ALRIGHT,

[00:00:01]

GOOD MORNING.

THANK YOU FOR JOINING US.

SORRY FOR THE MONDAY MORNING MEETING.

UM, AS WE GET SETTLED IN,

[1. Antitrust Admonition]

LEMME GO AHEAD AND PULL UP THE ANTITRUST ADMONITION.

UH, TO AVOID RAISING CONCERNS ABOUT ANTITRUST LIABILITY, PARTICIPANTS IN NARCOTIC ACTIVITIES SHOULD REFRAIN FROM OPPOSING ANY ACTIONS THAT WOULD EXCEED OR COST AUTHORITY UNDER FEDERAL STATE LAW.

FOR ADDITIONAL INFO, STAKEHOLDERS SHOULD CONSULT THE STATEMENT OF POSITIONAL ANTITRUST ISSUES FOR MEMBERS OF ERCOT COMMITTEES, SUBCOMMITTEES AND WORKING GROUPS, WHICH IS POSTED ON THE WEBSITE.

SO,

[2. Timeline and governance recap (10 mins)]

THE WAY TODAY'S GONNA UNFOLD, UH, I'M STILL WAITING FOR THE ERCOT PACKAGE OF PRESENTATIONS.

WHAT WE HAVE IS A COUPLE STAKEHOLDER PRESENTATIONS COME IN ON FRIDAY AND ANOTHER UPDATE THIS MORNING.

UM, SO ISH, SO TIME QUESTION NUMBER ONE IS ANYONE OPPOSED TO THE IDEA OF US HITTING THE, UH, DESIGN ELEMENTS FOR THE CONTROLLABLE LOAD RESOURCES AN HOUR FROM NOW? UH, WE HAVE SOME CONFLICTS IN THE AFTERNOON THAT TAKE AG AWAY.

THEY'RE NOT IRRESOLVABLE, BUT IF WE CAN GO AHEAD AND WALK THROUGH THE MARKET COMMENTS FOR THE FIRST HOUR AND THEN PIVOT OVER TO CLR.

DOES ANYONE HAVE ISSUES WITH THAT? ALRIGHT, SEEING NONE IN THE ROOM, WE WILL GO THAT WAY.

AND THEN LET ME SEE IF OUR MATERIALS ARE POSTED.

THEY HAVE NOT POSTED JUST YET.

SO LEMME WALK THROUGH THE AGENDA TODAY.

SO I'LL DO THE TIMELINE AND GOVERNANCE RECAP.

WE'LL DO THE MARKET COMMENTS.

RECEIVED, UH, WE HAD FOUR NEW SETS OF COMMENTS COME IN.

THEY'RE FROM ANJI TRACKED, CRUSO IS SHOPPER, AND THEN, UH, CYPRESS CREEK RENEWABLES.

UH, ANDRES SENT THE EXAMPLE FROM LAST MEETING WAS WHAT HAPPENS IF WE RUN A, THE INITIAL BATCH STUDY, THEN WE HAVE COMMITS OR DECOMMIT.

AND THEN WHETHER OR NOT BASED ON THOSE DECOM COMMITMENTS, DO WE STILL HAVE A TOPOLOGY THAT HOLDS THE SYSTEM TOGETHER? SO ANDRE'S DONE A, UM, KIND OF A A WHAT IF SCENARIO AND HE'S UPDATED HIS SLIDES THIS MORNING.

SO WHAT'S POSTING RIGHT NOW IS GONNA BE REPLACED BY SOMETHING 10 MINUTES FROM NOW.

SO WE'LL GO THROUGH THAT SET.

SO THAT'LL PROBABLY TAKE THE FIRST HOUR.

RUN US, UM, 9 45 TO 10 45.

UH, AT THAT POINT WE'RE GONNA PIVOT AND GO DOWN TO THE, UH, CLR PIECE.

AND THEN AFTER THE CLR WE'RE GONNA DO THE DEEP DIVE.

KIND OF THE FOUR THEMES TODAY IS AGENDA ITEM FOUR, DEEP DIVE ON ELIGIBILITY.

THAT IS ALL, YOU KNOW, THE LION'S SHARE OF COMMENTS WE RECEIVED TO DATE ARE ON ELIGIBILITY AND WHAT THAT LOOKS LIKE.

SO THAT'LL BE JEFF BILL TAKING US THROUGH THAT AGENDA.

ITEM NUMBER FIVE IS A DEEP DIVE ON YEAR SIX, TRANSMISSION PLANNING.

UH, SO THE IDEA HAS BEEN IF IT'S, YOU KNOW, BATCH RUNS FIVE YEARS, WE ASSUME EVERYTHING SHOWS UP ON YEAR SIX.

THERE'S ANOTHER WAY TO LOOK AT THAT.

AND SO JEFF WILL DO A WALK DOWN ON THE PROS AND CONS OF WHETHER OR NOT WE, UH, GO INTO ANOTHER OPTION ON THAT.

AND AT THAT POINT WE'LL HAVE ALREADY DONE THE DESIGN ELEMENTS FOR CLR AND THEN WE HAVE THE BRING YOUR OWN GENERATION OPTION.

UM, AND SO IN THE EMAIL, I THINK WHERE, HOW HAS IT GONE THROUGH THIS SO FAR? WE BROUGHT FORWARD MULTIPLE OPTIONS.

WE CONTINUE TO TAKE SOME OF THOSE OPTIONS OFF THE TABLE TO SEE WHAT WE CAN GET TO THE JUNE 1ST BOARD.

RIGHT NOW, WHAT THAT'S LOOKING LIKE IS SELF-LIMITING, IS THE, UM, THE ONE ELEMENT THAT WE THINK WE CAN LATCH ONTO AND FINISH WELL, UH, THE PUN PLUS, UM, I KNOW THAT SAM BRANDON WANTED TO DO SOME, A LITTLE WALK DOWN ON THAT.

SO WE'LL STILL GIVE THE IDEA OF WHAT A PUN PLUS COULD LOOK LIKE AND WE MAY BE SURPRISED IT MAY SIMPLIFY SOME THINGS THAT WE HADN'T THOUGHT ABOUT.

SO HE'LL HAVE THE FLOOR FOR, UM, THAT TIME WITH SLIDES THAT ARE BEING POSTED ALSO.

SO WITH THAT, LET'S HIT THE REFRESH BUTTON.

OH MAN, I'VE GOT GOOD PEOPLE.

OKAY.

JUST IN TIME.

BIT EARLY.

WOO.

AMEN.

OKAY, WE'RE READY FOR OUR MEETING NOW.

UH, AND BY THE WAY, THANKS TO A LOT OF PEOPLE WORK NIGHTS AND WEEKENDS ON THE ERCOT SIDE.

I KNOW TACK KEEPS SAYING NICE THINGS, BUT, UM, JEFF, AG, CHRISTINA, EVAN, THERE'S A LOT OF, HEY, RYAN, HOW'S GOING ON WEEKEND WORK GOING INTO THIS TO MAKE IT HAPPEN? ALRIGHT, SO LEMME TEE US UP.

OF COURSE, OF COURSE.

YEAH.

AND WE'RE GETTING SOME FEEDBACK ON THE PHONE IF YOU CAN MUTE YOURSELVES AND OFF WE GO.

, YES, ? UH, YES, WE HEAR YOU TALKING.

IF YOU'RE LAUGHING, WE HEAR YOU.

IF YOU CAN PLEASE MUTE YOURSELF.

WE'RE GONNA TRY TO FIND THE HAMMER, BUT IF WE CAN'T, THERE'S ONLY 166 TO GO THROUGH HERE.

SEE IF I CAN FIND IT.

ALL RIGHT.

OKAY.

YEAH.

SO WE, I LOOKED AT, UM, GOTHAM.

THERE IT IS.

OKAY, THAT'S FUN.

SUCH POWER .

ANYONE ELSE? OKAY, LET'S START THE MEETING.

OKAY, IT'S MONDAY.

GOOD MORNING, HAVE SOME COFFEE.

MY NAME'S MATT MARINAS ON BEHALF OF THE TEAM.

WELCOME.

WE'RE HONORED TO BE HERE AND START TO WALK THROUGH THE UPDATE FOR WORKSHOP NUMBER SIX.

UH, I JUST DID THE VOICEOVER ON THIS.

AGAIN, THESE FOUR STAKEHOLDER SETS WILL HIT PLUS ANDRE, UH, IN TERMS OF TIMELINE AND

[00:05:01]

GOVERNANCE, WE ARE ALREADY WORKSHOP SIX TIME FLIES, AND WE'RE GONNA HAVE ANOTHER MEETING NEXT WEEK.

UM, AND THE IDEA IS AS WE GET TO THE END OF THAT WORKSHOP SEVEN NEXT WEEK, THE ASSUMPTION WITH TAC LEADERSHIP HAS BEEN TO THEN PIVOT INTO DEDICATED ROS WORKSHOPS AND OR PRS WORKSHOPS TO GET US THE REST OF THE WAY.

YOU SAY, WELL, WILL IT CHANGE? WELL, IN SOME WAYS, NO, IT'S STILL HERE, IT'S STILL, EVERYONE'S WELCOME IT AND CAN SAY WHAT THEY SAY, BUT WE START TO HAVE THE VOTING MEMBERS AROUND THE TABLE BECAUSE IT'S THE VOTERS THAT ARE GONNA GET THIS OFF OF THE, UM, ESPECIALLY ON THE PLANNING GUIDE REVISION FOR ROS IS THE VOTING STRUCTURE TO GET IT OUT.

AND THEN ON THE PRS SIDE IS THE NPRR.

SO THAT'S WHY YOU START TO SAY WHY IF THE WORKSHOPS GO AWAY, WHAT TAKES THEIR PLACE.

BECAUSE IF YOU NOTICE, WE'RE STILL GONNA HAVE A MEETING EVERY WEEK FOR THE ALL OF APRIL.

SO WE GET TO SEE EACH OTHER ALL THE TIME.

UM, AND AGAIN, ERCOT HAS A, UH, THE ASPIRATIONAL, SO WE BELIEVE WE HAVE WHAT WE NEED TO GET THE, UH, CONTROL LOAD RESOURCE NPRR POSTED BY APRIL 8TH.

UH, THAT'S STILL A LOT OF WORK TO BE DONE.

UH, AGAIN, AG AND THE TEAM HAVE BEEN WORKING ON THAT.

THE BYOG, WE PROBABLY WON'T HIT THAT APRIL 8TH, I'LL JUST BE HONEST.

BUT WE HOPE TO BRING MORE INFORMATION TO THE APRIL 9TH MEETING, UH, THAT WE MAY HAVE.

UH, ONE PIECE, I CAN'T REMEMBER IF IT'S IN THE SLIDES HERE, IS WE DO WANT TO GET OUR NEXT ROUND OF COMMENTS OUT, UM, A WEEK AHEAD OF THE NEXT MEETING.

I THINK THAT'S ON THE NEXT SLIDE.

REMINDER OF HOW TO FILE COMMENTS.

SO ON THE PUC SIDE, I'M, I'M GOING OFF SCRIPT HERE.

UH, WE ARE GETTING A LOT OF QUESTIONS ERCOT ON HOW THIS IS INTERPRETED, HOW THIS SHOULD BE DONE, EDUCATIONAL SLIDES, WE'RE STRUGGLING TO KEEP UP WITH ALL THE OTHER TECHNICAL DETAILS.

IF SOMEONE WANTS TO OWN AND OR PRESENT ON FINANCIAL STUFF AT THE NEXT MEETING, I WOULD WELCOME THAT PERSON THAT SAYS, I WANT TO TACKLE THIS AND TALK ABOUT FOLLOW THE MONEY, FOLLOW THE EXAMPLE ON YOUR UNDERSTANDING OF HOW IT WORKS.

AND BARKSDALE MAY, I'M SEEING IF I'M GETTING SHOOTING DARTING EYES AT HIM.

BUT IF YOU ARE SOMEONE THAT'S DEEPLY IN TUNE WITH THIS, YOU'RE ASKING A LOT OF PEOPLE THAT ARE WORKING THE ENGINEERING SIDE, THE FINANCIAL SIDE, WE'D LIKE TO OFFLOAD THAT TO SOMEONE FOR THE NEXT WORKSHOP IF SOMEONE WANTS TO VOLUNTEER.

SO WHETHER YOU WANNA BE THE SUPERHERO TODAY OR EMAIL ME AFTER THE FACT, THAT WOULD BE FANTASTIC SUPERHERO.

ALRIGHT, BARATH, THANK YOU.

THANK YOU.

WHAT DOES BARATH NEED TO BRING TO US FOLKS BE THINKING ABOUT? WHAT IS IT? SO HE'S GONNA BRING US A ROCK.

I DON'T WANT HIM TO BRING A ROCK.

AND PEOPLE ARE LIKE, THAT'S NOT THE ROCK WE NEED.

HERE'S WHAT WE'RE CONFUSED ON.

UM, AND MAYBE TODAY IS THE MEETING UNFOLDS.

SOME OF THE COMMENTS THAT CAME IN ARE ABOUT THE FINANCIAL SIDE.

SO, YOU KNOW, WE CAN KIND OF MENTALLY BE KEEPING TRACK OF ANY CONFUSION THAT WE HAVE AND HOW THAT MET KIM FORWARD.

THANK YOU.

AND AGAIN, PEOPLE MAY SAY, WHY, WHY AREN'T WE, OH, GO AHEAD, JEFF, FINISH YOUR THOUGHT.

AND THEN I ADD A COUPLE COMMENTS.

WHY IS ERCOT NOT TRYING TO TAKE THIS HEAD ON? THIS HAS BEEN, AGAIN, WE'RE TRYING TO SHADOW WHAT'S HAPPENING AT THE COMMISSION.

UH, THE IDEA IS ALL OF THAT FINANCIAL AND THE DECISIONS AROUND IT ARE THAT IS THE MODEL THAT WE'RE FOLLOWING.

UH, BARKSDALE AT THE LAST MEETING TALKED ABOUT, THERE MAY BE A FORK IN THE ROAD BASED ON TIMING AS WE GET TO BATCH ZERO, WHERE THERE MAY BE A, YOU KNOW, BREAK LEFT AND THEN FINISH IT OFF.

UH, BUT WHEN IT COMES TO RIGHT NOW FOLLOWING THE MONEY BASED ON WHAT'S ALREADY IN THE, UH, THE PFP, UH, THAT'S WHERE I'M CONCERNED WHETHER OR NOT TO USE SOME HELP.

BUT JEFF, YOU CAN OVERRIDE ME ON ANY OF THIS.

GO AHEAD, MR. BILLOW.

WELL, I, I THINK YOU, YOU COVERED PART OF WHAT I WAS GONNA SAY IS, IS A LOT OF THIS IS, UH, AT, AT THE COMMISSION FOR 58 41.

SO IT, I THINK WHAT WE DON'T WANT IS, I DON'T LIKE WHAT THE COMMISSION RULES ARE.

THAT THAT'S NOT TO DISCUSS HERE.

LIKE WE, WE ARE GOING TO TAKE WHATEVER THE DIRECTION WE GET FROM THE COMMISSION AND THAT THAT'S WHAT WE'RE GOING TO IMPLEMENT.

UH, SO IF YOU HAVE COMMENTS ON SPECIFICS ON 58 41, UM, MARKDALE MENTIONED IT MULTIPLE TIMES THAT THERE'S A COMMENT PROCESS AT THE COMMISSION FOR THAT.

UM, THE, THE OTHER THING THAT, UM, I, I THINK THAT WE HAVE BEEN TAKING FOR GRANTED, BUT WE, WE'VE GOT A LOT OF COMMENTS ABOUT THIS.

UH, AND, AND SO WE ADDED A NOTE IN RED ON THIS SLIDE.

UH, SO TO CLARIFY, SO OUR, OUR INTENTION IS, UH, IF WE THINK ABOUT BATCH ZERO, UH, WE'RE GOING TO FOLLOW THE WHATEVER 58 41 DRAFT PFP SAYS, WE'RE GOING TO TAKE THAT, UH, AS WE GO INTO THE BATCH ZERO.

SO ELIGIBILITY TO GET IN WILL BE BASED ON THAT 58 41 RULE.

UM, HOWEVER, UH, SO, SO THAT STARTS THIS SUMMER.

UH, THE RULEMAKING WE EXPECT TO BE DONE, UH, I DON'T RE REMEMBER THE DRAFT TIMELINE, BUT I THINK SAY EARLY FALL, ROUGHLY, UM, BAT ZERO GETS COMPLETED IN JANUARY OF NEXT YEAR.

UH, AND SO OUR INTENTION IS IT IF THE INTERCONNECTION AGREEMENT REQUIREMENTS IS AN EXAMPLE OF THAT, IF THOSE FINANCIAL REQUIREMENTS, IF THOSE CHANGE THAT FINANCIAL SECURITY REQUIREMENTS, IF THOSE CHANGE IN, UM,

[00:10:01]

YOU KNOW, SAY SEPTEMBER OR WHENEVER IT IS THAT 58 41 GETS FINALIZED, THEN WE WILL FILE A PIGGER TO UPDATE THOSE REQUIREMENTS IN THE PLANNING GUIDE SUCH THAT IN, UH, JANUARY WHEN BACTERIA WAS DONE, THE REQUIREMENTS THAT LOAD LOADS WILL NEED TO MEET WILL MATCH WHATEVER THE FINAL IS IN 58 41.

UH, SAME THING ON THE TIMELINE.

WE'VE BEEN GETTING A LOT OF COMMENTS ABOUT, HEY, 30 DAYS IS REALLY SHORT, UH, 30 DAYS COMES, UH, STRAIGHT OUT OF 58 41.

IF THAT CHANGES, THEN WE WILL CHANGE THE, UH, THE PLANNING GUIDE WITH A, A NEW PICKER THAT, UH, WE WOULD HOPE TO GET IMPLEMENTED BY, UH, JANUARY.

UH, SO JUST WANT, WANTED TO MAKE THAT, UH, CLARIFICATION TODAY.

THANK YOU SO MUCH, JEFF.

THANKS.

THANKS ALL THAT, MATT AND JEFF, UM, I ALSO JUST WANNA SAY THAT FOR THE RULEMAKING PROCESS, THE COMMENT DEADLINE 4 58 41 IS APRIL 17TH, WHICH HAPPENS TO BE THE DATE OF AN OPEN MEETING.

AND, UM, MAY BE, AND I'M NOT PROMISING ANYTHING, BUT IT MAY BE AN OPPORTUNITY FOR THE COMMISSIONERS TO WEIGH IN, UM, ON THE DEVELOPMENT OF BATCH ZERO SPECIFICALLY.

SO THIS IS A LITTLE BIT OF A UNIQUE SITUATION HERE IN TERMS OF OUR RULE MAKING AND WE'RE TRYING TO LINE ALL OF THESE THINGS UP AT THE SAME TIME.

YOU MAY WANT TO CONSIDER FILING SOME COMMENTS PRIOR TO APRIL 17TH.

IF YOU ARE SERIOUSLY CONCERNED, ESPECIALLY ABOUT THE FINANCIAL SECURITY PIECE, YOU CAN SUBMIT MORE THAN ONE SET OF COMMENTS, THAT'S OKAY.

UM, YOU JUST HAVE TO HAVE YOUR COMMENTS IN BY APRIL 17TH, UM, IN ORDER FOR THEM TO, YOU KNOW, BE OFFICIALLY CONSIDERED, UH, IN THAT RULEMAKING PROCESS.

THE OTHER THING THAT I'D LIKE TO ADD, IF THAT'S OKAY, MATT, IS UM, WHATEVER OUR SUPERHERO IS GONNA BE TAKING ON IN TERMS OF PRESENTING ON FINANCIAL SECURITY, I WANNA MAKE SURE THAT NO ONE IS TAKING ANYTHING THAT'S BEING SAID HERE OR THAT MAY BE SAID IN THE FUTURE AS LEGAL COUNSEL ABOUT WHAT DOES THE PROPOSED RULE OR THE PROPOSED NPRR OR PIGGER MEAN FOR MY PROJECT SPECIFICALLY.

AND THEN IF THAT ADVICE TURNS OUT TO NOT BE EXACTLY RIGHT FOR YOUR SPECIFIC PROJECT, DON'T COME CAST IN KRYPTONITE, ROCKS OUT OUR MAN OVER HERE.

