVE THAT BEFORE LUNCH.

UH, AND, AND THEN, AND THEN WE'LL STOP AND, UM, AND TAKE COMMENTS AND QUESTIONS AT THAT TIME.

UH, BUT I'M GONNA START HERE WITH KIND O OVERALL HIGH, HIGH LEVEL.

WHAT, WHAT IS THE PROCESS THAT WE ARE PROPOSING? AND, AND THAT IS THAT WE WOULD HAVE A, UH, IN, IN BATCH ZERO.

AGAIN, THIS IS, UM, THAT, YOU KNOW, I THINK WE, WE'VE HEARD THE FEEDBACK ON SHOULD WE HAVE A, A LONGER PROCESS.

I THINK WE'RE, UM, WE, WE CAN DISCUSS THAT FOR, UH, YOU KNOW, THE, THE SUBSEQUENT FIGURE FOR THE ONGOING BATCH.

BUT FOR, FOR BATCH ZERO AS LAID OUT IN PI FIGURE 1 45 IS, IS THAT WE WOULD HAVE A SIX MONTH PROCESS WHERE WE WOULD DO, UH, ERCOT WOULD PERFORM STUDY STATE AND DYNAMIC STABILITY, UH, UH, STUDIES.

UH, WE WOULD IDENTIFY WHERE WE HAVE PLANNING CRITERIA VIOLATIONS DUE TO THE ADDITION OF THE NEW LARGE LOADS THAT ARE UNDER STUDY IN BATCH ZERO.

UH, AND THAT WE WOULD WORK ITER ITERATIVELY WITH THE TSPS TO IDENTIFY, UH, SOME UPGRADES THAT COULD BE, UM, UH, PUT IN PLACE IN TIME TO, UH, TO, UH, GET, GET THE LOADS, UH, SERVED AT A HIGHER LEVEL.

UH, AT THE END OF THAT STUDY, UH, THERE WILL BE A, UH, A COMMITMENT PERIOD THAT IS CURRENTLY LAID OUT AS A 30 DAY COMMITMENT PERIOD.

AND THAT 30 DAY IS A COPY PASTE FROM 58 4 81, UH, PFP, UH, DRAFT, UH, A A 30 DAY COMMITMENT PERIOD.

UM, AND, UH, THIS CAME UP IN FAQS, ARE ALREADY HEARD IT AGAIN TODAY.

UH, THAT COMMITMENT AND

[01:00:01]

ANY FINANCIAL SECURITY, UH, THAT IT WOULD BE REQUIRED BASED ON UPGRADES WOULD BE AT THAT SNAPSHOT IN TIME OF WHAT WE KNOW AT THE END OF THAT BATCH STUDY, UH, PROCESS.

SO, UH, YOU KNOW, OBVIOUSLY, UH, COMMISSION CAN, UH, YOU KNOW, THEY, THEY CAN CHANGE THE RULES, BUT AS WE ARE READING 58 41, THAT COMMITMENT IS A SNAPSHOT IN TIME COMMITMENT.

UH, AND, AND SO THAT IS WHAT, WHAT, YOU KNOW, AT THAT POINT IN TIME.

SO AT, IF THE REFINEMENT STUDY OR A LATER RPG PROJECT IDENTIFIES A DIFFERENT SET OF TRANSMISSION UPGRADES, THAT THAT DOES NOT IMPACT THE WHAT IS COMMITTED TO AT, AT THIS POINT IN TIME.

WHAT THIS COM, THIS I-L-E-I-L-L-E COMMITMENT PERIOD, UH, IS BASED ON WHAT WE KNOW AT THAT SNAPSHOT IN TIME, UH, BASED ON THE LOADS THAT THEN, UH, COMMIT.

THEN WE WOULD GO THROUGH A THREE MONTH BATCH, ZERO REFINEMENT.

THIS THREE MONTH WOULD BE, SAY NEXT SPRING.

UH, UH, SO APPROXIMATELY A YEAR FROM NOW, WE WOULD BE WORKING ON THIS REFINEMENT TO DETERMINE BASED ON, UH, WHICH OF THOSE LOADS HAVE COMMITTED, UH, WHICH TRANSMISSION PROJECTS WERE IDENTIFIED, UM, ARE NEEDED TO MOVE FORWARD.

WE WOULD ALSO LOOK AT ALTERNATIVE TRANSMISSION, UH, UH, UP UPGRADE OPTIONS, AND WE WOULD DEVELOP A TRANSMISSION PLAN THAT WOULD GO TO THE RPG AND IF NEEDED, WOULD RECEIVE, UH, BOARD ENDORSEMENT.

UH, SO THAT HIGH, HIGH LEVEL, THAT'S, THAT'S THE PROCESS.

UH, SO LET, LET'S GET INTO DETAIL.

SO, UM, MATT KIND OF NOTED THIS EARLIER, BUT I'LL, I'LL POINT OUT AGAIN.

UH, SO WE HAVE, UH, WELL, A LOT OF THESE SLIDES ARE CARRY OVER FROM THE FEBRUARY 26TH WORKSHOP, BUT WHERE WE HAVE MADE CHANGES OR MADE CLARIFICATION, SOME OF THESE AREN'T, AREN'T ACTUALLY CHANGES.

WE'VE, WE'VE TRIED TO MARK THAT WITH RED TEXT.

UH, SO SOME OF THIS IS JUST CLARIFICATIONS, BUT WE'VE MADE CHANGES AND, OR CLARIFICATIONS AND, UH, FROM THE FEBRUARY 26 SLIDES, THEN WE'VE TRIED TO NOTE THAT IN RED.

UH, SO THE, UH, THIS STUDY SCOPE IS, UH, ESSENTIALLY WHAT WE HAD LAID OUT AT THE FEBRUARY 26TH WORKSHOP WHERE WE WOULD BE STUDYING, STUDYING 2028 TO 2030, TIER 2032, WHICH IS YEARS ONE TO FIVE.

UH, AND, UM, THOSE, UH, YOU'RE TRYING TO IDENTIFY WHAT, WHAT ARE THE, UH, THE CRITERIA VIOLATIONS FOR SUMMER PEAK, UH, SUMMER, UH, NO, NO SOLAR CONDITION, UH, AS WELL AS FALL PEAK.

AND WE'LL, WE'LL DO THAT, TRY TO IDENTIFY THOSE CRITERIA VIOLATIONS, AND THEN TRIED TO, UM, COME UP WITH, UH, TRANSMISSION UPGRADES.

UM, THAT REALLY NO CHANGE ON THE STUDY METHODOLOGY IN THE STUDY ELEMENTS THAT, THAT WE HAD LAID OUT AT THE FEBRUARY 26TH WORKSHOP IS WE WILL, WE'LL PREPARE THE STUDY CASES.

UH, IF YOU LOOK AT THE TIMELINE, WE ACTUALLY START, UH, SO, SO WE, WE WILL TALK LATER ABOUT THE JULY 15TH AS AS BEING SORT OF OUR, OUR, OUR SNAPSHOT FOR WHEN WE ARE GOING TO, UH, UH, KIND OF IDENTIFY THE CRITERIA FOR THE, UH, YEAH, THAT'S FINE.

THE LOADS.

I'M NOT UNDER PG E, SO NO WORRIES.

BYE.

FIVE.

UM, UH, SO, UM, WE'LL, WE'LL IDENTIFY, UM, THE, OR, SORRY, UH, I WAS SAYING IS, UH, THE, THE STUDY CASES WILL ACTUALLY START BEFORE THAT JULY 15TH TO PUT TOGETHER THOSE STUDY CASES.

UH, THEN WE'LL, WE WILL RUN OUR RELIABILITY ASSESSMENT.

UH, WE WILL THEN, THAT'S PRIMARILY A STEADY STATE ANALYSIS.

THEN WE WILL ALSO RUN A STABILITY SCREENING ASSESSMENT AS WE, UH, TALKED ABOUT AT PREVIOUS WORKSHOPS.

WE'LL IDENTIFY WHAT THOSE TRANSMISSION IMPROVEMENT PROJECTS ARE.

AND, UM, UH, AND THEN WE WILL ALSO BE LOOKING FOR THE OTHER STUDY ELEMENTS.

YOU KNOW, IT'S NOT JUST STUDY STATE AND STABILITY STUDIES THAT GO INTO A LARGE LOAD INTER CONNECTION STUDY.

THERE ARE OTHER ELEMENTS.

SO WE'LL BE LOOKING FOR THOSE ELEMENTS AS WELL.

OKAY.

AT THE 26TH WORKSHOP, WE DID NOT HAVE THESE, UH, DATES LAID OUT, UH, BUT, UH, HAVE THOSE NOW AS, AS, UH, ARE INCLUDED IN FIGURE 1 45.

UH, THE, UH, THE, OUR, OUR CUTOFF DATE FOR GETTING INFORMATION TO GO INTO THIS STUDY WILL BE, UH, JULY 15TH.

UM, THAT WOULD ALLOW US TO, UH, POST THE, UH, OR, OR TO FINALIZE THE, THE BATCH SERIAL STUDY REPORT AT THE END OF JANUARY OF 2027, WHICH, UH, LEADS TO A MARCH 1ST, UH, COMMITMENT DEADLINE FOR THE, UH, LARGE LOAD.

SO, SO TSPS WOULD NEED TO NOTIFY US BY MARCH 1ST THAT THAT COMMITMENT DEADLINE OR THAT COMMITMENT HAS, UH, REQUIREMENTS HAVE BEEN MET.

UM, AND, UH, THAT THEN LEADS TO A JUNE 1ST COMPLETION OF THE BATCH ZERO REFINEMENT STUDY.

UH, WHICH WOULD, UH, AT THAT POINT, WE WOULD SUBMIT THAT, THAT, UH, SET

[01:05:01]

OF PROJECTS TO RPG.

UM, THE, UH, OUTPUTS REALLY AT A HIGH LEVEL HAVEN'T CHANGED SINCE THE, UM, UH, THE FEBRUARY 26TH WORKSHOP.

SO LOOKING TO HAVE A STUDY REPORT, A LOAD COMMISSIONING PLAN, UM, ESTIMATED SECURITY REQUIREMENTS FOR THE LOADS, UH, TO, UH, TO, TO MEET, UH, FOR THE, UM, UH, THAT MARCH 1ST DEADLINE.

AND THE, UM, AND THERE WOULD BE MAYBE SOME ADDITIONAL INFORMATION THAT WE WOULD, UH, SEND JUST TO, UH, TSP, SOME INFORMATION THAT MAY BE CONSIDERED CONFIDENTIAL.

UM, AND, UH, AGAIN, REFINEMENT AND RPG HANDOFF, UM, THAT, YOU KNOW, REALLY HASN'T CHANGED.

WE ADDED A CLARIFICATION THAT THE, UH, MEGAWATT ALLOCATION FOR THE LARGE LOADS THAT MEET THAT COMMITMENT CRITERIA, THAT, THAT, THAT, THAT IS NOT EXPECTED TO BE ADJUSTED DURING THE REFINEMENT PERIOD.

UH, SO IF, IF WE, UH, TELE LOAD THAT IN 2029 THAT THEY HAVE 250 MEGAWATTS, UH, ALLOCATED, UH, WE WOULD NOT, IF THE TRANSMISSION PLAN CHANGES, UH, THAT TWO 50 MEGAWATT DOESN'T CHANGE, THEY, THEY STILL HAVE THAT, THAT 250 MEGAWATTS IN THAT YEAR.

UM, SO, UH, TRIED TO PUT TOGETHER JUST A, A LITTLE CHART TO ILLUSTRATE, UH, WHAT WE'RE THINKING ON, YOU KNOW, HOW, HOW THIS WORKS.

UM, AND, UH, AND I'LL, I'LL WALK THROUGH IT REAL QUICK AND, UH, HOPEFULLY THIS WILL BE HELPFUL.

BUT THE, UM, UH, D THE DEVELOPERS ESSENTIALLY WOULD, WOULD NEED TO, UH, MEET THE, UM, INTERMEDIATE AGREEMENT REQUIREMENTS TO, UM, TO, TO QUALIFY AND, AND, AND WE'LL WALK THROUGH.

WHAT, WHAT DOES THAT MEAN? WE'LL WALK THROUGH THAT, UH, LATER ON IN THE PRESENTATION.

UH, BUT THE, UH, YOU KNOW, TSPS WOULD THEN SEND THE INFORMATION TO ERCOT OR ERCOT WILL THEN, UH, BUILD THE STUDY CASES.

WE'LL POST THOSE CASES ON MIS, UH, CERTIFIED.

UH, ERCOT WILL BE PERFORMING THE, UH, THE STUDY, STATE STUDY.

THEN, UH, TSPS, YOU KNOW, THEY, THEY CAN ALSO PERFORM THEIR OWN STUDY, UH, AND, AND THAT I THINK THAT PERFORMING THEIR OWN STUDY IS OPTIONAL, BUT WORKING WITH US, WE WOULD EXPECT THAT WE WOULD HAVE, UM, TRYING TO ILLUSTRATE HERE WITH THE ARROWS BACK, BACK AND FORTH WITH THE TSPS ON THE STUDY RESULTS.

UM, WE'LL ALSO SIMILARLY BE PERFORMING THE STABILITY SCREENING STUDY, AND WOULD EXPECT TO HAVE BACK AND FORTH CONVERSATIONS WITH TSPS AS WE ARE, UH, IDENTIFYING THE, THE PLANNING CRITERIA VIOLATIONS, UM, AT, AT THE CONCLUSION OF THE STABILITY SCREENING STUDY.

THEN WE WOULD HAVE ALL THE RESULTS.

WE WOULD COMMUNICATE THOSE RESULTS.

UM, AND THE, UM, AT, AT THAT POINT, THAT THAT'S THAT COMMITMENT WHERE THE DEVELOPER AND THE TSP WOULD ENTER INTO THE INTERCONNECTION AGREEMENT AND NEED TO MEET THE INTERCONNECTION AGREEMENT REQUIREMENTS, UH, AS WHAT WILL BE LAID OUT IN 58 41, UH, ERCOT WOULD THEN POST OR, OR WOULD PERFORM THE, UH, REFINEMENT TRANSMISSION PLANNING STUDY BASED ON WHICH LOADS THE TSPS HAVE COMMUNICATED TO US HAVE MET THE, THE INTERCONNECTION AGREEMENT REQUIREMENTS.

UM, WE WOULD, OF COURSE, NEED, UH, COST ESTIMATES AND A FINAL REVIEW OF THOSE.

COST ESTIMATES ARE IMPORTANT BECAUSE THAT INFORMATION WOULD BE NEEDED AS, AS WE'RE SUBMITTING THAT, THAT REFINEMENT TRANSMISSION PLAN FOR RPG REVIEW.

UM, UH, SO WE, OR ERCOT WOULD THEN, UH, THIS IS, IS SORT OF A CHANGE FROM THE CURRENT, UH, PROCESS IS ERCOT WOULD THEN SUBMIT THAT SET OF PROJECTS FOR RPG REVIEW, WE'LL RESOLVE ANY RPG COMMENTS AND IF NECESSARY, TAKE THOSE PROJECTS TO THE BOARD OF DIRECTORS FOR ENDORSEMENT.

UH, SO THAT HIGH, HIGH LEVEL HOPE, HOPEFULLY THAT HELPS.

UH, I KNOW IT'S, IT'S A LITTLE BIT OF A BUSY SLIDE, BUT HOPEFULLY THAT KINDA HELPS, UH, ILLUSTRATE THE PROCESS A LITTLE BIT BETTER.

UM, AND THIS IS, UH, ALSO A, UH, A CARRYOVER FROM THE, UH, LAST WORKSHOP, BUT THE DATES HAVE BEEN SLIGHTLY MODIFIED TO, TO ALIGN WITH WHAT WAS SUBMITTED IN PIRE 1 45.

UH, SO AGAIN, IT'S, WE'RE, WE'RE STARTING THAT CASE BUILD, UH, EARLY SO THAT WE CAN CAPTURE, YOU KNOW, IF THERE ARE, FOR EXAMPLE, RPG PROJECTS THAT ARE ENDORSED AT THE JUNE BOARD OF DIRECTORS, THEN WE WOULD TRY TO INCORPORATE THOSE PROJECTS INTO THE STUDY CASES.

WE'LL BUILD THOSE STUDY CASES.

AND THEN ROUGHLY LATE SEPTEMBER IS WHEN WE WOULD START THE STEADY STATE ANALYSIS WITH THE STABILITY SCREENING STARTING SHORTLY THEREAFTER, FINAL REPORT AT THE END OF JANUARY.

UM, AND THEN THAT GIVES THAT 30 DAY, THAT 30 DAY, UH, COMMITMENT WINDOW IS ROUGHLY THE MONTH OF, OF FEBRUARY.

UM, THAT, THAT THEN LEADS TO THE, UH, BATCH, UH, OR, SORRY, THE FACT TWO STABILITY STUDY.

SO THAT'S, WE DIDN'T TALK ABOUT THAT, THAT'S NOT REALLY IN THE PIGGER, BUT IT'S A COMPLIANCE OBLIGATION THAT ERCOT WOULD HAVE WHERE WE WOULD BE DOING A FULL STABILITY STUDY.

UM, BUT THEN THE BATCH REFINEMENT STUDY WOULD START, UM, UH, ROUGHLY MARCH 1ST AND GO THROUGH JUNE,

[01:10:01]

HAVE A RPG COMMENT PERIOD, RESOLVE ANY COMMENTS.

AND THEN THAT LEADS US TO A, UM, AUGUST TAC AND SEPTEMBER BOARD ENDORSEMENT, UH, IN 2027 FOR WHATEVER TRANSMISSION PROJECTS COME OUT OF THE REFINEMENT STUDY.

OKAY.

SO I'M GONNA WALK THROUGH EACH OF THOSE, UH, STEPS THAT ARE LAID OUT.

UM, IF YOU SEE, WE, WE'VE GOT THESE, UH, STEPS HERE, UH, ONE THROUGH NINE ON THE, UH, LEFT ON, ON THIS, UH, GANTT CHART VIEW.

I WANNA WALK THROUGH EACH OF THOSE AND WHAT, WHAT WOULD THOSE MEAN? UH, SO FOR THE CASE BUILD, FOR BATCH ZERO, UM, THE, THERE'S CERTAIN INFORMATION THAT WE WILL NEED FROM THE TD T DSPS, UH, AND, AND SO WE NEED, UH, THE TSPS TO SEND US THAT INFORMATION.

UH, WE WOULD THEN, UH, UH, BUILD THE CASES AND WE, WE WOULD MAKE OUR DETERMINATION REGARDING WHICH LOADS ARE MEETING THE, UH, CRITERIA TO BE INCLUDED IN, UH, BATCH ZERO, UH, BASED ON THE INFORMATION THAT, THAT THE TDSP ARE GIVING US.

UM, AND THEN WE WOULD, UH, OF COURSE BUILD THE CASES.

UM, STATE STEADY STATE ANALYSIS.

I THINK WE, WE'VE TALKED ABOUT THIS PREVIOUSLY.

UM, N NOTHING HAS REALLY CHANGED, UH, SINCE THE, UH, LAST WORKSHOP.

SO I'LL JUST, UH, SKIMM OVER THAT REAL FAST.

UM, THE, UH, STABILITY SCREENING, I, I THINK THIS IS MORE A CLARIFICATION IS, YOU KNOW, HASN'T REALLY CHANGED, BUT IT'S, UM, YOU KNOW, WE'RE, WE'RE LOOKING AT, UH, ANY STABILITY SCREENING CRITERIA VIOLATIONS.

UH, THIS IS PRIMARILY A VOLTAGE STABILITY, UH, TYPE ANALYSIS THAT WE'RE RUNNING.

UH, AND SO WE'RE GOING TO, UM, LOOK AT THAT.

WE'RE, WE'RE GONNA DO THAT SCREENING AND SEE, UH, YOU KNOW, HOW MUCH OF THE, UH, PEAK DEMAND CAN WE, CAN WE RELIABLY SERVE EACH YEAR.

UM, AND, AND WE WILL, UM, YOU KNOW, IDENTIFY THOSE, THOSE CONSTRAINTS.

UM, AND THEN, UH, WE WILL PRODUCE A, A FINAL REPORT SUMMARIZING THE RESULTS.

UM, WE'VE SAID THIS BEFORE, SO THIS IS JUST A CLARIFICATION THAT AS, UH, DESIGNED RIGHT NOW ON PIER 1 45, THE 2033 LOAD, UM, UH, WE WILL SET AT THE REQUESTED AMOUNT.

UH, SO THIS IS A YEAR SIX ASSUMPTION THAT WE WOULD BE ABLE TO CONSTRUCT THE TRANSMISSION THAT WOULD BE NECESSARY TO, UH, TO SERVE THE FULL LOAD BY 2033, EVEN IF WE DON'T IDENTIFY WHAT ALL THOSE TRANSMISSION UPGRADES ARE IN THAT, UH, BATCH STUDY TIMEFRAME.

UH, AND THE IDEA HERE IS, UH, IF, IF YOU LOOK AT THAT TIME WINDOW, UH, LEMME GO BACK 'CAUSE I, I, I DIDN'T, UM, TALK ABOUT THIS, BUT THAT, THAT WINDOW OF COMMITMENT LINES UP, UH, WITH THE BEGINNING OF 2027 RTP.

UH, SO THE IDEA HERE IS THAT, UM, THAT YEAR SIX ANALYSIS THAT WE WEREN'T, WEREN'T ABLE TO IDENTIFY ALL THOSE UPGRADES AS PART OF THE, UH, BATCH STUDY, UH, WE, WE WOULD, WOULD BE ABLE TO IDENTIFY ALL THOSE AS PART OF THE 2027 RTP.

UM, AND THEN, UM, YOU OF COURSE, THE INFORMATION, THE FINAL REPORT WOULD BE, UH, USED BY THE, UH, TSPS.

THEY WOULD KNOW WHAT THE, UM, UH, FINANCIAL SECURITY OBLIGATIONS.

AND, AND, YOU KNOW, THIS IS, AGAIN, DEPENDENT ON FINAL RULE FOR 58 41.

UH, BUT WHATEVER WOULD BE NECESSARY, UH, THE IDEA IS THAT THAT, UH, FROM AN ERCOT PERSPECTIVE, THAT, THAT THE INFORMATION WOULD BE INCLUDED IN THE FINAL REPORT.

OF COURSE, THERE'S GONNA BE INFORMATION THAT, THAT ERCOT DOESN'T HAVE, THE, THE TS TSPS OR T DSPS WOULD HAVE THEMSELVES, BUT ANY INFORMATION THAT, THAT THEY WOULD NEED FROM ERCOT WOULD BE INCLUDED IN THE FINAL REPORT.

OKAY? SO THE, UH, DEVELOPER COMMITMENT DEADLINE, UM, THE, UH, IDEA HERE IS THAT THE, UM, THE, THE DEVELOPERS WILL GET A, UH, A MEGAWATT BY YEAR, UH, ALLOCATION.

AND, UM, THEY WOULD THEN NEED TO ENTER INTO THAT BINDING INTERCONNECTION AGREEMENT, UH, BY MARCH 1ST.

UH, THE, THE DETAILS OF WHAT, WHAT ARE, WHAT IS NEEDED TO SATISFY THAT INTERCONNECTION AGREEMENT IS ESSENTIALLY WHATEVER COMES OUT OF 58 41.

UM, SO WE HAVE INCLUDED WHAT, WHAT WE THINK IS THE REQUIREMENTS RIGHT NOW BASED ON THE DRAFT PFP, BUT ULTIMATELY THIS WILL BE, AND AGAIN, THIS IS FEBRUARY OF 27, MARCH 1ST, 2027, WE'RE EXPECTING THAT WE WOULD HAVE THE FINAL 58 41 RULE IN PLACE BY THAT TIME.

SO IT'LL BE CLEAR WHAT THE REQUIREMENTS ARE AT THAT TIME FOR MEETING THE INTERCONNECTION AGREEMENT REQUIREMENTS.

UM, AND THEN ERCOT, WE, WE NEED

[01:15:01]

THE TDSP TO, UH, FORMALLY TELL US, UH, THAT THE LOADS HAVE MET THAT INTERCONNECTION AGREEMENT CRITERIA.