SO VERY GOOD.

THANKS.

ALL RIGHT.

AND WE HAD A COUPLE QUESTIONS COME IN.

UM, FIRST OF ALL IS KENT WINDROW, GO AHEAD.

THANKS, KENT.

WITHROW WITH CUSTOMIZED ENERGY SOLUTIONS.

I GUESS THIS COMMENT IS FOR BAR ROTH IF YOU'RE FOLLOWING THE MONEY, THE QUESTION THAT WE SEE POPPING UP OVER AND OVER IS JUST ON THE, THE FINANCIAL SECURITY REQUIREMENT.

UM, AND BASICALLY DOES THE $50,000 PER MEGAWATT FROM THE INTERMEDIATE AGREEMENT STAGE, HOW MUCH OF THAT ROLLS OVER TO THE INTERCONNECTION FEE, UM, FEE, UH, STAGE, UM, AT THE INTERCONNECTION AGREEMENT, UM, PHASE OF THE PROCESS? SO IS IT ALL OF IT ROLLS OVER, NONE OF IT ROLLS OVER, OR IT CAN PARTIALLY, UM, ROLL OVER AND BE APPLIED? THE INTERMEDIATE AGREEMENT PART CAN BE APPLIED AS AS, UM, PART OF THE INTERCONNECTION FEE.

THAT'S THE QUESTION THAT SEEMS TO BE, THERE SEEMS TO BE A COUPLE DIFFERENT INTERPRETATIONS OF AT LEAST THE DRAFT RULE AS IT STANDS FLOATING AROUND OUT THERE.

AND THAT'S WHAT SEEMS PEOPLE SEEMS TO BE, UH, PRIMARILY CONCERNED ABOUT.

SO YOU DIRECTED THAT TO BROTH.

SO IF YOU CAN TACKLE THAT, THAT WOULD BE GREAT.

YEAH.

SO BRO, DO YOU WANNA RESPOND? YEAH, I MEAN BOX STILL CAN ADD TO THIS, BUT I THINK MY UNDERSTANDING IS YOU POST AT THE INTERMEDIATE STAGE $50,000 PER MEGAWATT AND IT GOES FIRM OR NON-REFUNDABLE INTER INTERCONNECTION STAGE.

IS THAT ACCURATE AS PER THE CURRENT DRAFT ? WELL, LET'S JUST, LET'S NOT TRY TO GET PEOPLE ON RECORD FOR WHAT WE THINK IT ALL, HOW'S IT GONNA WORK? SO YEAH, BUT WE HEAR THE QUESTION.

I THINK THAT WAS THE NEXT QUESTION THAT CAME THROUGH THROUGH AI IS THE TAG ON IT.

IF YOU CAN LOG IN AS YOUR NAME OR YOUR COMPANY, THAT WOULD HELP.

I'M NOT USUALLY GONNA CALL ON AI, UM, BUT SIMILAR QUESTION ABOUT THE 50,000 AT THE, UH, INTERMEDIATE AND THE INTERCONNECTION.

UH, EXACTLY.

THANK YOU.

YOU BET.

ALRIGHT, AND THEN DANIEL MCGRAW, I GUESS YOUR HAND WENT UP AND BACK DOWN.

DID YOU WANT HAVE SOMETHING TO ASK? WE PUT YOU IN THE QUEUE.

ALRIGHT, WE'LL LET THAT ONE GO.

SO WE'LL CLEAR THE QUEUE AT THIS POINT AND MOVE ON.

THANK Y'ALL.

UH, YEAH, GO AHEAD RAY IF YOU GOT A QUICK ONE.

CAN YOU GUYS HEAR ME ALRIGHT? YES, WE CAN, SIR.

AWESOME.

JUST A QUICK QUESTION.

UH, THANKS RAY COREY, ENERGY POLICY MANAGER AT AMAZON WEB SERVICES.

JUST A QUICK QUESTION ON THE, THE, UM, FINANCIAL SECURITY AND AND COSTS.

DO WE ANTICIPATE THERE BEING A, A TOTAL CAP FOR WHAT YOU PAY FOR THESE INTERCONNECTION

[00:15:01]

FEES OR IS IT UNLIMITED TO THE POINT OF WHAT YOU ARE SUBMITTING AS A MEGAWATT? THANKS.

ALL RIGHT.

THAT'S SOMETHING WE CAN TAKE INTO ACCOUNT, IS THAT PART OF THAT WRITEUP? OKAY, THANK YOU.

ALRIGHT, OFF WE GO.

SO MARCH 4TH IS WHEN WE FILED THE ERCOT, WE, SORRY, FILED THE BATCH ZERO FIGURE 1 45 AND NPR 1325.

ALL THE COMMENTS TO DATE HAD BEEN ON P 1 45 BECAUSE THAT'S WHERE 99% OF THE INFORMATION IS.

UH, ERCOT POSTED ITS INITIAL SET OF COMMENTS ON MARCH 17TH, WHICH WAS MID MONTH.

WE'RE HERE AT THE END OF THE MONTH.

WE'RE GETTING READY TO THIS WEEK RELEASE THE NEXT ROUND OF COMMENTS, PART OF WHICH THE DISCUSSION TODAY WILL HELP WITH ALSO, IT'S A BIG BACKLOG OF 21 SETS OF COMMENTS TO NAVIGATE THROUGH AND MAKE SURE WE'VE CAUGHT EVERYTHING.

SO, UM, WORKSHOP NUMBER SIX TODAY IS THE MAJOR THEMES.

YES, HERE WE ARE APRIL 2ND TARGET FOR THE SECOND SET OF COMMENTS, WHICH WILL BE A WEEK BEFORE WORKSHOP NUMBER SEVEN, UM, TO THEN GO THROUGH.

WE WILL HAVE GIVEN YOU OUR COMMENTS A WEEK AHEAD OF THE MEETING.

SO THEN YOU CAN FILE COMMENTS AND WE COME TO THE MEETING AND I'LL PUT A DATE ON THERE PROBABLY TWO DAYS BEFORE THE WORKSHOP TO SAY WHOEVER GETS THEIR INFORMATION IN OR COMMENTS IN BY THEN CAN THEN PRESENT ON THEIR COMMENTS LIKE WE DID BEFORE.

SO WE'LL DO THAT ROUND ONE MORE TIME.

AND THEN AGAIN, THE IDEA OF CONTROLLABLE LOAD RESOURCE AND BYOG, GETTING THAT OUT AND THE LONG TERM BATCHES OUT OF SCOPE FOR NOW.

HEY MATT, REAL QUICK? YES, JEFF.

UM, SO JUST BE TRANSPARENT.

I THINK APRIL 2ND ASPIRATIONAL TARGET.

I THINK FRIDAY IS MORE LIKELY, UH, FOR OUR SECOND SET OF COMMENTS.

UM, BUT WE, WE WILL SEE WHAT WE CAN DO.

ALRIGHT, VERY GOOD.

THANKS JEFF.

ALRIGHT, UM, P 1 45

[3. Review any new comments received]

FEEDBACK.

SO HERE'S WHERE I'M GONNA PAUSE.

SO, UM, AGAIN, ANJI TRACK, CRUSO AND SHOPPER, UH, ALL FILED COMMENTS AND WE CAN GO IN ORDER OF THE AS RECEIVED.

UM, I EMAILED THEM BUT I DID NOT TRY TO ASK FOR CONFIRMATION ONE WAY OR THE OTHER.

SO BOB HILTON, DID YOU WANT TO TAKE ON A SET OF COMMENTS THAT I CAN OPEN FOR YOU? UH, SURE, YEAH, I MINE MINE'S REAL QUICK, SO, YEP.

YOU CAN START WHILE I'M GETTING THERE OR YOU CAN PAUSE 10 MORE SECONDS HERE.

YEAH, I MEAN REALLY I, I'M NOT GONNA READ THROUGH 'EM 'CAUSE THEY ONLY HIT ONE ISSUE AND THAT'S THE, UH, USING THE RETROACTIVE DATES, YOU KNOW, WHICH IS THE MARCH 4TH DATE RATHER THAN LOOKING AT A DATE, YOU KNOW, AFTER APPROVAL OF THE PI BY THE COMMISSION, WHICH WE, YOU KNOW, KIND OF TIED THAT IN WITH WHAT, UH, WAS IN THE ENCORE COMMENTS OF THE JULY THE 10TH, UH, SO THAT WE COULD KEEP THAT ALL CONSISTENT.

UH, AND, AND ACTUALLY IF YOU GO BACK AND LOOK AT OUR COMMENTS BACK, UH, BEFORE WHEN YOU WERE GOING AFTER THE, UH, GOOD CAUSE EXEMPTION, WE COMMENTED ON THE SAME ISSUE, DIFFERENT DATE, BUT THE SAME ISSUE.

SO, UH, WE JUST ARE TRYING TO CARRY CONSISTENCY THROUGH THAT AND TO IMPLEMENT THIS ONCE IT'S APPROVED RATHER THAN HAVING PIECES OF IT BEING IMPLEMENTED BEFORE IT'S APPROVED AND USING THOSE DATES.

SO THAT, THAT'S REALLY OUR, OUR EARLY COMMENT.

SO I THINK THEY'RE, THEY'RE, THEY'RE PRETTY SELF-EXPLANATORY ON THAT.

GREAT, THANK YOU.

SO THAT'S .

ALRIGHT, ANY QUESTIONS FOR BOB? ALL RIGHT, GO AHEAD AND SHUT THIS ONE DOWN.

NEXT ONE WAS TRACKED.

DID SIR.

GOOD MORNING.

THIS IS OR ALWOOD TRACKED.

MATT, CAN YOU HEAR ME? YES, YOU SURE CAN.

GO AHEAD, SIR.

GREAT, THANK YOU.

UM, THANKS AGAIN TO ERCOT FOR, FOR THIS WHOLE PROCESS.

I'VE BEEN THE UNFORTUNATE VETERAN WITH LOTS OF GENERATOR INTERCONNECTION AND LOAD INTERCONNECTION QUEUE REFORMS, AND THIS HAS DEFINITELY BEEN THE MOST, UM, UH, THE, THE MOST AMOUNT OF FEEDBACK WE'VE RECEIVED FROM, FROM THE REFORMING ENTITY.

SO REALLY APPRECIATE ALL THE FEEDBACK AND THE CHANGES.

UM, WE'VE MADE SIX PROPOSED REVISIONS, UH, TO THE PGRR IN IN THIS COMMENT.

UH, I'M NOT GONNA GO IN DEPTH ON ALL SIX, UM, BUT I'LL, I'LL TOUCH A FEW OF 'EM IN PARTICULAR.

SO THE FIRST IS REQUIRING THE REFUND OF THE BAT ZERO BASE LOAD NON, UH, REFUNDABLE FEE IF THAT BASE LOAD IS INVALIDATED, UM, AND KICKED TO THE STUDIED OR ALLOCATED BUCKET OF BADGE ZERO.

UM, IN JU THE WAY IT'S PROPOSED IN JULY, UM, UH, AN ILLE WOULD HAVE TO PUT DOWN THE NON-REFUNDABLE FEE IN ORDER TO GET INTO BATCH ZERO BASE, BUT IN AUGUST, UM, THAT ILLE COULD BE TOLD THAT THEIR STUDIES ARE INVALID, UH, BY ERCOT AND THEREFORE THEY WOULD BE STUDIED AS PART OF BAT ZERO STUDIED OR ALLOCATED.

WHEN THEY GO THROUGH BAT ZERO, STUDIED OR ALLOCATED, THEY COULD END UP RECEIVING FEWER MEGAWATTS IN WHAT THEY'VE REQUESTED, INCLUDING THEY ZERO MEGAWATTS.

[00:20:01]

AND SO WE THINK IT'S IN UNE INEQUITABLE AND, AND UNINTENDED THAT, UH, AN ILLE WITH AN ALLOCATION OF ZERO MEGAWATTS WOULD HAVE TO BE CHARGED AND NOT A NON-REFUNDABLE FEE IN THE AMOUNT OF $50,000 PER MEGAWATT.

UM, WE THINK IN THE LAST WORKSHOP, ERCOT ACKNOWLEDGED THIS ISSUE.

UM, AND, AND SO WE HOPE YOU ALL ARE WORKING ON CHANGES TO IT.

WHAT WE RECOMMEND IS BASICALLY YOU HAVE ONE EXCEPTION FOR WHEN THIS NON-REFUNDABLE FEE DOES BECOME REFUNDABLE.

AND THAT ONLY EXCEPTION WOULD BE WHEN ERCOT DEEMS THE ILLE, UH, STUDIES TO BE INVALID, UM, THAT ILE WOULD STILL HAVE TO PUT UP THE NON-REFUNDABLE FEE IF THEY PROCEED TO THE, TO THE JANUARY OR FEBRUARY, UM, FULL BATCH STUDY.

AND AT THE POINT THAT THEY HAVE TO PUT DOWN THEIR COMMITMENT IN THAT FEBRUARY OR MARCH 27 TIMEFRAME, THEN THEY'D HAVE TO PUT DOWN THE NON-REFUNDABLE FEE.

UM, SECOND ARGUMENT, HEY, REAL QUICK, LET ME JUST YEAH.

POINT.

SO AS YOU SAID, ERCOT NEEDS TO CONSIDER THAT WOULD BE THE WORLD THAT, THAT'S THE PUC DECISION.

SO WHAT WE HAVE IN THE PIGGER IS REFLECTIVE OF THE PUC OH, WHOA, WHOA, WHOA, SORRY.

ERCOT ACKNOWLEDGED THIS LAST TIME THAT THEY WERE WORKING ON THAT ER, ERCOT ACKNOWLEDGED THIS LAST TIME THAT THEY WERE WORKING ON THIS.

WE JUST WANNA MAKE SURE THAT'S THE CASE AND THAT WE'RE AVAILABLE TO WORK ON LANGUAGE, UM, WITH YOU GUYS.

SORRY.

NOPE, THAT'S ALL RIGHT.

CHRISTINA SWITZER, OUR SENIOR REGULATORY COUNCIL.

THAT IS SOMETHING WE ACKNOWLEDGED LAST TIME AND ARE WORKING ON.

IT'S, IT'S THE TIMING OF WHICH AGREEMENT YOU HAVE TO PROVIDE, WHEN AND HOW AND WHICH BUCKET YOU'RE THEN IN FOR WHETHER YOU'RE STUDIED OR BASE LOAD.

SO THAT IS SOMETHING WE'RE AWARE OF AND ARE LOOKING AT HOW TO ADDRESS.

ALRIGHT, MY COMPLETE APOLOGIES OR, UM, SO YOUR QUESTION IS VALID.

I WAS WRONG.

YOU'RE RIGHT.

LET'S KEEP GOING.

ALRIGHT, THANK YOU.

POINT TWO.

NO, NO WORRIES.

THANK YOU.

UM, THE, THE SECOND POINT IS, IS THE SAME ONE THAT BOB JUST HIT, WHICH IS ALLOW PROJECTS WHOSE STUDIES ARE COMPLETED BY THE TIME THAT ERCOT PGRR BECOMES EFFECTIVE FOR THOSE STUDIES TO BE USED TO GET INTO BAT ZERO BASE.

UM, WE THINK THAT THE MARCH 4TH CUTOFF IS, UH, UNJUSTIFIED, UH, RESULT IN WASTE.

UM, THOSE HAVE ALL BEEN TALKED ABOUT.

THE ONE I WANT TO TALK, THE ONE REASON WHY WE THINK THAT, UM, THIS SHOULD BE CHANGED, UH, THAT I DON'T THINK HAS BEEN TALKED ABOUT AS MUCH IS BECAUSE OF THE EXISTING GUIDANCE BY PUCT, UM, AT THEIR FEBRUARY OPEN MEETING, UM, THAT SAID THAT, YOU KNOW, PLANNING GUIDE SECTION NINE PGR ONE 15 IS THE LAW OF THE LAND.

THAT IS WHAT IS EFFECTIVE.

AND IF YOU MOVE WITH THIS MARCH 4TH CUTOFF DATE, THEN ESSENTIALLY THAT, THAT, THAT DOESN'T ALLOW FOR THE EXISTING LAW OF THE LAND, UM, TO, TO, TO BE THE WAY THAT PROJECTS MOVE FORWARD.

UM, SO THOSE PROJECTS THAT HAVE BEEN MOVING FORWARD, UM, SOME OF THESE, YOU KNOW, SOME OF THESE RPGS THAT WERE SUBMITTED IN IN SPRING OR SUMMER OF 25.

SO IT'S NOT LIKE THESE ARE LATE DELUGE ISSUES, UM, WHICH WE TOTALLY UNDERSTAND AND WE THINK THAT THE DECEMBER CUTOFF TAKES CARE OF, OF THE DELUGE CONCERN.

UM, BUT WE DO THINK THAT BECAUSE THE PUC SAID THE LAW OF THE LAND REMAINS IN PLACE UNTIL THIS PGR 1 45 IS ADOPTED, THAT THOSE STUDIES WHO FOLLOWED THAT EXISTING LAW, IF THEY ARE COMPLETED BY THE TIME THAT THE THE REVISION REQUEST BECOMES EFFECTIVE, SHOULD BE ALLOWED TO USE THOSE STUDIES TO QUALIFY FOR BADGE ZERO BASE.

UM, WE THINK THAT ULTIMATELY TAKES CARE OF THE UNDERLYING CONCERN, WHICH IS THAT THOSE STUDIES SHOULD HAVE COMPLETED RELIABLE WAYS TO, TO INTERCONNECT TO THE GRID IN A RELIABLE FASHION.

UM, AND SO WE, WE, WE THINK THAT STUDIES THAT COMPLETE BY JULY 10TH SHOULD BE ALLOWED TO BE USED TO GET INTO BAT ZERO BASE.

UM, THIRD ARGUMENT, UM, I I WON'T GET INTO MUCH HERE, MATT, BECAUSE A A AS YOU SAID, YOU KNOW, REALLY THESE ARE ARGUMENTS, UM, IN FRONT OF THE PUCT FOR 5 8 4 8 1.

SO WE WILL ADDRESS THOSE IN COMMENTS DUE TO THE COMMISSION, UM, BY APRIL 17TH.

THE ONLY THING I WANT TO P POINT OUT HERE IS THAT, YOU KNOW, WHILE THE PUC IS DECIDING WHAT SHOULD BE THE STANDARDS FOR NEW INTERCONNECTION REQUESTS, WE THINK IT'S WELL WITHIN ERCOT DISCRETION AND, AND ERCOT JURISDICTION TO DECIDE WHO GETS INTO BADGE ZERO.

UM, AND SO WE DON'T THINK YOU, YOU HAVE TO BE, UM, YOU HAVE TO BE WEDDED TO WHAT THE PUC LANGUAGE IS, ESPECIALLY BECAUSE THE PUC LANGUAGE IS GOING TO BE ISSUED IN FINAL ORDER AFTER BAT ZERO BASIS SORT OF, UM, INTAKED IN JULY.

UM, BUT I, I RESPECT THAT THAT'S REALLY AN ARGUMENT IN FRONT OF THE PUCT, SO WE CAN SKIP THE REST OF THAT FOR NOW.

UM, SAME THING WITH REMOVING NON-REFUNDABLE SECURITY.

WE'LL ADDRESS THIS IN OUR COMMENTS TO PUCT,

[00:25:02]

BUT ULTIMATELY THE POINT IS THAT FOLKS WILL BE SIGNING UP FOR AN INTERMEDIATE AGREEMENT WITH 50 K PER MEGAWATT DOWN, AND 80% OF THAT IS POTENTIALLY NON-REFUNDABLE EVEN BEFORE THE ILE KNOWS IT'S CAPACITY TIMING OR ULTIMATE COST OF ITS LOAD RAMP.

UM, WE THINK THAT'S INEQUITABLE AND THAT'S GOING TO SIGNIFICANTLY INCREASE THE COST OF OBTAINING FINANCIAL SECURITY.

IT'S NOT GONNA BE THE ONE TO 3% CARRY COST THAT I THINK FOLKS ARE GENERALLY, UH, FAMILIAR WITH.

AND FROM OTHER CONTEXT, IF IT'S 80% NON-REFUNDABLE BEFORE YOU KNOW ANYTHING, THEN THE, THE CARRY COST IS ALSO GONNA BE VERY HIGH.

UM, SO WE'LL ADDRESS THAT FURTHER BEFORE THE PUCT BY APRIL 17TH.

UM, AND, AND THEN THE NEXT TWO ARE CLARIFICATIONS, WHICH WE THINK ERCOT HAS ALREADY SIGNALED THAT IT'S ON BOARD WITH, BUT WE JUST WANNA MAKE CLEAR IN THE LANGUAGE.

SO, SO THAT'S THE FIRST, UM, REGARDING THE REFINEMENT STUDY PROCESS, UM, IT'S CLEAR FROM THE PGR LANGUAGE THAT THE LOAD RAMP WON'T CHANGE POST THE REFINEMENT STUDY.

HOWEVER, WE THINK IT SHOULD ALSO BE CLEAR THAT THE COST OR FINANCIAL OBLIGATIONS IMPOSED ON THE ILLE WILL ALSO NOT CHANGE AS A RESULT OF THE REFINEMENT STUDY.

IN COMMENTS AT THE LAST TWO WORKSHOPS, ERCOT HAS INDICATED AS MUCH SAYING THAT, YOU KNOW, IT'S, IT'S NOT TECHNICALLY POSSIBLE FOR ADDITIONAL UPGRADES TO BE IDENTIFIED AND THEREFORE COST, UM, ALLOCATED TO THE ILLE TO INCREASE.

SO WE THINK YOU SHOULD JUST PUT THAT IN LANGUAGE RIGHT NOW IN THE PGRR.

IT, IT SAYS THAT FOR THE LOAD RAMP, BUT WE THINK YOU CAN JUST ADD, YOU KNOW, FINANCIAL OBLIGATIONS, OR EXCUSE ME, FINANCIAL SECURITY OR COST OBLIGATIONS TO THAT SAME LANGUAGE TO MAKE SURE THAT THE REFINEMENT STUDY DOESN'T INCREASE THE LES'S ALLOCATED COSTS.

UM, AND THEN FINALLY AGAIN, WE THINK THIS IS, THIS WAS INTENDED BY ERCOT, BUT IT'S JUST NOT IN THE LANGUAGE AND THAT'S BADGE ZERO BASE LOAD SHOULD PROCEED THROUGH THE LEGACY PROCESS.

BASICALLY WHAT WE MEAN BY THIS IS THAT ONCE YOU GET INTO BAT ZERO BASE AND UNDER 9 2 1 4 SUB THREE ERCOT DETERMINES YOUR STUDIES ARE VALID, THEN YOU SHOULDN'T HAVE TO ENTER INTO ANY ADDITIONAL AGREEMENTS OR GO THROUGH ANY ADDITIONAL STUDIES BEYOND THOSE THAT A LEGACY LOAD WOULD HAVE TO GO THROUGH, FOR EXAMPLE, APPROVAL TO ENERGIZE OR GETTING IN THE QUARTERLY STABILITY ASSESSMENT.

WE THINK THAT'S ALL THAT SHOULD BE REQUIRED OF THE BAT ZERO BASE LOADS.

BUT THERE'S PARTS OF THE PIGGER THAT SAY, IF YOU'RE IN BAT ZERO BASE, THEN THE BATCH STUDY APPLIES TO YOU.

UM, AND SO WE, WE DON'T THINK THAT'S WHAT WAS INTENDED.

AND SO WE HAVE RECOMMENDED SOME LANGUAGE TO CLARIFY THAT ONCE YOU'RE FOUND VALID AS PART OF BAT ZERO BASE, THEN YOU HAVE NO FURTHER STUDIES OR AGREEMENTS OR OBLIGATIONS UNDER THE BATCH STUDY PROCESS AND YOU JUST CONTINUE TO ENERGIZE UNDER THE EXISTING LEGACY PROCESS.

SO THOSE ARE ALL OUR COMMENTS.

HAPPY TO ANSWER ANY QUESTIONS.

EXCELLENT, THANK YOU.

ANY QUESTIONS IN THE ROOM OR ONLINE? GIVE PEOPLE A MINUTE.

THERE'S NONE IN THE ROOM.

I'LL SEE IF THERE'S ANY QUESTIONS IN THE QUEUE.

ALL RIGHT, THANK YOU SO MUCH.

THANK YOU.

ALL RIGHT, NEXT UP IS CRUSO ROTH, ARE YOU GONNA WALK THROUGH THESE WITH US? YEAH, I CAN GO THROUGH THIS HERE.

YOU CAN COME HERE OR I CAN STAY RIGHT HERE.

HAPPY TO DO SO.

YEAH, I CAN GO FROM, SO OVERARCHING, UH, I'VE USED THREE TOPICS TO DISCUSS IN THIS.

NUMBER ONE, THE SSO TIMING.

UM, IF YOU GO TO PAGE TWO, I THINK THE CONCLUSION KIND OF CLEARLY, UH, I LAID OUT THERE THAT I, WE RESPECTFULLY REQUEST OUR COURT TO REVISE SECTION 9.6 C AND D, UH, OF PEGA 1 45 TO DECOUPLE SSO STUDY COMPLETION FROM QSA PREREQUISITE FOR INITIAL ENERGIZATION.

UH, I THINK THIS IS CONSISTENT WITH AN PARALLEL TRACK APPROACH THAT APPLIES TO GENERATE INTERCONNECTIONS.

UM, YOU KNOW, UH, RIGHT NOW WE NEED TO FINISH SSO BEFORE WE ENTER INTO QSA.

UM, SO I DO NOT FIND ANY TECHNICAL BASIS, UH, FOR THAT.

SO I APPRECIATE KO'S, UH, UH, ERCOT LOOKING INTO THIS AND COMING BACK TO US ON THAT, UH, ASPECT.

THE SECOND ONE IS THE FINANCIAL COMMITMENTS AND TIMING.

UM, I THINK I'VE SPOKEN ABOUT THIS LAST TIME AS WELL.

UM, I SEE BATCH ZERO AS CONSISTING OF THREE DIFFERENT TYPE OF LOADS.

LOADS THAT HAVE ALREADY

[00:30:01]

MET.

9.4 OR 9.5 ARE LOADS THAT DO NOT HAVE ANY UPGRADES THAT HAVE BEEN APPROVED.

SECOND ONE LOADS THAT ALREADY POSTED KAYAKS AND SECURITIES THAT ARE NEEDED AND HAVE BEEN GOING THROUGH THE NORMAL LEGACY PROCESS.

AND THE THIRD BATCH IS THE ONE THAT PROBABLY, YOU KNOW, NEED TO BE STUDIED AGAIN TO REQUIRE UPGRADES.

SO MY, MY COMMENTS REFLECT THOSE AND UH, MATT, IF YOU CAN GO TO PAGE FIVE.

UH, I THINK SCROLL DOWN A LITTLE.

YEAH, I'VE BUILT A TABLE IN THERE WHERE IT SAYS, SO THEY TIER ONE BASE LOAD, YOU KNOW, SHOULD BE FULLY GRANDFATHERED IN, YOU KNOW, EXISTING EXECUTED IA SHOULD SATISFY ALL BAD ZERO REQUIREMENTS.

UH, THEY SHOULDN'T BE SIGNING ANY NEW IAS TIER TWO LOADS THAT HAVE ALREADY PAID KAYAKS AND POST-IT SECURITIES, SAME THING.

THOSE INITIAL POSTINGS SHOULD BE RESPECTED AND SHOULD BE GRANDFATHERED INTO BAD ZERO.

AND, AND THEN IF YOU COULD SCROLL DOWN, THE THIRD ONE IS THE ONES THAT ARE NEW LOADS SHOULD SATISFY, UH, THE DOLLARS PER MEGAWATT FINANCIAL SECURITY AND COMMIT TO KAYAK OBLIGATIONS.

AND AGAIN, MY, OUR CRUCIAL STANCE IS THAT BIGGER 1 45 SHOULD ESTABLISH ITS OWN FINANCIAL COMMITMENT FRAMEWORK SELF-CONTAINED WITHIN, WITHIN THE BIGGER LANGUAGE.

AND THAT DOES NOT DEPEND ON, UH, 5 8 4 8 1.

UM, YEAH, SO THIS SHOULD HAVE ITS OWN, UH, STRUCTURED THREE TIER FRAMEWORK THAT I JUST TALKED ABOUT.

AND TO THE EXTENT, YOU KNOW, PROJECT FIVE, WHEN ULTIMATELY ESTABLISHES STANDARDS THAT DIFFER FROM THOSE IN FIGURE 1 45 ERCOT CAN ADDRESS ANY ALIGNMENT THROUGH A TARGETED REVISION REQUEST AFTER BAD ZERO IS COMPLETE.

UM, THAT'S MY THESIS OR CRUCIAL STANCE IN THIS.

UH, AND THEN THE FINAL PIECE IS THE RTP REFERENCES THAT HAVE BEEN IN BIGGER 1 45.

UH, YOU KNOW, TIME AND AGAIN WE DISCUSSED ABOUT RTP AND BAD ZERO BEING INDEPENDENT PROCESS AND THERE IS NO CORRELATION.

SO CRUSO THEREFORE PROPOSES THAT SECTION 9.2 0.12 A AND TWO B BE REVISED TO REPLACE 26 RTP DEMAND REFERENCE WITH, UH, THE RECENT LCP SUBMITTED TO .

WE BELIEVE THAT THE LCP INDICATES UPDATED INFORMATION, UH, COMING DIRECTLY FROM THE DEVELOPERS.

SO THAT WILL BE, UH, MOST ACCURATE AND LATE LATEST DATA RATHER THAN TAKING A MINIMUM OF 26 RTP AND LCP.

SO THOSE ARE THE THREE COMMENTS THAT WE HAVE.

VERY GOOD.

AND SOME SUPPORT HAS COME IN FROM SKYBOX AND SATOSHI IN YOUR COMMENTS.

ANY QUESTIONS IN THE ROOM OR COMMENTS? ONLINE QUESTIONS? YEAH, SANDEEP, GO AHEAD.

YEAH, SANDEEP BOKAR WITH L-C-R-A-I NOT, NOT SPECIFIC TO WHAT WAS PRESENTED BY BY BARIO, BUT I SEE THE REFERENCES TO VALID STUDIES.

UH, AND I WANT TO UNDERSTAND, UH, FROM ERHART WHAT EXACTLY THAT MEANS IN TERMS OF MODELING LOADS IN THIS.

UM, I'LL GIVE YOU AN EXAMPLE IF A LOAD IS VALID BECAUSE OF A RPG STUDY BEING APPROVED, UH, THE RPG STUDY USUALLY IDENTIFIES A SET OF PROJECTS BY A CERTAIN FUTURE IN SERVICE STATES AT 2031 IS THE POSITION THAT THE STUDY IS VALID.

PROJECTS WILL BE IN SERVICE BY 2031.

SO THE LOADS THAT WERE APPROVED AS PART OF THIS VALID STUDY WILL BE MODELED AT ZERO MEGAWATTS UNTIL 2031.

SO MAYBE, UH, UNDER YOUR EXAMPLE SANDY, UM, CLARIFICATION.

SO WHAT, WHAT IS, UM, THOSE PROJECTS IN LLIS PROCESS? NO, THIS IS, UH, AND THAT'S THE SECOND SCENARIO.

THE FIRST SCENARIO IS USING RPGS AS YOUR, UH, PRIMARY WAY OF VALIDATING A STUDY, BUT IT, IT NEVER WENT THROUGH LLIS BECAUSE IT WAS ONE OF THOSE LEGACY LOADS TO SO IT WAS EXEMPT? IT WAS EXEMPT, YES.

YEAH.

UH, I, I THINK WE, WE PROBABLY NEED TO TAKE IT BACK.

I DON'T PROBABLY YOU WANNA ADD SOMETHING TO THAT OR? YEAH, I, I, I THINK THE WAY WE ARE DEALING WITH RIGHT NOW IS, YOU KNOW, ANY, ANY, ANY PROJECT, ANY, ANY LOAD THAT'S DIRECTLY DRIVING THE PROJECT, WE ASSUME THAT AS LIKE THE,

[00:35:01]

THE BASE LOAD, UM, AGAIN, THE CURRENT PROCESS IS THEY HAVE TO GO THROUGH BOTH LAIS AND THE, AND THE RRP T APPROVAL.

SO, UH, WE PROBABLY HAVE TO THINK ABOUT IT, RIGHT? YEAH, I, I, WE PROBABLY NEED TO TAKE THAT BACK.

THAT'S, IT'S A GOOD QUESTION.

I DON'T KNOW THAT WE'VE TALKED THROUGH THAT SCENARIO IN INTERNALLY.

UM, YEAH, THANKS FOR THAT.

I, I THINK FOLKS HERE SHOULD UNDERSTAND THAT IT'S NOT JUST THAT YOUR STUDY'S VALID, BUT ALSO WHAT LEVEL YOU'LL BE MODELED AT IN THESE BATCH LOADS.

'CAUSE YOU MAY BE IN IT AS A BASE LOAD, BUT YOU MAY NOT SEE THAT MEGAWATT UNTIL CERTAIN THINGS ARE DONE.

NOW, THE PART TWO OF THAT IS THE LARGE LOAD STUDY.

SO IF YOU WENT THROUGH AN LI AN LI IS APPROVED, BUT IT ALSO IDENTIFIES IN YOUR LOAD COMMISSIONING PLAN THAT THE FIRST MEGAWATT CAN BE SERVED IN 2031 BECAUSE OF YOUR PREEXISTING ISSUES AND WHATNOT.

WHAT'S THE APPROACH AT THAT POINT? YEAH, I THINK THE, FOR, FOR THAT ONE, UM, IT WOULD BE CONSISTENT WITH, UH, WHAT HAS BEEN STUDIED ALREADY IF IT'S BASE LOAD.

SO IF THE STUDY INDICATES THE SYSTEM CANNOT RELIABLY SERVE, THE VALID STUDY INDICATES THE SYSTEM CANNOT RELIABLY SERVE UNTIL 2030 OR 2031, THEN THAT WOULD BE WHERE THE, UH, LOAD WOULD ASSUME TO BE COMING ON THE SYSTEM.

OKAY.

THAT'S, THAT'S HELPFUL CLARIFICATION.

AND, UH, THE LARGE LOAD STUDY SCOPES, AS YOU ALL KNOW, THE WAY THERE'S A REASON WHY WE ARE IN THE BATCH PROCESS TODAY IS BECAUSE THE ASSUMPTIONS THAT WENT INTO IT WERE, I DON'T KNOW, DIDN'T LEND TO A REALISTIC CASE, UH, AT THAT TIME.

UM, SO I, I'LL, I'LL LEAVE IT AT THAT.

UH, I, I WOULD SAY THE PURPOSE OF THE BATCH PROCESS IS TO EVALUATE WHAT CAN BE RELIABLY SERVED.

SO I DON'T KNOW IF WE, IT'S IT'S APPROPRIATE TO USE THAT AS AN ENTRY POINT TO SAY, HEY, YOUR LOAD SHOULD BE RELIABLY SERVED BEFORE YOU ENTER THE BATCH PROCESS, THOUGH I, I, I SEE THE RATIONALE FOR BOTH, BUT, UM, MAYBE ONE, ONE OPTION TO CONSIDER HERE IS IF SOMEONE HAS POSTED THE IDA AND POSTED THE SECURITY, THEN YOU EVALUATE THAT IN THE BATCH STUDY AND THEN IDENTIFY HOW MUCH CAN BE ALLOCATED FOR THAT BASED ON THE CRITERIA DRAWN, NOT SO MUCH OF WHETHER WHAT WAS DONE IN A PREVIOUS STUDY AND WHETHER THE CAPACITY THAT WAS IDENTIFIED WAS APPROPRIATE, UH, OR NOT.

SANDEEP, JUST TO ADD A, ASK A CLARIFYING QUESTION THERE, ARE YOU PROPOSING THAT EFFECTIVELY NOBODY IS TREATED AS BASE LOAD, BUT THERE'S POTENTIALLY REALLOCATION EVEN, UH, FOR LOADS THAT HAVE VALID STUDIES? I AM SAYING THAT THERE ARE LOADS OUT THERE, UH, THAT PROBABLY HAVE PUT DOWN THE FULL SECURITY FOR INTERCONNECTION AGREEMENTS.

AND IF THEY ARE THERE AND THEY ARE ADVANCED STAGE, THAT IS THEY MOVE FORWARD, MADE DECISIONS ON THEM, THEN THOSE ARE YOUR FAIR PLACE TO START WITH A BASE LOAD.

BUT OTHERS, YOU, YOU WANT TO RETHINK, UH, SOME OF THAT.

UM, THE MAIN, MAIN THING IS IT, IT GOES BACK TO HOW THE STUDIES WERE CONDUCTED, WHAT SCOPES OF WORK WERE USED, WHAT LOADS WERE INCLUDED IN IT, UM, AND, AND, UH, NOT IN THE POSITION TO ANSWER YOUR QUESTION, WHETHER THEY SHOULD BE CONSIDERED A BASE LOAD OR NOT.

ALL I'M SAYING IS YOU HAVE TO REVISIT IT BECAUSE FINALLY THE QUESTION IS GOING TO BE OKAY, SAY YOU ASSUME 500 MEGAWATTS AS BASE LOAD, MODEL IT AS SUCH, BUT YOU FIND RELIABILITY ISSUES IN THE BATCH LOAD.

WHAT ARE YOU GOING TO DO? ARE YOU GOING TO CURTAIL THEM, SHED THEM, OR, OR READJUST THEIR ALLOCATED FORECAST REGARDLESS OF WHETHER THEY WERE BASED OR NOT? YEAH.

AND UM, I, I WANT TO GET INTO THIS LITTLE BIT LATER WITH, WITH, UM, AND, AND, UH, I, I APOLOGIZE THAT WE ONLY POSTED, UH, THE, UH, PRESENTATION AT, AT THE RIGHT AT THE BEGINNING OF THIS MEETING.

BUT I, I HAVE SOME SLIDES ON THIS AND, BUT I WANT TO TALK THROUGH THAT EXACT ISSUE.

BUT I, I THINK THE SHORT ANSWER IS THAT IF YOU ARE, UH, IF THAT LOAD IS CONSIDERED BASE LOAD IN BATCH ZERO WE'RE, WE WILL NOT GO BACK AND REALLOCATE WHAT WE'RE NOT GONNA SAY, HEY, WE TOLD YOU 500 BEFORE, BUT YOU KNOW, NOW IT'S, IT'S 300 IF, IF YOU'RE CONSIDERED BASE LOAD.

BUT WHAT THAT MEANS THOUGH IS THAT WE, WE NEED TO MAKE SURE, AND, AND THIS IS WHERE THE STUDY VALIDITY QUESTION COMES INTO PLAY, IS WE NEED TO MAKE SURE THAT THAT LOAD, THAT, THAT WE HAVE A STUDY THAT SHOWS US THAT WE CAN RELIABLY SERVE THAT LOAD.

AND, AND IF WE DON'T, THEN WE NEED TO GO BACK AND LOOK AT, OKAY, WE TOLD YOU 500 BEFORE,

[00:40:01]

BUT WE DON'T KNOW IF WE CAN RELIABLY SERVE.

THE IMPLICATION IS IF THERE ARE RELIABILITY ISSUES, THEN THAT'S GONNA SHOW UP IN REAL TIME AND YOU'RE GONNA GET CURTAIL IN REAL TIME NOW.

NO, NOBODY WANTS THAT.

UH, AND SO THAT, THAT, THAT'S THE TRADE OFF THAT WE HAVE TO KIND OF BALANCE THERE.

UH, I DO HAVE SOME SLIDES ON THAT AND WHAT WE'LL PUT INTO THAT.

YEAH, I HOLD FOR THAT THEN.

YES, THANKS FOR THAT.

WE, WE ARE PROBABLY THINKING ABOUT THE SAME THING OVER THE WEEKEND AND WORKING ON THINGS.

ALRIGHT, SHANNON, YOU HAD A QUESTION? WELL, IT'S REALLY A COMMENT ON SANDEEP'S UH, OBSERVATIONS HERE AND, AND MAYBE AS JEFF SAID, THIS WILL BE COVERED LATER, BUT IT SEEMS LIKE WHAT SANDEEP'S BRINGING UP WAS EXACTLY THE THING THAT I WAS MENTIONING IN OUR LAST, UH, WORKSHOP.