SO WE, WE NEED THAT, THAT FORMAL NOTIFICATION, UH, THAT, THAT THE LOADS HAVE, UH, MET THAT, UM, IF A LOAD, UH, DOES NOT MEET THAT, THEN WE WOULD ASSUME THAT THAT LARGE LOAD HAS WITHDRAWN, UH, THEIR APPLICATION.

UH, SO IT IS NOT LIKE TODAY WHERE LOADS, UM, I GUESS THERE IS A DEADLINE TODAY, BUT I'LL SAY IT'S NOT LIKE IT WAS PREVIOUSLY WHERE YOU COULD KIND OF INDEFINITELY HANG OUT.

UH, THERE WOULD BE A DEFINITE DECISION POINT THAT THE LOAD NEEDS TO MAKE, UH, IN ORDER TO MOVE FORWARD.

WE ARE CONTEMPLATING HAVING A, UM, YOU KNOW, SOME SORT OF, UM, UH, RAMP IN, IN, THIS IS NOT IN THE BATCH, THIS IS NOT IN BIGGER 1 45, BUT IN THE ONGOING, UH, PROCESS, HA HAVING SOME SORT OF KIND OF BRIDGE WHERE IF YOU DIDN'T LIKE THE RESULTS, UH, YOU DON'T HAVE TO START COMPLETELY OVER AGAIN.

UH, YOU WOULD BE ABLE TO GO INTO THE NEXT BATCH.

UH, BUT WE'LL LAY THAT OUT WHEN WE GET TO THAT, UH, THAT BATCH STUDY PROCESS.

UM, BUT THERE, THERE IS A CLEAR DECISION POINT THOUGH, UH, IN, AT, IN, AT THE END OF JAN, BETWEEN THE END OF JANUARY AND MARCH 1ST, WHERE THE LOADS WOULD HAVE TO MAKE THAT DECISION ON IF THEY WANT TO COMMIT OR, OR WITHDRAW.

IF THEY DON'T COMMIT, THEN WE'RE, WE WILL ASSUME THAT THEY, UH, ARE GOING TO WITHDRAW.

UM, AND, AND THEN JUST TO REITERATE, UH, IF THAT LOAD MAKES THAT COMMITMENT, UH, NO MATTER WHAT HAPPENS DOWN THE ROAD, WE WE'RE NOT GOING TO REALLOCATE THOSE MEGAWATTS.

SO IF YOU COMMIT TO 250 MEGAWATTS, THEN WE WOULD NOT GO BACK AND REALLOCATE THAT.

YOU'RE, YOU'RE, UM, DIDN'T USE THIS LANGUAGE IN THE, UH, IN THE PICKER, BUT COLLOQUIALLY IT'S, YOU'RE, YOU'RE LOCKED IN ON THOSE MEGAWATTS.

UH, BUT AT MARCH 1ST, UM, AND WE'VE, UH, TALKED ABOUT THIS REFINEMENT STUDY QUITE A BIT, BUT, UH, YOU KNOW, THE IDEA IS THAT WE WOULD THEN TAKE WHICHEVER LOADS HAVE COMMITTED, THEN WE WOULD, UH, GO THROUGH THIS REFINEMENT PROCESS WHERE WE'RE LOOKING AT THE, UH, THE LOADS, UM, THAT HAVE COMMITTED AND THE TRANSMISSION UPGRADES AND ASSESSING WHETHER THOSE ARE THE RIGHT TRANSMISSION UPGRADES STILL.

UM, YOU KNOW, WE MAY ALSO, YOU KNOW, THIS GIVES US SOME, SOME ADDITIONAL TIME TO LOOK AT ALTERNATIVES, UM, TO, EVEN IF ALL THE LOADS, UM, COMMITTED, UH, YEAH, THERE, THERE'S STILL SOME, UH, TIME PERIOD IN THERE WHERE WE COULD MODIFY THE, THE TRANSMISSION UPGRADES.

UM, BUT AGAIN, THAT DOES NOT AFFECT THE FINANCIAL COMMITMENT OR DOES NOT AFFECT THE MEGAWATTS FROM THE, UH, THE LOADS.

UM, AND THEN THAT REFINEMENT STUDY WOULD RESULT IN A FINAL REPORT AND RECOMMENDED TRANSMISSION FACILITY IMPROVEMENTS THAT WOULD BE SUBMITTED FOR RPG PROJECT REVIEW.

UM, WE, UH, WOULD THEN TAKE THAT THROUGH AND RPG, UH, COMMENT PROCESS, UH, THAT RPG PROJECT CLASSIFICATION.

UH, THE WAY THAT WE'RE THINKING ABOUT THIS IS THAT YOU WOULD, UH, GROUP ALL OF THE TRANSMISSION PROJECTS THAT ARE INCLUDED IN THAT REFINEMENT STUDY AND THAT THAT WOULD BE SUBMITTED AS A SINGLE PACKAGE.

AND, AND SO THAT SINGLE PACKAGE WOULD BE BASED ON, UH, THE, THE TIER CLASSIFICATION WOULD BE BASED ON THAT ENTIRETY OF THAT PACKAGE.

UH, SO IF IT'S, UM, YOU KNOW, FIVE $50 MILLION PROJECTS, THAT WOULD BE, YOU KNOW, AT SOME, SOME TOTAL, THAT WOULD BE A $250 MILLION PROJECT.

IT'D BE A TIER ONE PROJECT.

SO WE WOULD TAKE THAT TO THE BOARD FOR BOARD ENDORSEMENT.

UH, BUT THE REFINEMENT STUDY WOULD ACT AS, OR COTS INDEPENDENT REVIEW.

SO WE WOULD NOT THEN GO AND, AND DO A SEPARATE INDEPENDENT REVIEW OF THAT.

THE REFINEMENT STUDY IS ARCOS, IT'S BOTH THE SUBMITTAL AND THE INDEPENDENT REVIEW FOR THAT, THAT SET OF PROJECTS.

UM, AND THEN, UH, WE WILL GO THROUGH AN RBG, UH, STUDY MODE IF WE HAVE COMMENTS, UH, THAT THE, THE COMMENTS ARE NOT REALLY LOOK, WOULD, WOULD NOT BE, YOU KNOW, DON'T, DON'T SERVE THIS LOAD, DON'T REALLOCATE THE MEGAWATTS.

IT, IT'S, IT'S REALLY MORE REFINEMENT OF THE, THE, UH, TRANSMISSION ALTERNATIVES.

UM, AND THEN WE WOULD, UM, UH, AS, AS NOTED, WE WOULD TAKE THAT TO T AND THE BOARD FOR ENDORSEMENT.

UM, AND, AND THEN THIS, UH, IS NOT, NOT REALLY, UM, PART OF P 1 45, BUT WE WANTED TO REITERATE THIS, UH, IDEA THAT AS LAID DOWN IN P 1 45 AND HEARD THE COMMENTS, UH, IN FROM THE SURVEY AND COMMENTS THIS MORNING ON POTENTIALLY, YOU KNOW, IS A SIX MONTHS STEADY CADENCE, IS THAT THE RIGHT THING? BUT A, A AS WE HAVE AT LEAST, UH, UH, CONTEMPLATED IT, IT IS A SIX MONTH PROCESS, UM, A SIX MONTH CADENCE THAT IS A LONGER PROCESS IF YOU CONSIDER THE REFINEMENT AND, AND, AND THAT, UH, BUT THE, UM, UH, THAT THE CADENCE AT LEAST IS, IS THAT THIS WOULD HAPPEN EVERY SIX MONTHS.

UM, OKAY, SO WITH THAT, THAT'S, THAT'S

[01:20:01]

A LOT OF, UH, GETTING INTO DETAILS.

UM, BUT LET'S, UH, PAUSE AND, UH, TAKE ANY QUESTIONS THAT FOLKS HAVE.

GREAT.

AND I DON'T KNOW IF IT'S CLEAR IN THE, I AM I SENT A MINUTE AGO.

WE WERE GONNA WAIT UNTIL THEY GOT TO THE END AND THEN OPEN THE QUEUE.

SO WE JUST OPENED THE QUEUE.

SO IF YOU'RE ALREADY IN THE QUEUE, GET IN AGAIN BECAUSE THAT WAS THE IDEA SOME, AND THE REASON I'M DOING THIS, AND IF I DIDN'T ARTICULATE IT WELL, SOMETIMES THE SLIDES WILL ANSWER THE QUESTION AND WE JUST WANT TO KEEP THIS AS EFFICIENT AS POSSIBLE.

SO NOW WE'LL START WORKING THROUGH.

AND AGAIN, ALSO, NOTHING THAT JEFF REALLY DID WENT INTO ELIGIBILITY.

THIS IS THE MECHANICS OF HOW THE PROCESS IS RUN AND HOW FIT TOGETHER.

WE HAVE A WHOLE NOTHER SECTION ON, UH, ELIGIBILITY IN THE NEXT PIECE.

SO, ALRIGHT, WITH THAT, WE'LL START THE QUEUE.

DO YOU KNOW WHO'S NUMBER ONE? ALRIGHT, NED, YOU'RE NUMBER ONE.

I FEEL LIKE I GUESSED THE RIGHT NUMBER OF JELLY BEANS IN THE JAR.

THAT'S RIGHT, THAT'S RIGHT.

.

UM, ALL RIGHT.

UH, SO I'VE GOT A, A COUPLE, I THINK SOME OF 'EM WILL BE PRETTY QUICK.

UH, THE FIRST ONE IS ON SLIDE 30, UM, WITH THE JULY 15TH DEADLINE OR, UH, THE, THE REQUIRED PROJECT INFO SUBMITTED FOR INCLUSION.

I, I THINK IN SOME OF THE PRIOR, UH, MATERIALS Y'ALL HAD COMMUNICATED AN EXPECTED EFFECTIVE DATE OF AUGUST 1ST, IS, DOES THIS IMPLY THAT THAT IS CHANGING AND MOVING UP? NO, UM, IT'S, UM, IT, IT, IT'S REALLY, I THINK THE, UM, EFFECTIVE DATE OF THE PIG WOULD BE, UH, TECHNICALLY IF THE, UH, I THINK IF THE COMMISSION APPROVES IT.

AND, UH, SO WAY I'M THINKING ABOUT IT IS THE, UH, BOARD ENDORSES IT ON JUNE ONE OR JUNE TWO.

UH, I THINK THE NEXT 30 DAYS THAT THE, UH, COMMISSION WOULD HAVE TO APPROVE IT WOULD, WOULD BE, OR THEIR NEXT MEETING, 30 DAYS AFTER, WOULD BE JULY 9TH OPEN MEETING, UH, WHICH WOULD MAKE IT EFFECTIVE ON AUGUST 1ST IF WE FOLLOW KIND OF THE NORMAL PROCESS, RIGHT.

UH, SO THAT, THAT IS THE EFFECTIVE DATE.

BUT, YOU KNOW, THAT, THAT CAN LOOK BACK AND SAY THAT JULY 15TH IS OUR CUTOFF FOR, FOR WHEN WE ARE, UH, LOOKING AT, YOU KNOW, THAT CAN, IT CAN LOOK BACK FOR THAT JULY 15TH DATE AND SAY THAT THAT'S OUR CUTOFF DATE FOR WHEN WE WOULD ACCEPT THE, UM, UH, THE, THE PROJECT INFORMATION.

OKAY.

SO Y'ALL ARE LOOKING AT THAT AS KIND OF A, THE, YOU KNOW, IT'S BEEN APPROVED.

IT'S NOT IN EFFECT, BUT IT'S IN, IT'S IN THE, UH, THE, THE GRAY AREA IN BETWEEN.

YES.

OKAY.

UM, OKAY.

WANNA, WANNA THINK A LITTLE BIT ABOUT THAT? YEAH.

AND, AND THAT'S IMPORTANT BECAUSE WE NEED TO START, WE NEED TO GET THOSE CASES BUILT.

WE NEED TO, UM, YEAH, I, I THINK WHAT WE'VE HEARD A LOT OF COMMENTS IS, OR, OR YOU NEED TO HURRY AND START THIS AS SOON AS POSSIBLE SO YOU CAN GET RESULTS AS SOON AS POSSIBLE.

YEAH.

UH, AND SO THAT, THAT'S, THAT THAT'S OUR THINKING THERE.

YEAH.

AND IT'S IMPORTANT TRADE OFFS TO THINK THROUGH IS, YOU KNOW, THE, TRYING TO BE TIGHT WITH THE PROCEDURAL, UH, YOU KNOW, NOT, NOT HAVING THINGS BE RETROACTIVE IN APPLICATION, BUT UM, ALSO BE ABLE TO MOVE FAST.

SO, UM, BUT I APPRECIATE THAT THERE'S A TENSION YOU'RE TRYING TO BALANCE AND, AND RESOLVE THERE.

SO, UM, YEAH.

YEAH.

AND NOT TO BELABOR THAT, BUT THE, UM, THE, THE TIE IN WITH THE 2027 RTPI, I THINK IS IMPORTANT.

SO WE, WE WANT TO HAVE THAT COMMITMENT WINDOW BE SUCH THAT THE, THE LOADS THAT ARE COMMITTED ARE COMMITTED IN A TIMEFRAME WHERE, WHERE WE, WE WOULD BE ABLE TO GET THEM INTO THE 2027 RTP.

YEAH.

AND GONNA APPRECIATE THAT FROM THE PRIOR DISCUSSION.

SO, SO THAT, THAT'S HOW WE KIND OF BACK UP AND GET TO JULY 15TH.

OKAY.

MAKES SENSE.

UM, SO NEXT ONE IS, UH, CLARIFICATION ON SLIDE 31.

UM, YOU'VE GOT THE, THE GREEN BOX IN THE MIDDLE BOTTOM SAYS PROVIDE COST ESTIMATES, AND WE'RE JUST TALKING ABOUT HAVING A POINT IN TIME COST ESTIMATE AT THE END OF THE BATCH THAT WOULD, UH, FEED INTO THE BOTTOM LEFT BOX ON SIGNING THE INTERCONNECTION AGREEMENT.

SO WOULD THERE BE A TRUE UP WITHIN THE THREE MONTHS OF THE, UH, THE REFINEMENT OR IT IT WOULD BE LOCKED IN AT THE INTERCONNECTION AGREEMENT? UM, POINT, YEAH.

SO, UM, AGAIN, AND I'LL, YOU KNOW, 58 41 IS SUBJECT TO CHANGE, BUT I THINK THE, THE WAY THAT WE ARE READING THAT IS THAT IS A POINT IN TIME COMMITMENT.

OKAY.

UH, SO IT IS AT THE END OF THAT TIME, THE LOAD NEEDS TO MAKE THAT FINANCIAL COMMITMENT.

OKAY.

AND ALLOCATION WITHIN, YOU KNOW, IF YOU'VE GOT A BUNCH OF PROJECTS THAT ARE ALL CONTRIBUTING TO DIFFERENT UPGRADES, UH, WILL YOU BE DOING THAT ON JUST A, YOU KNOW, EVEN SPLIT? OR IS THERE A PERCENTAGE ALLOCATION ON HOW CONTRIBUTIONS TO A PARTICULAR UPGRADE WOULD NEED TO BE, UH, CONSIDERED THERE? UM, I, I, I THINK THAT IS, UM, I THINK RIGHT NOW THAT WE'RE, WE'RE THINKING WE SHOULD WAIT ON 58 41 THAT, THAT, THAT WILL LIKELY PROVIDE CLARITY ON WHAT WE SHOULD DO THERE.

OKAY.

AND THEN LAST ONE, YEAH, IF YOU DON'T MIND, I'LL JUST JUMP IN AND JUST REMIND FOLKS THAT THE, UM, THE PRIMARY COMMITMENT THAT'S BEING CONTEMPLATED IN 5 8 4 8 1

[01:25:01]

IS ABOUT THE SECURITY, RIGHT? YEAH.

AND NOT NECESSARILY ABOUT THE CONSTRUCTION AND NATIVE OR THE CONTRIBUTION AND NATIVE CONSTRUCTION RELATED TO THE DIRECT COST TO INTERCONNECT.

AND SO I KNOW THIS IS A POINT OF CONTENTION AND I KNOW THAT THE RULE THAT'S BEFORE THE COMMISSIONERS, UM, FOR THURSDAY, UM, YOU KNOW, I THINK LOTS OF PEOPLE ARE WEIGHING IN ON KIND OF THE TIMING AND DOLLAR AMOUNTS OF THOSE SECURITY COMMITMENTS AS THEY TIE INTO THE INTERCONNECTION AGREEMENT.

AND THEN HOW THAT PLAYS INTO WHAT YOUR KAYAK, UM, UH, CONTRIBUTIONS ARE AND, UM, OTHER TYPES OF FINANCIAL SECURITY.

I THINK THOSE ARE KIND OF A WATERFALL EFFECT AFTER THAT.

OKAY.

I APPRECIATE THAT.

I CLARIFICATION.

UM, LAST, LAST QUESTION I HAD WAS ON SLIDE 39, UM, AND THE PLAN TO HAVE ALL OF THE REFINEMENT PROJECTS GO THROUGH A SINGLE RPG PROJECT, UM, IN COMBINATION.

IS THERE A REASON WHY ERCOT WOULDN'T WANT TO MAYBE CONSIDER DOING SOME MAYBE SUB-REGIONAL, UM, ALLOCATION? SO INSTEAD OF LIKE ONE BIG ONE FOR THE ENTIRE STATE OF TEXAS, YOU MIGHT HAVE ONE THAT'S APPLICABLE FOR WEST TEXAS, ONE FOR SOUTH TEXAS, ONE FOR NORTH, ONE FOR EAST.

YEAH.

I, I THINK EFFICIENCY, IT, IT'S, UH, OUR, OUR THINKING HERE IS, IS WE JUST WANNA BE AS EFFICIENT AS POSSIBLE.

SO, UM, YOU SUBMIT A SINGLE PACKAGE OF, OF PROJECTS, WE THOUGHT THAT THAT WOULD BE MOST EFFICIENT RATHER THAN PREPARING, YOU KNOW, HAVING TO MAKE A JUDGMENT CALL, OKAY, IS, IS THIS, YOU KNOW, IS THIS LINE UPGRADE? IS THAT GOOD WITH THIS? YOU KNOW, OR, OR THIS REGION OR THAT REGION IS JUST, JUST PUT IT ALL IN ONE PACKAGE.

OKAY.

THE ONE THING THAT STOOD OUT TO, TO US IN REVIEWING THAT WAS YOU COULD GET INTO, UH, KIND OF A NUMBER OF, A LOT OF COMMENTS AROUND, UH, A SINGLE PACKAGE AND THEN, YOU KNOW, THERE MAY BE ONE REGION WHERE IT'S PRETTY CLEAR AND THERE ISN'T A WHOLE LOT OF DEBATE ABOUT IT, BUT THEN THE COMMENTS ON ANOTHER REGION COULD HOLD UP THE OTHER.

SO THERE MIGHT BE A, THERE MAY BE SOME NEED TO CONSIDER, UH, WHETHER YOU CAN MOVE FASTER IF YOU DON'T DO IT ALL AS A SINGLE SHOT, BUT A COUPLE OF LARGE AGGREGATED SHOTS.

OKAY.

OKAY.

ALRIGHT, NEXT QUESTION.

MARTHA.

THANKS MATT.

MARTHA HENSON WITH ENCORE ON SLIDE 30 WHERE IT SPOKE TO THE, UM, JULY 15TH, 2026 DATE WHERE YOU NEED ALL THE INFORMATION FROM THE TSPS, ARE YOU EXPECTING THAT TO LOOK LIKE AN RFI FROM ERCOT TO TSPS? MAYBE LIKE SOMETHING SIMILAR TO THE R-T-P-R-F-I OR HAVE YOU THOUGHT YET ABOUT WHAT THE FORMAT OF THAT IS GONNA LOOK LIKE? UM, I, I HAVE NOT THOUGHT A A LOT ABOUT THAT.

UH, I, I THINK THE, UM, JUST TO BE FRANK, I, I THINK THAT, UH, WHAT WE HAD ENVISIONED WAS MORE, UH, THAT THIS IS A REQUIREMENT IN THE PLANNING GUIDE FOR THE TSPS TO PROVIDE THIS INFORMATION TO US.

AND, AND SO IT WOULDN'T TAKE, WOULD NOT NEED AN RFI, THE TSPS WOULD JUST, UH, PROVIDE THE INFORMATION, UH, THAT SAID IF, IF IT WOULD BE HELPFUL IF WE PROVIDED A TEMPLATE OR YOU KNOW, SOMETHING LIKE THAT, THEN I THINK WE'RE OPEN TO THAT.

YEAH.

UM, I THINK THAT MIGHT BE HELPFUL.

THERE'S A LOT OF INFORMATION THAT YOU'RE GONNA NEED FROM US AND DIFFERENT DATES ATTACHED TO DIFFERENT THINGS.

UM, I GUESS THE OTHER THING ALONG THAT LINES, UM, IT'D BE HELPFUL IF ERCOT CONSIDER, COULD CONSIDER WOULD BE WHETHER THERE'S SOME WAY YOU COULD STANDARDIZE THE, AT ALL THE VARIOUS ATTESTATIONS THAT ARE NEEDED, LIKE FOR OUR EQUIPMENT, THE CUSTOMER'S EQUIPMENT AND THE SITE DEVELOPMENT AND STUFF.

LIKE IF, I THINK IT'LL BE EASIER BOTH ON YOU AND ON US TO HAVE A STANDARD FORM FOR THAT, THAT THAT COULD BE USED SO WE'RE NOT SEEING LIKE 20 DIFFERENT RIGHT.

TYPES OF ATTESTATIONS.

YEAH.

YEAH.

THAT, THAT'S GOOD FEEDBACK.

THANK YOU.

THANKS.

ALRIGHT, NEXT.

KEVIN HANSEN? YEAH, UH, JEFF, MY QUESTION WAS, JUST MAKE SURE, I'M TRYING TO UNDERSTAND THIS, IS THAT RIGHT NOW YEAR FIVE, WOULD IT BE LIMITED BY THE AMOUNT OF LOAD BUT YEAR SIX COULD THEORETICALLY BE INFINITE LOADS ADDED AND THE CASES WOULD STILL SOLVE? 'CAUSE WE HAVE INFINITE GENERATION FROM BIGGER 1 27? YEAH, I THINK THEORETICALLY THAT'S CORRECT.

PRACTICALLY.

OKAY.

I THINK THAT'S, I'M JUST NOT LIKELY MAKING SURE THERE'S NO LIMITATION ON YOUR SEX.

CORRECT.

OKAY.

THANKS.

ALRIGHT, NEXT QUESTION.

UH, SHANNON CARAWAY, SAME SLIDES OR WHAT AS HIS WAS 28? SO HERE ON THIS STUDY HORIZON, YOU'RE SAYING 28 THROUGH 32, I WAS PREVIOUSLY SORT OF EXPECTING IT'D BE 27 THROUGH 31.

SO FOR A LOAD THAT'S ENERGIZING IN 27, HOW ARE YOU, HOW ARE YOU TREATING THAT HERE? UM, I, SO I THINK THE, UH, LOADS THAT ARE ENERGIZING IN 27, UM, I, I, I THINK THAT, UH, THE EARLIEST,

[01:30:01]

IF YOU LOOK AT THE, UM, UH, I THINK IT'S FOURTH QUARTER IF I REMEMBER RIGHT, OR IS THE EARLIEST YOU COULD ENERGIZE IN 27 IF YOU ARE IN THIS, UM, UH, IN, IN, IN, IN THIS STUDY, THAT'S WHERE YOU HAD TO PROVIDE, UH, PROOF THAT YOU HAD MET CERTAIN CRITERIA YOU COULD, BUT IT WASN'T, YOU COULDN'T ENERGIZE BEFORE THEN, IT'S ANY WORD THEN.

AND EARLIER YOU HAD TO PROVIDE PROOF THAT YOU WERE READY.

YEAH.

SO, HEY, JEFF AG WAS WILLING TO PIPE IN ON THIS ONE IF YOU WANT.

YEAH.

OKAY.

YEAH, AG GO AHEAD.

HEY, UH, THIS IS AG SPRINGER ERCOT, UM, SHANNON, THE, THE, THE WAY THAT THIS IS, UH, STRUCTURED, UM, IS IS VERY SIMILAR TO THE FLOW CHART THAT WAS SHOWN AT THE FEBRUARY 26TH WORKSHOP.