I HAD A RELATED BUT DIFFERENT IDEA THEN AND I WAS THINKING OF IT ON THE FLY AND TRIED TO WORK THROUGH IT IN SOME COMMENTS SINCE THEN.

BUT IF BETWEEN NOW AND JULY 10TH, 24TH, WHICHEVER THE JULY DATE YOU PICK THAT THE TSP THAT DEVELOPED THE RPG PLAN AND SUBMITTED IT, IF THEY COULD TAKE AND PUT TOGETHER THEIR OWN, UM, LOAD COMMISSIONING PLAN OF THE LOADS THAT ARE IN IT, BECAUSE MANY OF THEM HAVE APPLIED IN DIFFERENT YEARS, UH, LIKE WE HAVE SOME RPGS THAT WE HAVE TWO PROJECTS IN AND THERE'S SEQUENTIAL, YOU KNOW, ONE OF THEM COMES AFTER THE FIRST ONE AND UM, SUCH THAT IT'S A BIG CONTINUOUS RAMP IN THAT AREA, NOT THAT THEY'RE OCCURRING AT THE SAME TIME.

SO THE TSP THAT PUT THAT TOGETHER, I I THINK IN MANY CASES COULD DO THAT, UH, YOU KNOW, FILE LIKE A SUPPLEMENTAL LOAD COMMISSIONING PLAN THAT WOULD GO WITH THAT RPG OF HOW THEY WOULD SEE IT.

AND IF YOU COULD, THEN YOU COULD GET THAT DONE AHEAD OF THE START OF THE BATCH PROCESS.

AND UM, AND IN OUR OWN CASE, THE ONE WE'RE IN, WE'VE STUDIED THAT A LOT, LIKE I KNOW THE ANSWERS AS WELL AS WHAT'S IN THERE AND MUCH OF THE LOAD CAN BE SERVED WITH EITHER BASE SYSTEM, NON CCN UPGRADES OR SOME THINGS LIKE THAT.

AND THEN THE REMAINING KIND OF BACK END COMPONENT IS THERE'S CLEARLY CCN COMPONENT, LONGER LEAD TIME NEED, NEED NEW RIGHT OF WAY.

AND THE TSP IS AWARE OF ALL OF THOSE THINGS.

SO HOPEFULLY THAT'S SOMETHING WE COULD CONSIDER.

BUT I AGREE THIS IS AN ISSUE THAT YOU WANT TO ADDRESS, UH, SO THAT ERCOT DOESN'T GET CAUGHT IN A BIND LATER WITH IT AND THE ILLE DOESN'T GET SURPRISED EITHER.

ALRIGHT, THANKS SHANNON.

JUST, UH, YEAH, FOR ROSS ACTUALLY THINK PROBABLY WANTS TO, CAN I MAKE A COMMENT? YES, GO AHEAD.

PROBABLY SHANNON'S POINT, I, I THINK I, I JUST WANNA LAY OUT THE, THE WAY WE STUDY, UH, RPG RIGHT NOW IS WHEN PEOPLE SUBMIT PROJECTS OR LOADS THAT GOES INTO RPG STUDY, WE'RE NOT STUDYING THE COMMISSIONING PLAN OF THE LOAD WE ARE STUDYING FOR A PROJECT, RIGHT? FOR SOME THESE EXAMPLE, THERE COULD BE LOADS THAT SUBMITTED FOR RPG, WHAT COMES OUT OF RPG IS YES, THERE IS A PROJECT THAT'S NEEDED IN 2032.

SO WE HAVEN'T GONE THROUGH THE COMMISSIONING PLAN, LIKE WHAT THE BATCH STUDY IS GOING TO GO THROUGH.

SO I WANT PEOPLE TO BE CAREFUL BECAUSE JUST THE LOAD WAS SUBMITTED IN RPG DOESN'T MEAN THAT LIKE TO BE SERVED PRIOR TO THE PROJECT.

THAT'S SOMETHING WE HAVEN'T STUDIED.

I COMPLETELY AGREE.

THAT'S WHY I WAS POINTING THAT OUT LAST TIME.

YEAH, AND, AND UM, I'M, I'M OPEN TO THAT IDEA.

I'VE THOUGHT ABOUT THAT SHANNON.

IT, IT SEEMS TO ME LIKE THAT THAT'S A PRETTY COMPLEX STUDY THAT WE WOULD BE ASKING TSPS TO TAKE ON RIGHT NOW WHEN THEY'RE, THEY'RE, THEY'RE TRYING TO COMPLETE L-L-L-I-S-L-L-I-S STUDY, SO I, I THINK I WOULD MAYBE TURN THAT TO THE TSPS AND ASK THEM IF THEY THINK THAT THAT, THAT IT WOULD BE AN ACHIEVABLE THING.

'CAUSE IT, THAT SEEMS PRETTY COMPLEX, ESPECIALLY NOT KNOWING WHICH LOADS ARE GONNA, SHOULD BE INCLUDED IN THAT.

YOU KNOW, AS YOU KNOW, WE'RE, WE'RE GETTING UH, MULTIPLE PER DAY, YOU KNOW, REQUESTED TO GET STUDIES APPROVED AND, AND GET LOADS ACROSS THE FINISH LINE HERE.

UM, YEAH, I WAS THINKING THOUGH IS SOMETHING THAT'S, IF THE TSP CAN GET IT DONE, IT'S VOLUNTARY OF THE TSP.

IF THEY CAN GO DO IT, PUT IT TOGETHER, BRING IT TO YOU, SEEMS LIKE IT HAS A LOT OF VALUE.

THAT MAY NOT BE POSSIBLE IN ALL CASES, EVEN FOR ANY INDIVIDUAL TSP.

IF THEY HAVE SIX OR SEVEN OF THESE OUT THERE, THEY MAY NOT BE ABLE TO GET 'EM ALL DONE IN TIME, BUT IF THEY COULD GET FIVE OF 'EM DONE, THAT'D BE GREAT.

ALRIGHT, SO WE START WORK THE QUEUE.

WE HAVE THREE IN THE QUEUE RIGHT NOW.

SO BROTH THEN EVAN, THEN ERIC, GO AHEAD.

BROTH.

YEAH, QUICK COMMENT ON MY, UH, TIERS THAT I PROPOSE RIGHT NOW FOR US TO SIGN ANY INTERCONNECTION AGREEMENT OR, YOU KNOW, DIFFERENT LANGUAGES THAT EACH TSP USES.

IT TAKES US ANYWHERE BETWEEN 60

[00:45:01]

TO ONE 20 DAYS, UH, IN TERMS OF SIGNING ONE AGREEMENT.

NOW THINK ABOUT THE HUGE AMOUNT OF APPLICATIONS, UH, THAT WE NEED TO SIGN, UH, THE TSPS NEED TO HANDLE.

AND THEY ONLY, WE ONLY HAVE 30 DAYS TO SIGN ALL THIS AFTER THE STUDY.

SO I THINK, AND THAT'S WHY IT MAKES SENSE FOR US TO FILTER OUT THESE LOADS THAT HAVE ALREADY SIGNED SO THAT IT'S NOT GOING TO BE AN ADMINISTRATIVE NIGHTMARE, UH, IN TERMS OF SIGNING THEM IN 30 DAYS.

AND THE LOADS THAT ACTUALLY HAVE FINISHED AT IS STANDARD RISK BECAUSE THEY HAVE NOT WITHOUT THEM DOING ANYTHING CHANCE, STANDARD CHANCE OF RISK TO UH, NOT SI SIGNING THAT IN 30 DAYS AS WELL.

SO THAT'S AN IMPORTANT PIECE OF INFORMATION I WANTED TO CON CONVEY.

YEAH, THANKS ROTH.

I'M JUST GONNA GO RIGHT DOWN THE ROAD THEN EVAN, THEN ERIC, MAYBE WE CAN GET IAN IN HERE AFTER THAT.

UM, SO JUST, JUST TO GO BACK TO THE RRP G CONVERSATION, TWO QUICK COMMENTS.

SO THE FIRST ONE IS, UM, YOU KNOW, I UNDERSTAND THE ARGUMENT THAT THE RPG IS NOT SOLVING FOR AN LCP, BUT IT IS KIND OF SOLVING FOR AN LCP.

THE LCP IS JUST A CLIFF.

I MEAN WE'RE ACKNOWLEDGE, I MEAN I UNDERSTAND WE'RE SOLVING FOR THE, THE TRANSMISSION PLAN, BUT WE ARE ACKNOWLEDGING THAT THE TRANSMISSION PLAN CAN RELIABLY SERVE THE LOADS THAT ARE JUSTIFYING IT.

SO IN THAT SENSE, THE LCP IS THE LOAD RECEIVES A HUNDRED PERCENT OF ITS REQUESTED AMOUNT ONCE THAT TRANSMISSION PROJECT GOES LIVE.

SO I MEAN I, I AGREE WITH WHAT SHANNON'S SAYING, BUT I'M JUST SAYING THAT THAT THAT ALREADY DOES EXIST TO SOME EXTENT.

AND THEN THE OTHER THING I WANTED TO BRING UP IS WHAT YOU WERE TALKING ABOUT JEFF LEAST I THINK SO, UM, OF KIND OF RECONCILING, YOU KNOW, WE'RE GETTING ALL THESE NEW LOAD REQUESTS NOW AND HOW DO YOU RECONCILE WITHOUT THE RPG? I MEAN, I WOULD MAKE THE COUNTER ARGUMENT THAT THAT IS ALSO HAPPENING IN THE LILLIS PROCESS.

I MEAN THE LILLIS PROCESS TODAY INVOLVES A PROCESS WHERE YOU DO YOUR STUDY AND YOU SAY, WELL I DO NEED TRANSMISSION FOR THIS.

AND YOU INCLUDE THAT IN YOUR LILI STUDY AND IT GOES INTO THE LCP.

THE ONLY DIFFERENCE IS IT'S NOT IN RPG OR HAS BEEN REALLY FORMALIZED WITH THE TRANSMISSION PROVIDER IN SOME CASES IN ANY WAY.

AND THEN YOU HAVE TO, THE SUBSEQUENT LILI STUDY HAS TO INCLUDE THE PREVIOUS LILLY'S IMAGINARY TRANSMISSION UPGRADE IN THAT AND YOU JUST KIND OF HAVE A, A STACKED CARD TOWER OF IMAGINARY TRANSMISSION UPGRADES.

SO I DON'T THINK THAT THAT COMPLICATION SOLELY EXISTS IN THE METHOD THAT SHANNON HAS LAID OUT.

I THINK IT EXISTS IN THE PROCESS WE'RE WE'RE DOING RIGHT NOW AS WELL.

ALRIGHT, ERIC, UM, IN SPEAKING WITH MANY TSPS ABOUT THIS TOPIC, UM, I THINK THAT IN ALMOST EVERY CASE THE TSP HAD, UM, LOADS IN MIND WHEN THEY SUBMITTED THE RPG PLANS AND, UM, KNOW WHAT LOADS THEY WOULD SAY WERE STUDIED AS PART OF THIS.

AND YOU KNOW, THE TSPS ALSO DO ALL OF THE REQUIRED RPG UM, STUDIES THAT ARE LISTED IN THE, UM, RPG SECTION OF THE PROTOCOL THAT INCLUDE, YOU KNOW, THE STABILITY ANALYSIS AND OTHER THINGS THAT ARE PARALLEL, UM, STUDIES TO WHAT'S REQUIRED IN LIST.

SO I, I DO THINK IT'S POSSIBLE TO IDENTIFY, YOU KNOW, WHAT LOADS ARE THERE AND IF IT'S UNCLEAR, THE TSP WOULD KNOW.

ALRIGHT, THANK YOU ERIC.

ALRIGHT, WELL THANKS KEN.

BROTH GOING DOWN THE LINE HERE TO SHOPPER ENGINEERING, SHOPPER ENERGY CONSULTING.

ANDREW, YOU'RE UP.

AH, SEE IF I CAN FIGURE THIS OUT.

THANKS FOR HAVING ME.

YEAH, WE'RE GOOD TO GO.

UM, THERE'S A LOT OF TEXT HERE, SO I THINK, UM, BARATH ACTUALLY COVERED MY POINTS PROBABLY THE BEST SO FAR.

UM, BUT WHAT WE DECIDED TO LAY OUT WAS SORT OF JUST A TIMELINE FOR HOW THIS WOULD ACTUALLY PLAY OUT.

I DON'T THINK WE HAVE ANY OBJECTION TO TRYING TO ADOPT THE 58 4 81 LANGUAGE INTO THE PICKER, LIKE, AND UNDERSTAND THAT THERE MIGHT BE LIKE A BREAK POINT.

BUT FROM A PRACTICAL PERSPECTIVE, FOR THOSE LOADS THAT ARE CONSIDERED BASE LOAD, NOT SUBJECT TO ADDITIONAL STUDY, I, WE THINK OF THIS MORE AS A CHECKPOINT, LIKE A CHECKPOINT TO CONTINUE ON AND BE CONSIDERED AS AS A BASE LOAD, NOT SUBJECT TO ADDITIONAL STUDY.

AND SO THERE'S TWO REQUIREMENTS.

THE FIRST IS THAT YOU'VE SORT OF MET THE LEGACY REQUIREMENTS.

THE NEXT IS THAT YOU'RE GONNA MEET THESE HIGHER STANDARDS THAT ARE ADOPTED AT THE PUC.

AND SO YES, WE HAVE MADE COMMENTS TO THAT RULEMAKING SEVERAL TIMES.

UM, BUT ONE OF THE ISSUES IS

[00:50:01]

JUST THIS IS GOING TO, BY DEFINITION THIS WILL BE RETROACTIVE.

SO THE WAY THAT IT'S SET UP NOW IS THAT THERE IS A JULY 10TH AT A STATION DATE, BUT THE PIGGER WILL NOT BE ACTIVE UNTIL NOTIONALLY, I GUESS EIGHT AUGUST 1ST.

SO I GUESS IT COULD BE BOARD APPROVED POTENTIALLY BY JUNE 1ST.

BUT AS BARATH I THINK POINTED OUT, I MEAN ON AVERAGE I WOULD SAY 90 TO 120 DAYS TO GET A FULLY EXECUTED INTERCONNECTION AGREEMENT AND, AND ACKNOWLEDGING THAT THESE COULD BE AMENDMENTS TO CONTRACTS.

BUT I THINK THE PROBLEM IS YOU'RE GOING TO HAVE TO ATTEST TO HAVING A CONTRACT OF A CERTAIN TYPE WITH A RULE THAT WILL NOT BE FINALIZED UNTIL AFTER THAT.

SO I WOULD MAYBE JUST ASK IF ERCOT HAS THOUGHTS ON THIS OR IF Y'ALL HAVE CONSIDERED THIS AS A, UM, AN ISSUE THAT WE THINK WE'RE GONNA FACE COMPLIANCE WISE AND JUST ADMINISTRATIVELY IF FOR ANYBODY THAT WANTS TO TAKE THAT QUESTION.

GREAT.

HEY ANDREW, THIS IS AG SPRINGER, RIGHT? UM, I I, IF I'M UNDERSTANDING YOUR CONCERN CORRECTLY, UH, YOU'RE CONCERNED THAT THE JULY 10TH DATE IS RETROACTIVE.

UM, I'M LOOKING, LOOKING AROUND THE ROOM FOR MATT, BUT, UH, OH, THERE HE IS.

UH, IT, OUR UNDERSTANDING IS THAT THERE IS A PATH FOR THAT TO BE THE EARLIEST POSSIBLE EFFECTIVE DATE.

AND SO THAT WAS THE INTENTION FOR WHY WE PICKED THAT DATE.

IS IT, UH, UH, POTENTIALLY COULD BE, UH, THE EARLIEST POSSIBLE EFFECTIVE DATE.

OKAY.

SO JULY 10TH COULD BE THE EARLIEST POSSIBLE EFFECTIVE DATE OF THE PIGGER, BUT THE LANGUAGE OF THE PIGGER WOULDN'T BE FORMALIZED UNTIL JULY 10TH.

RIGHT.

THAT IS THAT FAIR.

I BELIEVE THE OPEN MEETING THAT IT WOULD BE CONSIDERED OUT WOULD BE THE DAY BEFORE.

SO THAT WOULD BE THE DATE.

SO LOAD CUSTOMERS THAT ARE BEING CONSIDERED BASE LOAD, NOT SUBJECT TO ADDITIONAL STUDY WILL HAVE ONE DAY TO MAKE SURE THEIR INTERCONNECTION AGREEMENTS CONFORM TO THE RULE AS IT'S DRAFTED HERE.

IS THAT WHAT I'M STANDING? YES, THAT'S CURRENTLY DRAFTED.

THAT'S CORRECT.

OKAY.

ANDREA, IF I, THIS IS MARK SALE.

SURE, GO AHEAD.

I'M JUST GONNA SUPPOSE HERE FOR A MINUTE THAT, UM, IF THE BOARD OF DIRECTORS ENDS UP APPROVING PGA 1 45 IN WHATEVER FORM IT ULTIMATELY TAKES, I THINK THAT'S PROBABLY A PRETTY CLEAR SIGNAL TO THE INDUSTRY THAT THIS IS A PATHWAY THAT IS, UM, POTENTIALLY VIABLE, ONE THAT THE COMMISSIONERS WILL STRONGLY CONSIDER GIVEN ALL THE WORK THAT'S BEEN GOING ON HERE.

AND I DON'T WANT TO FORECLOSE ANY COMMISSION'S ABILITY TO MAKE CHANGES, UH, WHICHEVER OPEN MEETING THE, THE COMMISSION ULTIMATELY TAKES UP P 1 45.

UM, BUT I THINK YOU COULD PROBABLY TAKE THAT, YOU KNOW, MAYBE EVEN EARLIER AFTER ATTACK VOTE.

UM, YOU KNOW, MAYBE THAT'S THE TIME WHERE YOU START TALKING WITH YOUR, YOUR INTERCONNECTING UTILITY ABOUT STARTING TO WORK ON THOSE AGREEMENT CHANGES.

THE TIMING OF EVERYTHING IS HARD AND I GET IT AND I RESPECT THE, THE CHALLENGES, THE TIMING THAT'S BEEN PLACED ON ERCOT, ON THE PUC ON THE INDUSTRY IS ONE THAT'S BEING DRIVEN AT THE HIGHEST LEVELS.

AND SO I THINK WE ALL JUST NEED TO TRY OUR DARNEDEST TO WORK TOGETHER TO, TO MAKE SURE THAT THE RATS ARE, ARE BEING HERDED IN THE RIGHT PLACE.

YEAH.

DID, HOW DID I DO THAT? I THINK IF IT WAS A, IF THIS WAS A MATTER OF A LOAD CUSTOMER, LIKE HAVING TO PUT A LOT OF EFFORT IN TO GET THIS DONE.

SURE.

RIGHT.

BUT FROM OUR VANTAGE POINT, THIS ISN'T POSSIBLE.

LIKE, IT'S NOT POSSIBLE TO ACTUALLY CONFORM TO THIS.

SO THIS IS A COMPLIANCE TRAP I THINK IN OUR MIND THAT NOBODY'S GONNA KNOW WHAT THIS LOOKS LIKE UNTIL THE LAST MOMENT AND THEN WE'RE GOING TO HAVE TO ATTEST TO HAVING AN INTERCONNECTION AGREEMENT THAT LOOKS LIKE THIS.

SO FOR THOSE FOLKS WHO UNDER SECTION 9.2 0.1 AS DRAFTED, MEET THE BASE LOAD, NOT SUBJECT TO ADDITIONAL STUDY, IT MEANS THEY WOULD'VE ALREADY SIGNED A CONFORMING INTERCONNECTION AGREEMENT UNDER LEGACY 9.5 AND THEY SHOULD NOT HAVE ANY FURTHER OBLIGATIONS IS OUR POSITION.

SO I JUST DON'T THINK FROM A TIMING PERSPECTIVE, I DON'T THINK IT'S GONNA WORK.

RIGHT.

I I DON'T THINK IT'S POSSIBLE.

SO THAT'S IT.

AND ANDREW, I I WOULD SAY, UM, I I DON'T THINK I, IF THE TIMING DOESN'T WORK, I DON'T THINK THAT THE DIRECTION WE WOULD GO IS JUST TO SAY NINE FIVE IS GOOD ENOUGH BECAUSE

[00:55:01]

I, I THINK THAT, UM, WHAT, WHAT WE HEARD IN THE, UM, WHEN, WHEN WE, IN THE INTERVIEWS WHEN WE TALKED TO STAKEHOLDERS MM-HMM THERE WERE A SIGNIFICANT, UH, NUMBER OF STAKEHOLDERS THAT SAID, UM, THAT NINE FIVE IS NOT SUFFICIENT TO, AS CURRENTLY WRITTEN, IS NOT SUFFICIENT TO CURRENTLY, UH, TELL WHICH, WHICH PROJECTS ARE QUOTE UNQUOTE REAL, REAL PROJECTS.

UM, AND WE NEED A HIGHER HURDLE.

I THINK THE COMMISSION HAS, UH, GIVEN US SOME DIRECTION ON WHAT THAT HER HURDLE MAY BE.

UH, SO I THINK WE WOULD, UH, LIKE TO FOLLOW THAT TO AGAIN, ADDRESS THOSE COMMENTS AND, AND ADDRESS THE, UH, KIND OF THE, THE DRAFT DIRECTION THAT WE'VE BEEN GIVEN FROM THE COMMISSION.

SO I, I THINK IF JULY 10TH IS NOT POSSIBLE, I, I I THINK THE ALTERNATIVE WOULD BE TO PUSH THAT DATE OUT, NOT TO GO BACK TO 9.5.

AND I'M GONNA PIGGYBACK ON, ON WHAT JEFF JUST SAID IN TERMS OF, YOU KNOW, TRYING TO, TO SET THE HURDLE CORRECTLY, MAKE SURE THAT WE'RE FILTERING, UH, SETTING OUR FILTERING CRITERIA APPROPRIATELY.

IF THERE IS A DIFFERENT SET OF, I'M GONNA SAY PROJECT MATURITY CRITERIA THAT WE SHOULD BE CONSIDERING FOR BATCH ZERO THAT SIGNIFICANTLY ACCOUNTS FOR THE PROBABILITY OF A PROJECT TO MOVE FORWARD.

THOSE ARE THE KINDS OF IDEAS THAT NEED TO CONTINUE TO PERCOLATE UP HERE SO THAT WHEN WE GET TO THIS POINT OF DIVERGENCE, WHICH WE WILL GET TO IN THE NEXT FEW WEEKS, WE KNOW WHAT PROJECT MATURITY MEANS FOR BATCH ZERO.

PERHAPS IT ACCOUNTS FOR THIS TIMING PROBLEM, PERHAPS IT DOES NOT.

IT'S, IT'S A WORK IN PROGRESS.

I THINK, UH, THE, I THINK THE MAIN ISSUE, AND JEFF BACK TO YOUR POINT ON, HEY, WHAT IS THE INTENT OF THE COMMISSION? WHAT ARE THEY TRYING TO MAKE SURE THAT WE DO HERE? RIGHT? WE'RE TRYING TO MAKE SURE THAT LOADS ARE COMMITTED.

STAKEHOLDER FEEDBACK ON SECTION 9.5 OF THE PLANNING GUIDE IS NOT, I MEAN IT'S CERTAINLY IS IMPORTANT, BUT IN EVERY CASE WHERE WE'VE MET THAT CONDITION, THERE'S BEEN TENS OF MILLIONS OF DOLLARS THAT'S BEEN PUT WITH THE UTILITY AND AT RISK.

SO I WOULD, I WOULD CANDIDLY LIKE TO HEAR THOSE FOLKS SPEAK UP HERE AT THIS MEETING IF THEY HAVE OBJECTIONS TO HAVING THAT AS AN INTERIM CRITERIA.

UM, I THINK THE BIGGEST ISSUE THAT WE HAVE HERE IS NOT WHETHER OR NOT NEW INTERCONNECTION STANDARDS SHOULD BE PUT FORTH, BUT RATHER HOW TO COMPLY WITH THEM IN A WAY THAT DOESN'T FOOT FAULT A BUNCH OF CUSTOMERS.

RIGHT? THAT'S, THAT'S OUR CONCERN.

IT'S NOT CAN YOU DO IT OR NOT, BUT IF YOU GIVE THE LOAD CUSTOMER 60 DAYS, I THINK THAT'S PLENTY OF TIME.

THE PROBLEM IS ALSO JUST THAT THIS IS BACKWARD LOOKING, RETROACTIVE EXISTING CONTRACTS THAT HAVE BEEN SIGNED BY LOAD CUSTOMERS IN RELIANCE ON THE CURRENT RULE.

SO IT ACTUALLY KIND OF GOES BACK TO THE OTHER POINT THAT WAS BEING MADE AROUND THE PLANNING STUDIES.

FOLKS ARE RELYING ON THE CURRENT RULE AS THEY ARE, THEY'VE BEEN HEARING FROM THE COMMISSION THAT SAYS, HEY, THE CURRENT RULE IS GOOD, YOU CAN RELY ON IT.

THAT THAT ACTUALLY GOES FOR THE INTERCONNECTION AGREEMENT STANDARDS AS WELL.

SO YOU'LL HAVE A BREAK POINT, BUT THERE DOES NEED TO BE AN ORDERLY TRANSITION WHERE FOLKS ARE NOT PENALIZED, YOU KNOW, BECAUSE OF THIS LOOK BACK.

UH, AND THE, ACTUALLY I WOULD ARGUE THAT THE, UM, CONTRACTING IS GONNA BE THE MOST DIFFICULT PART OF THIS WITHOUT A DOUBT.

SO GO AHEAD, TAKE THEM FROM YOUR SEAT.

ALRIGHT.

ALRIGHT, SO I'LL GET BACK TO THE HELM HERE AND ANDREW WILL GET BACK TO THE SEAT IS SOME OF THESE QUESTIONS COME IN.

UM, SO I'LL GO TO JANICE'S KEY.

OKAY.

SHANNON CAREWAY, GO AHEAD.

I WANNA SAY, I THINK ANDREWS BROUGHT UP SOME OUTSTANDING POINTS HERE THAT WE NEED.

I, I THINK THESE ARE VERY REAL.

AND I APOLOGIZE, I HADN'T TRIED TO FOCUS ON THIS PIECE.

I'D BEEN FOCUSED ON ANOTHER PIECE OF IT, BUT I'D IDENTIFIED THAT THIS WAS AN ISSUE THAT I WANTED TO APPLY SOME, UM, UH, THOUGHT ON.

SO I THINK THIS IS VERY VALID.

AND I HAVE A QUESTION ON, BACK TO JEFF ON SOMETHING YOU SAID, WHERE YOU STAKEHOLDERS HAVE SAID THAT THEY THINK NINE FIVE IS NOT SUFFICIENT.

TODAY'S, I PRESUME YOU MEAN TODAY'S 9.5 TO, UM, BUT IT IS QUOTE, THE LAW OF THE LAND.

UH, YOU SAID THAT MULTIPLE, MULTIPLE TIMES.

AND IF, UM, CURRENT FIGURE ONE 15 PROCESS IS

[01:00:01]

IN PLACE FROM NOW UNTIL WHATEVER JULY DATE, WE WIND UP WITH STAKEHOLDERS WHO HAVE THAT VIEW, IT'S SORT OF IRRELEVANT BECAUSE THERE'S, THERE'S NOT, YOU KNOW, WE HAVE PROTOCOLS, WE HAVE PLANNING GUIDES, AND WE HAVE COMMISSION RULES THAT ARE IN PLACE TODAY.

AND FOR CONTRACTS THAT HAVE ALREADY BEEN SIGNED, THOSE ARE THE THINGS THAT MATTER.

NOT SOMEBODY'S OPINION THAT, WELL, THAT SHOULD HAVE BEEN HIGHER.

WELL, IT WILL BE HIGHER ONCE WE GET THE COMMISSION RULE.

AND THEN FOR THEN ON GO FORWARD, THAT'LL BE WHAT APPLIES.

BUT FOR EXISTING CONTRACTS, IT HAS TO BE WHAT'S TODAY'S BOTH RULES AT THE COMMISSION AND TODAY THAT'S IN EFFECT, NOT THINGS BEING UNDER A PROJECT AND ERCOT CURRENT BINDING DOCUMENTS TO BE ANYTHING DIFFERENT THAN THAT.

I'VE JUST, THAT BREAKS ALL PRECEDENT I'VE EVER SEEN, UH, HERE.

SO I'D BE CURIOUS ON YOUR COMMENTS ON THAT.

YEAH, NO, I, I, I THINK I UNDERSTAND THE CONCERN.

I THINK WHERE WE'RE TRYING TO GET TO IS, UM, WHAT SHOULD WE, UH, WHAT SHOULD WE BE DOING GOING FORWARD? H HOW, AS WE THINK ABOUT THESE FOR BATCH ZERO H, HOW SHOULD WE THINK ABOUT THAT? I THINK WHAT WE HEARD WAS TH THERE'S HOW TSPS ARE APPLYING NINE FIVE IS NOT CONSISTENT.

UH, THAT, THAT THERE'S, UM, THE, THE FINANCIAL SECURITY HURDLES IN MANY CASES.

I FOLKS FELT LIKE THAT THAT'S NOT, I THINK WHAT WE THOUGHT WE HEARD WAS THAT, THAT THAT'S NOT SUFFICIENT.

AND WHAT WE HEARD FROM MANY DEVELOPERS WAS, UM, MY LOAD IS REAL.

MY COMPETITORS IS NOT BECAUSE THEY DIDN'T, YOU KNOW, THEIR, THEIR THRESHOLD'S NOT THAT HIGH, UH, TO GET INTO THIS.

AND, AND, YOU KNOW, SO THAT I, IT WAS THAT, THAT WAS KIND OF THE NATURE OF THOSE COMMENTS.

UM, BUT, UH, BUT I, YOU KNOW, I, I UNDERSTAND THAT CONCERN.

WE'LL, WE'LL TAKE THAT BACK AND WE'LL, WE'LL THINK ABOUT THAT.

UM, BUT YEAH, IT'S, YEAH, I'LL LEAVE IT AT THAT.

ALRIGHT.

AND WE HAVE A FEW HERE IN THE QUEUE.

SO IAN HALEY, YOU'RE NEXT.

THANK YOU.

IAN HALEY, MORGAN STANLEY BARK SALE.

ACTUALLY HAVE A QUESTION FOR YOU.

SO IN THAT PREVIOUS CONVERSATION, THE BOARD ADOPTS AN A PIGGER AND SENDS IT TO THE COMMISSION, IS THE COMMISSION, UM, AND I APOLOGIZE, I'M NOT USING THE RIGHT WORD, BUT IS THE COMMISSION REQUIRED TO ACCEPT THAT BOARD RECOMMENDATION AND OR RESEND IT BACK? OR CAN THEY MAKE MODIFICATIONS THERE AND THEN TO KEEP IT ON THAT TIMELINE, YOU KNOW, WANT TO DOUBLE CHECK WITH, UM, OUR ATTORNEYS, BUT MY UNDERSTANDING, OR AT LEAST OUR TYPICAL PRACTICE, HAS BEEN TO EITHER APPROVE THEM OR TO SEND THEM BACK FOR REFINEMENT.

YES.

UM, WHETHER WE HAVE THE ABILITY TO MAKE CHANGES AT THE COMMISSION ITSELF, THAT'S SOMETHING THAT I WOULD WANT TO INVESTIGATE.

UM, BUT IT IS NOT PART OF HOW I'M THINKING ABOUT THE PROCESS FOR P 1 45 TO WORK.

ABSOLUTELY.

IL DO YOU MIND GETTING BACK TO THIS GROUP? 'CAUSE I THINK THAT'D BE AN INTERESTING UNDERSTANDING FOR US.

I'D BE HAPPY TO FOLLOW UP, ESPECIALLY BECAUSE THE COMMISSION, UM, HAS BEEN SO ADAMANT ABOUT KEEPING ON THE TIMELINE.

UM, I WANT TO UNDERSTAND FULLY THEIR TOOLS AS WELL TO KEEP ON THAT TIMELINE.

SO THANK YOU VERY MUCH.

NO PROBLEM.

ALRIGHT, NEXT, UH, LEE BRATCHER, LEE BRATCHER, CIPHER DIGITAL BARKSDALE.

SORRY, ANOTHER QUESTION FOR YOU.

WOULD THE COMMISSIONERS BE OPEN TO PERHAPS A MEMO, UM, INDICATING THAT THEY WOULD SUPPORT THE LANGUAGE ADOPTED BY THE ERCOT BOARD, UM, OR, OR NOT DEVIATE SIGNIFICANTLY OR SOME SOMETHING THAT COULD GIVE DEVELOPERS MORE CERTAINTY.

THAT'S KIND OF MORE LIKE A 30 DAY WINDOW FOR PEOPLE TO REALLY KNOW WHAT 5, 8, 4 8 ONE'S GONNA LOOK LIKE? WHEN YOU SAY A MEMO, CAN YOU TELL ME A LITTLE BIT MORE ABOUT WHAT YOU MEAN? JUST SOME SORT OF OUTWARD SIGNAL FROM THE COMMISSIONERS THAT THEY WON'T SIGNIFICANTLY DEVIATE FROM WHAT IS, AND MAYBE THEY DON'T WANT TO COMMIT TO THIS TODAY, BUT AS IT GETS NEARER AND THE, IT'S PASSED ROSS AND IT'S ON ITS WAY TO TACK AND IT GOES TO THE BOARD, UH, JUST AN OUTWARD SIGNAL THAT THEY WOULD NOT SIGNIFICANTLY DEVIATE FROM THAT.

YEAH, I, I FEEL SUPER UNCOMFORTABLE MAKING ANY KIND OF COMMITMENT, UM, OF THAT NATURE.

I WILL

[01:05:01]

SAY THAT THE, YOU KNOW, THE CHAIRMAN AND, UH, COMMISSIONER ALTMAN OR MEMBERS OF THE ERCOT BOARD, UM, EX OFFICIO MEMBERS, NON-VOTING OF COURSE, UM, AND ALL OF THE REST OF THE COMMISSIONERS, UH, TYPICALLY ATTEND BOARD MEETINGS.

AND, UM, I THINK AT THAT MOMENT, ONE MIGHT, UM, ANTICIPATE THAT IF, IF ANY OF THOSE COMMISSIONERS HAVE CONCERNS, THEY MAY CHOOSE THAT MOMENT TO RAISE THOSE, THOSE, UM, CONCERNS.

OF COURSE, THEY DON'T HAVE TO, UH, THEY CAN WAIT UNTIL THE ISSUE IS BEFORE THEM IN AN OPEN MEETING.

UM, I WILL ALSO SAY THAT OUR, OUR TYPICAL PRACTICE IS TO GIVE, GIVE ANY REVISION REQUEST 30 DAYS IN FRONT OF THE COMMISSION BEFORE THE COMMISSIONERS VOTE ON IT.

UH, I, I THINK THAT'S A, GIVEN THE SENSITIVITY AROUND THE TIMING AND THE COMPLIANCE TRAPS, WHICH I VERY MUCH APPRECIATE THAT CONCERN.

UM, YOU KNOW, MAYBE THAT'S A THING THAT, THAT WE AT THE COMMISSION THINK ABOUT IS CAN WE GET THE REVISION REQUEST IN FRONT OF THE COMMISSIONERS FOR A VOTE EARLIER THAN 30 DAYS? THAT'S A MAYBE ANOTHER TOOL IN OUR TOOLBOX.

ALRIGHT, VERY GOOD.

UH, DURGA AND THEN BOB KING DURGA FROM SOFTBANK ENERGY.

UM, I'LL GO BACK TO WHAT, UH, JEFF, UH, SAID ABOUT 9.5.

SO, UM, WE PUT, UM, UM, BOOTS ON THE GROUND, UM, BASING EVERYTHING ON PGR 1 5 1 1 5, LEGACY 9.5.

UM, AND TSPS CONFIRM THAT WE ARE MEETING THE 9.5.

UM, IF, IF YOU THINK THAT 9.5 IS NOT GOOD ENOUGH TO SHOW THAT PROJECTS ARE IN ADVANCED STAGE, I BELIEVE THE ATIONS THAT'S, THAT ARE NEEDED IN THE 1 45 SHOULD BE ABLE TO SHOW THAT.

AND IF MORE ATTESTATIONS ARE NEEDED FROM THE LOADS, THAT COULD ALSO BE AN OPTION RATHER THAN RETROACTIVELY GOING AND APPLYING THE MARCH 4TH.

AND, AND ANOTHER THING ON THE MARCH 4TH THING, RIGHT, WE HAVE BEEN WORKING WITH A LOT OF DSPS, UM, AND CO-OPS, UM, E EVEN IF WE ARE APPLYING THE MARCH FOUR DEADLINE, BECAUSE THAT'S THE DAY PG R 1 45 WAS FILED, ONE OF THE THING THAT COULD BE CHECKED IS IF THE CO-OPS AND DSPS ALREADY HAD I IN PLACE, RIGHT? EVERYTHING SORTED OUT AND, AND THE IA FORMAT WAS AGREED UPON AND THERE WAS A SYSTEM IN PLACE FOR US TO SIGN, RIGHT? UH, I SAY THAT BECAUSE I KNOW FOR A FACT THAT FEW DSPS AND CO-OPS DIDN'T HAVE LIKE THEIR BOARD APPROVALS ON THOSE IAS, SO THERE'S NO WAY WE COULD HAVE GONE BACK AND SIGNED BY MARCH 4TH.

SO THERE'S A CERTAIN LOOPHOLE THERE.

SO IF, IF THAT COULD BE TAKEN INTO CONSIDERATION, UH, FOR THE LOOK BACK DATES, THAT, THAT'LL BE GREAT.

THANK YOU JEFF.

ALRIGHT THEN.

BOB KING, BOB KING FOR TRACK TODAY.

UM, I'M GETTING CONFUSED WITH ALL THESE DATES MYSELF, BUT I THINK ONE OF THE ISSUES IS IF WE HAVE AN LLIS TODAY OR, OR AN INTERCONNECTION AGREEMENT UNDER THE CURRENT SYSTEM TODAY AS A DEVELOPER, WE MIGHT BE RELATIVELY FLEXIBLE ABOUT CHANGING THAT OR WHATEVER, BUT THE, THE IMPRESSION I HAVE FROM TARKIN UTILITIES IS THAT THEY DON'T FEEL LIKE THEY HAVE A CLEAR PATH TO SIGNING THE NEW AGREEMENT WITH US BECAUSE THIS IS IN DISCUSSION AND SO IT, IT MAY NOT BE US.

THAT'S THE ISSUE.

AND I, I'D KIND OF LIKE TO HEAR FROM THE UTILITIES ARE ODDLY QUIET DURING THIS DISCUSSION.

UM, IN FACT I HEARD FROM SHANNON THAT SOME PUT IN COMMENTS AGREEING THAT SOME OF THIS NEEDS TO BE ADDRESSED.

SO CAN THE UTILITIES SPEAK ABOUT, UM, THIS ISSUE ABOUT THE NEW INTERCONNECTION REQUIREMENTS AND SO ON, MAKING IT INTO OLD AGREEMENTS? CAN YOU GO BACK THROUGH YOUR QUESTION AGAIN, BOB, PLEASE? WELL, I MAY NOT EVEN UNDERSTAND ALL THIS CONVERSATION, BUT I THINK PART OF IT IS IF YOU HAVE A EXISTING AGREEMENT WITH THE UTILITY, CAN WE QUICKLY BETWEEN NOW AND SOME DATE UPGRADE IT TO EQUAL WHATEVER THE INTERCONNECTION AGREEMENT WILL BE REQUIRED UNDER THE DRAFT OR PROPOSED 58,481, OUR CONVERSATION WITH UTILITIES, NOT YOURS IN PARTICULAR, MARTHA, BUT, UM, THEY'RE NOT CLEAR ABOUT WHETHER THEY CAN DO THAT YET, OR THEY DON'T, YOU KNOW, THEY'RE A LITTLE LESS FLEXIBLE OFTEN THAN WE DEVELOPERS ON THIS SORT OF THING.

SO, UM,

[01:10:01]

HOW ARE THE UTILITIES FEELING ABOUT TRYING TO UPDATE OR UPGRADE INTERCONNECTION AGREEMENTS THEY ALREADY HAVE SIGNED TO THE NEW REQUIREMENTS OF A PROPOSED RULE ACCORDING TO, UM, PICK 1 45 BEFORE IT'S ADOPTED.