THAT, UH, THERE IS A PATH FOR LOADS ENERGIZING IN 2027 TO DEMONSTRATE THAT THEY HAVE, UH, SUFFICIENT DEVELOPMENT PROCESS PROGRESS FOR THAT TO BE REALISTIC.

AND, UH, AS A RESULT, IF THEY MEET ALL THE CRITERIA, THEN THEY'RE INCLUDED AS BASE LOAD, UM, IN THE EVENT THAT THE, THE LOAD IS NOT ABLE TO DEMONSTRATE THAT IT IS INCLUDED AS STUDIED LOAD, BUT WITH A 2028 JANUARY 1ST, 2028 IMMUNIZATION DATE OR LATER.

UH, SO THAT'S BASED ON THE STAKEHOLDER FEEDBACK THAT, YOU KNOW, LOADS THAT WERE NOT ALREADY UNDER CONSTRUCTION WERE REALLY HAD NO REALISTIC PATH TO ENERGIZING IN 2027.

ALRIGHT.

I THINK THAT'S REALLY HELPFUL.

SO LET ME RESTATE AND SEE IF THIS IS WHAT YOU'RE SEEING.

IF YOU'RE A 27 PROJECT AND YOU MEET THE CRITERIA, YOU COME IN AS BASE LOAD, THE 2028 THROUGH 32 IS REALLY THE YEARS YOU'RE STUDYING FOR ALLOCATION.

IS THAT A FAIR STATEMENT? YES, I'D SAY THAT'S ACCURATE.

OKAY.

THAT'S SUPER HELPFUL.

VERY, UH, CLEAR.

NEXT QUESTION ARE COMMENTS ON 31 OVER AT THE RIGHT SECOND BOX? YOU'VE GOT BILL CASES AND POST ON MIS CERTIFIED AREA.

THANK YOU FOR THAT.

UH, I THINK THAT'S HELPFUL.

I THINK WE SHOULD HAVE ALSO A POST ON MIS CERTIFIED AREA AFTER THE COMMUNICATE RESULTS PIECE.

SO IN OTHER WORDS, WHAT'S COMING OUT OF IT, THERE SHOULD BE A WHOLE SET OF TRANSMISSION UPGRADES THAT WERE ASSUMED.

SO LET'S, LET'S GET, LET'S ADD A FLOW A BOX TO GET THAT PUBLISHED AS WELL WOULD BE REALLY HELPFUL.

OKAY.

YEAH, I THINK WE COULD DO THAT.

THANKS.

ALL RIGHT, THANK YOU.

NEXT UP IS LEE CHER.

HEY, GOOD MORNING.

UM, BASED UPON THE, UH, FLOW CHART THAT AG AND SHANNON WERE JUST DISCUSSING, UM, WHEN YOU GO TO SLIDE 30, THERE, THERE SEEMS TO BE A WAY FOR A LOAD THAT HAS AN ENERGIZATION DATE IN 2028 TO MAKE IT INTO BATCH ZERO AS LOAD THAT IS NOT CONSIDERED FOR REALLOCATION.

UM, BUT THAT LOAD WOULD HAVE TO HAVE MET THE FULL INTERCONNECTION AGREEMENT CRITERIA BEFORE THE JULY 15TH DEADLINE.

UM, AND THEN IT'S ALSO SAYING HERE THAT THAT LOAD NEEDS TO MEET THE FULL INTERCONNECTION CRITERIA BY MARCH 1ST, 2027.

WOULDN'T IT HAVE ALREADY HAD TO MEET THAT CRITERIA? IS THAT JUST A UNIQUE CASE OR AM I UNDERSTANDING THIS INCORRECTLY? YEAH, AND WE MAY, UH, MIGHT GET INTO THIS A LITTLE BIT MORE, UM, LA LATER ON IN THE, IN THE PRESENTATION, BUT I, I THINK IT IS, UM, THERE ARE LOADS THAT WILL BE CONSIDERED, UM, UH, NOT, NOT SUBJECT TO TU IN FIRM, UH, IF YOU WILL, IN BACHELOR LAW.

AND THERE ARE OTHER LOADS THAT IN BATCH ZERO WILL BE, UH, STUDIED AND ALLOCATED MEGAWATTS.

UM, THE, UH, THAT FIRMNESS, I THINK, UH, THAT THOSE, THOSE LOADS THAT ARE NOT RESTUDIED, UH, I THINK THAT THAT DATE IS, UH, JULY 15TH TO, TO MEET THAT.

BUT THE LOADS THAT ARE STUDIED, THEIR INTERCONNECTION AGREEMENT DATE IS MARCH 1ST OR DEADLINE I SHOULD SAY.

OKAY.

THAT'S VERY HELPFUL AND THAT MAKES A LOT OF SENSE.

LAST QUESTION IS, UM, UNRELATED, IT'S ON THE, UH, A PREVIOUS SLIDE.

I'M NOT SURE REMEMBER WHICH ONE, BUT IT'S THE NO SOLAR SCENARIO.

BUT MY QUESTION IS, SINCE SOLAR IS SO COMMONLY MATCHED WITH BATTERIES AND THE CHANCES OF A NO WIND NIGHT TO CHARGE BATTERIES AND THEN A NO SOLAR DAY, THE DAY FOLLOWING IS, IS PRETTY LOW.

AND ALSO ERCOT HAS THE ABILITY TO CAR CURTAIL LARGE LOADS IF EMERGENCIES ARISE, YOU KNOW, BECAUSE OF THE SENATE BILL SIX ARE, ARE WE SURE THAT IT'S NECESSARY TO INCLUDE A NO SOLAR SCENARIO? IT SEEMS LIKE IT'S, UM, SELF-LIMITING IN A SENSE BECAUSE OF THOSE PROTECTIONS.

[01:35:02]

S SO, UM, A COUPLE CLARIFICATIONS.

SO, UH, I, UH, THE WAY THAT WE ARE THINKING, IF I'M UNDERSTANDING THE, UM, THE SECTION YOU'RE REFERRING TO OUTTA SB SIX, UH, CORRECTLY, THE WAY, THE WAY THAT WE WERE THINKING ABOUT THAT IS THAT THAT'S REALLY A FOR SYSTEM WIDE EMERGENCIES.

SO THAT, UH, CURTAILMENT PIECE WOULD NOT BE APPLICABLE FOR, UH, TRANSMISSION, UH, TO MANAGE TRANSMISSION CONSTRAINTS.

THAT, THAT, THAT'S REALLY A SYSTEMWIDE, UH, ENERGY EMERGENCY.

UM, AND SO WOULD, WOULD NOT WANT TO RELY ON THE LOADS FOR, YOU KNOW, E EVERY DAY THE, THE SUNSETS MANAGING TRANSMISSION CONSTRAINT.

UM, AND, AND SO WE, WE DO SEE THAT THIS, AND THIS SHOWS UP QUITE A BIT IN REAL TIME NOW, UH, TH THIS IS A CRITICAL OPERATING CONDITION THAT WE NEED TO STUDY.

IS THAT NO SOLAR CASE? NOW YOU MENTIONED BATTERIES.

I THINK THERE, THERE WILL BE A, UH, AN ASSUMPTION ON, UH, YOU KNOW, SOME OUTPUT FROM THE, THE BATTERIES.

I DON'T KNOW WHAT THAT IS OFF THE TOP OF MY HEAD.

I'D HAVE TO GO BACK AND TALK TO THE, UM, THE ENGINEERING TEAM.

UH, BUT THERE, THERE IS SOME ASSUMPTION THERE THAT YOU WOULD GET SOMETHING FROM THE BATTERIES, UH, AT THAT NO SOLAR TIME.

UNDERSTOOD.

THANKS.

ALL RIGHT.

NEXT QUESTION.

OOPS.

GOT COVERED UP THERE, JOEL, GO AHEAD.

YEAH, UM, SLIDE 38 PLEASE.

SO IN THIS, UM, SORT OF REFINEMENT AND, AND THE IDEA THAT, UM, MEGAWATTS THAT HAVE BEEN COMMITTED TO AREN'T SUBJECT TO REALLOCATION, DOES THAT INCLUDE THE RAMP SCHEDULE? IS THAT, IS THAT CORRECT? YES, AS WELL.

SO EVEN IF THE REFINEMENT RESULTS IN TRANSMISSION PROJECTS THAT ARE GONNA TAKE LONGER, YOU'RE NOT GONNA CHANGE THE RAMP SCHEDULES OF THE LOADS? YEAH, THAT I, I WOULD MAYBE SAY THAT THE OTHER WAY AROUND IS THAT A, THE TRANSMISSION PLAN CAN, THE, THE ALTERNATIVE TRANSMISSION PROJECTS WOULD NOT BE CONSIDERED VALID IF THEY CAN'T MEET THE RAMP SCHEDULE THAT HAS BEEN COMMITTED TO.

OKAY.

THANK YOU.

ALL RIGHT.

NEXT CLAYTON GREER CLAYTON, IF YOU'RE TALKING, WE DON'T HEAR YOU YET.

UH, SORRY, I WAS MUTED.

YEAH.

UH, SLIDE 31, PLEASE.

I THINK YOU CORRECTLY SHOW IN THERE THE BACK AND FORTH THAT WOULD, UNDER THIS CURRENT STYLE PROCESS, YOU'RE GONNA HAVE A MASSIVE BACK AND FORTH BETWEEN THE, UH, THE PERFORMING THE STEADY STATES AND THEN, UH, ALLOWING THE TSPS TO REVIEW THOSE, UM, WITH WHAT WE SAW, UH, WITH THE GRID ASRA TOOL.

ARE YOU NOT THINKING OF USING GRID ASRA, I GUESS ON THIS? UM, YOU'RE, UH, YOU'RE PUTTING ME IN AN AWKWARD SPOT, GLEN.

UH, 'CAUSE WE, I, I, SO I'LL, I'LL SAY, UM, WE ARE CURRENTLY EVALUATING, UH, DIFFERENT, UH, SOFTWARE TOOLS THAT COULD HELP WITH THIS PROCESS.

UH, I THINK OUR, OUR EXPECTATION IS THAT FOR, UH, BATCH ZERO, UH, THAT WE WILL BE USING THE, UH, TOOLS THAT WE CURRENTLY HAVE.

UM, NOT SURE YET ABOUT THE ONGOING PROCESS, BUT, UH, I THINK WE'RE, WE'RE USING CURRENT TOOLS, WHICH ARE, YOU KNOW, PRIMARILY GONNA BE POWER WORLD AND PSSE FOR, FOR RUNNING THE ANALYSIS.

UM, BUT, UH, YOU KNOW, I, I WILL ACKNOWLEDGE THAT WE ARE LOOKING AT VARIOUS SOFTWARE TOOLS FOR SPEEDING UP THE PROCESS GOING FORWARD.

OKAY.

I, I, I GUESS I, I'M A LITTLE CONFUSED AT HOW WE THINK WE'RE GONNA ACTUALLY GET THIS TO SOLVE.

I, YOU KNOW, FROM YOUR PREVIOUS PRESENTATION, IT LOOKS LIKE YOU'RE GONNA TRY TO PUT 140 GIGS THROUGH THIS FIRST BATCH IF IT ALL, I MEAN, DEPENDING ON HOW THE, THE RULE COMES OUT AND IF PEOPLE POST THEIR, THEIR SECURITY AND WHATNOT.

UM, BUT, YOU KNOW, IT'S TAKEN OVER A YEAR FOR THE RPG PROCESS TO PROCESS A FOUR, UH, GIGAWATT UPGRADE IN THE SOUTHERN DALLAS AREAS, THIR, YOU KNOW, SO IT'S GOING ON THIR OVER 13 MONTHS FOR THAT.

SO, YOU KNOW, I, I'M NOT SURE, YOU KNOW, THERE'S A LOT OF WAYS THAT THIS COULD NOT BE SUCCESSFUL.

AND I, I THINK THAT IF YOU DON'T ADOPT SOME OF THESE TOOLS, YOU'RE NOT GOING TO BE SUCCESSFUL IF YOU'RE TRYING TO CLEAR THAT MUCH LOAD AND COME UP WITH THAT MANY PROJECTS THAT HAVE TO GO THROUGH THAT COMPLEX OF A STR OF A, OF A STRATEGY WITH THE, THE TSPS, YOU KNOW, NOT WORKING, YOU KNOW, WORKING INDEPENDENTLY AND YOU'RE THROWING PROJECTS AT THEM AND THEN THEY'RE PROVIDING FEEDBACK BACK.

I, I, I JUST DON'T KNOW HOW THIS WORKS.

YEAH, I, I APPRECIATE THE COMMENT AND I'LL, I'LL JUST SAY, YEAH, WE, WE UNDERSTAND THE, UH, MODELING CHALLENGES AND, UM, ARE ACTIVELY LOOKING FOR, UM, WAYS TO RESOLVE THOSE CHALLENGES.

[01:40:02]

OKAY, GOOD.

UH, THAT'S GOOD TO HEAR.

AND THEN ON THE, UM, I, I FORGET THE SLIDE WHERE YOU'RE ASKING FOR, UM, AFFIDAVITS FROM THE, FROM THE TSPS ON WHAT LOADS THAT, THAT PROCESS PROBABLY NEEDS TO BE AUTOMATED TO WHERE YOU'RE CLICKING BOXES, YOU KNOW WHO, WHO POSTED AND WHO DIDN'T, SO THAT YOU'RE NOT GOING THROUGH A MA YOU KNOW, LIKE PAPERWORK THROUGH, UH, DO AN EXECUTIVE'S DESK SIGNING OFF ON EACH INDIVIDUAL PROJECT.

'CAUSE IT'S FOR LIKE ENCORE FOR INSTANCE, THAT'S PROBABLY GONNA BE, YOU KNOW, QUITE A FEW PROJECTS THAT THEY'RE HAVING TO PROCESS.

SO I WOULD SUGGEST MAYBE ON THE BACKEND, I MEAN, I KNOW THAT, THAT YOU'RE LOOKING AT ALL THESE IMPROVEMENTS, BUT THAT WHAT THAT SEEMS LIKE LOW HANGING FRUIT TO TRY TO MAKE THAT A MORE AUTOMATED PROCESS.

THANKS.

OKAY.

THANK YOU.

ALL RIGHT.

THANK CLAYTON.

CHRIS MATTIS, UH, CHRIS MONTES, GOOGLE.

THIS IS ON SLIDE 42.

AND SO HERE'S WHERE I THINK MAYBE WE'RE JUST HAVING COMMUNICATION ISSUES ABOUT WHAT'S SIX MONTHS, WHAT'S NINE MONTHS AND WHAT'S A YEAR? BECAUSE TO ME THIS LOOKS LIKE A NINE MONTH PROCESS, AND I THINK Y'ALL WOULD CALL IT A SIX MONTH PROCESS, BUT THE DELIVERABLE IS AT THE END OF, WELL, A LITTLE MORE THAN NINE MONTHS.

IF I THINK MAYBE, AND, AND I'M OPEN TO FEEDBACK ON THIS, I THINK I WOULD JUST CALL THIS ALL, YOU KNOW, THE NINE MONTH BATCH PROCESS, BECAUSE IT'S GONNA INCLUDE THE REFINEMENT, IT'S GONNA INCLUDE THE TRANSMISSION PLAN FINALIZATION, AND STAKEHOLDERS WOULD PROBABLY FEEL A LOT MORE COMFORTABLE BECAUSE THEN THEY, AGAIN, KNOW THE OUTCOMES OF THIS ENTIRE THING.

IT'S NOT JUST LIKE, YOU KNOW, WE RUN THE, THE FIRST STUDY STATE AND THAT'S THE BATCH PROCESS.

NO, IT'S, WE RUN THE STUDY STATE, WE DO THE REFINEMENT, WE GET TO THE TRANSMISSION PLAN FINALIZATION, AND THAT'S THE BATCH PROCESS.

SO IF THIS IS LIKE CLOSER TO THE SIX MONTHS THAT YOU ARE REFERRING TO, AND YOU, YOU CAN COMMIT TO THE REFINEMENT AND TRANSMISSION PLAN FINALIZATION AT THE END OF JANUARY, Y YEAH.

LIKE LOOSELY, I GUESS THAT'S LIKE A 12 MONTH PROCESS RIGHT ON THERE.

YEAH.

WELL, O OKAY.

YEAH.

THE, THE SEMANTICS I THINK WE HAVEN'T BEEN CLEAR ON.

YEAH.

YEAH.

I, I THINK IT IS IF YOU LOOK AT REALLY THAT JULY 15TH AS THE START DATE SAY FOR, FOR THAT, THAT THAT'S WHEN WE NEED THE INFORMATION.

YEAH.

AND EVEN REALLY, YOU KNOW, WE WE'RE PROBABLY STARTING IN JUNE TO BUILD THOSE CASES, UHHUH , UM, THE FINAL BOARD ENDORSEMENT OF THOSE PROJECTS ISN'T UNTIL SEPTEMBER OF 2027.

OKAY.

SO THAT, THAT PROCESS IS ACTUALLY MAYBE A 15 MONTH PROCESS.

YEAH.

BUT I THINK WHAT IS PROPOSED HERE IS THAT YOU'RE RUNNING THAT, CALL IT A 15 MONTH PROCESS ON A SIX MONTH CADENCE.

THAT'S FINE TOO.

I LIKE THE CADENCE OF GOING EVERY SIX MONTHS WITH A PROVIDED, YOU KNOW, IN THE NEXT SIX MONTHS WE HAVE THE BASELINE FROM THE PRIOR STUDY TO MAKE IT GO FORWARD.

I THINK, I THINK THIS QUE THE QUESTION HAS BEEN A SEMANTICS ISSUE.

'CAUSE I LIKE THIS, BUT THIS IS, YOU KNOW, CLOSER TO LIKE A 12 MONTH ACTUAL PROCESS PLUS THE BOARD TIME FOR APPROVAL.

SO MAYBE WE ARE ACTUALLY TALKING THE SAME THING HERE.

OKAY.

IT'S A SIX MONTH CADENCE, WHICH IS FINE.

CORRECT.

BUT IT IS A 12 ISH MONTH PROCESS THAT COMES WITH, UH, BATCH REFINEMENT AND TRANSMISSION PLAN FINALIZATION.

SO IF WE COULD JUST CLARIFY THAT SOMEHOW.

YEAH.

OKAY.

UM, .

YEAH.

O OKAY.

YEAH, WE'LL, WE'LL THINK ABOUT HOW TO COMMUNICATE THAT BETTER.

YOU KNOW, I, I THINK, UM, IN, IN THE, UH, LIKE PC CHAIRMAN SAID THIS EARLY AT, AT ONE OF THE, THE OPEN MEETINGS THAT THERE ARE TRADE OFFS HERE.

YEAH.

UH, IN, IN HOW WE DO THIS.

THE, THE, THE PARTICULAR TRADE OFF THAT WE'RE TRYING TO MAKE WITH A SIX MONTH CADENCE IS, UH, YOU HAVE SPEED, BUT THERE ARE THINGS THAT ARE RUNNING IN PARALLEL, RIGHT.

IF YOU DO THAT AND THAT, THAT PARALLEL, I, I THINK WE'RE, WE'RE, WE'VE HEARD FEEDBACK FROM, UH, THE, UM, UH, YOU KNOW, VARIOUS STAKEHOLDERS IN PREVIOUS WORKSHOPS IS THAT THAT PARALLEL EFFORT MEANS THAT THERE'S, UH, I, I THINK THAT'S MORE FROM A TRANSMISSION PERSPECTIVE IS I, I'M STARTING THIS BATCH WITHOUT KNOWING WHAT THE FINAL TRANSMISSION SOLUTION IS FROM THE PREVIOUS BATCH.

AND, AND THERE, THERE ARE, UH, CHALLENGES WITH DOING THAT.

UH, IF YOU'RE RUNNING A SIX MONTH CADENCE, YOU, YOU HAVE TO MAKE THAT TRADE OFF.

UM, I SEE IF YOU, WE COULD LENGTHEN THE CADENCE AND WE COULD DO IT NINE MONTH CADENCE OR 12 MONTH CADENCE.

UH, AND, AND MAYBE THAT, YOU KNOW, WE, WE, YOU KNOW, DON'T HAVE THAT TO MAKE THAT TRADE OFF THEN.

YEAH.

UH, WE'RE, WE'RE, YOU KNOW, WE HAVE TO HAVE THAT UNCERTAINTY IN THE TRANSMISSION PLAN MM-HMM .

UM, BUT, AND THIS LONG-WINDED WAY OF SETTING UP A QUESTION BACK TO YOU

[01:45:01]

IS FROM A, A DEVELOPER PERSPECTIVE, FROM A LOAD PERSPECTIVE, UM, THAT, THAT TRANSMISSION CERTAINTY IS THAT IMPORTANT TO YOU IF IT DOESN'T CHANGE YOUR, YOUR MEGAWATTS? I THINK RIGHT NOW, BECAUSE PAST PROJECTS ARE CURRENTLY BEING TREATED AS FUTURE INDICATORS AT EASE BECAUSE THE LACK OF CERTAIN TRANSMISSION PROJECTS BEING COMPLETED HAS OBJECTIVELY AFFECTED MY ENERGIZATION.

SO I, AND, AND, AND THAT'S JUST A CONSEQUENCE I THINK, OF THE SIZE OF THE LOADS THAT ARE TRYING TO INTERCONNECT, RIGHT? SO I DON'T KNOW HOW WE CAN ENTIRELY SEPARATE THOSE TWO ISSUES.

I, I THINK WITHIN THIS PROCESS WITH YOUR REFINEMENTS, YOU DON'T HAVE TO HAVE A PERFECT BASE MODEL IN THE FIRST SIX MONTHS AND, AND GO ON THE CADENCE AND THE REFINEMENT MAY BE ABLE TO CATCH IT.

SO THERE, THERE'S CERTAINLY SOME QUESTIONS FROM A PROCESS POINT, BUT I WOULD HAVE A VERY HARD TIME ACCEPTING A PROCESS THAT DOESN'T OFFER AT LEAST FIRM TRANSMISSION UPGRADES FOR, FOR RPG APPROVAL AT THE END OF THE REFINEMENT.

BECAUSE I CURRENTLY HAVE PROJECTS NOW THAT CANNOT ENERGIZE WITHOUT THOSE TRANSMISSION PROJECTS.

MM-HMM .

OKAY.

AND SO THAT'S, YEAH, I UNDERSTAND.

I UNDERSTAND WHEN Y'ALL SAY LIKE, WE'LL BE ABLE TO ENERGIZE IR RESPECTIVE OF THIS LIKE TRANSMISSION PIECE COMING OUTTA THERE AND SURE.

WITH THE, WITH YOUR SIX YEAR SORT OF BACKSTOP ON IT, THAT'S PROBABLY POSSIBLE.

I'M NOT GONNA SAY THAT BECAUSE IN THEORY YOU CAN GET MAYBE THE TRANSMISSION UPGRADES IN SIX YEARS.

I'M VERY SKEPTICAL BECAUSE THE CURRENT PROCESS IS DELAYING MY ENERGIZATION FOR PROJECTS THAT HAVE BEEN IN WAITING FOR OVER A YEAR IN RPG.

SO I THINK AS A, A SIX MONTH STUDY FOR PLUS BATCH PROCESS REFINEMENT AS A BATCH PROCESS, THAT'S FINE.

AND THEN TAKING THE BATCH PROCESS AND DO, AND STARTING IT ON A SIX MONTHS CADENCE IS ALSO FINE, BUT IT WILL BE HARD TO DIVORCE, LIKE BATCH ZERO NOT COMING OUT WITH FIRM TRANSMISSION AND BATCH PLAN FINALIZATION IN MAY.

AND TO ME THAT'S NOT A SIX MONTH STUDY, IT'S A 11TH MONTH PROCESS, CALL IT 15 WITH BOARD APPROVAL KIND OF THING.

AND THAT IT, IT'S NOT NECESSARILY A SEMANTICS ISSUE.

IT'S UNDERSTANDING THE DIFFERENCE BETWEEN WHAT IS THE BATCH PROCESS, WHAT IS THE PROCESS I'M TAKING A PROJECT THROUGH, AND WHAT IS THE CADENCE OF ME TO SUBMIT DIFFERENT PROJECTS.