OKAY, SO MARTHA HENSON WITH ENCORE, I THINK IT'S, IT'S NOT APPARENT TO US AT THE CURRENT TIME THAT THE INTERCONNECTION AGREEMENT ITSELF NEEDS SIGNIFICANT REVISIONS UNDER THE RULE LANGUAGE.

WE DON'T HAVE A STANDARD INTERCONNECTION AGREEMENT BEING PROPOSED AT THIS TIME, ALTHOUGH MAYBE THAT'S SOMETHING THAT GETS WORKED ON LATER.

IT'S MORE AN ISSUE OF THE ATTESTATIONS THAT ARE REQUIRED UNDER THE PROPOSED RULE.

UM, ENCORE HAS BEEN COLLECTING SOME OF THOSE ATTESTATIONS FOR SOME TIME NOW, SO WE'VE ALREADY STARTED TO WORK ON THAT BECAUSE IT'S NSV SIX ON TO SOME LEVEL.

UM, I THINK THE OTHER PIECE IS, IT'S, IT'S MOSTLY THE COLLECTION OF SECURITY, WHICH WE DON'T KNOW WHAT THE AMOUNT IS GOING TO BE AT THIS POINT AND HOW LONG WE HAVE TO COLLECT THAT, PARTICULARLY FOR, YOU KNOW, MEETING A MILESTONE FOR A CUSTOMER TO BE EITHER BASE LOAD, RIGHT, MAINLY FOR THE BASE LOAD, UH, REQUIREMENT IN BATCH ZERO.

SO, UM, ENCORE WILL MEET WHATEVER IS NECESSARY UNDER THE PLANNING GUIDE REVISION AND THE RULE ULTIMATELY.

UM, SO I THINK, I THINK THAT'S WHERE WE ARE AND TO THE EXTENT WE CAN WORK EARLIER BASED ON DRAFT LANGUAGE THAT WE THINK IS LIKELY TO BE, YOU KNOW, INCORPORATED, WE WILL DO THAT.

UH, BUT IT'S ALL TIGHT TIMELINES FOR US TOO.

YEAH.

WE WILL DO WHAT WE NEED TO DO TO MAKE IT HAPPEN.

OKAY, GREAT.

AND I SEE SANDEEP, UH, FROM LCRA JUMPED IN THE QUEUE.

GO AHEAD.

YEAH, JUST I GUESS ADD THAT WHAT MARTHA SAID ON ALL THE THINGS WE GENERALLY AGREE WITH, WITH WHAT SHE SAID, THE POSITION, UH, WHERE LCI IS AT.

THE REASON WHY I GOT INTO THE QUEUE WAS MORE TO POINT OUT, I THINK IT WAS CENTERPOINT'S COMMENTS THAT I, I, I LOOKED AT AND I LIKED IT, DIDN'T TALK ABOUT CHANGING ANY AGREEMENTS, BUT IT TALKED ABOUT IF YOU HAVE A INTERCONNECTION AGREEMENT ALREADY SIGNED, THAT SHOULD BE EXTRA THAT WAS OR ADDED IN THE CRITERIA FOR WHAT GETS INTO, UH, UH, INCLUDED AS A BATCH, UH, AS AN ENTRY CRITERIA FOR THE BATCH STUDY.

SO IF YOU HAVE A INTERCONNECTION AGREEMENT ALREADY SIGNED, THEN THAT SHOULD HOLD THE SAME VALUE AS YOU DON'T NEED TO POST INTERCONNECTION AGREEMENT.

AT LEAST THAT'S, THAT'S HOW IT READ.

UM, SO WE, WE WERE ALSO LOOKING AT, UH, FILING SOME COMMENTS TO HELP, UH, HELP WITH THAT, UH, POSITION.

UM, BUT YEAH, NOT, NOT NECESSARILY CHANGING ANYTHING IN THE AGREEMENTS ITSELF AT THIS POINT, 'CAUSE THOSE ARE ALL THE PAST AGREEMENTS, BUT ALL THE POINTS THAT MARTHA LAID IS, I MEAN, THAT, THAT'S, THAT'S, UH, APPLICABLE THE AMOUNTS, THE TIMING FOR COLLECTION.

BUT I SEE YOUR POINT.

IF YOU ALREADY COMMITTED FULL SECURITY TO BUILD A PROJECT, DO YOU NEED TO AGAIN GO BACK AND, UM, POST ANOTHER FEE TO SAY, OKAY, NOW STUDY ME WELL, AND ARE YOU PREPARED WITHIN THE TIMELINE TO HELP US DO THAT? 'CAUSE WE DON'T WANT TO FAIL TO BE BASELINE BECAUSE OF YOUR FAILURE, RIGHT? WELL, WE JUST WENT THROUGH A, A, A SEMI HERCULEAN EFFORT TO GET THE 2026 RTP COMPLIANCE IDA, THE INTERCONNECTION INTERMEDIATE AGREEMENT SIGNED AND MONIES COLLECTED.

AND SO WE, WE'VE DONE THAT AND WE'LL DO WHATEVER IS NEEDED TO SUPPORT THE, THE BIGGER PROCESS AND THE BATCH PROCESS.

SO, UH, AND THAT'S WHY THAT, UH, ADVANCED NOTICE WILL DEFINITELY BE HELPFUL, UH, SO WE CAN START WORKING ON COMMUNICATING THIS, CALCULATING THE NECESSARY SECURITY AND ALL.

OKAY, THANK YOU.

ALRIGHT.

ALL RIGHT, WELL THAT TAKES US TO THE END OF THE FORMAL COMMENTS, BUT STILL ON THIS AGENDA ITEM, UH, AGAIN, ANDRE HAD AT THE LAST WORKSHOP BROUGHT UP AN EXAMPLE AND SO I'M GONNA LET HIM PRESENT HIS EXAMPLE HERE AND WE'LL LET YOU GO AND SEE IF I CAN GET A BETTER VIEW OF THIS.

THERE YOU GO.

THANK YOU MATT.

GOOD MORNING EVERYONE.

MY NAME IS ANDRES MINE, I'M A DIRECTOR OF GRID INTEGRATION AT CYPRESS CREEK RENEWABLES.

I WANNA START FIRST BY THANKING ERKO FOR THE OPPORTUNITY TO, TO SPEAK HERE ABOUT THIS, UM, BATCH STUDY CONCERN THAT WE HAVE.

AND WE ALSO WANNA, UM, SAY THANK YOU FOR ALL THE WORK THAT'S BEEN PUT IN FOR THIS FIGURE 1 45.

SO I WANNA START BY LAYING OUT CCRS CONCERN THAT RELATES SPECIFICALLY TO THE REFINEMENT STUDY PHASE WHERE ER'S CURRENTLY PROPOSING NOT TO ADJUST MEGAWATT ALLOCATIONS OR LOAD COMMISSIONING PLANS.

[01:15:01]

WE SEE A FUNDAMENTAL RISK ON THIS APPROACH ONCE A LOAD COMMITS AND EXECUTES AN IA, ITS MEGAWATT ALLOCATION WILL BE FIXED EVEN IF OTHER LARGE LOADS DROP OUT WITHOUT A STUDY TO VALIDATE UPDATED SYSTEM CONDITIONS.

ERCO MAY FACE A SCENARIO WHERE AN APPROVED LOAD IS UNABLE TO RECEIVE ITS ALLOCATED MEGAWATTS WITHOUT CAUSING RELIABILITY VIOLATIONS, ESPECIALLY IF NEW NETWORK UPGRADES ARE IDENTIFIED DURING THE REFINEMENT PERIOD.

SO NEXT I'M GONNA WALK YOU GUYS THROUGH A, A SIMULATION THAT WE DID, UH, INTERNALLY USING, USING TARA JUST TO SHOW THAT THIS CONCEPT EXISTS.

WHEN A LARGE LOAD DROPS OUT FROM A PLANNING STUDY OR POWER FLOW, IT CAN CAUSE RELIABILITY ISSUES.

SO WHAT WE DID IS WE, WE JUST GRABBED A 2029 SUMMER P CASE SSWE CASE.

WE LOOKED AT THE TRANSMISSION SYSTEM, I THINK THE EAST AND BUS LAKES AROUND THE TEMPLE AREA, CENTRAL TEXAS.

WE LOOKED AT THOSE 3 45 KB LINES BECAUSE THEY WERE HEAVILY LOADED ALREADY.

AND I JUST WANNA NOTE THAT THE ANALYSIS PRESENTED HERE IS RESTRICTED TO N MINUS SERIAL CONDITIONS BASE CASE.

JUST TO ILLUSTRATE THE CONCEPT OF LOAD WITHDRAWAL TRIGGERING NEW, UH, RELIABILITY VIOLATIONS.

IT'S NOT A REPRESENTATION OF A FULL INTERCONNECTION STUDY.

I ALSO WANNA NOTE THAT THE TRANSMISSION PLANNER FROM CCR WHO HELPED PREPARE THIS POWER FLOW IS NOT HERE TODAY.

SO I'M GONNA DO MY BEST TO WALK YOU GUYS THROUGH THIS.

SO THIS IS WHAT THE STUDY SHOWS, RIGHT? WHEN I PULL THE CASE, I'M LOOKING AT TWO BUSES, BELL EAST, BUS LAKE, TWO LINES CONNECTING THESE BUSES LINES ARE LOADED AT 90% OF OF THEIR, UM, MBA RATING.

SO WHAT WE DID NEXT IS WE ADDED TWO LOADS, LOAD A AND LOAD BH LOAD 750 MEGAWATTS AT UNITY POWER, POWER FACTOR.

AND THEN WE SOLVED THE BASE CASE.

AND THIS IS WHAT YOU SEE.

YOU SEE NO OVERLOADS, RIGHT? YOU HAVE LOAD A PULLING 750 MEGAWATTS, YOU SEE LOAD B PULLING 750 MEGAWATTS.

IF THIS WAS A BATCH STUDY AND THERE WAS A LOAD COMMISSIONING PLAN, THEN I MEAN, MOST LIKELY YOU WOULD GET YOUR 750 MEGAWATTS BECAUSE THERE'S NO VIOLATIONS, RIGHT? THE LOAD CAN BE SERVED, THE LINES ARE NOT ABOVE A HUNDRED PERCENT.

SO I JUST WANNA FLAG AND MENTION THAT NEITHER LOAD A NOR B WOULD BE REQUIRED TO PROVIDE SECURITY FOR NETWORK UPGRADES IN THIS SCENARIO.

BUT IF WE MOVE ON TO THE NEXT PHASE, WHICH IS THE, THE COMMITMENT PERIOD, 30 DAYS OR 60 DAYS, WHATEVER WE DECIDE IT'S POSSIBLE FOR SOME LOADS TO DROP, RIGHT? I MEAN IT'S GONNA HAPPEN.

SO IN THIS SPECIFIC SCENARIO, LET'S ASSUME THAT LOAD A DOES NOT SIGN THE INTERCONNECTION AGREEMENTS.

AND LET'S ASSUME LOAD B SIGNS THE INTERCONNECTION AGREEMENTS, THEY PAY THE 50 K PER MEGAWATT INTERCONNECTION FEE, NON-REFUNDABLE, THEY PAY FOR KAYAK FINANCIAL SECURITIES UPGRADES.

IN THIS CASE THERE'S NO UPGRADES OF COURSE, BUT YOU SEE MY POINTS.

SO WHAT WE DID NEXT IS WE'RE GONNA TURN OFF LOAD A AT BELL EAST THREE 40 5K BBO.

SO THIS IS WHAT HAPPENS ONCE YOU TURN, UH, LOAD A OFF ONCE LOAD A WITHDRAWS FROM THE PROCESS.

NOW YOU SEE AN OVERLOAD THAT WAS NOT THERE ORIGINALLY IN THE BATCH STUDY PROCESS, RIGHT? AND THIS IS THE PROBLEM THAT WE SEE OUTSIDE OF ERCOT.

YOU GO TO LIKE FERC CLUSTER STUDIES, THIS IS WHAT HAPPENS.

THIS IS WHY IT'S AN ENDLESS TUDY THAT TAKES YEARS TO GO THROUGH BECAUSE UTILITIES, THEY DON'T KNOW.

I MEAN, THEY DON'T KNOW IF THIS IS GONNA HAPPEN, RIGHT? THERE COULD BE A SCENARIO WHERE LIKE, THIS DOESN'T HAPPEN AND EVERYBODY'S HAPPY AND, AND, AND WE MOVE FORWARD.

THE PROBLEM IS THEY DON'T KNOW.

AND BECAUSE THEY DON'T KNOW THEY NEED TO TUDY BECAUSE THIS IS A SIMPLE SCENARIO.

I HAVE TWO BUSES ON TWO LOADS.

NOW, COULD YOU IMAGINE BEING A COMPLEX SYSTEM WITH THOUSANDS OF BUSES, THOUSANDS, THOUSANDS OF LINES ON MULTIPLE LOADS, YOU KNOW, YOU COULD HAVE A HUNDRED LOADS IN A STUDY.

THE MOMENT YOU START TWEAKING PULLING LOADS, YOU DON'T KNOW THAT THIS IS NOT GONNA HAPPEN.

THE ONLY WAY TO KNOW IS TO ACTUALLY DO A STUDY.

SO WITH THAT SAID, UM, I I I WANNA BRING UP THREE, THREE MAIN QUESTIONS FOR THIS QUESTION.

NUMBER ONE, WILL THE REFINEMENT STUDY IDENTIFY SCENARIOS LIKE THIS AND PROPOSE NEW TRANSMISSION? IF SO, THAT BRINGS ME TO QUESTION NUMBER TWO.

WHO'S GONNA SECURITIZE THESE UPGRADES? IS IT GONNA BE LOAD A OR LOAD B, LOAD A, IT'S GONE.

THEY DIDN'T SIGN THE INTERCONNECTION AGREEMENT, LOAD B STAYED.

AND IN THEIR INTERCONNECTION AGREEMENT THERE WAS NO NETWORK UPGRADES.

THIS IS THE ISSUE WE SEE OUTSIDE OF ER CODE IN THE FERC WORLD.

UM, QUESTION NUMBER THREE.

HOW IS ER CODE GONNA SERVE THE 750 MEGAWATTS IN THIS SCENARIO IN 2028 WITH A BASE CASE OVERLOAD? SO NEXT, IN, IN

[01:20:01]

THIS SPECIFIC SCENARIO, UM, ERKO CAN NO LONGER SERVE 750 MEGAWATTS FOR LOAD B IN 2028, AS NOW A NEW NETWORK UPGRADE IS REQUIRED.

SO ASSUMING THERE'S A TWO TO THREE YEAR UPGRADE TIMELINE, I MEAN THE, THE LCP SHOULD BE UPDATED.

'CAUSE THE BIGGEST HIGHLIGHT THAT I WANT TO SAY ON THIS SLIDE IS THAT LOAD B EXECUTED AN IA BASED ON THREE ASSUMPTIONS, MEGAWATTS, TIMELINE, AND COST LOAD B EXECUTED ON IA THINKING IT WAS GONNA GET 750 MEGAWATTS IN 2028 WITH NO NETWORK UPGRADES, AND NOW THEY'RE LEARNING AFTER THE FACT THAT THERE MIGHT BE, UM, A PROBLEM TO SERVE THAT LOAD.

UM, I JUST WANNA SAY IF I'M LOAD BII WOULD BE VERY CONCERNED AND I WOULD LIKE TO KNOW THIS, UM, THIS RISK OF COURSE, UM, LOADS SHOULD BE AWARE THAT EXECUTING AN I A WITH FIRM DELIVERABILITY MAY STILL CARRY RISK IF NETWORK UPGRADES ARE REQUIRED TO SERVE THAT LOAD.

BECAUSE IF THESE CONDITIONS HAPPEN IN REAL TIME AND THERE'S NO GENERATION SOLUTION THAT EXISTS TO SOLVE THIS PROBLEM, MAY NEED TO DECLARE A TRANSMISSION EMERGENCY AND CARTEL LOAD TO MAINTAIN SYSTEM RELIABILITY.

AND I CAN SPEAK TO THAT FROM EXPERIENCE.

I USED TO WORK IN THE CONTROL ROOM AS A SHIFT ENGINEER.

I DEVELOPED LOAD CHECK PLANS DURING WINTER STORM URI.

UH, EVEN THOUGH THAT WAS OF COURSE AN EXTREME, I ALSO DEVELOPED A LOAD CHECK PLAN BACK IN SEPTEMBER, 2020.

WE HAD A SITUATION LIKE THIS IN THE CONTROL ROOM.

WE HAD A BASE CASE OVERLOAD IN SOUTH TEXAS THAT WE COULDN'T HAVE SOLVE IT.

WE TRIED TO MOVE ANCILLARY SERVICES TO GET MORE GENERATION NOW TO SEE IF WE COULD LIKE HELP WITH THAT.

OF COURSE, WE COULDN'T DO, UM, A TO OR A POST CONTINUOUSLY MITIGATION PLAN BECAUSE IT WAS A BASE CASE OVERLOAD.

WE ALSO TRIED DO REMEDIAL SWITCHING MOVE FLOWS AROUND ANYWAY, WE COULDN'T FIND A SOLUTION.

SO WHAT DID WE DO? WE HAVE TO SHED FIRM LOAD TO SOLVE THIS PROBLEM.

SO, UM, I JUST THINK THAT NOBODY SHOULD BE EXPECTED TO SIGN AN INTERCONNECTION AGREEMENT EXPECTING TO GET MEGAWATT COST AND TIMELINE TO LATER KNOW THAT THE REFINEMENT STUDY CAN CHANGE THAT.

AND HERE I HAVE ON THE RIGHT, UH, A LITTLE TABLE THAT I DO LIKE A LOT BECAUSE WE SEE THAT THE BATCH STUDY RESULTS WITH BOTH LOADS AND YOU CAN SEE THAT THERE'S NO ISSUES AND EACH LOAD GETS ITS MEGAWATT.

BUT THE MOMENT THE REFINEMENT STUDY IDENTIFIES AN UPGRADE, THEN EVERYTHING CHANGES.

AND THIS CAN ONLY BE KNOWN AFTER THE REFINEMENT STUDY ONCE LOAD B EXECUTES, UH, AND COMMITS.

SO THIS NEXT SLIDE JUST SHOWS WHAT WE HAD TO DO ON THE POWER FLOW STUDY TO SOLVE THAT BASE CASE VIOLATION.

WE HAD TO DROP THE LOAD 50% OF ITS MEGAWATT TO 3 75 TO SOLVE THE THE PROBLEM.

SOME OF THE CAVEATS AS STATED EARLIER ON, THE INTENTION OF THIS IS TO ILLUSTRATE THE POTENTIAL FOR THIS TO OCCUR.

IT'S NOT TO SAY THAT THIS IS GONNA BE AN ISSUE EVERY TIME WE RUN THIS.

SO IT'S, IT IS NOT BY ALL MEANS, A REAL WORLD EXAMPLE OF ACTUAL STUDY RESULTS.

ALSO, I DO WANNA MENTION THAT THIS ANALYSIS WAS ONLY FOCUSED TO N MINUS ONE BASE CASE, BUT THIS, THIS RISK ACTUALLY OCCURS WITH EVERY SINGLE CONTINGENCY, RIGHT? LIKE YOU'RE RUNNING PC ROUTE THROUGH P SEVEN AND THERE'S MULTIPLE WITHDRAWALS, UH, PERMUTATIONS.

AS SOON AS YOU START REMOVING LOADS, ALL THE POSSIBILITIES OF WHERE THAT POWER FLOW COULD FLOW, IT COULD CAUSE A LOT OF A LOT OF ISSUES.

AND YOU WON'T KNOW THAT UNLESS YOU, YOU TUDY.

SO LASTLY, WELL, WHAT'S THE SOLUTION? IF WE HAVE THIS BIG PROBLEM, HOW CAN WE SOLVE IT? WELL, I I'M, I'M SORRY TO SAY THIS, BUT THERE'S NO, THERE'S NO PERFECT SOLUTION.

I MEAN, EVERY SINGLE MARKET SOLVES THIS OUTSIDE OF THE ERCOT BY DOING A RE STUDY, NOT BY CHOICE, BUT BY NECESSITY.