WHEN DO YOU HAVE APPROVAL TO ENERGIZE YOUR LOAD? WHEN, WHEN, WELL RIGHT NOW I HAVE APPROVAL TO ENERGIZE MY LOAD CONTINGENT ON TRANSMISSION UPGRADES.

SO THAT'S, THAT'S WHY I'M SAYING EXACTLY, THAT'S WHY I'M SAYING LIKE THE BATCH PROCESS TO ME IS THE SIX MONTH STUDY PLUS THE REFINEMENT, BUT THE CADENCE IN WHICH YOU'RE GOING THROUGH BATCHES IS, IS A SEPARATE THING.

YEAH.

OKAY.

ALRIGHT.

UH, NEXT BILL BARNES.

THANKS.

UH, JEFF, WHEN ARE TSPS IDENTIFIED FOR THE SPECIFIC PROJECTS IN THE PLAN COMING OUTTA THE BATCH STUDY REFINEMENT STUDY? IS THAT PART OF WHAT YOU'RE DOING? YOU'RE ASSIGNING TSPS EACH PARTICULAR PROJECT OR WHERE DOES THAT HAPPEN? YEAH, I LOST MY SLIDE.

UM, YEAH, SO THAT, UM, I THINK TODAY THAT HAPPENS AT, UM, UH, ACTUALLY I, I DON'T KNOW WHEN THAT HAPPENS.

I THINK IT'S, I THINK THAT HAPPENS AT RPG.

UH, I, I THINK THAT THAT'S WHEN THAT WOULD UM, OCCUR IS AT THE RPG PHASE.

I, I THINK IT'S, YEAH.

AND I'M, I'M SPEAKING A LITTLE BIT OUTTA TURN 'CAUSE I'M, I'M GOING BACK TO MY OLD TRANSMISSION PLANNING DAYS AND I THINK THAT THAT'S A LITTLE BIT MORE SPELLED OUT IN STATUTE NOW.

UM, UH, SO, UM, ACTUALLY I MIGHT NEED A TRANSMISSION PLANNING FOR END TO HELP ANSWER THAT.

BUT I, I THINK THAT THAT'S OCCURRING AT, AS PART OF THAT RPG PROCESS.

OKAY.

BECAUSE THAT'S, I WAS JUST THINKING ABOUT WHAT TAC AND THE BOARD IS APPROVING AND USUALLY THAT'S, UH, THE OUTCOME OF THE RTP WITH A TSP FILING A PROJECT TO, TO MEET THAT, UH, THAT NEED.

AND SO I'M JUST KINDA WONDERING, 'CAUSE IT LOOKS LIKE IN YOUR TIMELINE FOR WHAT PAC APPROVES, IT'S THE REFINEMENT STUDY PLAN.

SO IT FEELS LIKE THAT WOULD HAVE TO HAVE THE TSPS ALREADY IDENTIFIED IN THAT AND THE COST FOR TACKING THE BOARD TO APPROVE IT.

SO I'M JUST CURIOUS WHEN THAT HAPPENS.

AND ALSO WHAT HAPPENS IF TSPS DISAGREE ON WHO GETS WHAT SEGMENT.

YEAH, I THINK PROBABLY STEPPED UP TO THE MIC, SO I MIGHT PHONE A FRIEND THERE.

[01:50:02]

YEAH, PROBABLY NO MORE.

CUT.

SO THE, THE WAY WE, AT LEAST THE, IN P 1 45, THE WAY WE ARE THINKING ABOUT BATCH IS DIFFERENT FROM WHAT RPG IS IN THE CURRENT FORM.

SO, UH, WE ARE TRYING TO EXPEDITE THE PROCESS FOR THE BATCH PROCESS THAT'S LAID OUT IN PI THINK JEFF WILL PROBABLY TALK ABOUT IT LATER, BUT YOU KNOW, I KNOW PEOPLE ARE THINKING ABOUT THE CURRENT RPG CONTEXT AND THIS BATCH IS, THIS IS DIFFERENT.

THIS IS NOT, YOU KNOW, IT IS, IT'S, IT'S DIFFERENT FROM WHAT WE DO IN THE CURRENT RPG.

SO I THINK SOME OF THE THINGS WILL BE ANSWERED THERE.

BUT IF THERE ARE PROJECTS THAT WE CAN PROCESS THROUGH THE BATCH, THAT'S SOMETHING WE NEED TO THINK ABOUT WHETHER IT HAS TO GO THROUGH A REGULAR RPG.

UH, I THINK IT'S ALL, IT'S, THAT'S MY INITIAL THINKING, BUT YOU KNOW, THAT'S SOMETHING WE NEED TO DISCUSS.

OKAY.

SO TAC AND BOARD WILL APPROVE AN OVERALL TRANSMISSION PLAN THAT WILL SHOW COST AND WHAT TRANSMISSION IMPROVEMENTS NEED TO HAPPEN.

WE MAY NOT KNOW THAT IN THE TSPS FOR EACH SEGMENT UNTIL THEY KIND OF WORK THAT OUT AMONGST THEMSELVES AND FILE CCNS AT THE COMMISSION.

UH, YES AND I THINK THE WAY I'M IMAGINING THIS IS BATCH STUDY IS GONNA IDENTIFY PROJECTS THAT CAN BE BUILT AND THAT CAN BE, YOU KNOW, SORTED OUT IN THE PROCESS.

IF THERE ARE PROJECTS THAT CANNOT BE SORTED OUT IN THE BATCH PROCESS, I'M THINKING THAT, YOU KNOW, IT HAS TO GO THROUGH A SEPARATE PROCESS.

SO YEAH, I MEAN I'LL LEAVE IT THERE.

THANKS.

THANKS.

ALRIGHT, THANK YOU.

AND I'M PROBABLY GONNA GO AHEAD AND CUT THE QUEUE AT THIS POINT.

SO SAM JUNG IS THE LAST ONE IN HERE AND SEE IF WE CAN CLEAR OUT.

IT LOOKS BE ABOUT 15 QUESTIONS BEFORE, UH, NOON LUNCH.

SO ON WE GO.

ANGELA, YOU'RE NEXT.

HEY JEFF.

JUDDS HAD A QUICK CLARIFYING QUESTION ON SLIDE 37 ON DEVELOPMENT COMMITMENT.

SO MY QUESTION IS, DO ALL LOADS AND BADGES ZERO NEED TO MEET THE INTERCONNECTION AGREEMENT REQUIREMENTS AT THIS COMMITMENT STAGE? EVEN LOADS THAT ARE NOT SUBJECT TO ALLOCATION, I'M THINKING SPECIFICALLY FOR LOADS THAT ARE OPERATIONAL, UM, AND OR LOADS THAT ARE LATE STAGE AND CAN MEET ALL OF THOSE REQUIREMENTS TO BE CONSIDERED A FIRM LOAD.

UM, DO THEY STILL HAVE TO SIGN THIS IA AND POST ALL THE SECURITIES LAID OUT ON 5 8 4 8 1? SO I, I THINK, UH, CONCEPTUALLY, UH, AND YEAH, A AJ OR CHRISTINA, YEAH, FEEL FREE TO CHIME IN IF I GO STRAIGHT HERE.

YEAH, JEFF, I'M HAPPY TO TAKE THIS ONE IF, IF YOU YEAH.

OKAY, THANKS AG.

UM, YEAH, SO ANGELA, THE, THE, WITH THE EXCEPTION OF LOADS THAT ARE, UH, OR BECOME OPERATIONAL PRIOR TO, UM, JULY 15TH AND THE CURRENT, UH, IN THE, THE FILE DRAFT OF THE PIGGER, UH, UM, OR LOADS THAT MAKE THE, THE MAY 1ST QUARTERLY STABILITY ASSESSMENT THIS YEAR, OR ONE OF THE INTERIM VOLTAGE RIDE THROUGH ASSESSMENTS THAT HAVE BEEN PERFORMED, UH, THOSE ARE THE ONLY LOADS THAT WOULD NOT NEED TO MEET THE, UH, INTERCONNECTION AGREEMENTS CRITERIA DEFINED IN SECTION 9 7 2.

UM, THE, THE THINKING THERE IS THAT THOSE LOADS WILL BE OPERATIONAL PRIOR TO JULY 15TH.

UM, OR IN THE CASE OF THE QSA WILL, UH, UH, BE ENERGIZED WITHIN, UH, THE, THE LAST QUARTER OF THE YEAR.

UM, ALL OTHER LOADS THAT HAVE A PATH TO TREATMENT AS FIRM IN THE STUDY WOULD NEED TO MEET THE, THE 9 7 2 INTERCONNECTION AGREEMENTS CRITERIA.

THANK YOU.

ALRIGHT.

UH, NEXT UP IS GODFREY ARTHUR.

YEAH, HELLO.

UM, I DID ASK THIS QUESTION EARLIER BEFORE THIS SECTION.

I WAS HOPING TO, UM, GET AN ANSWER AND IT KIND OF SIMILAR TO ANGELA'S QUESTION EXCEPT THAT I ASKED ABOUT THE INTERMEDIATE, UM, CRITERIA.

WERE SPECIFICALLY ASKING IF LOADS WERE PARTIAL STUDIES COMPLETE, WERE OBLIGATED TO, UM, MEET THE SAME FINANCIAL THAT'S A HUNDRED THOUSAND PER MEGAWATTS, UM, COMMITMENTS TO BE CONSIDERED IN THE BATCH ZERO PROCESS I SAW ON SLIDE 36, BUT THAT'S STILL, I DON'T KNOW, I DON'T, IT'S NOT TOO CLEAR FOR ME.

IF YOU GO TO SLIDE 36, UM, THE THIRD BULLETS I BELIEVE, YES.

SO, UM, I GUESS THE QUESTION STILL STANDS 'CAUSE I, I STILL CAN'T SEE THE ANSWER TO, UM, TO THE QUESTION FROM THE DISCUSSION SO FAR.

UM, UNLESS THE MOST RECENT ANSWER

[01:55:01]

STILL APPLIES TO IT, WHICH IS TO SAY THAT EXCEPT FOR THOSE WHO HAVE BEEN, UM, STUDIED IN THE MAY 1ST ACCURACY AND THOSE ENERGIZED IN JULY 15TH, UM, EXCEPT FOR THOSE ONES, EVERYBODY ELSE IS SUBJECT TO IT.

YEAH.

AND GOD, FRED, I I, UM, I HATE TO DO THIS TO YOU, BUT I'M GONNA TELL YOU TO HANG ON A LITTLE BIT LONGER TO THAT QUESTION 'CAUSE I, I THINK THIS, THIS AFTERNOON, UH, LATER SLIDES IN THIS DECK, I THINK WE'RE GONNA COVER THAT.

SO I, I APOLOGIZE FOR, UH, PUTTING YOU OFF AGAIN, BUT I I, I THINK THAT WE'LL GET TO THAT AND, AND HOPEFULLY YOU'LL BE ABLE TO EXPLAIN THAT BETTER WITH LATER SLIDES.

NO PROBLEM.

I'LL KEEP FINDING IT ON.

OKAY.

YEAH, YOU'LL GIVE THE PATIENCE AWARD GOD FOR.

ALRIGHT, UH, HANE, STRADER, GO AHEAD.

THANK YOU.

THANK YOU.

HANE STRADER WITH SKYBOX.

UM, JUST A QUICK QUESTION.

SO IF YOU GO TO, THIS GOES BACK TO KIND OF WHERE CHRIS WAS TALKING, BUT IF YOU GO BACK TO SLIDE, UH, SORRY, 32, JUST SO I'M CLEAR, YOU'RE SAYING, SO THE FINAL REPORT WILL GO OUT OR YOU'LL GET THE FINAL REPORT OUT IN, IN JANUARY, AND THEN THE LOADS WILL HAVE FEBRUARY TO MAKE THE FINANCIAL COMMITMENT AND AT THAT POINT THEY'RE LOCKED.

WHAT YOU WERE SAYING, JEFF IS AT THAT POINT, YOU'RE LOCKED IN THE AMOUNT OF MEGAWATTS, BUT THE TRANSMISSION PLAN WILL THEN HAVE TO GO THROUGH THE RRPG PROCESS AND YOU'RE JUST NOT GONNA KNOW PERHAPS EXACT DATES AND ALLOCATIONS UNTIL, YOU KNOW, YOU'RE SAYING HERE'S SEPTEMBER REALLY FOR FINAL APPROVAL.

IS THAT NO.

SO, SO WHAT, UM, THE REPORT THAT COMES OUT AT THE END OF JANUARY, IT WILL HAVE A MEGAWATT ALLOCATION BY YEAR AFTER THAT REPORT COMES OUT.

UH, THAT DOES NOT CHANGE FOR ANY LOADS THAT MEET THE INTERCONNECTION AGREEMENT CRITERIA.

SO, SO THAT, SO IT'S 250 MEGAWATTS IN 2029 AND 350 MEGAWATTS IN 2030.

NO MATTER WHAT HAPPENS LATER IN THE PROCESS, THOSE MEGAWATT VALUES WILL NOT CHANGE.

OKAY.

AND I THINK THAT RAMP SCHEDULE DOESN'T CHANGE.

OKAY.

TWO QUICK FOLLOW UPS, BUT JUST SO WAS THE, CHRIS, WAS THE POINT OF CONTENTION THERE THAT JUST 'CAUSE THE DATES ARE ON PAPER WITH ERCOT, THERE MAY BE SOME DOUBT IN THE DELIVERY DATE ON A TRANS IF, IF THERE ARE TRANSMISSION UPGRADES REQUIRED WITH THOSE DATES.

WAS THAT, I JUST WANNA MAKE SURE I'M FOLLOWING THE CONCERN.

YEAH, I, I THINK THE QUESTION IS ONE, IT KIND OF RELATES BACK TO THE SURVEY QUESTION AND THE, THE, THE HUGE DIFFERENCE I THINK BETWEEN SIX MONTH AND 12 MONTH AND WHAT'S COMING OUT OF THAT WHEN WE DEFINE THE SIX MONTH PROCESS, I THINK AS ERCOT IS ACTUALLY DESCRIBING, IT'S REALLY JUST THE FIRST STEADY STATE PROCESS, RIGHT? AND NOT THE REFINEMENT PLUS THE UM, RPG UPGRADES.

BUT IF YOU ACCOUNT FOR THAT SECOND PART, YOU KNOW, AND THIS IS WHERE I THINK IT'S SOMEWHAT OF A SEMANTICS ISSUE, THAT PROCESS IS NOT THE SIX MONTH PROCESS THAT DEVELOPERS, I THINK BELIEVE IT IS ON THE CHECK.

IT'S ACTUALLY JUST THE FIRST STUDY STATE.

AND THAT THE WHOLE BATCH, IF YOU'RE GOING THROUGH BATCH ZERO WITH A LOAD, IT IS ACTUALLY CLOSER TO A 15 MONTH PROCESS LIKES DEFINED IN HERE.

BUT THEN THOSE BATCHES ARE RUN ON SIX MONTH CADENCES.

SO THE NEXT BATCH STARTS, CALL IT HALFWAY THROUGH THE ENTIRE PRO BATCH ONE STARTS, CALL IT HALFWAY THROUGH THE ENTIRE PROCESS OF BATCH ZERO.

AND SO IT, I THINK BASICALLY WHAT I WAS TRYING TO DO WAS TRY NOT TO BE AS HARSH IN MY CRITICISM, REALIZING WE MIGHT HAVE BEEN TALKING PAST EACH OTHER ON VERY SIMILAR ISSUES.

BUT I THINK THERE'S A BIT OF A MISUNDERSTANDING THAT LIKE SIX MONTHS IS WHAT THIS PROCESS IS AND YOU'RE, YOU'RE GOING TO BE DONE WITH IT WITH FIRM UPGRADES OR NOT.

SIX MONTHS IS JUST THE FIRST STABILITY SCREENING.

AND THEN WHEN WE'RE DONE WITH THAT, YOU HAVE THE DECISION PERIOD BEFORE YOU HAVE, UM, THE REFINEMENT STUDY IN THE RPG UPGRADES COME OUT OF IT.

SO THIS ENTIRE BATCH ZERO PROCESS IS, AND, AND EVERY SUBSEQUENT BATCH PROCESS IS ON THIS TIMELINE ON A SIX MONTH CADENCE.

IT IS A 15 MONTH BATCH ON A SIX MONTH CADENCE OF BATCHES.

GOT IT.

OKAY.

AND THEN, AND THEN, SORRY, LAST, UM, PIECE IS JUST IF, UM, HOW, HOW DO YOU DETERMINE ONCE, ONCE A DEVELOPER'S COMMITTED TO THE FINAL REPORT? WHAT RISK IS THERE THAT THIS DOESN'T GET APPROVED DOWN THE LINE? THAT THE TRANSMISSION PLAN DOES NOT GET APPROVED? UM, I, YOU KNOW, I, I CAN'T STAND HERE AND SAY THAT THERE'S, THERE'S NOTICE TO THAT, BUT I THINK HISTORICALLY, UM, PROJECTS THAT HAVE, UM, THAT ERCOT HAS ENDORSED THOSE PROJECTS HISTORICALLY GET CONSTRUCTED.

OKAY.

THAT'S,

[02:00:01]

THAT, THAT'S CONSISTENT WITH MY UNDERSTANDING AS WELL.

THANK YOU.

ALL RIGHT.

MICHAEL JEWEL? YEAH, THANK YOU VERY MUCH.

TAKING A LOOK AT SLIDE 30, PLEASE.

SO ON THE, UM, PRIMARY OUTPUTS THAT ARE COMING OUT OF THE, THIS PROCESS, UH, THIRD BULLET, WE'VE GOT ESTIMATED SECURITY REQUIREMENTS AND KAYAK OBLIGATIONS.

SO, SO ONE OF THE THINGS THAT WILL COME OUT OF THIS IS, YOU'LL KNOW WHAT YOUR KAYAK IS, IS YOU'RE GONNA HAVE TO PAY, UH, WHEN YOU'RE SIGNING THE INTERCONNECTION AGREEMENT, CORRECT? UH, YES.

AND THEN THAT'S OUR EXPECTATION.

OKAY.

AND THEN THE, THE NEXT BULLET, THE DETAILED UPGRADE LIST AND ASSOCIATED LARGE LOADS IS THIS SAYING THAT, YOU KNOW, IF THERE'S REMOTE TRANSMISSION UPGRADES, OTHER THAN WHAT'S NECESSARY TO IMMEDIATELY INTERCONNECT YOU, THAT THOSE WILL BE IDENTIFIED AND THEN THE COST OF THOSE, AND I, IT IS GONNA BE DETERMINED AS TO WHAT IS APPLICABLE TO WHICH LARGE LOAD, AND THEN THEY'RE GONNA HAVE TO PRO PROVIDE THE FINANCIAL SECURITY FOR THOSE COSTS.

UH, THE WAY THAT WE ARE THINKING ABOUT THAT RIGHT NOW IS THAT, UM, WE NEED TO SUPPORT WHATEVER COMES OUT OF 58 41.

SO IF 58 41 ENDS UP REQUIRING THAT FINANCIAL SECURITY, THEN WE NEED TO HAVE THAT INFORMATION AVAILABLE IN THE FINAL REPORT.

OKAY.

BUT, BUT I, I THINK IT'S, UH, I, I THINK THAT IS A COMMISSION DECISION OR, OR CUTS, YOU KNOW, WE'RE, WE'RE JUST TRYING TO MEET WHATEVER THE COMMISSION DECIDES IS APPROPRIATE.

OKAY.

THAT'S HELPFUL.

THANK YOU.

ALRIGHT, NEXT.

CINDY KAR.

YEAH, A QUESTION ON THE 2033 REFERENCE, JUST A CLARIFICATION, UH, JUST GOING THROUGH THE PROCESS, I THINK ON SLIDE 32, IS IT THE, THE, THE TIMELINE IF, UH, TAKE AN EXTREME EXAMPLE, A LOAD IS IN THE QUEUE, GETS STUDIED, GETS ALLOCATED ZERO IN THE FIRST FIVE YEARS IN, AND IN YEAR SIX YOU GET ALL OF YOUR AMOUNT.

IS THERE ANYTHING STOPPING THAT LOAD FROM GOING AHEAD AND SIGNING AN AGREEMENT? UH, A I A AND FIRMING UP THAT 2033 CAPACITY AND IN PARALLEL THE TSP IS THEN FILING RPG PROJECT FOR 2033 OR, AND THEN DOES THAT GET LOCKED IN IN THE NEXT BATCH CYCLE? YEAH, SO, SO, UH, IN, IN THAT EXAMPLE, YEAH, THERE, THERE'S NOTHING THAT WOULD PREVENT THAT FROM HAPPENING.

YEAH.

SO IT'S TOTALLY ON THE DEVELOPER IF THEY WANT TO TAKE THE RISK OF PUTTING DOWN THE, THE COMMITMENT, NOT KNOWING WHETHER THEY'LL HAVE CAPACITY ON IN YEAR SIX OR NOT.

WE'RE, WE'RE MAKING AN ASSUMPTION THAT, YEAH, AGAIN, BASED ON HISTORY, WE'RE MAKING AN ASSUMPTION THAT WE WOULD BE ABLE TO GET THE TRANSITION BUILT TO SERVE THAT LEAD.

GOT IT.

THANKS.

UM, THAT'S, AND, AND SO THAT WAS IT FOR THE 2033 QUESTION.

THE, THE SECOND COMMENT WAS MORE FOR AWARENESS FOR THE GROUP.

UM, AS WE WERE THINKING THROUGH IT, UH, REALIZED THAT, UH, FOLKS WHO WILL BE WORKING ON AGREEMENTS WILL BE DOING KIND OF OVERTIME, RIGHT? THEY'LL BE WORKING ON IDEAS FOR THE, THE INTERIM AGREEMENTS FOR THE NEXT BATCH AND WORKING ON THE IAS FOR THE PREVIOUS BATCH.

AND SO WE FACTOR THAT INTO THAT 30 DAY THAT WE ARE PUTTING ON, UH, ON, ON, ON TSPS TO GET THOSE AGREEMENTS SIDE FACTOR THAT BOTH OF THEM HAVE TO GENERALLY MEET THAT, UH, SMALL WINDOW.

ALRIGHT.

UM, ABIJIT, GO AHEAD.

HELLO.

HI.

UH, SO MY QUESTION IS, UH, BASICALLY ON SLIDE 34, 31, THE PREVIOUS ONE, SORRY, 34.

31 31, YEAH.

YEAH.

AB IF YOU SPEAK UP A LITTLE BIT, THAT'LL HELP.

THANKS.

IS IT CLEAR NOW? YES, THAT'S BETTER.

OKAY.

SO I HEARD THAT, UH, THERE'S AN OPTION FOR DSP TO CONDUCT STUDIES IN PARALLEL WITH THE BATCH STUDY.

IS THAT, UH, LIKE WHAT WILL BE THE IMPORTANCE OF THE STUDY? UH, YOU KNOW, WHAT, WHAT DEVELOPER WILL GET OUT OF IT? WILL THERE BE ANY ADDITIONAL COST FOR THE STUDY? AND, UH, DOES ELCOT PLAN TO GIVE ANY DIRECTIONS TO TSP ON ON THOSE KIND OF STUDIES? YEAH.

OKAY.

GOOD, GOOD CLARIFICATION.

SO TH THIS IS, UM, THIS IS NOT TO PRODUCE, UM, LIKE A, A PARALLEL, YOU KNOW, A DIFFERENT STUDY RESULT.

UH, OUR, OUR, OUR THINKING HERE IS BASED ON FEEDBACK THAT WE'VE GOTTEN FROM TSPS, IS THAT THEY MAY WANT

[02:05:01]

TO ALSO BE PERFORMING ANALYSIS SO THAT THEY CAN, UH, BETTER IDENTIFY WHAT ARE THE APPROPRIATE TRANSMISSION UPGRADES.

SO RATHER THAN WAIT FOR ERCOT TO SEND THEM THE RESULTS OF THE STUDY, IF THEY ARE IN PARALLEL STUDYING, THEN, THEN THEY WOULD BE ABLE TO IDENTIFY AND, AND WORK ON SOLUTIONS, UH, FOR THE, THE, UH, CONSTRAINTS THAT WE, THAT WE WILL ALL SEE IN OUR ANALYSIS.

OKAY.

SO IT'S, IT'S AT THE DISCRETION OF THE, IT'LL BE AT THE DISCRETION OF THE TSP IF THEY WANT TO DO THAT STUDY, SOMETHING LIKE THAT FOR, FOR ANY OF THE DEVELOPERS, RIGHT? YEAH, I, I, I THINK THAT'S RIGHT.

I, I DON'T THINK THAT WE PUT A REQUIREMENT IN THE PICKER THAT THEY NEED TO, TO PERFORM A STUDY.

UM, I, I, I THINK, YEAH.

YEAH.

THERE'S NOT A REQUIREMENT IN, IN THE PICKER THAT THEY PERFORM THAT STUDY.

MAYBE ANOTHER WAY TO SAY THIS IS THEY'RE DOING THE STUDY TO SUPPORT ERCOT NOT TO SUPPORT THE INDIVIDUAL DEVELOPER.

IS THAT WHAT YOU SAY? YEAH.

OKAY.

DOES THAT HELP HELP G? ALRIGHT.

OKAY.

YEAH, YEAH, THAT'S HELPFUL.

THANK YOU.

ALRIGHT, NEXT QUESTION.

UH, ANDRES MENEZ GUYS HEAR ME? UH, THERE YOU'RE, YES, GO AHEAD.

HI, THIS IS ANDRES WITH CYPRESS CREEK.

UH, CAN YOU PLEASE GO TO SLIDE 28? THANK YOU.

CAN YOU PLEASE CLARIFY THE DIFFERENCE BETWEEN PAGE 1 45 LANGUAGE AND THE STUDY HORIZON FROM THIS SLIDE? IT SEEMS LIKE ER'S ONLY STUDYING ON DOING MEGAWATT ALLOCATIONS FOR LOADS, UH, 2028 THROUGH 2032.

BUT THAT'S NOT HOW I'M READING THAT P LIKE IT, IT SEEMS LIKE IF LOADS DO NOT MEET THAT JULY 15 DEADLINE AND THE MAKE USA AND THE VALIDITY OF THE STUDIES, IT LOOKS LIKE THOSE LOADS WILL NOT QUALIFY AS BASE LOADS, AS BASE LOADS.

SO THEY WILL NEED TO BE INCLUDED IN THE BATCH.

SO WOULDN'T THAT MEAN THAT THE STUDY HORIZON SHOULD ALSO INCLUDE LOADS THAT DO NOT QUALIFY FOR THAT BASE LOAD CRITERIA? YEAH, JEFF, I CAN TAKE THIS ONE.

YEAH.

OKAY, THANKS.

HEY ANDRES, IT'S AG.

UM, SO THE, THE CRITERIA FOR LOADS TO BE ASSESSED IN THE BATCH IS DEFINED IN SECTION, UH, 9.2.

UM, SO 9.2 DEFINES THE, THE BASE LOAD AND THEN, UH, THAT NEXT SECTION WOULD COVER WHO IS ASSESSED.

UM, AND THEN FROM THERE, UH, THE, UH, THE YEARS ASSESSED IN THE STUDY, I BELIEVE IS COVERED IN, UH, 9.3 0.2.

UM, SO HOPEFULLY THAT HELPS.

WELL, NO, I MEAN, I, I GOT THAT SECTION PULLED UP LIKE THAT SECTION THAT YOU MENTIONED.

9.21 HAS FOUR CRITERIA, RIGHT? CRITERIA NUMBER ONE LOADS UP ENERGIZED BETWEEN MARCH, 2022 AND JULY 15TH, 2026.

SECOND ONE IS THE MAY 1ST, QSA THIRD IS, UH, ALL THE, UH, LOAD SYNER ENERGIZING BY 2027 AND THEN FORWARD IS PAST 2028.

SO I GUESS THE QUESTION WHERE THE CONFUSION IS, IS LIKE IF A LOAD THAT DOES NOT MEET, LIKE JUST FOR EXAMPLE, A LOAD FOR END OF YEAR 2026 OR EARLY 2027, WELL THAT LOAD DOESN'T MEET CRITERIA NUMBER ONE, RIGHT? BECAUSE IT, IT, IT DOESN'T MEET THE JULY 15TH, 2026.

LET'S SAY THAT LOAD DOESN'T MEET THE MAY 1ST QSA AND IT DOESN'T MEET THE, AND, AND LET'S SAY IT HA IT ALREADY HAS AN IA, BUT IF ERCO DETERMINES THAT THOSE LOAD STUDIES ARE NO LONGER VALID, WHAT HAPPENS TO THAT LOAD? I MEAN, IS IS NOT GONNA BE INCLUDED AS BASE LOAD, BUT I MEAN IT'S STILL AT 20 26, 20 0.7.

LIKE IS THE BATCH GONNA CAPTURE 2026 AND 2027 LOADS, I GUESS IS THE QUESTION? SURE, YEAH.

I GET, YEAH, MAY MAYBE, UM, I THINK THIS IS A VARIATION OF SHANNON'S QUESTION, BUT LET, LET ME MAYBE TRY, UM, SHOWING IT IN, UM, IN, IN THE GANTT CHART.

SO IF YOU, UH, DON'T MEET THE CRITERIA TO BE, UM, THE, THE FIRM, THEN YOU WON'T KNOW THE STUDY RESULTS UNTIL JANUARY, 2027.

AND YOUR COMMITMENT WINDOW IS ROUGHLY FEBRUARY THE 1ST OF MARCH.

IT, IT, IT, UM, IF YOU MEET THAT COMMITMENT CRITERIA, THE NEXT POSSIBLE QSA FOR YOU TO GET INTO, BECAUSE WE, WE NEED TO STUDY THESE STABILITY IMPACT, RIGHT? THE, THE NEXT POSSIBLE QSA WOULD BE THE MAY 1ST QSA, WHICH WOULD, WHICH WOULD PUT YOUR EARLIEST ENERGIZATION INITIAL ENERGIZATION AS OCTOBER 1ST, 2027.

[02:10:02]

OH, THAT'S CLEAR TO ME.

JEFF.

WHAT I'M GETTING CONFUSED IS, EARLIER YOU GUYS SAID THAT THE BATCH, IT'S ONLY GONNA BE DOING MEGAWATT ALLOCATIONS FOR 20 28, 20 23 THROUGH 2032.

IS THAT NO LONGER THE CASE? 'CAUSE LIKE BASED ON WHAT YOU SAID, IT LOOKS LIKE WITH MY EXAMPLE FOR LOADS FOR 2026 AND 2027 THAT DON'T MEET THE CRITERIA FOR 9 2 1 1, THOSE LOADS WILL BE PART OF THE BATCH, RIGHT? LIKE, YEAH.

SO THEN, SORRY TO INTERRUPT ANDRE.

SO YEAH, I'D REFER YOU TO PARAGRAPH ONE A OF SECTION 9 2 1 2, UM, WHICH WOULD CATCH, CATCH THOSE LOADS THAT DON'T MEET 9 2 1 1, BUT HAVE THOSE CLOSE AND ENERGIZATION DATES AND UM, I MEAN I'M, I'M SORRY, WE, WE DON'T HAVE THE, THE FLOW CHART WE SHOWED AT THE LAST WORKSHOP IN THIS DECK.

BUT, YOU KNOW, EFFECTIVELY IF THOSE LOADS CANNOT DEMONSTRATE THAT THEY HAVE SUFFICIENT DEVELOPMENT PROGRESS TO MEET A 20, 27 OR EARLIER ENERGIZATION, UH, THEN THE, THOSE LOADS WOULD BE STUDIED FOR A 2028 OR LATER ENERGIZATION DATE IN THE BATCH.

AND THAT'S PARAGRAPH TWO OF SECTION 9 2 1 2.

SO EFFECTIVELY WHAT'S GONNA HAPPEN IS, UH, THE LOADS WOULD BE INCLUDED AS STUDIED LOADS IN THE BATCH, BUT IT WOULD BE FOR A 2028 OR LATER ENERGIZATION TO EIGHT.

OH, I SEE.

SO YOU GUYS ARE NOT GONNA STUDY ANY LOADS FOR 20 26, 20 27 IN THE BATCH.

IF THEY DON'T MEET THAT BASE LOAD CRITERIA, THEY GET, THEY GET PUSHED TO THE NEXT MONTH, CORRECT.

'CAUSE THEY GET 2028.

CORRECT.

OKAY.

UH, REAL QUICK, THE NEXT QUESTION I HAVE WAS, UH, IN REGARDS TO THE FINANCIAL SECURITY THAT WE JUST COVERED, THAT ER'S GONNA BE SUPPORTING 5 8 4 1.

UH, I GUESS THE QUESTION IS, ERCO EXPECTS FROM THAT COMMITMENT PERIOD ON THOSE 30 DAYS, I MEAN HERE, LIKE THAT RED BAR, UH, FOR DEVELOPERS TO POST THAT FINANCIAL SECURITY FOR NETWORK UPGRADES, THE WAY THE PFP IS RATED RATED RIGHT NOW WITH THE PCT, WHAT HAPPENS IF ERCOT OVER COLLECTS MONEY? LET'S SAY THERE'S 10 LOADS, 10 GIGAWATTS, LET'S SAY 500 MILLION ARE REQUIRED IN UPGRADES, AND YOU GUYS COLLECT THAT, BUT THEN YOU GUYS GO TO THE REFINEMENT PROCESS AND YOU GUYS DETERMINE THAT, HEY, HAVE THE LOADS DROPPED.

WE NO LONGER 500 MILLION IN UPGRADES, WE ONLY NEED TWO 50, BUT YOU GUYS COLLECTED 500 FROM DEVELOPERS.

ARE YOU GUYS GONNA GIVE THAT MONEY BACK? I, I I THINK THAT WOULD BE WHATEVER, 5 8 4 8 1 TELLS US TOO.

CHRISTINA, YOU WANNA ADD? YEAH, CHRISTINA SWITZER, ERCOT SENIOR REGULATORY COUNCIL.

UM, JUST TO CLARIFY, ERCOT WILL NOT COLLECT ANY MONEY THAT WILL DEF THAT WILL BE BETWEEN THE TSP AND THE INTERCONNECTING, UH, ENTITY, LARGE LOAD ENTITY.

UM, SO IT, IT WILL NOT BE ERCOT.

UM, AS FAR AS WE ENVISION IT RIGHT NOW, BASED ON THE DRAFT PFP, UM, THE, THE FINANCIAL SECURITY WILL BE BASED ON THE RESULTS OF THE BATCH STUDY.

NOTHING WOULD CHANGE AFTER THE BATCH REFINEMENT STUDY AS, AS WE READ THE DRAFT PFP.

RIGHT NOW, ALL THE REFUND OBLIGATIONS, UM, AND TERMS ARE, ARE BUILT IN BASED ON EITHER WITHDRAWING OR ENERGIZATION.

SO WE, WE DO NOT SEE THAT THERE'S A PERIOD FOR THAT AFTER THE REFINEMENT STUDY, BUT THAT COULD CHANGE.

OKAY.

SO JUST TO CONFIRM, ER'S NOT GONNA BE COLLECTING MONEY, IT'LL BE THE TSP, BUT I MEAN MAYBE THIS IS A TOPIC WITH THE P-U-C-T-I, I JUST WORRY THAT IF, IF, IF WE SIGN IN THAT COMMITMENT PERIOD WITHIN 30 DAYS AND WE POST SECURITY TO THE TSPS, LET'S SAY ALL DEVELOPERS POST FOR 500 MILLION OR 1 BILLION FOR UPGRADES, THE PROBLEM IS IT DURING THE REFINEMENTS IF, IF SOME PEOPLE DROP OUT AND THERE'S NOT ANOTHER DECISION POINTS, I MEAN WE STILL POST THE 500 OR 1 BILLION, EVEN THOUGH THAT'S NOT GONNA BE THE MONEY THAT'S GONNA BE NEEDED FOR THE FINAL, UH, RPG PROJECT.

THAT'S THE ONLY COMMENT I WANNA, I WANNA RAISE.

THANK YOU.

ALRIGHT, NEXT IS JOELLE.

JOELLE ABIAN AHEAD? YES.

HEY, THIS IS JOELLE WITH EPE.

CAN YOU ALL HEAR ME? YES, VERY WELL.

GO AHEAD.

OKAY, VERY GOOD.

QUICK QUESTION, UM, IN, IN THIS, UH, TOPIC, SO FINANCIAL SECURITY, THE A HUNDRED K PER MEGAWATT INTERMEDIATE, AND THEN AFTER THE BATCH WE HAVE THE FINANCIAL SECURITY AND KAYAK.

DID WE DEFINE IF THESE ARE REFUNDABLE? UH, CHRISTINA SWITZER, AGAIN, THE REFUNDABILITY IS BASED ON WHAT IS IN THE DRAFT PFP IN 58 4 81.

AND THOSE ARE REFLECTED IN SECTION 9 7 2 OF 1 45, WHICH IS DIRECTLY LIFTED FROM 58 41.

[02:15:03]

OKAY.

UM, WHAT I WAS TRYING TO GET TO, SO THE FINANCIAL SECURITY THAT IS REQUIRED AFTER THE, AFTER THE RESULTS, RIGHT? UH, WITH THAT, WITHIN THAT COMMITMENT, THIS IS GOING TO INCLUDE NOT JUST THE TIFF, NOT JUST THE WHATEVER THEY NEED TO PHYSICALLY INTERCONNECT, BUT THIS WILL ALSO COVER UPGRADES, CORRECT? ? CORRECT.

WE TOOK WHAT IS IN DRAFT 58 41 AND PUT IT INTO PI 1 45.

ALRIGHT.

AND IS THERE, OR IS THIS ON THE TSP TO COME UP WITH AN ALLOCATION METHODOLOGY? HOW, HOW ARE THEY LIKE COST ALLOCATION? WE WILL ERCOT AS PART OF THE PLAN, WE'LL HAVE THE COST ESTIMATE THAT IT'S DEVELOPED WITH THE TSP AND THEN WOULD BE SPLIT AMONG THOSE THAT CONTRIBUTE TO THE SYSTEM UPGRADE.

THE NEED FOR THE SYSTEM UPGRADE.

I DON'T HAVE THE DETAILS ON THAT METHODOLOGY RIGHT NOW.

OKAY, THANK YOU.

I HAVE QUICK OTHER QUESTIONS WITH THE CASES.

I CAN SEE THAT, UH, IN SLIDE 31 WE MENTIONED THAT THEY ARE GOING TO BE POSTED ON MIS SECURE.

ARE THEY ALSO GONNA BE POSTED ON A MIS THE ONES THAT WE CAN, FOR EXAMPLE, SEE THE SSWG CASES OR NO? UM, WE WOULD, WOULD NOT BE ON MS PUBLIC.

UM, I, I THINK IT'S, IT'S MS CERTIFIED RIGHT NOW, BUT, UH, IT, IT'S, UM, BUT YEAH, I, I'M NOT SURE.

I, I APOLOGIZE.

I DON'T KNOW TODAY IF THAT'S, IF S WG IS MS CERTIFIED OR MS. SECURE? IT, IT'S, IT'S ON PUBLIC, THE SSWG CASES.

SO IS THERE ANY RECONSIDERATION ON KO'S PART FOR THIS SPECIFIC THING? YEAH, ACTUALLY I, I, I DON'T THINK THAT THEY'RE ON MIS PUBLIC.

I'M, I'M PRETTY SURE THEY'RE NOT.

'CAUSE THEY'RE EEC, E-C-E-I-I, RIGHT? THEY'RE ON MIS SECURE AND I THINK FOR THE BATCH PROCESS, WE'RE GONNA FOLLOW EXISTING PLANNING TYPE POSTINGS.

SIMILARLY NOT INTRODUCE NEW TOP NEW CONCEPTS.

ALRIGHT, SO SSWG CASES ARE ON MIS SECURE, BUT I THINK THERE'S A DISTINCTION BETWEEN SECURE AND CERTIFIED.

SO WILL THE CASES BE ON MIS SECURE THE SAME WAY SSWG CASES ARE? YEAH, SO I, I, UH, I BELIEVE THE DRAFT RIGHT NOW IS THAT IT'S ON MIS CERTIFIED.

UM, SO THAT, THAT'S THE, UH, I THINK THAT, THAT, THAT'S OUR PLAN RIGHT NOW IS, IS ON MIS CERTIFIED.

ALRIGHT.

UM, SO HERE FOR THE TRANSMISSION IMPROVEMENT ANALYSIS THAT WE SEE ON SLIDE 31, THIS IS WHERE ERCOT AND THE TSPR COMING UP WITH THE TRANSMISSION UPGRADES NEEDED, RIGHT? ALRIGHT.

UM, IN BATCH ONE, LET'S SAY, OR THE BATCH, SO THIS ONE IS SIX MONTHS, WE HAVE A COMMITMENT, THEN WE HAVE REFINEMENT, THEN THERE'S THE OTHER BATCH THAT STARTS THAT BATCH FOR LET'S SAY YEAR ONE.

YEAR ONE TO YEAR SIX, YEAR ONE.

WILL THEY, WILL IT ASSUME ALL THE UPGRADES IDENTIFIED IN BATCH ZERO AS IMPLEMENTED EVEN THOUGH RPG IS STILL IN PROCESS? NO, WE, WE'D FOLLOW THE EXISTING, UH, TRANSMISSION PLANNING PROCESSES WHERE, WHICH WOULD BE, UH, WE WOULD ADD THOSE IN TO THE CASES ONCE THEY ARE RPG APPROVED.

UH, BUT THAT DOES NOT PRECLUDE AN ENGINEER WHEN THEY SEE A PROBLEM FROM, UH, IN THAT SUBSEQUENT BATCH FROM USING THAT SAME IDENTIFIED TRANSMISSION SOLUTION AS AN OPTION TO RESOLVE THAT.

BUT WE DO NEED TO IDENTIFY, UH, WE DO NEED, DO NEED TO IDENTIFY THAT PROBLEM WITH, WITHOUT THAT PROJECT, SINCE THAT PROJECT'S NOT RPG UH, APPROVED.

OKAY.

OKAY.

ALRIGHT.

AND UNTIL, LET'S SAY SOMEBODY GAVE AN EXAMPLE, LET'S SAY THE RESULTS CAME BACK AS ZERO MEGAWATT FOR LET'S SAY FIVE YEARS, AND THEN ON YEAR SIX YOU HAVE SOME ALLOCATION.

WILL THE LOAD DEVELOPER BE ABLE TO BE NET ZERO ON THESE FIVE YEARS? OR IS THIS STILL BEING DISCUSSED AS PART OF THE BRING YOUR OWN GENERATION? OR IS THERE ANY PORTION WHERE, YOU KNOW, FOR THESE FIVE YEARS YOU HAVE ZERO, SO YOU CAN BE NET ZERO ON THE GRID? YEAH, I, I I THINK THAT'S, UH, YOU CORRECTLY IDENTIFIED THAT THAT'S STILL UNDER DISCUSSION AND I THINK WE'RE GONNA TRY TO HIT THAT, UH, LATER THIS AFTERNOON.

IRA.

THANK YOU EVERYBODY.

THAT'S IT.

ALRIGHT.

THANK YOU EVAN.

NEIL.

EVAN NEIL WITH LANING.

I JUST HAVE A FEW INTERRELATED, UH, QUESTIONS HERE.

UM, SO THE FIRST IS JUST, OOPS, SORRY, THE FIRST ONE IS JUST ABOUT THE CASES IN GENERAL.

UM, IS THERE GONNA BE ANY PROCESS TO KIND OF TALK ABOUT THE ASSUMPTIONS THAT GO INTO THOSE IN GREATER DETAIL? IS IT GONNA BE PART OF THE SSWG PUBLISHED CASES AND LIKE THERE'S GONNA BE A MANUAL APPROVED BY ROSS.

UM, AND THEN LIKE SPECIFICALLY IF, IF YOU GUYS KNOW ALREADY, I'M CURIOUS HOW OFFICER LETTER LOADS WILL BE TREATED IN THE BATCH ZERO BASE CASE?

[02:20:01]

YEAH, SO, UM, TO THE FIRST POINT, IT'S, THESE ARE NOT SSWG CASES, UH, SO WILL NOT BE POSTED WITH SSWG.

THEY'LL BE POSTED ON MS CERTIFIED, UH, IN, IN INTERNALLY.

WE'VE TALKED ABOUT TAKING THE STUDY ASSUMPTIONS TO RPG AND, YOU KNOW, TAKING COMMENTS AT, AT RPG, UM, YOU KNOW, THAT DIDN'T, DID NOT PUT THAT IN THE PICKER, BUT, YOU KNOW, I THINK CONCEPTUALLY WE'RE, WE'RE OPEN TO THAT IDEA, UH, JUST TO GET STAKEHOLDER FEEDBACK.

UM, AND THEN, UM, REMIND ME THE SECOND PART OF YOUR QUESTION, EVAN, DO YOU KNOW RIGHT NOW IF YOU'RE GONNA INCLUDE OFFICER LETTER LOADS AT THEIR FULL MODELED OR ARE YOU GONNA TURN TO ZERO? YEAH, SO, UM, SO OFFICER LETTER, UH, IS FOR LOADS, UH, LESS THAN 75 MEGAWATTS.

UH, TH THOSE WOULD BE INCLUDED, UH, AS, AS THE INFORMATION IS PROVIDED TO US BY THE TSPS.

UH, 75 AND GREATER WOULD BE BASED ON THE CRITERIA AS LAID OUT IN, UM, UH, THE ESSENTIALLY 9.2.

OKAY.

THANKS.

AND THEN, UM, FOR THE NET PEAK LOAD CASES SPECIFICALLY, UM, I AM, I'M JUST, WELL, LET ME BACK UP, BUT KEEP THE NET PEAK LOAD CASES IN MIND.

SO FOR THE REFINEMENT PERIOD, UH, THAT STUDY, DO YOU ANTICIPATE THERE BEING OUTCOMES OF THAT THAT CHANGED THE ENDPOINTS OF LINES THAT WERE PREVIOUSLY IDENTIFIED? OR I MEAN, HOW, HOW BIG OF A CHANGE CAN WE EXPECT? YEAH, I, I THINK THAT THAT COULD BE, UH, YOU KNOW, I THINK THAT WE WOULD WANT TO, UM, THE IDEA IN THAT REFINEMENT STUDY IS THAT YOU WANT TO, DO YOU WANNA HAVE A PROCESS THAT IS SIMILAR AS, AS PROBABLY NOT, IT'S NOT, IT'S NOT EXACTLY THE SAME AS RRP G, BUT I THINK IT'S SIMILAR TO RPG TODAY WHERE WE'RE EVALUATING ALTERNATIVES AND, YOU KNOW, WANTING TO, UH, GET THE, THE BEST SOLUTION THAT WE CAN.

OKAY, GREAT.

I MEAN, AND, AND JUST TO THAT POINT, I WOULD ITERATE THAT SINCE THE DEVELOPERS HAVE TO PUT THEIR COMMITMENT UP BEFORE THAT REFINEMENT HAPPENS, JUST TO THE EXTENT THAT ANY LIKE CCN RISK COULD BE INTRODUCED BY CHANGING ENDPOINTS AND ALL THAT STUFF, I, I JUST WOULD HOPE THAT THE RPG AND TCC WOULD, WOULD ADDRESS THAT.

UM, AND THEN I, I GUESS SO IF YOU GET TO THE DECISION POINT AND SAY LIKE A QUARTER OR HALF OF THE LOADS HAVE END UP DROPPING OUT AND THEY DON'T PROCEED MM-HMM .

AND SO YOU HAVE A PRETTY SIGNIFICANT CHANGE TO MAKE, MAKE IN THE REFINEMENT PROCESS.

I'M THINKING ABOUT THE NET PEAK LOAD CASES, AND I'M THINKING THEN YOU WOULD HAVE TO CONSIDERABLY CHANGE THE GENERATION ASSUMPTIONS THAT WOULD GO IN ASSUMING YOU'RE ADDING GENERATION TO THE PICKER 1 27 PROCESS.

YEP.

BUT IF YOU'RE TAKING THAT LOAD OUT AND YOU'RE TAKING GENERATION OUT, THEN WOULDN'T YOU BE CHANGING WHEN THE NET PEAK LOAD IS IN THE CASE? SO THE, UH, I'LL, I'LL SAY THE WAY THAT WE HAVE BEEN THINKING ABOUT IT UP TO THIS POINT IS THAT WE WOULD NOT CHANGE THE GENERATION IN THE CASE UNLESS THERE ARE NEW GENERATORS THAT HAVE MET SECTION 6.9 THAT WERE NOT ALREADY INCLUDED.