IT IS THE ONLY WAY TO MAKE SURE THAT NO NEW VIOLATIONS HAPPEN WHEN PROJECTS DROP.

AND TO MY KNOWLEDGE, NO MARKET IN THE US HAS ELIMINATED THIS PROBLEM EXCEPT ERCOT.

ERCOT HAS SOLVED THIS PROBLEM WITH ITS CONNECT AND MANAGE APPROACH FOR GENERATION.

WHEN YOU GO THROUGH THE FIS PEOPLE LOVE COMING HERE FOR GENERATION BECAUSE THEY DON'T HAVE TO DEAL WITH THE FERC RABBIT HOLE OF ENDLESS RISK STUDIES AND WAITING, RIGHT? IT, IT'S GREAT.

SO MY QUESTION IS, HOW HAS T'S BATCH PROPOSAL SOLVED THIS TUDY PROBLEM BY HAVING ONE DECISION POINT WHERE LOADS EXECUTE AN IA AND COMMIT AND GET THEIR ALLOCATED ALLOCATED CAPACITY REGARDLESS IF OTHER PROJECTS DROP OUT.

A SEEN ON MY SLIDE, THIS, THIS APPROACH MAY NOT WORK.

ERCO CANNOT GUARANTEE MEGAWATTS TIMELINE NOR COST, AND WE CANNOT ASSUME THAT STUDIES ARE NOT NEEDED.

AND LASTLY, LARGE LOADS SHOULD NOT SIGN AN INTERCONNECTION AGREEMENT THAT CLAIMS TO GUARANTEE MEGAWATT CAPACITY.

A FURTHER RELIABILITY VIOLATIONS DUE DUE TO WITHDRAWALS REQUIRE ADDITIONAL NETWORK UPGRADES TO PROVIDE FIRMS LOAD SERVICE THAT WERE NOT THERE IN THE BATCH.

AND

[01:25:01]

WITH THAT, UM, I WANNA FINISH AND I'M HAPPY TO TAKE ANY QUESTIONS.

ALL RIGHT, AND CAN YOU GO BACK TO YOUR SLIDE THAT HAD THE THREE QUESTIONS, SLIDE 10 OR SO? UH, HERE, THERE YOU GO.

OKAY, THANK YOU.

JEFF, DO YOU WANT TAKE A SHOT? YEAH, ANDRES, I I APPRECIATE THE POWER FLOW ANALYSIS HERE.

UM, QUESTION, DID YOU DO GENERATION RE-DISPATCH? I DID NOT.

AND THE REASON I, WE DID NOT DO GENERATION RE-DISPATCH.

I MEAN, I'M, I'M NOT TRANSMISSION PLANNING ENGINEER, BUT MY UNDERSTANDING IS YOU CANNOT DO GENERATION RE-DISPATCH ON A PC VIOLATION.

MY UNDERSTANDING IS GENERATION RE-DISPATCH IS ALLOWED ON P THREES AND P SIX'S AND MINUS ONE, MINUS ONE.

WELL, WE, WE WOULD, WE WOULD DO A GENERATION RE-DISPATCH IN THE BATCH STUDY FOR THIS.

SO LET ME ASK A, A FOLLOW UP QUESTION THAT YEP.

IF WE DO GENERATION RE-DISPATCH HERE, I MEAN IN, IN MY MIND THAT'S, THAT'S LIKE A CONTRADICTION OF LIKE WHAT WE'RE DOING IN BATCH BECAUSE IN BATCH WE'RE GOING IN WITH A FIRM POWER FLOW STUDY.

LIKE WHY NOT JUST DO GENERATION RE-DISPATCH IN IN, IN THE, IN THE INITIAL, IN THE INITIAL BATCH.

I MEAN, I GUESS MY POINT IS LIKE WHY WOULD WE GO THROUGH THE BATCH STUDY TO DO A FIRM LOAD STUDY AND THEN MIDWAY CHANGE TO A GENERATION RE-DISPATCH SOLUTION? SO WELL, SO, SO WE WOULD, AS PART OF BATCH, THERE IS A SECURITY CONSTRAINT.

OPTIMAL POWER FLOW IS, IS HOW WE WILL SOLVE THAT.

SO THAT, I MEAN THAT, THAT IS FUNDAMENTAL, THAT IS HOW WE WOULD PERFORM THE STUDY.

SO AS I SEE THIS, I, IF YOU HAD 750 MEGAWATTS OF LESS LOAD, YOU ALSO NEED 750 MEGAWATTS OF LESS GENERATION.

SO YOU, YOU HAVE TO DO A GENERATION RE-DISPATCH ANYWAY BECAUSE NOW YOU'VE LOWERED YOUR LOAD.

SO TO GET YOUR POWER FLOW CASE TO SOLVE, YOU HAVE TO LOWER YOUR GENERATION.

AND, AND SO I, I THINK THE WAY THAT WE WOULD LOOK AT THIS IS WE WOULD DO, WE, WE WOULD DISPATCH THAT 750 MEGAWATTS OF GENERATION DOWN ON THE LEFT HAND SIDE OF YOUR DIAGRAM, WHICH SHOULD THEORETICALLY RESOLVE THOSE OVERLOADS.

BUT YOU SAY THEOR, I MEAN IT MAY, MAY OR MAY NOT SOLVE THE GENERATION RE-DISPATCH THIS PROBLEM, RIGHT? I MEAN, I I'M NOT PLANNING ENGINEER, BUT LIKE PER NERC STANDARDS, ARE WE ALLOWED TO DO GENERATION RE-DISPATCH ON BASE CASE OVERLOADS AND, AND PLANNING STUDIES? I MEAN, THAT'S A QUESTION FOR TSPS HERE.

YEAH, WELL, I WE ALREADY DO THAT.

I MEAN THAT, THAT'S HOW WE, THAT THAT THAT'S HOW WE PERFORM AND, AND, AND I THINK WHAT MAKES US SLIGHTLY DIFFERENT AND, AND I'M, I AM NOT AN EXPERT ON FERC JURISDICTION, BUT I I THINK GENERATORS GET FIRM TRANSMISSION IN THE FERC WORLD.

AND SO THAT'S, THAT'S WHY THEY HAVE MORE OF THESE ISSUES WHERE WE DON'T HAVE THAT IN ERCOT.

UM, IT IT, BECAUSE, BECAUSE OF WHAT YOU SAID, IT'S CONNECT AND MANAGE ON THE GENERATION SIDE.

SO, SO I I, WE WOULD LOOK AT THIS AND WE WOULD RE-DISPATCH GENERATION TO SOLVE THAT OVERLOAD.

AND, AND I THINK, AND WE'VE RUN STUDIES ON THIS PREVIOUSLY AND, AND I, I THINK THAT IT SHOWS THAT YOU, YOU ANY, UH, DROP IN LOAD, LIKE YOU, YOU CAN'T HAVE MORE OVERLOADS IF YOU RE-DISPATCH A GENERATION AND IF THERE'S NO GENERATION SOLUTION, BECAUSE THAT DOES HAPPEN.

I MEAN, IN, IN REAL TIME, LIKE SOMETIMES WITH MY EXAMPLE IN, I MEAN, IN SOUTH TEXAS, YEAH, SOMETIMES THERE'S NOT A SOLUTION, RIGHT? YEAH.

BUT YOU SHOULD SEE THAT IN, IN THE STUDY.

AND, AND IF WE SEE THAT, THEN HOW WOULD WE, IF THERE'S NO GENERATION SOLUTION, THEN HOW ARE WE GONNA ANSWER THESE, THESE QUESTIONS? BUT, BUT AGAIN, YOU'VE, YOU'VE LOWERED YOUR LOAD, SO IF YOU'VE LOWERED YOUR LOAD, YOU CAN ALSO LOWER THE GENERATION.

SO THIS IS KIND OF THE SAME, UH, TO USE THE SOUTH TEXAS EXAMPLES, IT'S AS IF I HAD 750 MEGAWATTS LESS LOAD IN SOUTH TEXAS.

I I CAN LOWER THE GENERATION COMING OUT OF SOUTH SOUTH TEXAS BY 750 MEGAWATTS, AND I'M STILL TRANSFERRING THE SAME AMOUNT OF POWER FROM SOUTH TO NORTH AS I WAS BEFORE THAT.

OKAY.

I MEAN, IF THAT'S THE CASE, I I JUST WORRY BECAUSE THIS IS A PROBLEM THAT NOBODY ELSE SEEMS TO, TO BE ABLE TO SOLVE OUT OUTSIDE OF ERCOT BECAUSE THEY'RE IN THIS TUDY LOOP WHERE THEY DON'T KNOW IF GENERATION RE-DISPATCH IS, IS GONNA SOLVE THIS PROBLEM.

AND, AND THAT'S THE MAIN FLAG THAT I WANNA RAISE, THAT THERE MIGHT NOT BE A SOLUTION TO SOLVE THIS PROBLEM.

I MEAN, THIS IS A SIMPLE EXAMPLE.

LIKE I SAID, THERE COULD BE, YOU KNOW, WITH MULTIPLE BUSES, MULTIPLE LINES, THERE COULD BE A SCENARIO WHERE GENERATION DISPATCH IS NOT, IS NOT A SOLUTION.

AND NOW WE'RE GONNA BE STUCK WITH, WITH THIS.

BUT I HEAR YOUR POINT.

YEAH.

OKAY.

YEAH, I'LL JUST SAY I, I DON'T THINK WE, WE DON'T SEE THIS AND, AND YOU KNOW, WE, WE'VE RUN STUDIES ON THIS IN JUST NORMAL TRANSMISSION PLANNING AND, AND SO

[01:30:01]

WE DON'T SEE THIS SCENARIO AS BEING POSSIBLE ON ERCOT.

I I UNDERSTAND IN FERC WORLD, WE'RE, WE'RE THE GENERATORS THAT THEY HAVE FIRM TRANSMISSION THAT, THAT, THAT COULD BE AN ISSUE.

BUT I, I DON'T THINK THAT WE HAVE THAT HERE.

OKAY.

ALL RIGHT.

WE HAVE FOUR PEOPLE IN THE QUEUE, SO WE CAN KEEP TALKING THROUGH THIS HERE.

UH, SORRY, CAN I MAKE A COMMENT ON THIS? WHO'S, I'M SORRY.

IF YOU CAN GET IN LINE WITH GOOGLE, SORRY, WHOEVER'S SPEAKING, YOU CAN JUMP IN THE QUEUE.

YOU CAN REQUEST TO TALK.

OKAY, NEXT UP IS BOB WHITMEYER.

YEAH, JEFF, UM, STU, STUPID QUESTION OF THE DAY.

WHEN WE DO THESE LARGE LOAD STUDIES, DO WE ASSUME THE LOAD IS ALWAYS CONSUMING OR IS THAT FACTORED IN WHEN WE'RE DOING THE BATCH STUDIES THAT SOME OF THESE ARE GONNA BE OFF AND SOME ARE GONNA BE ON, UM, THE, WE WOULD ASSUME THAT THEY'RE ALWAYS STUDYING EXCEPT WE WILL RUN, UH, THE CONTINGENCY LOSS OF THAT LOAD.

THAT THAT'S, THAT IS A, A VALID CONTINGENCY IN THE PLANNING GUIDE.

OKAY.

SO WE ARE SORT OF LOOKING AT THIS ALREADY, RIGHT? UNDER THAT CONTINGENCY SCENARIO UNDER, RIGHT.

YES.

OKAY, THANK YOU.

YEAH.

ALL RIGHT, NEXT, CINDY KAR.

UH, YEAH, JUST A CLARIFICATION.

WILL THE BATCH PROCESS HONOR THE MDC CRITERIA THAT YOU CANNOT DISPATCH AROUND, UH, NON, UH, NON-RENEWABLE GENERATION? YOU LOST ME WITH THAT ACRONYM.

OH, MINIMUM DELIVERABILITY CRITERIA.

IT'S, YEAH.

YES, STILL THIS IS , I THINK THE BATCH ZERO STUDY, UM, THAT WILL BE CONSIDERED AS PART OF THE SCOPE.

THAT'S SOMETHING WE HAVE TO CONSIDER BECAUSE THAT'S AN EXISTING CRITERIA.

SO WE, WHEN WE, WHEN WE DO THE STUDY, WE WILL HAVE TO ACCOUNT FOR THAT.

YES, I WOULD THINK SO.

YEAH.

SO I, I GUESS THE POINT WAS CONCEPTUALLY THAT'S A RISK, WHAT'S MENTIONED THERE.

UH, IT, AND IT MAY POSE AS A SPECIFIC SCENARIO BASED ON WHAT WE ADD OR WHAT WE DON'T.

UM, SO SOMETHING TO FACTOR IN WHEN WE SAY WE CAN USE A-S-E-O-P-F TO DISPATCH AROUND THESE ISSUES.

UH, OFTEN THOUGH, THAT TOOL HAS BEEN REMOVED FROM OUR TOOLKIT AS A PLANNER, UH, IN THE RECENT CHANGES.

YES, SANDEEP, YOU'RE RIGHT.

SO ONE THING TO NOTE IS THAT, YOU KNOW, THE, THE DELIVERY CRITERIA IS ONLY APPLICABLE TO DISPATCHABLE RESOURCES AND THE LOAD THAT USED IN THE STUDY IS NOT THE COINCIDENT PEAK.

IF I'M RIGHT, IT'S, UH, I'M SORRY, IT'S NOT THE NON COINCIDENT PEAK.

IT'S, IT MIGHT BE A LOAD LESS THAN WHAT WE STUDY IN THE, IN THE TRANSMISSION PLANNING.

YEAH, YOU, YOU WILL HAVE A SUMMER PEAK CASE AND IF YOU CAN ARGUE THAT MDC DOESN'T APPLY TO THAT PARTICULAR CASE, THEN IT CHANGES HOW WE PLAN THE SYSTEM, AT LEAST THE WAY WE HAVE BEEN APPROACHING IT.

YEAH, FOR THE NET PEAK CASE, I AGREE, YOU CAN DISPATCH AND TRUST ALL THOSE ISSUES.

ALRIGHT, NEXT IN THE QUEUE IS BOB KING.

I JUST WANTED TO, UH, SAY THAT I REALLY APPRECIATE THE, UH, PRESENTATION.

IT BRINGS UP SOME GOOD QUESTIONS, BUT, AND ONE OF THE IMPORTANT QUESTIONS WAS, WOULD IT CHANGE THE FINANCIAL REQUIREMENTS, THE FEE REQUIRED OF THE LOAD THAT REMAINS? 'CAUSE IT COULD CHANGE THE COST TO SERVE THAT LOAD SIGNIFICANTLY, BUT I THINK GIVEN THE FACT THAT WE'RE ALL PUTTING UP $50,000 A MEGAWATT HOUR NON-REFUNDABLE FEE TO PAY, IF THERE'S A LITTLE READJUSTMENT IN THE ACTUAL, DURING THE REFINEMENT, I, I WOULD STILL LIKE TO SEE US FIX THE FINANCIAL REQUIREMENT AT THE TIME THAT WE MAKE THE COMMITMENT IN THE COMMITMENT PERIOD BECAUSE, UM, I MEAN SOME OF US WILL DO BETTER AND SOME WILL DO A LITTLE WORSE IN THAT PROCESS, BUT THE CERTAINTY IS WORTH SOMETHING AND MOVING FORWARD AND NOT RESTUDYING ALL THAT'S WORTH SOMETHING TOO.

SO I THINK WE'RE KIND OF COVERING ON THE FINANCIAL SIDE WITH VERY SIGNIFICANT NON-REFUNDABLE FEE COMPARED TO ANY OTHER MARKET.

SO MAYBE WE DON'T HAVE TO WORRY ABOUT THE ISSUE THAT YOU BROUGHT UP THERE.

DOES THAT MAKE SENSE? YES.

I MEAN, THIS ISSUE, I WORRY ONLY IN SCENARIOS WHERE LIKE LOADS DROPPING CAUSE NEW OVERLOADS, LIKE THIS IS JUST AN ISSUE WHAT I PRESENTED.

IF WHAT I'M SAYING HERE, IT IT'S AN ACTUAL POSSIBILITY, WHICH IT IS, UH, OUTSIDE OF KOT, I GUESS MY, I I GUESS MY FOLLOW UP QUESTION TO ERCOT IS THEN THIS WILL NEVER HAPPEN IN THE BATCH.

IS THAT MY UNDERSTANDING, ONCE YOU SIGN AN IA, AN IA ON THAT DECISION POINT, REGARDLESS OF WHAT

[01:35:01]

HAPPENS, WILL GUARANTEE THE MEGAWATTS THE COST AND THE TIMELINE.

SO THERE WOULD NEVER BE AN OVERLOAD CAUSED BY ANOTHER LOAD.

'CAUSE LIKE IN THEORY, I MEAN SCOPE F SHOULD RESOLVE THAT, BUT I, I MEAN, I GUESS THE RISK IS WHAT IF IT DOESN'T? LIKE WHAT IF FOR SOME REASON THERE'S SPECIFIC UNITS THAT ARE ALREADY MAXED OUT OR WE CAN'T MOVE THOSE UNITS FOR ANY REASON, THEN THIS MIGHT BE A PROBLEM.

AND I GUESS THIS MIGHT BE A PROBLEM ONLY IF WE CAN'T LIKE, YOU KNOW, SOLVE THOSE VIOLATIONS.

YOU HAVE TO BE CLEAR.

YEAH, AND I'M UNCOMFORTABLE WITH THE WORD GUARANTEE, BUT, UH, BUT YEAH, THE, THE INTENTION IS THAT, UM, GUARANTEED FROM A PLANNING PERSPECTIVE, I, I THINK THAT THAT'S WHAT WE'RE DOING IS WE'RE, WE'RE NOT GONNA GO BACK AND CHANGE THE MEGAWATTS.

WE'RE, WE'RE, UM, UH, YOU KNOW, TO THE EXTENT THAT FINANCIAL SECURITY REQUIREMENTS ARE BASED ON THE STUDY, WE WE'RE NOT GONNA GO BACK AND AND READJUST THOSE.

IT'S WHAT, WHAT HAPPENS AT THE END OF BATCH ZERO? UH, ANY CHANGES AFTER THAT SHOULD NOT IMPACT THE LOADS THAT, THAT'S THE INTENTION.

AND HOW WILL ERCO KNOW THAT THE SCOPE F WILL SOLVE THIS ISSUE IF BATCH STUDY HAS NOT BEEN RUN? UH, SO WE HAVE, I THINK BASED ON PAST STUDIES, WE BELIEVE THAT S-E-O-P-F SHOULD SOLVE THAT ISSUE.

OKAY.

ALRIGHT, THANK YOU VERY MUCH.

THERE'S STILL SOME PEOPLE IN THE QUEUE.

STAY UP THERE.

HERE WE GO, DURGA.

SO THERE'S THREE MORE AND THEN HOPEFULLY WE'LL MOVE ON TO THE NEXT PART.

SO DURGA, THANK YOU.

UM, DURGA FROM SOFTBANK.

UM, SO JUST TO CONFIRM, SO ONCE A BATCH STUDY'S COMPLETE AND THE LOAD SIGNS AND IA AND WE GO FORWARD AND SIGN ALL OF THIS STUFF WITH FINANCIAL STUFF, YOU'RE SAYING THERE'S NO WAY THE IA IS GONNA CHANGE, RIGHT? THERE'S NO NEED FOR AN IA AMENDMENT IN THE FUTURE, UH, SAYING THE, THE MEGAWATT CAPACITY HAS CHANGED.

IS THAT A, IS THAT TRUE? THAT'S, THAT'S TRUE.

OKAY.

UM, SEC SECOND QUESTION ON THE, ON THE SOLUTION, RIGHT? SO, UM, YOU SAID THAT GENERATION DISPATCH IS GONNA SOLVE THE ISSUE IF THE LOAD DROPS, BUT GENERATIONS ALSO DROP, RIGHT? UM, HOW COMFORTABLE IS THE CAR PROPOSING SOLUTIONS BASED ON GENERATIONS, ESPECIALLY FOR BEST? IS THERE, WHICH HAS A NEGATIVE SHIFT FACTOR ON THIS LOAD AND DISPATCHING THAT IS SOLVING THAT, THAT TRANSMISSIONS PROBLEM AND THE BEST DROPS IN THE FUTURE? UM, I JUST WANT TO UNDERSTAND HOW IS THINKING ABOUT IT BECAUSE THERE'S GONNA BE A LOT OF SPECULATIVE GENERATION AS WELL, ESPECIALLY BEST.