WE WOULD ADD THOSE INTO THE MODEL, BUT OTHERWISE WE WOULD NOT CHANGE THE, THE GENERATION IN THE CASE.

OKAY.

SO THE, THE REFINEMENT STUDY COULD HAVE GENERATION INCLUDED IN IT THAT WAS MODELED BASED OFF LOAD THAT IS NOT NO LONGER INCLUDED.

YES.

DO WE ANTICIPATE THAT THAT COULD SIGNIFICANTLY DRIVE THE TRANSMISSION OUTCOMES THAT ARE IDENTIFIED? UM, YEAH, I'LL SAY DON'T KNOW UNTIL WE GET INTO IT, BUT IT'S, UH, I IT'S A FAIR POINT.

WE NEED TO THINK ABOUT THAT.

OKAY, GREAT.

AND THEN JUST LAST ONE, I PROMISE IN, IN THAT SAME BREATH, I KNOW, I THINK, UH, HAYNES WAS KIND OF ASKING THIS EARLIER AND, AND I RECOGNIZE THAT AS FAR AS I'M AWARE THERE'S NOT, UH, TAC HAS NEVER VOTED NO ON AN RPG PROJECT, BUT WE'VE ALSO NEVER PROPOSED AN RPG PROJECT FOR BATCHES TO APPROVE THIS MUCH LOAD.

WE'VE NEVER DONE IT ON A NET PEAK LOAD CASE, AND WE'VE NEVER DONE IT WITH THE PERIOD 1 27 PROCESS.

AND SO HAS JUST CONSIDERED THE POSSIBILITY THAT THERE COULD BE A NO VOTE SOMEWHERE OR SOME TYPE OF DELAY IN RPG AND HOW THAT AFFECTS THE OVERLAPPING TIMELINES THAT YOU GUYS HAVE FOR LIKE SUBSEQUENT BATCHES? UH, I, SO, UM, AGAIN, YOU NEVER KNOW UNTIL YOU GET THERE.

UH, I, I THINK HISTORICALLY, UM, TECH AND THE BOARD HAVE BEEN SUPPORTIVE OF PROJECTS THAT ARE BASED ON CRITERIA THAT IS LAID OUT IN NERC STANDARDS AND PLANNING GUIDE, UH, THE, THE PLANNING GUIDE.

UM, I, I, I THINK FOR BOTH OF THOSE, I, I FEEL LIKE WE'RE ON SOLID GROUND WITH THIS, IS WE, WE FOLLOWED THE PROCESS, THE CRITERIA AND THE PROCESSES THAT HAVE BEEN LAID OUT.

SO, YOU KNOW, I I, I THINK AGAIN,

[02:25:01]

BASED ON HISTORY, UH, YOU KNOW, I THINK WE'RE PRETTY CONFIDENT THAT WE COULD GET, UH, TRANSMISSION PROJECTS APPROVED.

OKAY.

AND, AND I'M HOPEFUL THAT THAT'S THE CASE.

I'M JUST THINKING CONTINGENCIES, WHICH I KNOW YOU CAN APPRECIATE AS A PLANNER.

I APPRECIATE THAT.

THANKS.

GOOD FUN.

OKAY.

UH, SHANNON HERE, WE, I WANT TO COME BACK TO THIS SLIDE, BUT COULD WE GO TO 42 FIRST? YOU KNOW, THERE WAS SEVERAL COMMENTS MADE EARLIER ABOUT IS THIS A SIX MONTH PROCESS OR NINE MONTH OR 12 MONTH OR WHATEVER, UNLESS I'M MISSING SOMETHING.

I THINK WHAT ERCOT IS PRESENTING TO US IS VERY CLEAR, AND I THINK IT WORKS, AND HERE'S WHY.

SIX MONTHS IS WHAT DEVELOPER SLASH LOADS, THAT'S, THAT'S FROM THE TIME YOU COME IN TO THE TIME YOU GET A, UM, YOU KNOW, PUBLISH RESULTS AND YOU HAVE 30 DAYS TO MAKE A COMMITMENT AT THAT POINT, UNLESS I'M MISUNDERSTANDING SOMETHING AS LOAD YOUR FIRM.

IS THAT CORRECT? THAT'S CORRECT.

OKAY.

AND THEN THE REFINEMENT, MAYBE LET'S NOW GO BACK TO 31, BECAUSE WHAT YOU JUST DESCRIBED, OH, LET ME ASK A CLARIFYING QUESTION ON THAT PIECE.

TO THE DEGREE THAT THE SET OF UPGRADES THAT WAS ASSUMED DURING THE SIX MONTH PROCESS, BECAUSE SOME LOADS DROP OUT INHERENTLY IT WILL BE A DIFFERENT SET LATER, BUT IT COULD ONLY BE A SMALLER SET BECAUSE LOADS CAN'T ADD, THEY CAN ONLY DROP OUT, RIGHT? CORRECT.

YEP.

SO AGAIN, I THINK THIS WORKS GREAT BECAUSE THE TSPS IN YOUR, IN THE MIDDLE PIECE, THEY'RE INVOLVED IN WORKING ALONGSIDE YOU ALL ALONG THE WAY ON THE SET OF UPGRADES THAT ARE GOING INTO THE SIX MONTH BATCH STUDY.

SO FOR THEM, THEY HAVE BEEN INVOLVED ALL ALONG, YOU COMMUNICATE THE RESULTS AND THEN THE SCOPE CAN ONLY GET SMALLER IF NOT A HUNDRED PERCENT OF THE LOADS COMMIT.

SO I THINK THIS WORKS JUST, JUST FINE AND, AND IT'S, AND SINCE THE LOADS, THE COMMUNICATING RESULTS TO THE LOADS IS NO LONGER TIED TO WHICH UPGRADES, UH, ULTIMATELY COME OUTTA THE REFINEMENT PROCESS, I THINK YOU'VE ACHIEVED, YOU'VE KIND OF THREADED THE NEEDLE AND ACHIEVED ALL THE OBJECTIVES, AND I THINK YOU'VE DONE IT REAL WELL.

AND THERE WAS A COMMENT BACK, UH, IN A PRIOR SECTION ON 22 ABOUT THE 12 MONTH VERSUS SIX MONTH RTP, AND MAYBE SOMEHOW IT COULD BE INFLUENCED HERE.

I THINK THERE'S NO PROBLEM WITH MOVING TO A SIX MONTH RTP AND THEN IT'S ALL ALIGNED.

I MEAN, YOU'RE, THIS IS REAL WELL LAID OUT.

I THINK YOU'RE SOLVING THE DEVELOPER'S PROBLEMS AND FOR THOSE WHO THINK, WELL, SOME OF THE UPGRADES MAY NOT BE THERE.

I'LL REMIND YOU THAT ERCOT IN REAL TIME HAS A WHOLE SUITE OF TOOLS THAT HAVE BEEN USED FOR A LONG PERIOD OF TIME, YOU KNOW, CONTINGENT, UH, MITIGATION PLANS AND THINGS OF THAT NATURE.

AND I'LL TAKE YOU WAY BACK IN TIME, THE CULBERSON LOOP, ALL THAT WEST TEXAS LOAD THAT WAS ADDED, IT WAS ADDED, AND LATER THERE WAS A DETERMINATION THAT A, IT EITHER TAKE A LITTLE LONGER OR YOU NEED A LITTLE MORE SCOPE.

AND ERCOT HAD AND ERCOT IN COMBINATION WITH THE TSPS, UM, CONTINGENCY MITIGATION PLANS THAT WERE USED UNTIL THAT TIME WAS FINISHED.

SO ERCOT HAS THOSE TOOLS AND THEY'VE GOT A RICH HISTORY OF USING THOSE, THOSE THEY AND THE TSPS, I, I DON'T SEE THE PROBLEM THAT, THE CONCERN THAT PEOPLE HAVE.

ALRIGHT, THANKS SHANNON.

DOWN TO THREE QUESTIONS BEFORE LUNCH HERE.

SO IT'LL BE KEVIN BROTH AND THEN SAM.

SO KEVIN, GO AHEAD.

YES.

UM, SLIDE THREE, TWO, PLEASE.

D UM, DOES THIS TIMELINE INCLUDE THE TIME FOR DYNAMIC STUDIES AS WELL FOR LARGE LOADS, OR DO WE NEED TO ADD THAT, OR DO WE NEED TO ADD THAT TIME AS WELL TO GET TO THE ACTUAL GO LIVE DATE FOR THE NEW LOAD? UM, YOU KNOW, WE, WE'VE GOT, SO THIS, UH, FACT TWO STABILITY THAT THIS IS OUR, UH, IN INTERNAL FULL STABILITY ANALYSIS.

SO, SO WE'LL, WE'LL DO A SCREENING STUDY FOR STABILITY, UM, AS IN, IN PART OF THIS TIMELINE.

BUT WE WILL DO THE FULL STUDY SUBSEQUENTLY.

DOES ARCHIVE ENOUGH STAFF THAT SAY IT'S, ASSUME WE GOT 50 LARGE LOADS TO LOOK AT IT.

DOES HAVE ENOUGH STAFF TO GET THIS DONE IN THAT TIMEFRAME? UM, I, I, UH, I DON'T, I THINK FRED WOULD TELL ME THAT WE DON'T HAVE THE STAFF TODAY TO DO THAT.

UH, BUT WE WOULD, UH, PLAN TO RAMP UP THE STAFF TO DO THAT.

OKAY.

AND ONE ADDITIONAL QUESTION.

UM, RIGHT NOW WE'RE ASSUMING WE'RE USING THE FIGURE 1 27 LANGUAGE TO SUPPORT THE, UH, POTENTIAL ADDITIONAL GENERATION, WE NEED TO

[02:30:01]

SOLVE THE CASES.

WHAT HAPPENS WHEN WE MOVE TO REALITY TIME, LET'S SAY 20 30, 23 1, AND LET'S SAY WE'VE ADDED IN THE MODEL, LET'S SAY WE ADDED A HUNDRED GIGAWATTS OF LOAD, BUT WE ONLY HAVE ENOUGH REAL GENERATION ON THE GRID TO SERVE 50 GIGAWATTS.

DO WE HAVE A PLAN IN PLACE FOR CURTAILMENT TO THE LARGE LOADS AT THAT POINT? SO, UM, I MEAN THE, THE, UM, TEXTBOOK ANSWER ON THAT IS, I MEAN, ABSOLUTELY SB SIX HAS RULES ON, ON, NOT CURTAILMENT.

I I, THIS IS MORE JEFF SPEAKING, BUT, UH, YOU KNOW, WE, WE, WE HAVE A MARKET IN PLACE THAT I THINK IS GONNA TAKE CARE OF A LOT OF THAT.

WE'RE, WE'RE NOT, NOT NOT GOING TO HAVE A SITUATION WHERE WE'RE GONNA HAVE, YOU KNOW, CURTAILMENT FOR HUNDREDS OF HOURS A YEAR.

RIGHT.

I THINK THAT THE MARKET IS GOING TO SELF-CORRECT FOR THAT.

I'M JUST SUPER ASSUMING THE MARKET IS WORKING, LIKE THE MARKET SHOULD WORK.

I WOULD AGREE WITH YOU THERE, BUT OUR FALLBACK IS WE'LL USE THE KILL SWITCH HOURLY IF WE NEED TO.

UH, WE, THE, UH, LEGISLATURE GAVE KOTT TOOLS AND SB SIX, AND IF, IF WE NEED TO USE THOSE TOOLS IN REAL TIME, THEN WE WILL USE THOSE TOOLS.

OKAY.

THANK YOU.

ALRIGHT.

UH, DOWN TO BROTH AND THEN SAM YEAH, RA CRUSO.

MY QUESTION IS WITH REGARDS TO THE SUPPLY CHAIN AND PHYSICAL REALITIES OF THIS.

SO IF I'M UNDERSTANDING THIS RIGHT, UH, UNTIL WE SIGN THE INTERCONNECTION AGREEMENT AND RPG APPROVES IT, THE TSPS WON'T GO AND PROCURE THESE OR START CONSTRUCTION ON THE TRANSMISSION LINES, RIGHT? SO THAT WOULD BE SOMEWHERE NEAR JUNE, 2027? UH, WELL ULTIMATELY, YEAH.

UH, THAT, UH, BATCH REFINEMENT TRANSMISSION PLAN, YES.

UH, IT'S, LET'S ASSUME IT NEEDS BOARD ENDORSEMENT.

YEAH.

THAT BOARD ENDORSEMENT WOULD HAPPEN IN SEPTEMBER OF 27.

SEPTEMBER OF 27.

SO I THINK IF, I WOULD ASSUME MAJORITY OF THESE LOADS MAY REQUIRE TRANSMISSION UPGRADES.

SO IF WE KNOW THOSE DETAILS IN SEPTEMBER 27, THEN THE TSPS NEED TO START PROCURING LLE, YOU KNOW, WORK ON TRANSMISSION UPGRADES.

I'M THINKING AT LEAST 24 MONTHS, RIGHT? SO IT WOULD BE AROUND SEPTEMBER, 2029 THAT WE MAY BE ABLE TO ENERGIZE THE INITIAL LOAD RAMP.

SO THERE WILL NOT BE ANY 28 POWER FOR LOADS THAT GET IN HERE, IS MY UNDERSTANDING, UNLESS, YEAH, OBVIOUSLY THERE ARE SOME LUCKY LOADS WHICH DON'T REQUIRE ANY UPGRADES.

YEAH, YEAH.

UM, YEAH.

YEAH.

SO I, I THINK, UH, I'LL SAY IT THIS WAY, UM, A COUPLE THOUGHTS THERE.

UM, THE, UH, TRANSMISSION UPGRADE SOLUTIONS NEED TO RESPECT THE, THE TIMELINE NEEDED, UH, WHICH THAT TIMELINE INCLUDES GETTING THAT ENDORSEMENT, WHICH, YOU KNOW, WE, SO WE NEED TO RESPECT, HEY, WE, WE MAY NOT GET ENDORSEMENT FOR THESE PROJECTS UNTIL SEPTEMBER OF 2027.

GOT IT.

UH, SO THAT WHATEVER TIMELINE WE COME UP WITH YEAH.

IT, IT HAS TO RESPECT THAT.

UM, ALSO RECOGNIZE THAT THERE ARE TRANSMISSION UPGRADES THAT ARE ALREADY IN FLIGHT.

YEAH.

UH, THAT, THAT WILL BE THERE, YOU KNOW, O OVER, YOU KNOW, THEY'LL BE IMPLEMENTED OVER TIME.

UH, YOU KNOW, WE ALL KNOW WE'VE GOT THE 7 65 AND, AND THERE, YOU KNOW, I I DON'T THINK ANY OF THOSE LINES WILL BE THERE IN 28, BUT, YOU KNOW, IN, IN, UH, YEARS AFTER THAT IT SAID THE, THE, THE STUDY SHOULD RESPECT ALL OF THAT.

IT SHOULD RESPECT THE TRANSMISSION PROJECTS ALREADY IN FLIGHT, SHOULD RESPECT THE TIMELINES FOR NEW, NEW TRANSMISSION PROJECTS, UNDERSTANDING WHEN THE ENDORSEMENT ALL HAPPEN, SUPPLY CHAIN CONSTRAINTS AND, AND ALL OF THAT.

SO THAT, THAT, THAT SHOULD, YOU KNOW, MY GENERIC ANSWER IS THAT THAT SHOULDN'T FALL OUT OF THE STUDY.

YEAH.

I THINK WHAT WOULD BE GREAT IS TO HAVE A CLOSE LOOP.

HONESTLY, WE CAN JUST CHANGE THAT TO LIKE, LIKE, I THINK WHAT WOULD BE GREAT IS TO HAVE A CLOSED LOOP BETWEEN THE OUTCOMES OF BAD ZERO PLUS THE PHYSICAL REALITIES THAT WOULD YOU WOULD GET FROM TSPS AND PRESENT A MORE CLEAR PICTURE OF THE REALITIES.

BECAUSE IF I SIGN, LET'S SAY FOR A EP, I'M JUST PICKING A EP BECAUSE IF I SIGN LOA, THERE MAY NOT BE TODAY, THERE MAY NOT BE A POWER AVAILABLE UNTIL 29 IF I SIGN TODAY.

NOW, IF I DO THAT IN 27 BECAUSE I NEED TO SIGN INTERCONNECTION AGREEMENTS AND EVERYTHING IN 27, THERE MAY NOT BE ANYTHING AVAILABLE UNTIL 29.

SO I THINK BAD ZERO OUTCOMES WOULD BE 29 PLUS IN MY OPINION, UNLESS I'M MISSING SOMETHING HERE.

[02:35:01]

OKAY.

YEAH.

AND I, I'M NOT, UM, PRESUMING THAT UNTIL THE STUDY TELLS ME.

YEAH.

WHAT DO YOU THINK? OOPS, SORRY, GO AHEAD.

SEE LAST ONE FOR LUNCH.

JUST NIX THAT.

HEY, THIS IS SAM JOHN FROM EPE.

UM, I GUESS UMM, MAYBE PIGGYBACKING ON BARTA'S QUESTION AND MAYBE SOME OTHERS, UH, I THINK SLIDE 28 IS THE BEST, UH, SLIDE FOR THIS.

UH, AND THIS MAY BE MORE OF A COMMENT THAN A QUESTION, BUT JUST TO CONFIRM, YEAR SIX, SO ACCORDING TO THIS YEAR SIX OF BATCH ZERO WOULD ALIGN WITH YEAR FIVE OR BATCH ONE, AND THEN CONSEQUENTLY, UH, YEAR FOUR OR BATCH TWO OR THREE, I GUESS, WHATEVER THAT ALIGN.

UM, IS THAT CORRECT? UH, APPROXIMATELY? YES.

UH, I DON'T HAVE THAT LAID OUT, BUT YEAH.

APPROXIMATELY, YES.

RIGHT.

SO THEN BASED ON, I GUESS WHAT HAS BEEN PRESENTED SO FAR, BATCH ONE WILL STUDY YEAR ONE THROUGH FOUR WITH THE LIMITED ALLOCATION THAT'S STUDIED IN BATCH ZERO, AND THEN THE YEAR FIVE OF BATCH ONE WILL BE LIKE THE FULL BLOWN LOAD PLUS WHATEVER THE TRANSMISSION UPGRADE'S BEEN IDENTIFIED.

AND THEN I GUESS, YOU KNOW, CONSEQUENTIALLY BATCH TWO OR THREE WILL HAVE YEAR ONE YEARS ONE THROUGH THREE WITH THE LIMITED ALLOCATION, AND THEN YEARS FOUR THROUGH FIVE STUDY WITH THE FULL BLOWN LOAD AND TRANSMISSION UPGRADES.

I JUST WANNA MAKE SURE THAT'S LIKE THE CURRENT EXPECTATION SLASH PLAN.

YEAH, I, I, I THINK WHAT YOU SAID IS CORRECT, BUT MAYBE ONE CLARIFICATION IS THAT THIS IS MEANT TO BE AN ONGOING PROCESS.

SO, UM, AND AGAIN, YOU, WE WILL, UH, COME OUT WITH A, A PICKER AND THE OTHER REVISIONS REVISION REQUEST TO IMPLEMENT THE ONGOING BATCH, BUT I THINK AS ENVISIONED, UH, YOU WOULD, YOU KNOW, BY THE TIME YOU GET TO BATCH ONE, THEN YOUR, YOUR YEARS ONE THROUGH FIVE, YOU'RE, YOU'RE STILL IDENTIFYING WHATEVER TRANSMISSION UPGRADES THAT YOU CAN, UH, FOR THAT TIME PERIOD.

UM, BUT THEN YEAR SIX, YOU, YOU'LL STILL, YOU KNOW, 20, 20 34 WILL BE YEAR SIX AND, AND YOU WILL GET THE FULL ALLOCATION IN 2034 FOR, UH, BATCH ONE.

BUT YOU MAY, MAY, MAY NOT IN 2029 THROUGH 2033, BE ABLE TO GET FULL ALLOCATION DEPENDING ON WHATEVER TRANSMISSION UPGRADES ARE FEASIBLE.

GOTCHA.

BUT I THINK, YEAH, I THINK WHAT WE MEANT, THE YEAR SIX OF BATCH ZERO WILL BE IMPLEMENTED IN YEAR FIVE OF BATCH ONE.

I, I THINK THAT'S CORRECT.

THAT'S OKAY.

JUST WANTED TO MAKE SURE.

THANK YOU.

ALRIGHT, WELL THAT TAKES US TO THE END OF THE QUEUE.

SO WE'RE GONNA BREAK FOR LUNCH.

HERE'S THE IDEA.

IT'S 10, 12, 10 RIGHT NOW.

SO TAKE AN HOUR AND FIVE MINUTE LUNCH.

WE'LL COME BACK AT ONE 15.

WE'RE GONNA RUN UNTIL TWO 30 ON THE ELIGIBILITY PIECE.

UH, AND THEN WE'LL HAVE AN HOUR FOR THE, UH, PRESENTER, FOR THE, UH, PEOPLE THAT FILED COMMENTS.

SO EACH GET 15 MINUTES AND THEN WE'RE GONNA SAVE THE LAST HOUR PURPOSELY FOR C-L-R-B-Y-O-G DISCUSSION, AND THAT'LL TAKE US TO FOUR 30.

SO AT THIS POINT WE'LL STAND ADJOURNED UNTIL ONE 15.

ALRIGHT, SO WE'RE GONNA START TO LAUNCH INTO ELIGIBILITY EXCITEMENT.

UH, WHAT I'M GONNA DO IS, AGAIN, START WITH THE, THE QUEUE'S GONNA REMAIN CLEAR.

IF YOU ASK TO GET IN THE QUEUE, YOU'RE NOT GETTING IN THE QUEUE BECAUSE THERE IS NO QUEUE.

ONCE HE'S DONE PRESENTING, THEN WE'LL OPEN THE QUEUE FOR QUESTIONS TO THEN HIT THIS.

YOU SAY, WHY DO WE DO THIS? IT'S BECAUSE HALF THE TIME THE QUESTIONS ARE EVENTUALLY ANSWERED.

SO, UM, AGAIN, WE'LL JUST HOLD THE QUEUE, UM, UNTIL JEFF SAYS OTHERWISE.

AND, UH, JEFF WILL TURN IT OVER TO YOU TO START TO RUN THROUGH.

THANK YOU SO MUCH.

AND AGAIN, WE'RE HOPING TO TIME BOX THIS TO AN HOUR AND 15 MINUTES.

UM, ON OR AROUND, UH, TWO 30, UH, IS WHEN WE WANNA PIVOT OVER TO PEOPLE THAT FILED FORMAL COMMENTS.

SO OFF YOU GO, JEFF.

THANK YOU, SIR.

OKAY, THANKS MATT.

SO, UH, JUST WANTED TO START REAL QUICK WITH WHAT OUR PRINCIPLES WERE.

UM, OBVIOUSLY FIRST OFF, WE NEED TO MAKE SURE THAT WE ARE, UH, INTERCONNECTING LOADS IN A RELIABLE MANNER, UH, SO THAT THAT RELIABILITY HAS TO, TO TO BE AT THE CENTER OF EVERYTHING THAT WE DO.

UH, WE ALSO ARE WANTING TO RESPECT THE SB SIX AND, AND THE, THE PUC UH, GATING RULES, UM, AND RESPECT, UH, TO THE EXTENT THAT IT'S, IT'S POSSIBLE AND DOESN'T CONFLICT WITH THE FIRST TWO PRINCIPLES, EXPECT THE, UH, RESPECT THE EXISTING, UH, PROCESSES AND, AND APPROVALS THAT HAVE HAPPENED.

UM, ALSO, WE TALKED ABOUT THIS AT THE, AT THE LAST WORKSHOP, BUT THINK FEEDBACK THAT WE'D HEARD FROM STAKEHOLDERS IS THAT THERE SHOULD BE A CHECK FOR LOADS THAT HAVE NEAR TERM ENERGIZATION, UH, THAT, THAT THEY ARE, UH, FEASIBLE TO BE, UM, UH, ENERGIZED.

AND THEN, UM, THE, THE, THE, THE LAST BULLET WAS, UM, SOMETHING THAT WE HAD IN, IN THE, UH, PREVIOUS WORKSHOP, BUT IT IS ACTUALLY, AS WE HAVE THOUGHT ABOUT IT, UH, YOU KNOW, HAVE DECIDED TO CHANGE THAT, THAT REALLOCATION

[02:40:01]

OF THE NON UTILIZED CAPACITY.

UH, SO IF YOU'LL NOTICE, UH, THE PIGGER ACTUALLY DOES NOT HAVE THAT CONCEPT.

WE, UH, REMOVE THAT.

AND THE REASON FOR THAT IS, UM, YOU KNOW, I THINK THINK THERE'S A, A RISK THAT, UM, IF WE WERE TO REALLOCATE NON UTILIZED CAPACITY FROM EXISTING LOADS, UM, AND, AND THEN LATER THE 58 41 RULES CHANGED ON THAT THEN, UH, CAPACITY THAT WE HAVE CLAWED BACK COULD ACTUALLY THEN BE, UH, YOU KNOW, CONSIDERED FIRM IN THE FUTURE AND THAT THAT MAY PRESENT A RELIABILITY RISK FOR US, A RELIABILITY CONFLICT.

UH, SO IN OTHER WORDS, UH, AS AN EXAMPLE, UH, I THINK THIS IS AN EXAMPLE I USED LAST TIME.

IF YOU HAD A LOAD THAT HAD, UH, 500 MEGAWATTS, BUT UH, THEY HAD GONE THROUGH THE PREVIOUS PROCESS, UH, AND WERE 500 MEGAWATT LOAD, BUT WE'D ONLY SEEN THEM CONSUMING 300 MEGAWATTS, THEN WE WOULD, UH, YOU KNOW, CALL BACK THAT 200 MEGAWATTS AND REALLOCATE THAT.

BUT, UH, IF MAYBE THE RULE CHANGES AND, AND MAYBE THEY DON'T ACTUALLY, YOU KNOW, THAT THEY, UH, YOU KNOW, WOULD, WOULD NOT QUALIFY FOR THAT, THAT REALLOCATION THEN IF WE HAVE ALL REALLOCATED THAT 200 MEGAWATTS AND THEN THEY ARE ALSO GRANTED THAT 200 MEGAWATTS BACK THEN, NOW WE'VE GOT A A RISK THERE.

AND SO, UH, WE'VE TAKEN THAT OUT OF THE PIGER, UH, AND I THINK WE'RE GONNA, UH, AT LEAST FOR BATCH ZERO, I THINK WE'RE GONNA HOLD ON THAT AND THEN WE'LL WAIT TO SEE WHAT COMES OUT OF 58 41 DOWN THE ROAD.

UH, SO THAT'S, THAT'S THE THINKING ON THAT.

UM, THIS IS A, UM, KIND OF A REVISION TO THAT FLOW CHART, UH, THAT WE HAD PREVIOUSLY ON.

UM, AND I, IT'S FOR THE MOST PART HASN'T CHANGED, UH, FROM THE, THE, UH, FLOW CHART THAT WE SHOWED EARLIER.

BUT THIS IS HOPEFULLY, UH, SLIGHTLY CLEAR, UH, WAY TO LOOK AT THIS, UM, WITH THE, UH, REFERENCES.

I THINK FOR THE SAKE OF TIME, I'M, I'M NOT GONNA WALK THROUGH THIS.

I'M, I'M JUST GONNA WALK THROUGH THE, UM, THE SUBSEQUENT SLIDES, BUT E ESSENTIALLY THERE ARE THESE KIND OF THREE, THREE BUCKETS ON THE RIGHT WHI, WHICH ARE LOAD THAT WOULD BE INCLUDED IN BATCH ZERO AS, UH, BASE LOAD.

UH, THEN THERE WILL BE LOADS THAT WILL BE, UH, STUDIED IN BATCH ZERO.

SO THEY'RE INCLUDED IN BATCH ZERO, BUT THEY ARE STUDIED AND, AND SUBJECT TO, UH, RECEIVING AN ALLOCATED, UH, MEGAWATTS.

UM, UH, SO, SO THE FIRST BUCKET, THE NUMBER ONE, THE GREEN, UH, IF YOU WILL, THAT, THAT ONE, IT'S BASE LOAD.

YOU'RE, WE'RE NOT REALLOCATING OR ALLOCATING MEGAWATTS.

UH, THE SECOND BUCKET IS YOUR STUDIED IN BATCH ZERO AND, AND YOU RECEIVE A, A LOAD ALLOCATION AMOUNT.

AND THEN THE THIRD BUCKET IS YOU'RE JUST NOT INCLUDED IN BATCH ZERO.

IF YOU'RE LOOKING AT THE PIGGER, THE, UM, THE SPECIFIC SECTIONS TO LOOK AT ARE, UM, NINE POINT FOR THAT FIRST BUCKET, 9.2 FOR THE SECOND BUCKET, AND 9.23 FOR THAT THIRD BUCKET.

UM, AND THEN WHEN WE GET INTO THE, UH, OR ARE THE STUDIES STILL CONSIDERED VALID? UH, THAT IS 9.24.

SO THOSE ARE KINDA THAT FOURTH SECTIONS UNDER 9.2 0.1 OR WHAT ONE FIRST SECTION IS INCLUDED AS BASE LOAD, SECOND IS INCLUDED AS STUDIED, THIRD IS NOT INCLUDED.

AND THEN THE, THE FOURTH IN THAT SECTION IS THE, UH, ARE THE STUDY STILL VALID? OKAY.

SO, UH, LET, LET'S, LET'S DEEP DIVE INTO THESE.

UM, OKAY, SO, UM, FOR LOADS THAT HAVE, UH, ALREADY RECEIVED INITIAL ENERGIZATION SOMETIME BEFORE MARCH 25TH, 2022, WHY, WHY IS THAT DATE SPECIAL? THAT IS WHEN WE STARTED THE INTERIM LARGE LOAD INTERCONNECTION PROCESS.

SO, UH, ANY LOAD THAT WAS ENERGIZED BEFORE THAT.

SO THE ID HERE IS, I, I, YOU KNOW, STEEL MILL THAT'S BEEN THERE FOR 30 YEARS, UH, YOU'RE, YOU'RE INCLUDED AS BASE LOAD, UH, SO THAT, OR YOU ACHIEVED INITIAL ENERGIZATION SOMETIME BETWEEN WHEN WE STARTED THE LARGE LOAD INTERCONNECTION PROCESS AND, UH, JULY 15TH OF THIS YEAR.

UH, AND ANY LOADS THAT ARE, UM, YOU KNOW, HAVE ACHIEVED THAT, UH, THEN YOU'RE INCLUDED AS, UH, BASE LOAD.

UM, AND THEN, UH, AND, AND THEN YOU ARE NOT SUBJECT TO, UH, BEING RESTUDIED, UM, AND YOU, FOR THE SAKE OF TIME, I'M NOT GONNA WALK THROUGH THE DETAILS ON THE RIGHT, BUT IT IS ESSENTIALLY, IT'S, UH, YOU KNOW, WE WILL LOOK AT VARIOUS WAYS TO, TO DETERMINE WHAT, UH, WHAT IS THAT LOAD AMOUNT, WHAT, WHAT IS THAT MEGAWATT AMOUNT, UH, SO THE LEFT IS KIND OF CRITERIA.

AND THEN WHAT, WHAT MEGAWATTS ARE WE INCLUDING? UH, IF YOU'RE A STEEL MILL THAT'S BEEN THERE FOR 30

[02:45:01]

YEARS, THEN IT'S GONNA BE THE, THE MEGAWATTS THAT, THAT WE HAVE IN, UM, USE IN OUR STUDY CASES, UH, IS, IS KINDA THE SHORT WAY OF SAYING THAT.

UM, AND THEN WHEN WE GET INTO QUESTIONS, IF, IF YOU WANNA GO BACK AND, AND ASK QUESTIONS ON THAT, HAPPY TO DIVE INTO THAT.

OKAY.

SO, UM, OTHER LOADS THAT ARE INCLUDED AS BASE LOAD.

SO IF YOUR REQUESTED ENERGIZATION DATE IS, UH, BEFORE END OF 2027, AND YOU HAVE COMPLETE AND VALID INTERCONNECTION STUDIES, UH, AND THAT SPECIFICALLY IS, UH, REFERENCES, UH, 9.24, UM, AND YOU HAVE EXECUTED AN INTERCONNECTION AGREEMENT, UH, BY, UH, JULY, UH, 15TH, UM, THEN YOU WILL BE INCLUDED AS, UH, BASE LOAD OR IF YOU'RE IN A CONNECTION OR YOUR INITIAL ENERGIZATION DATE IS AFTER THE END OF 2027, JANUARY 1, 20, 28 OR LATER, AND YOU HAVE, UM, YOUR COMPLETE INVALID INTERCONNECTION STUDIES AND YOUR EXECUTED INTERCONNECTION AGREEMENT BY JULY 15TH, THEN AGAIN, YOU'RE INCLUDED AS, UM, UH, AS, UH, UH, BASE LOAD, UH, IN THIS CASE.

UH, I, I THINK I'VE FAILED TO MENTION IN THAT FIRST BUCKET ON THIS SLIDE, UH, YOU ALSO HAVE TO SHOW THAT YOU HAVE METHOD DEVELOPMENT CRITERIA.

UH, SO WE'RE, WE'RE DOING THAT CHECK TALKED ABOUT THIS AT THE LAST WORKSHOP, UM, BASED ON FEEDBACK FOR LOADS THAT ARE NEAR TERM ENERGIZATION, WHICH WE'RE DEFINING AS, UM, END OF 27, THEN, UM, THEN THAT IS A, UM, UH, WE'RE GONNA, WE'RE GONNA DO THAT CHECK.

UM, AND THEN I SEE A, A TYPO, UH, SOMEBODY MAY HAVE JUST, UH, I THINK ASKED THIS, UM, IS THIS, UH, AND THIS MAY BE AN AG QUESTION IF HE'S ONLINE OR, OR CHRISTINA, WE SAY EITHER, AND THEN WE HAVE AN AND ON I ON ON ONE AND TWO THERE.

UH, I DON'T REMEMBER WHICH IT IS.

IS IT EITHER OR OR IS IT, AND YEAH, SORRY, ON, ON THIS SECOND ONE HERE, IT'S AN, AND IT'S AN, AND SO EITHER THAT WORD EITHER SHOULD NOT BE THERE, RIGHT? OKAY.

YEAH, SORRY ABOUT THAT.

UM, OKAY.

OKAY.

SO, SO THOSE WERE THE LOADS THAT WILL BE INCLUDED AS, AS BASE LOAD.

SO, UH, SLIDES 45 AND 46, THESE, THESE ARE LOADS THAT WILL BE INCLUDED IN BASE LOAD AND BATCH SERIAL.

UM, AND THEN, UH, THE NEXT SLIDE IS WHAT ARE THE LOADS THAT WILL BE STUDIED IN BATCH ZERO? UH, AND, AND SO LOADS THAT WILL BE STUDIED, WERE ARE THOSE THAT, UH, IF YOU'RE, YOUR INITIAL ENERGIZATION DATE IS, UH, BY THE END OF 2027 BETWEEN NOW AND, AND, AND END OF 2027, UM, AND YOU DON'T MEET THE REQUIREMENTS THAT TO BE CONSIDERED BASE LOAD, UM, BUT YOU, YOU DO MEET THE INTER INTERMEDIATE AGREEMENT CRITERIA, UH, THEN YOU WOULD BE STUDIED IN BATCH ZERO AND YOU'RE, YOU'LL BE ALLOCATED WHATEVER, YOU KNOW, MEGAWATTS, THE STUDY SHOW CAN RELIABLY BE ACCOMMODATED.

UH, SO THEN, UM, IF YOUR INITIAL ENERGIZATION DATE IS ON OR AFTER JANUARY 1ST, 2028, THEN UM, WE WOULD LOOK TO SEE IF YOUR, UM, STUDIES MEET THE, UM, THE, UH, 9.2 0.4 UH, REQUIREMENTS, AND YOU HAVE YOUR INTERMEDIATE AGREEMENT, UM, UH, BY JULY 15TH, 2026.

UH, THEN THAT WOULD BE LOAD, THAT WOULD BE STUDIED IN BATCH ZERO.

UM, AND THEN, UH, SO THE, SO AGAIN, UH, 9.2 FOR THESE TWO SLIDES, 9.2 FOR THIS SLIDE, AND THEN NOW WE'RE GONNA GO TO 9.23.

UM, AND IF WE NEED TO GO OVER TO THE LANGUAGE THAT WE CAN, UH, BUT I'M GOING TO STILL CONTINUE WORKING THROUGH THIS SLIDE HERE.

UH, SO IF YOU DO NOT MEET THE CRITERIA, UH, LAID OUT IN 9 2 1 1 OR 9 2 1 2, UH, SO, SO ANY OF THOSE, THE, THE PREVIOUS SLIDES I JUST PRESENTED, IF, IF YOU DON'T MEET THOSE CRITERIA, UM, YOU ARE, UH, NOT INCLUDED IN BATCH ZERO, UM, OR IF YOUR, UH, STUDIES ARE, UM, THE, UH, SUFFICIENT FOR MEETING 9 2 1 4, BUT YOU DON'T MEET THAT CRITERIA IN, IN 9 2 1 2, UM, THE ELIGIBILITY CRITERIA, THEN, THEN YOU'RE NOT INCLUDED.

UH, OR IF YOU

[02:50:01]

MEET THOSE, BUT, UM, UH, THE INFORMATION IS NOT SUBMITTED TO ERCOT BY JULY 15TH.

UH, THEN, UH, ALSO YOU WOULD, UH, NOT BE INCLUDED IN BATCH ZERO.

SO YOU CAN'T, YOU KNOW, COME BACK THREE MONTHS LATER AND SAY, WELL, YOU KNOW, I WOULD'VE MET THIS, BUT, YOU KNOW, WE JUST DIDN'T TURN THE, THE DATA IN.

UM, YOU KNOW, OBVIOUSLY THEN WE, WE COULDN'T INCLUDE YOU IN BATCH ZERO.

OKAY.

SO LET'S, UM, GET INTO THE, UM, UH, THE INTERCONNECTION STUDIES.

UM, SO, UM, AGAIN, THE WAY THAT WE'RE LOOKING AT YOUR INTERCONNECTION STUDIES ARE, DO WE, CAN WE SEE THAT WE CAN RELIABLY SERVE THIS LOAD? UH, DO WE KNOW, DO WE HAVE STUDIES THAT WE CAN POINT TO AND SAY, CAN WE RELIABLY SERVE THIS LOAD? UM, AND, AND THAT IS BASED ON ERCOT UNDERSTANDING OF HAVING THE STUDY THAT CAN SHOW THAT, UH, WE, WE, WE CAN MEET THAT CRITERIA OF, UM, BEING ABLE TO RELIABLY SERVE, UH, THE LOADS.

UM, AND, UH, I THOUGHT, SORRY, I THOUGHT WE HAD ANOTHER SLIDE ON THIS, BUT, UM, YEAH, MAY, MAYBE LET ME JUST, UM, LET ME POP OVER 'CAUSE I, UM, THIS MAY BE BETTER JUST TO GET INTO THE, THE LANGUAGE HERE AND HOW WE'RE THINKING ABOUT THIS.

OKAY.

AND ACTUALLY, LEMME DOUBLE CHECK AGAIN BECAUSE I, I THOUGHT WE HAD ANOTHER SLIDE ON THIS, BUT MAYBE I'M MISTAKEN.

OKAY.

OKAY.

SO, UM, THE, THE WAY THAT WE'RE THINKING ABOUT THIS IS, UM, THAT, UM, IF YOU LOOK AT PARAGRAPH THREE, WHAT WE ARE GOING TO DO IS, UH, ON, UH, JULY 15TH, WE ARE GOING TO MAKE AN ASSESSMENT OF ALL OF THE LOADS THAT ARE MEETING THE CRITERIA FOR, UH, GETTING INTO BATCH ZERO, UH, AS BEING UNDER STUDY.

UH, AND THAT ASSESSMENT IS GOING TO LOOK AT THE PREVIOUS STUDIES THAT HAVE BEEN COMPLETED.

UM, AND THE, UM, AND, AND LEMME BACK UP TO I THINK THE FEBRUARY 3RD WORKSHOP WE HAD PROPOSED, UH, MAKING THE CUTOFF ON JANUARY 28TH, 2026, UH, SORT OF A RETROACTIVE CUTOFF.

AND SO ANY LOADS THAT DID NOT MEET THE, THE, UH, THE STUDIES DIDN'T MEET THE CRITERIA AS OF JANUARY 28TH, IF YOU'LL REMEMBER, WE SAID, OKAY, THAT, YOU KNOW, THAT THAT'S, UM, YOU KNOW, THAT WOULD NOT BE CONSIDERED A A, A GOOD STUDY AFTER THAT.

UM, I THINK THE FEEDBACK THAT WE GOT IS YOU, YOU NEED TO MAKE THAT DATE FORWARD LOOKING DATE, UH, AND YOU NEED TO GIVE A CHANCE FOR, UH, THE LOADS TO, TO MEET THAT CRITERIA.

UM, AND SO I THINK THE CHALLENGE THAT WE EXPRESSED AT THE TIME WITH THAT CONCEPT, UM, IS THAT IF YOU MAKE IT FORWARD LOOKING, THAT MEANS LOADS THAT, UM, MEET THAT AT A FUTURE DATE.

UH, YOU, YOU HAVE THE SAME PROBLEM THAT YOU HAVE TODAY IN THAT THERE MAY BE OTHER STUDIES THAT ARE HAPPENING IN PARALLEL THAT INVALIDATE, UH, THE, THE STUDIES INVALIDATE EACH OTHER.

UH, SO AS AN EXAMPLE, I HAVE TWO LOADS THAT ARE UNDERSTUDY, AND NEITHER OF THOSE LOADS INCLUDE THE OTHER ONE IN THE STUDY RESULTS.

THEN WHAT HAPPENS IF THEY BOTH SIGN THEIR INTERCONNECTION AGREEMENT? THEY, THEY BOTH MEET 9.5 ON THE SAME DAY.

I, I NOW DON'T HAVE A STUDY THAT I CAN LOOK AT THAT ERCOT CAN LOOK AT AND SAY, WE KNOW THAT WE CAN RELIABLY SERVE BOTH OF THESE LOADS, UH, SO THAT THAT IS THE SAME RISK THAT EXISTS IN THE CURRENT PROCESS.

THAT RISK DOES NOT GO AWAY.

UH, SO BY HAVING A FORWARD-LOOKING JULY 15TH DATE, WE HAVE TO TAKE THAT RISK INTO ACCOUNT, UH, AND WE HAVE TO THEN COME UP WITH SOME SORT OF ORDERING FOR WHICH STUDY DO WE DETERMINE OVERRIDE OR, UM, OVERRIDE'S NOT THE RIGHT WORD, BUT, UM, SU SUPERSEDES, THANK YOU.

UH, SU SUPERSEDES THE, UH, THE, THE OTHER STUDY.

UH, AND SO THE WAY THAT WE HAVE THOUGHT ABOUT THIS IS THAT IT, IT SHOULD BE BASED ON THE, UM, THE, THE STUDIES THAT ARE COMPLETED SOONER ARE THE STUDIES THAT WILL, UH, SUPERSEDE THE STUTTER STUDIES THAT COME LATER.

UH, AND THE, THE COMMITMENT THAT HAPPENS WILL SUPER, SUPER, UH, THE COMMITMENT THAT HAPPENS FIRST WILL SUPERSEDE LATER COMMITMENTS.

UM, AND, AND SO I THINK THAT IS JUST A CONSEQUENCE OF NOT HAVING A RETROACTIVE DATE,

[02:55:01]

IS THAT HAVING THAT FORWARD LOOKING JULY 15TH DATE, WE'RE, WE'RE GONNA HAVE TO HAVE SOME, SOME KIND OF ORDERING, UH, IN, IN HOW WE THINK ABOUT THESE STUDIES.

AND, AND SO, UH, THAT, THAT'S WHAT WE, UH, ARE ATTEMPTING TO DO WITH THE WAY THAT WE'VE CRAFTED THIS, UM, IS COME UP WITH THAT ORDERING.

UM, WE, UM, I THINK WE HAD A, A QUESTION EARLIER ABOUT RPG PROJECTS.

UH, AND THE, THE REASON WE CHOSE THE DECEMBER 15TH IS BECAUSE UNDER THE, THE PRIOR PROCESS OR THE INTERIM PROCESS IS THAT, UH, LOADS, UH, UH, TO, TO GET, UH, KIND FIRMED UP AND, AND REACHED THAT WHAT WE CALLED, UH, MUST STUDY STATUS, UH, PREVIOUSLY, UH, THEN THEY, UH, BEFORE THE UNBOXING OF, OF PIGGER ONE 15, WHICH HAPPENED ON DECEMBER 15TH, AND THEY COULD GO THROUGH, UH, A REGIONAL PLANNING GROUP PROCESS.

UH, BUT AFTER UNBOXING OF ONE 15, THEN THAT'S NO LONGER A PATH.

AND SO YOU HAVE TO GO THROUGH THE, THE PIGGER ONE 15 PROCESS.

THAT'S WHAT WE ARE ATTEMPTING TO DO WITH THE WAY THAT WE'VE CRAFTED THIS, UM, IS COME UP WITH THAT ORDERING.

UM, WE, UM, MARKET PROJECTS, UH, IF THAT'S THE PAST OR THE FUTURE, WE CHOSE THE DECEMBER 15TH.

OKAY.

UM, OKAY.

SORRY.

OH, ARE WE MUTED NOW? OKAY.

ON THE PHONE.

CAN YOU CONFIRM? YOU CAN STILL HEAR ME? WE CAN HEAR YOU.

OKAY.

THANK YOU.

OKAY.

SO, UM, YEAH, SO, SO, OKAY, SO THAT, THAT'S HOW WE, SO THE THOUGHT ABOUT, UM, OKAY, WHAT WHAT MAKES A COMPLETE AND VALID STUDY.

SO COMPLETE AND VALID STUDY IS, UM, I, I WAS ON IN THE, UM, INTERIM PROCESS AND I, UH, WENT THROUGH AN RPG PROJECT APPROVAL.

UH, SO AGAIN, THE THINKING THERE, JUST TO PUT IT IN LAYMAN'S TERMS, IS OKAY, ERCOT CAN LOOK AT THAT STUDY AND SAY, OKAY, AND RPG PROJECT WAS IDENTIFIED.

WE'D KNOW WHAT THAT SCHEDULE IS FOR THE RPG PROJECT, AND, AND WE, WE KNOW THAT WE CAN RELIABLY SERVE THIS LOAD BECAUSE I, I HAVE THAT STUDY.

UM, OR WE, WE CAN MEET THE, UM, OR HAVE NOW, UH, MOVED TO SECTION 9.9, NINE POINT 10, PREVIOUSLY NINE FOUR AND NINE FIVE IS, UH, I HAVE A STUDY THAT, UH, IT WENT THROUGH THE LARGE LINE AIR CONNECTION STUDY PROCESS AND THE LOADS MET THE, UH, WHAT WAS PREVIOUSLY NINE FIVE, THE COMMITMENT CRITERIA AS LAID OUT IN NINE FIVE.

OKAY? SO IF IT MEETS THOSE CRITERIA, THEN WHAT WE ARE GOING TO DO IS WE'RE GOING TO MAKE THIS LIST WHERE WE'RE GOING TO CREATE AN ORDER IN WHICH THE LOADS THAT MET THESE CRITERIA, HOW WHEN, WHEN THEY MET THAT CRITERIA WE'RE, UH, WE'RE, WE'RE ESSENTIALLY GONNA LAY THAT LIST OUT, AND WE WILL THEN WORK OUR WAY THROUGH THAT LIST, UM, WHERE WE WILL LOOK AT, OKAY, THE, THE LOADS AT THE TOP OF THE LIST, THOSE LISTS, WE WILL, WE CAN SAY, OR THOSE LOADS AT THE TOP OF THE LIST, WE CAN SAY, OKAY, THOSE LOADS, UH, WE KNOW THAT WE CAN RELIABLY SERVE THIS LOAD BECAUSE THAT LOAD WAS INCLUDED IN THIS STUDY AND, AND, UM, YOU KNOW, AND THAT STUDY IS STILL VALID.

UH, AND THEN WE WILL WORK OUR WAY DOWN THE LIST AND WE WILL LOOK AT ALL OF THE LOADS THAT ARE, UH, ABOVE THAT.

UH, SO, SO WHEN WE GET TO THE 12TH LOAD AND LIST, WE'LL LOOK AT THE 11 PREVIOUS LOADS AND SEE, OKAY, WERE ANY, WERE ALL THOSE LOADS INCLUDED IN THAT LOAD NUMBER 12, UH, IN, IN THE STUDY? AND WE'LL, WE'LL CONTINUE DOING THAT THROUGH, YOU KNOW, HOWEVER MANY HUNDRED PROJECTS WE HAVE THAT MEET THIS CRITERIA.

WE, WE WILL LOOK AT THAT, UH, THAT LIST IN THAT WAY.

AND SO THAT'S THE, THE KIND OF THE ORDERING.

SO, UH, AS AN EXAMPLE, IF YOU MEET THE 9 4, 9 5 REQUIREMENTS, IF YOU MET THAT ON JANUARY 28TH, THEN ANOTHER LOAD COMES IN ON JULY 14TH AND MEETS REQUIREMENTS, WE WOULD GIVE PREFERENCE TO THE LOAD THAT MET THE REQUIREMENTS ON JULY, UH, ON JANUARY 28TH OR JULY 13TH, OR, YOU KNOW, WHATEVER THE CASE MAY BE, UH, AS OPPOSED TO THE ONES THAT COME IN RIGHT AT THE END.

UH, AND SO THE, AGAIN, THE PURPOSE THERE IS WE, WE CAN'T HAVE A SITUATION WHERE WE HAVE A BUNCH OF LOADS THAT, UH, MEET THE REQUIREMENTS EXACTLY ON JULY 15TH, UH, AND THEN THAT INVALIDATES EACH OTHER'S STUDIES.

WE, WE HAVE TO HAVE A WAY TO, TO, UH, KIND OF WORK THROUGH THAT ORDERING.

UM, SO THAT'S, THAT, THAT, THAT'S THE IDEA BEHIND HOW, HOW WE CAME UP WITH THIS, UM, UH, WITH, WITH THIS, UH, 9.2 0.1 0.4 AND, AND THIS, UH, ORDERING.

SO, UM, YEAH, I THINK I'M GONNA SWITCH BACK TO THE, UH, POWERPOINT PRESENTATION NOW.

UM, AND I'M GONNA CONTINUE TO WALK THROUGH, BUT YOU KNOW, I'M SURE THERE ARE QUESTIONS.

WE'LL, WE'LL COME BACK TO THAT.

[03:00:01]

OKAY.

SO, UM, WE, UM, I THINK HEARD SOME FEEDBACK ON THE DEMONSTRATED DEVELOPMENT ACTIVITY AND, UM, YOU KNOW, AGAIN, WANTED TO, UH, TRY TO IN INCLUDE THIS, UH, IDEA, UH, OF LOADS THAT, UM, ARE, UH, SAYING THAT THEY HAVE A 2026 OR 2027 ENERGIZATION DATE.

UM, WE NEED TO MAKE SURE THAT THAT'S ACTUALLY, UH, FEASIBLE.

UM, AND, AND, AND SO WE'RE PUT THESE CHECKS IN, UH, THE FIRST CHECK IS, UM, DOES THE LOAD, IS, IS THE LOAD IN THE QSA, UM, HAS THE, UH, LARGE LOAN ENTITY BEGUN SITE PREPARATION AND CONSTRUCTION, UH, TO MEET, UH, SUCH THAT IT CAN MEET THE INITIAL ENERGIZATION DATE AND HAS THE TSP AND DSP PURCHASED ALL NECESSARY, UH, ESSENTIALLY LONG, LONG LEAD TIME EQUIPMENT.

UM, AND IF NOT, THEN WE KNOW THAT THAT PROJECT IS NOT LIKELY TO BE ENERGIZED IN 2027.

UH, SO THERE, THERE'S THAT OR, UH, YOU KNOW, HAS, SO IF YOU DON'T, IF YOU'RE NOT IN THE, THE QSA, THEN, UM, OOPS, SORRY.

UH, THEN, YOU KNOW, DO YOU MEET THE, UM, DO YOU HAVE VALID STUDIES AND YOU KNOW, CAN YOU SHOW THAT YOU HAVE THIS INTERCONNECTION AGREEMENT THAT MEETS THE REQUIREMENTS IN 9 7 2, DO, DO YOU HAVE THIS DEVELOPMENT ACTIVITY, UM, AND HAVE YOU PURCHASED THOSE LONG LEAD TIME EQUIPMENT? UH, SO THOSE ARE KIND OF THE TWO PATHS TO PROVING, UH, DEMONSTRATED DEVELOPMENT ACTIVITY.

AND THAT'S BASED ON, I THINK WHAT, WHAT WE, WE THINK WE'RE, WE'RE MEETING THE, THE, UM, THE, THE FEEDBACK, UH, THAT WE GOT PREVIOUSLY ON THAT.

UM, YEAH.

AND THEN, UH, LAST LAST THING I JUST WANTED TO MENTION, UH, I THINK WE, WE'VE SAID THIS A COUPLE OF TIMES IS, UM, WHEN, WHEN WE WERE THINKING ABOUT THIS, THE COMMITMENT CRITERIA, UH, THERE WERE KIND OF TWO PATHS THAT, THAT WE CONTEMPLATED, UH, WITH 58, 41, UNDERSTANDING THAT, UH, AS IT IS TODAY, IT'S, IT'S A DRAFT, UH, PROPOSAL FOR PUBLICATION.

UM, AND WE WILL LIKELY SOMETIME IN THE FALL, UH, MAYBE LATE SUMMER OR FALL, WE'LL LIKELY HAVE FINAL RULE.

UM, SO WE COULD EITHER, UH, START, UH, OR WE, WE COULD EITHER, UH, KIND OF COPY 58 41 INTO PICKER 1 45.

UH, AND THIS IS THE PATH THAT WE CHOSE, IS TO COPY IT AS, AS IT WAS IN THE DRAFT, UH, UNDERSTANDING THAT IF IT CHANGES BETWEEN NOW AND WHENEVER WE GET TO, UH, FINAL STAKEHOLDER APPROVAL IN, IN MAY, IF IT CHANGES, THEN WE, WE CAN UPDATE THE, UH, THE LANGUAGE IN THE PIGGER.

UH, BUT WE WANTED TO HAVE THAT SO THAT THAT ALLOWS US TO THIS SUMMER START THE BATCH ZERO PROCESS, UH, SO THAT WE CAN HAVE RESULTS IN TIME, UH, TO, UH, ALLOW LOADS TO COMMIT IN TIME TO GET TO THE 2027 RTP IN INCLUDED IN THOSE BASE CASES.

UM, SO THAT, THAT, THAT IS ONE PATH, UH, THE OTHER PATH THAT WE CHOSE NOT TO DO.

BUT, YOU KNOW, AGAIN, THIS IS, THIS IS STILL OPEN FOR DISCUSSION.

IT IS, WE COULD, UM, WAIT UNTIL 58 41 IS COMPLETE.

UH, AND, UM, YOU KNOW, BARKSDALE MENTIONED, YOU KNOW, THERE, THERE'S SOME CONTENTION WITH, WITH, WITH WHAT'S IN THE PFP.

UM, YOU KNOW, WE, WE COULD WAIT, BUT THE CONSEQUENCE OF WAITING IS THAT THAT MEANS THAT WE NEED TO WAIT TO START BATCH ZERO, UH, WHICH MEANS BATCH ZERO STUDY RESULTS ARE LIKELY NOT DONE IN TIME TO GET INTO THE 2027 RTP.

UH, SO THAT, THAT'S A, YEAH, AGAIN, ANOTHER SITUATION WHERE WE HAVE A TRADE OFF, WE'VE CHOSEN TO GO OPTION ONE, UM, BUT, YOU KNOW, OPEN TO FEEDBACK ON THAT AS WELL.

UM, SO, UH, WITH THAT, I WILL PAUSE AND, UH, SEE WHAT QUESTIONS THERE ARE.

ALL RIGHT, JEFF, THANK YOU AGAIN.

SO I'LL OPEN THE QUEUE FOR BUSINESS.

HERE WE GO.

ALL RIGHT, AND THE IDEA IS I WANNA RUN ABOUT 30 TO 45 MINUTES OF QUESTIONS, AND THEN AGAIN, WE'LL LET THE COMMENTERS, UH, THE PEOPLE THAT FILED COMMENTS, UM, PRESENT HERE FOR AN HOUR AFTER THAT.

OKAY.

HEY, MATT, THIS IS, THIS IS AJI I WANNA ADDRESS, UM, MICHAEL JULES QUESTION, UH, IN THE CHAT ABOUT, UM, ON ONE OF THE EARLIER SLIDES, THERE WAS A DISCUSSION ABOUT WHETHER, UM, BOTH REQUIREMENTS WERE NEEDED OR, AND I'M SORRY, I DON'T REMEMBER THE, THE SLIDE NUMBER, UM, BUT MIKE, UH, MICHAEL POINTED OUT CORRECTLY THAT IN PARAGRAPH, UH, SECTION 9 2 1 1 PARAGRAPH EE RUMINANT TWO, UM, THAT IT SAYS, OR, AND THAT IS UNINTENTIONAL, UH, IT SHOULD SAY, AND BETWEEN THE FIRST REQUIREMENT AND THE SECOND REQUIREMENT.

SO, UH, JUST WANTED TO CLARIFY THAT THE, UH, UH, LANGUAGE IN THE PIG WILL, UH, NEED TO BE CORRECTED THROUGH, THROUGH COMMENTS AS WELL.

ALRIGHT, THANKS FOR CLARIFICATION, AG.

ALRIGHT, SO LEE, CHER, YOU'RE UP FIRST.

[03:05:01]

THANKS.

UH, SO IN THE 9.2 0.1 0.4, UM, PROCESS, AS YOU ARE DETERMINING LOADS THAT ARE, UM, SEEKING TO BE, UH, FIRM IN BATCH ZERO, UH, ARE THE PUC PROJECT 5 8 4 8 1 INTERCONNECTION COMMITMENT CRITERIA USED IN THE ORDERING OF THOSE, UM, YOU KNOW, I THINK YOU SAID THAT IT WAS BASED ON THE DATE THAT ERCOT RECEIVED FROM THE TSP THAT THE 9.4 AND 9.45 REQUIREMENTS WERE COMPLETE.

UM, IS THAT ALSO GOING TO BE KIND OF CHECKED UP AGAINST THE LOADS THAT ARE MEETING THE INTERCONNECTION COMMITMENT CRITERIA? OR HOW DOES THAT, HOW DO THOSE TWO THINGS INTERPLAY? YEAH, SO, UM, I THINK THE, UM, THE ANSWER TO THAT IS THAT THE, THE ORDERING IS, UH, STRICTLY BASED ON THE CURRENT REQUIREMENTS, WHICH, WHICH WOULD BE NINE FIVE TODAY OR NINE 10 IN PICKER 1 45, AND NOT ON THE, UM, THE TIMING ON WHEN THEY MEET THE 58 41, UH, REQUIREMENTS, UH, NOW 58 41, UM, YOU KNOW, THAT THAT'LL BE A, UH, A, UH, NOT, NOT 58 41 ITSELF, BUT, UH, THE LANGUAGE THAT WE'VE COPIED, YOU KNOW, THAT THAT WILL BE A GATING CRITERIA THAT, THAT, YOU KNOW, BY JULY 15TH, THEY'LL NEED TO MEET THAT.

BUT THE ORDERING OF WHEN THEY MET THAT IS, UM, DOESN'T FACTOR INTO THE, UH, THE ORDERING IN THE SECTION 9.24.

OKAY.

SO I JUST WAS WANTING TO MAKE SURE THAT, YOU KNOW, IF YOU DO MEET THAT CRITERIA, YOU'RE NOT GOING TO BE STUCK BEHIND A LOAD THAT HAS MET THE 9.4 9.5 BEFORE YOU, BUT FAILED TO MEET THE PUC 5 8 4 8 1 INTERCONNECTION CRITERIA.

YEAH, I THINK THAT'S CORRECT.

YEAH.

SO, YEAH, SO IF THEY FAILED TO MEET THE 9 2 1 4, OR SORRY, IF THEY FAILED TO MEET THE INTERCONNECTION, UM, I THINK 9 2 7, CHRISTINA'S SHAKING HER HEAD, UH, IF THEY FAILED TO MEET 9 2 7, THEN YEAH, THEN, THEN THEY, THEY'RE OUT ANYWAY, SO I THINK IT'S A 9 7 2 9 7 2.

THANK YOU.

IS THE INTERCONNECTION AGREEMENT STANDARDS.

ALL RIGHT, NEXT SHANNON, UH, SLIDE 46 PLEASE.

THE LEFT COLUMN, SECOND BULLET.

UM, THE PIECE ABOUT COMPLETE AND VALID INTERCONNECTION STUDIES IS, THE WAY I'M UNDERSTANDING IT, AND PLEASE CORRECT ME IF I'M WRONG, IS THAT'S VALID AND COMPLETE INTERCONNECTION STUDIES ARE COMPLETE AND VALID UP THROUGH JULY 15TH OR 14TH, AND THEN THEY'RE TAKEN IN ORDER, THEY COME, IS THAT CORRECT? OR THAT MEET THE SENATE BILL SIX OR THE MEET THE, UH, PC RULE REQUIREMENT 58 41? UM, I THINK IT'S, THEY, UH, THE ORDER IN WHICH THEY MEET, UM, NOT 58 41, THE ORDER IN WHICH THEY MEET P ONE 15, THEY MEET P ONE 15, BUT I WAS ONLY AT REASON, I WAS ADDING THAT LAST PIECE.

IS YOUR CLARIFICATION TO WHOEVER ASKED IT IS IF THERE WERE TWO AND AN EARLIER ONE DIDN'T MEET THE 58 41 INTERCONNECT REQUIREMENTS, THEN THEY'RE REMOVED.

IS THAT RIGHT? THEY, THEY WOULD FALL OUT OF THE LIST.

ALRIGHT, 40 NINES NEXT.

UM, LET'S SEE HERE.

I TELL YOU WHAT, YOU ALREADY ANSWERED MY QUESTION ON THAT, AND THEN IF WE CAN GO TO THE PC, OR EXCUSE ME, THE BIGGER, UH, RULE, UH, PAGE 18 ON THE SECTION THAT IS 9.2, 0.1 0.4, PARAGRAPH THREE I WHERE IT'S ACTUALLY, UH, SORRY, IT'S TOO LITTLE, LITTLE TOO.

I BIG A, SO IT'S WHERE THE DECEMBER 15TH CAME IN.

YEAH.

YOUR LOGIC FOR THAT A MOMENT AGO IS, HEY, THAT'S WHEN WE UNBOX BIGGER ONE 15, AND SO WE DON'T NEED TO GO BEYOND THAT.

PRACTICALLY SPEAKING, YOU, THERE'S NO TSP THAT, UH, CAN PREPARE, UH, RPG FILING THAT HASN'T WORKED ON, YOU KNOW, FOR ANYTHING OF SCOPE, YOU KNOW, SIZE THAT HASN'T WORKED ON THAT FOR MANY, MANY, MANY MONTHS, AND YOU HAD NO IDEAS THE TSP OR LOAD THAT WAS PART OF THAT PROCESS WHEN THE UNBOXING MIGHT EVENTUALLY OCCUR.

SO TO MAKE IT TO WHERE THEY

[03:10:01]

COULD HAVE CONCEPTUALLY BEEN WORKING ON SOMETHING FOR 7, 8, 9 MONTHS AND YOU WERE, AS A LOAD WERE A PART OF THAT, THAT AFTER THE DAY THAT YOU FINALLY UNBOX IT, SAY KING'S X, BUT YOU DON'T TELL 'EM KING'S X, THEN YOU WAIT TILL SIX, EIGHT WEEKS LATER AND SAY, OH NO, I'M LOOKING BACK TO THAT PRIOR DATE.

THAT DOESN'T SEEM LOGICAL.

UM, I UNDERSTAND YOU WOULD LIKE TO CLOSE THAT DOOR FULLY, THAT'S FULLY REASONABLE.

GOING BACKWARDS THAT FAR IN TIME, I DON'T THINK IS REASONABLE FOR TSPS THAT ARE CONTINUING, THAT HAVE BETWEEN THEN AND NOW SUBMITTED, UH, RPG FILINGS IN GOOD FAITH THAT THEY MAY HAVE BEEN WORKING ON FOR NINE, 10 MONTHS.

AND THE REASON THEY WERE WORKING ON THEM THAT LONG IS YOU HAD NO IDEA WHEN PIER ONE 15 WOULD EITHER PASS OR FINALLY GET UNBOXED.

SO I WOULD ASK YOU TO MAKE THAT SOMETHING MORE LIKE MAYBE MAKE IT THE FOURTH OF, UM, MARCH THE DAY YOU PUBLISH THIS OR SOMETHING.

OR I, I COULD MAKE THE CASE IT OUGHT TO GO THROUGH JULY 15TH, BUT, BUT I UNDERSTAND YOU'RE WANTING TO CLOSE THE DOOR.

I WOULD ASK YOU TO TAKE THAT INTO ACCOUNT AND DON'T DISRESPECT ALL THE HARD WORK BY THE TSP AND THE INTERCONNECTING ENTITIES THAT WENT THROUGH THAT WITH THIS ARBITRARY LOOK BACK.

UM, IT'S IN THERE NOW.

OKAY.

THANKS FOR THE COMMENTS.

ALRIGHT, NEXT WHO HELP ME, UH, ANDREW CHOPPER.

HEY GUYS.

ANDREW CHOPPER.

UM, ONE QUICK QUESTION.

I GUESS MAYBE FOR ERCOT ON THIS SAME PROVISION, UH, THREE TWO A AND B, WHAT IS YOUR PLAN TO GET, UH, COMMITMENTS FROM THE LOAD THAT THEY'RE UNDER CONSTRUCTION WHILE YOU'VE GOT THIS LOOK BACK PERIOD THAT YOU'RE CONTEMPLATING THAT WOULD, I THINK TAKE US THROUGH THE THIRD QUARTER OF THIS YEAR? HOW, HOW'S THAT GONNA WORK? YEAH, I'M NOT SURE I UNDERSTAND THE QUESTION.

WELL, TO GET INTO THE BASE LOAD TO BE FIRM, YOU'RE REQUIRING THAT THE CUSTOMERS PROVIDE A CONSTRUCTION AND PROCUREMENT AT A STATION, WHICH THEY WOULD NEED A FIRM LOAD QUALIFICATION TO MAKE THAT ATTESTATION TO YOU, WOULD THEY NOT? HOW IS, HOW IS SOMEBODY GOING TO START CONSTRUCTION IF THEY'RE NOT SURE IF THEIR LOAD IS FIRM? YEAH, I I I THINK THAT'S THE SAME THAT, THAT'S THE SAME ISSUE AS TODAY, RIGHT? IS IS YOU'RE, YOU'RE AT RISK TODAY.

SO I THINK OUR, OUR ASSUMPTION HERE IS THAT YOU, UH, AND AGAIN, THIS IS BASED ON FEEDBACK AND YOU KNOW, WE'RE, WE'RE OPEN TO, TO, UH, YOU KNOW, ADDITIONAL FEEDBACK, BUT, UH, THE FEEDBACK IS THAT IF YOU ARE ENERGIZING IN, UH, I THINK 2026 IN YOUR EXAMPLE, THEN YOU WILL HAVE ALREADY STARTED YOUR CONSTRUCTION.

WHAT ABOUT YOU SHOULD ALREADY BE ABLE TO MAKE THAT, BE ABLE TO MEET THAT ATTESTATION PRE 2027, END OF 2027, YOU'RE REQUIRING THE SAME CONSTRUCTION ATTESTATION AS DRAFTED, IS THAT RIGHT? CORRECT.

AND SO YOU'VE GOT FOLKS WHO HAVE SATISFIED NINE FOUR AND NINE FIVE THE LEGACY, OR NINE NINE AND NINE 10 WHO COULD BE UNDER CONSTRUCTION AND HAVE ALREADY RELEASED THE UTILITY OR ARE ABOUT TO RELEASE THE UTILITY FROM NOW THROUGH THE END OF, YOU KNOW, THROUGH, THROUGH, UH, JULY 15TH.

WHAT, WHAT, WHAT DOES THAT MEAN FOR THEM? IF, HOW, HOW, HOW ARE THEY SUPPOSED TO OPERATE IN LIMBO CONTINUING CONSTRUCTION IF THEY'RE NOT SURE IF THEIR STUDIES ARE VALID? HOW'S THAT GONNA WORK? YEAH, I I'M NOT SURE I UNDERSTAND THAT YOUR, YOUR QUESTION THERE, UH, I GUESS LOW CUSTOMERS ARE OPERATING AS IF MEETING 9 4 9 5, LEGACY 9 4 9 5 MEANS THEIR LOAD IS FIRM AND THEY'VE, THEY'VE MADE BINDING COMMITMENTS TO THE UTILITY BASED ON THAT.

AND SO THERE ARE CUSTOMERS IN THIS RULE WHO HAVE MET THAT CONDITION, OR YOU'RE SAYING YOU ARE GONNA LOOK BACK AT THEIR STUDIES TO SEE IF THEY'RE VALID OR NOT.

IS, AM I READING THAT WRONG? YEAH, I, I THINK THAT'S CORRECT.

THAT'S, IS IT JUST THAT ERCOT DOESN'T BELIEVE THERE'S ANY INVALID STUDIES IN THAT BUCKET? I, I GUESS I'M, I'M HAVING A HARD TIME UNDERSTANDING WHY THAT'S NOT CONSIDERED AN ISSUE.

YEAH.

HEY, ANDREW, UH, THIS IS AJI.

MAYBE I CAN, UH, STEP IN YEAH, PLEASE.

AND ADD TO JEFF WHAT JEFF HAS SAID.

UH,

[03:15:01]

I, I THINK IT IS, YOU, YOU NOTICE IN THIS PARAGRAPH THERE'S TWO PATHS INTO, UM, THE, THE, AND THIS ALSO I GUESS GETS BACK TO SHANNON'S COMMENT, UM, UH, PRIOR TO YOURS, UH, THERE'S TWO PATHS INTO THIS KIND OF REVIEW.

UM, ONE IS THROUGH THE RPG AND THE, UM, THE REASON THAT THERE IS THE DECEMBER 15TH CUTOFF DATE, THAT THAT'S NOT AN ARBITRARY DATE.

THE CURRENT PLANNING GUIDE, UH, DISALLOWS LARGE LOAD INTERCONNECTION WITHOUT GOING THROUGH THE LARGE LOAD INTERCONNECTION STUDY PROCESS.

SO, UM, YOU KNOW, AFTER DECEMBER 15TH, THE, UH, THERE'S ONLY ONE PATH FOR LARGE LOADS TO PROCEED FORWARD, AND THAT'S THROUGH THE SECTION NINE PROCESS.

UM, BUT BECAUSE THERE WAS AN INTERIM PROCESS FOR THREE YEARS AND SOME OF THE RPG SUBMISSIONS HAVE BEEN IN FLIGHT FOR A WHILE, UM, WE NEED TO REVIEW ALL OF THE LOADS THAT HAD A VALID PATH INTO THE, UH, POTENTIALLY A VALID PATH INTO THE STUDY.

AND, UH, THAT MEANS THAT, UH, LOADS THAT HAVE MET NINE FOUR AND NINE FIVE UNDER THE CURRENT PLANNING GUIDE, WHICH AS YOU POINT OUT ARE, ARE RECLASSIFIED NINE NINE AND NINE 10.

UM, WE HAVE TO REVIEW THAT IN, IN CONTEXT WITH THE OTHER STUDIES THAT, UH, YOU KNOW, THAT VALID PATHWAYS PRIOR TO DECEMBER 15TH.

UM, AND I, YOU KNOW, I THINK THAT I, I GUESS I WOULD CHARACTERIZE THAT AS A CONSEQUENCE OF HAVING A FORWARD LOOKING CUTOFF