WELL, UM, SO A COUPLE THOUGHTS THERE.

SO GENERATION WON'T BE ADDED TO THE CASE UNLESS IT MEETS 6.9 UN UNLESS WE HAVE TO GET TO PICKER 1 27.

BUT ON, UH, THAT, THAT METHODOLOGY, BUT ON, UM, THE BES, UH, THE BATTERY SPECIFICALLY, UH, THERE, THERE ARE DIFFERENT DISPATCH ASSUMPTIONS DEPENDING ON THE CASE THAT WE'RE RUNNING AND WE WON'T RESPECT THOSE, UH, DISPATCH ASSUMPTIONS, WHICH I THINK TYPICALLY FOR SOME REPEAT IS ZERO, RIGHT? IT'S, YEAH, THIS IS, UH, PR SO THE, THE BATTERY DISPATCH, IT, IT HAS TO MEET A CERTAIN DURATION TO BE CONSIDERED AS A, YOU KNOW, DISPATCHABLE AND SUMMER PEAK CONDITIONS.

UM, I THINK TO ANSWER YOUR QUESTION, THE, THE GENERATION CHANGE, ESPECIALLY LOOKING AT THE NEAR TERM YEARS, JEFF IS RIGHT, YOU KNOW, YOU ONLY MODEL GENERATORS THAT MEET 6.9.

UM, SO EVEN IF GENERATION LIKE, YOU KNOW, GENERATION EXPECTATION CHANGES, I THINK, UM, ESPECIALLY RELATED TO THIS LOAD ISSUE, I DON'T THINK THIS WE HAVE, WE ARE, I MEAN, I'M NOT SAYING THIS COULD NOT HAPPEN, THERE COULD BE RARE SITUATIONS, BUT THE LIKELIHOOD OF THAT HAPPENING BASED ON THE WAY WE DO PLANNING WHERE WE DO DISPATCH GENERATION, LIKE JEFF SAID, SO THAT TAKES INTO QUANT, LIKE, YOU KNOW, ON ON TOP OF THAT WE ALSO STUDY THE G MINUS ONE AND MINUS ONE, WHICH IS KIND OF A N MINUS ONE CRITERIA WITH THE ERCOT.

SO THERE, THERE ARE SOME SAFEGUARDS, YOU KNOW, HOW WE ACCOUNT FOR THIS, YOU KNOW, UNCERTAINTY WITH GENERATION.

YEAH.

SO JUST TO DOUBLE DOWN ON WHAT HE SAID, THIS IS ALREADY HOW WE DO TRANSMISSION PLANNING IN ERCOT.

SO THIS IS, THIS IS NOT NEW.

WE'RE NOT BREAKING NEW TERRITORY HERE.

THAT, THAT, THAT IS, THIS IS WHAT WE ALREADY DO.

YEAH, THE REASON I WAS ASKING THIS QUESTION IS BECAUSE WITH SO MUCH SPECULATIVE LOAD, I THINK A LOT OF FICTITIOUS GENERATIONS ARE GONNA GET ADDED AS WELL TO SOLVE THE CASE.

AND, AND THAT'S WHERE MY QUESTION WAS ALLUDING TOWARDS, LIKE IF, IF THAT GENERATION DROPS, THEN HOW, HOW DO YOU HANDLE THAT BASICALLY IS MY QUESTION.

AND ESPECIALLY FOR A NO SOLAR SCENARIO, IT BECOMES MORE CRITICAL BECAUSE YOU DON'T HAVE ANY SOLAR IN THERE, RIGHT? SO ANY GENERATION THAT YOU'RE USING TO RE-DISPATCH AND SOLVE ISSUES, UH, THE SOLUTION

[01:40:01]

IS EXTREMELY SENSITIVE TO THAT GENERATION, UH, GOING ONLINE OR NOT, RIGHT? SO THAT, THAT, THAT'S, THAT'S WHERE I'M, MY QUESTION IS HEADING TOWARDS HERE AGAIN, THIS , UM, YES, YOU'RE RIGHT.

SO IF YOU'VE BEEN FOLLOWING THE LAST FEW PLANNING STUDIES, INCLUDING THE RTP, THE, THE GENERATION, WHAT YOU DEFINE ASPHYXIATION AS A PROBABLY OUTSIDE THE PLANNING GUIDE, THAT'S MORE APPLICABLE FOR THE FURTHER OUT YEARS.

AGAIN, WE, WE DON'T KNOW THE LOAD PROJECTIONS FOR THE UPCOMING STUDIES.

YEAH, THAT, THAT'S SOMETHING WE, WE TAKE A LOOK.

I MEAN IF WE DID ADD THOSE KIND OF GENERATION, WE DO SOME SENSITIVITIES TO MAKE SURE THAT'S NOT DRIVING THE, OR MASKING THE PROBLEM OR DRIVING TRANSMISSION PROJECTS.

SO IT'S, IT'S SOMETHING WE, WE TAKE INTO ACCOUNT IN OUR STUDIES, BUT UM, THE WAY THE BAT STUDY IS DEFINED RIGHT NOW, THE BAT ZERO, I DON'T THINK THAT'S GOING TO BE A SIGNIFICANT ISSUE FOR THE NEAR TERM YEARS WHEN YOU'RE LOOKING AT THE LOAD ALLOCATION PLAN OR THE LOAD COMMITMENT PLAN.

THANK YOU.

ALRIGHT, THANK Y'ALL.

UH, THREE MORE COMMENTERS.

SO SAM, BRANDON, GO AHEAD.

THANKS SAM, BRANDON WITH THE GENETIC INFRASTRUCTURE.

UM, SO I GUESS NOW I HAVE A QUESTION ON THAT DIALOGUE JUST NOW.

SO TO BE CLEAR, ENERGY STORAGE TODAY IN TERMS OF HOW IT'S REFLECTED IN THE, IN THE PLANNING MODELS IS BASED OFF THE ELCC CURVES IN THE CDR REPORT, RIGHT? LIKE IT'S NO LONGER ZERO.

THAT WAS LIKE THE LEGACY APPROACH.

I GOTTA GO AND LOOK BACK AT THE, I DON'T HAVE, I CAN'T RECALL THAT, BUT YOU ARE RIGHT, IT'S BASED ON THE SO, BUT WHAT I'M SAYING IS IT HAS TO HAVE A CERTAIN DURATION TO BE MODELED AS A DISPATCH PER RESOURCE.

YEP, YEP.

NO, THAT CERTAINLY MAKES SENSE.

UM, AND THEN, YEAH, SEPARATELY, MY POINT WAS JUST THAT, SO THE CONVERSATION JUST NOW JUST MADE ME THINK ABOUT PICKER 1 27 AND HOW THAT THE HIGH, THE HIGH LEVEL IS THAT PICKER 1 27 IS GOING TO ALLOW FOR PROJECTS THAT ARE NOT AT 6.9 TO BE INCLUDED IN THIS MODEL.

AND ESPECIALLY IF WE GET TO THE PARTICULARLY DISCRETIONARY KIND OF LEVEL OF THOSE DECISIONS THAT COULD IMPACT THIS SORT OF DYNAMIC IN A PRETTY MEANINGFUL WAY.

SO I'M NOT SURE IF ERCOT HAS ANY IMMEDIATE THOUGHTS ON HOW YOU GUYS PLAN TO, LIKE, IS THERE ANY SPECIAL LIKE CASE CRITERIA THAT'S EXPECTED ONCE WE GET TO THAT LEVEL OF STUDY? YEAH, NO, TIM, YOU BRING UP GOOD POINT.

UM, AT THIS POINT WE'RE NOT PLANNING ON DOING ANYTHING SPECIAL AROUND THAT.

UM, THERE IS A RISK THERE.

UM, AND, AND I THINK WE UNDERSTAND THAT, UM, BUT AT THIS POINT WE'RE NOT PLANNING ON DOING ANYTHING SPECIAL TO ADDRESS THAT.

ALL RIGHT, NEXT IS RUSSELL.

UH, HI EVERYBODY.

UH, RUS THOMPSON HERE WITH ASPHALT.

UH, UM, I'M NOT SURE IF THIS IS, UH, TOO SIMPLE OF A QUESTION, BUT I'D LIKE TO BE EDUCATED ON IT.

UH, THERE WAS A NOTE EARLIER ABOUT MEGAWATTS NOT BEING ABLE TO BE CHANGED, UH, DURING THE APP APPLICATION PROCESS, BUT SINCE MEGAWATTS AT THE APPLICATION ARE THEORETICAL, BECAUSE WE DON'T ACTUALLY HAVE THE REACT STUDY TO BE INCOMPLETE, WE DON'T HAVE THE FACTORY ACCEPTED TEST REPORTS OF THE EQUIPMENT.

SO WHAT IS THE THRESHOLD OF CHANGE THAT IS ALLOWABLE, UM, AFTER THOSE MEGAWATTS NEED TO BE UPDATED? 'CAUSE THE MEGAWATTS ARE WHEN IN THE APPLICATION THEY'RE DETERMINED AT THE 3 45 KV BUS, NOT AT THE POI OR AM I WRONG ON THAT? YEAH, I, I THINK THAT, UM, IT, IT, WHATEVER YOU PUT IN YOUR APPLICATION, YOU, YOU SHOULD ACCOUNT FOR THE, UM, YOU KNOW, ANY, ANY POTENTIAL CHANGES.

SO IF YOU THINK IT COULD GO UP, YOU SHOULD SUBMIT YOUR APPLICATION FOR WHATEVER THAT HIGHER AMOUNT IS.

OKAY.

SO WE, WE, IT'S OKAY TO GO FOR A HIGHER AMOUNT AND THEN IF IT'S NOT ACTUALLY THAT AMOUNT, IT'S FINE, IT'S FINE TO REDUCE IT DOWN, BUT IT'S NOT OKAY TO UNDERESTIMATE THAT THEN HAVE IT TO GO UP.

YEAH.

IF YOU WANTED TO GO UP, THEN THAT WOULD, UM, YOU, YOU'D HAVE TO GO IN FOR ANOTHER REQUEST FOR ADDITIONAL MEGAWATTS, SO IT IT'D BE A SECOND REQUEST AND YOU'D HAVE TO GO THROUGH THE STUDY PROCESS FOR THAT ADDITIONAL AMOUNT.

CORRECT.

UH, WHAT, IS THERE A SPECIFIC THRESHOLD OF, OF THAT? UH, SO LIKE FIVE MEGAWATTS OR SOMETHING? I THINK AGE JUST WALKED OUT, BUT I, I DON'T, UH, SO I DON'T, I DON'T KNOW WHAT THE ANSWER TO THAT IS, BUT I I THINK IT'S, UM, DEFINED IN PLANNING GUIDE, UH, SECTION NINE POINT.

CHRISTINA OR EVAN? NO, OFF THE TOP OF THEIR HEAD, IT'S EITHER, I THINK IT'S 9.2, BUT I DON'T REMEMBER THE SUBSECTION EXACTLY.

OKAY, I'LL, I'LL GO LOOK THAT UP IN THE, IN THE, IN THE PLANNING GUIDES THERE, BUT, BUT THE STRATEGY GOING FORWARD NEEDS TO BE THAT YOU OVERESTIMATE SO THAT WAY YOU CAN REDUCE BECAUSE REDUCING IS NOT THE PROBLEM.

AND THE PROBLEM IS IF YOU HAVE TO

[01:45:01]

INCREASE THE, UH, BASED ON THE RESULTS.

SO THESE, UH, STUDIES GOT, I'M, I'M NOT RECOMMENDING YOU OVERESTIMATE, BUT, UM, OR, OR RECOMMENDING ANY STRATEGIES, BUT, UM, YEAH, BUT THAT, THAT WOULD SEEM LIKE YOU, YOU, IT WOULD BE HARDER TO GO INCREASE THAN TO DECREASE.

OKAY.

ALL RIGHT.

THANK YOU.

ALL RIGHT, GREAT.

AND LAST QUESTION, UH, LEE CHER LICHER CIPHER DIGITAL, JUST A CLARIFICATION FROM DURGA QUESTION EARLIER IT WAS MENTIONED THAT IF YOU MEET THE 5 8 4 8 1 CRITERIA, UH, YOU HAVE AN INTERCONNECTION AGREEMENT SIGNED, YOU PAY THE, WHATEVER THE DOLLAR AMOUNT ENDS UP BEING, UM, TO GET INTO BATCH ZERO FIRM OR BATCH ZERO BASE LOAD, UM, THAT, THAT THOSE MEGAWATTS WOULD NOT BE LOCATABLE.

BUT ISN'T THERE A SCENARIO WHERE YOU COULD BE FAR ENOUGH DOWN THE LINE AND YOUR LOAD MET THOSE CRITERIA AFTER A BUNCH OF OTHER LOADS? DID THAT, AS YOU GO DOWN THAT CHRONOLOGY AND LOOK AT THE STUDIES, IF YOU HAD A STUDY THAT WASN'T INCLUDED IN A STUDY THAT WAS APPROVED BEFORE, YOU JUST WANNA CLARIFY, THAT'S STILL THE CASE THAT YOU COULD POTENTIALLY BE IN BATCH ZERO, UM, BASE LOAD, AND THEN IN THE EVENT THAT THAT DOES OCCUR, YOU WOULD BE KICKED OVER TO BATCH ZERO LOCATABLE, IS THAT CORRECT? UH, YEAH, I THINK I WOULD SAY IT'S SLIGHTLY DIFFERENT THAN THAT, BUT I, I THINK THAT THAT'S RIGHT.

SO, BUT YOU WOULD KNOW THAT AHEAD OF TIME.

IT, IT WOULDN'T BE THAT IN SEPTEMBER WE WOULD TELL YOU, OH, YOU'RE, YOU'RE NO LONGER BASE LOAD.

YOU'RE, YOU'RE, UM, YOU COULD BE REALLOCATED.

WE, WE WOULD KNOW THAT UPFRONT LIKE JU JULY 10TH TIMEFRAME.

YEAH, I, I THINK J JULY TIMEFRAME OR, UM, AND I'LL GET INTO THIS IN MY PRESENTATION, BUT WE, WE ARE INTENDING TO, UH, PROVIDE REGULAR UPDATES TO THE TSPS ON THE STATUS OF THESE, SO YOU WILL KNOW.

SO IF, IF YOU CAME IN ON MARCH 30TH, THEN YOU KNOW, YOU, YOU, YOU SHOULD KNOW IN APRIL ABOUT WHETHER YOU'RE WOULD BE CONSIDERED, UH OH UNDERSTOOD.

ELIGIBLE FOR BASE LOAD.

UNDERSTOOD.

THANK YOU.

YOU WOULDN'T HAVE TO WAIT UNTIL AUGUST OR JULY.

THAT'S VERY HELPFUL.

HEY JEFF, REAL QUICK, JUST ONE FOLLOW UP QUESTION JUST TO MAKE SURE THAT I'M UNDERSTANDING THIS RIGHT.

ERCO WILL USE GENERATION RE DISPATCH SCOPE PF OPTIMAL POWER FLOW TO SOLVE AND MAINTAIN THE LOAD THAT STAYED AFTER THE, AFTER THE REFINEMENT AND SOLVE ALL THE RELIABILITY VIOLATIONS.

I GUESS THE FOLLOW UP QUESTION WOULD BE, WHY CAN WE USE THAT SAME CONCEPT INITIALLY? I MEAN IF ER CODE CAM GUARANTEE, LIKE, JUST TO GIVE YOU AN EXAMPLE, IF WE, WE HAVE 10 GIGAWATTS ON THE QUEUE AND TWO DROP AND, AND NOW WE HAVE EIGHT AND ER CODE GUARANTEEING THAT SCOPE F WILL SOLVE FOR THOSE EIGHT AND IT WILL SOLVE ALL THE VIOLATIONS THAT HAPPEN FROM LARGE LOADS WITHDRAWING.

I MEAN, WOULDN'T WE BE ABLE TO USE SCOPE F INITIALLY FOR THE 10 GIG AND, AND GIVE HOLD THAT 10 GIGS LIKE FIXED AND HAVE SCOPE F SOLD FOR EVERYTHING AND GIVE EVERYBODY THE, THE 10 GIGS? YEAH.

SO THAT, THAT, THAT'S THE, IN, IN, WELL I WOULD, MAYBE, AGAIN, I'LL SAY IT SLIGHTLY DIFFERENT, BUT WE WILL USE S-E-O-P-F IN, IN THAT INITIAL BATCH OF STUDY.

UH, BUT WE EXPECT THAT EVEN WITH THAT THERE MAY BE OVERLOADS.

SO IT'S, SO, SO THE WAY THE PROCESS IS WORKING IS WE PUT ALL THE LOADS IN THE CASE, WE RUN S-E-O-P-F AND WE SEE WHAT OVERLOADS THERE ARE, AND THEN WE WORK WITH THE TSPS TO TRY TO, UH, COME UP WITH TRANSMISSION SOLUTIONS AND, AND MAYBE WE IDENTIFY A DOZEN TRANSMISSION SOLUTIONS AND WE PUT THOSE IN THE CASE WE RUN S-E-O-P-F AGAIN, WHATEVER VIOLATIONS EXIST AT THE END OF THAT PROCESS, WE, WE HAVE RUN S-E-O-P-F.

SO WE'VE DONE ALL THE GENERATION RE-DISPATCH THAT WE CAN DO.

IF THERE ARE STILL OVERLOADS, THEN WE WILL RUN AN ADDITIONAL ANALYSIS AND IT'S, IT'S ALSO S-E-O-P-F, BUT IT, IT'S, UH, IT WILL, UH, REDUCE THAT LOAD AMOUNT, UH, UNTIL WE GET A SOLVED CLEAN CASE.

BUT IT, IT, IT MAY NOT BE POSSIBLE WITH THE GENERATION THAT'S IN THE CASE TO RESOLVE ALL OF THE OVERLOADS, UH, BECAUSE IT, YOU KNOW, THERE JUST MAY NOT, THAT JUST MAY NOT BE POSSIBLE.

GOT IT.

THANK YOU VERY MUCH.

ALRIGHT.

YEP.

GOOD DISCUSSION.

THANK YOU EVERYBODY.

ALRIGHT,

[6. Design elements for CLR]

SO WE'RE GONNA TRANSITION.

SO IF YOU'RE FOLLOWING AT HOME, WE ARE NOW JUMPING TO AGENDA ITEM SIX.

THIS IS THE DESIGN FOR CLR.

SO WE'RE GONNA GO BACK TO THE MAIN ERCOT PRESENTATION AND I'M GONNA TURN THIS OVER TO AG AND WE'RE GONNA GO DOWN TO SLIDE.

OOH, THERE WE ARE.

SLIDE 16 AND RYAN'S HAPPY TO DO SLIDE.

[01:50:07]

ALRIGHT, UH, GOOD MORNING.

UH, A SPRINGER OR KA, UM, THANK Y'ALL FOR, UH, ACCOMMODATING US FOR GOING A LITTLE BIT OUT OF ORDER.

UM, SO, UH, I THINK AT THE LAST WORKSHOP I HAD INDICATED THAT WE WERE HOPING TO HAVE LANGUAGE TO REVIEW, UH, AT TODAY'S WORKSHOP.

UH, WE DIDN'T QUITE GET THERE.

UM, THERE'S STILL, UH, A NUMBER OF, UH, TOPICS THAT WE ARE STILL VETTING INTERNALLY AND, UM, BECAUSE OF THAT WE'RE, WE'RE NOT QUITE READY TO SHARE LANGUAGE TODAY, BUT WE ARE, UM, STILL TARGETING THE APRIL 8TH DATE THAT MATT TALKED ABOUT, UH, EARLIER IN THE WORKSHOP FOR FILING THESE REVISION REQUESTS.

UM, SO WHAT WE'RE GONNA BE DOING TODAY IS NOT JUST REHASHING THAT, UH, ONE SLIDE, ALTHOUGH I'M GONNA START WITH IT, UH, BUT WE WILL WE'LL COVER, UH, MUCH MORE DETAIL ABOUT THE STRUCTURE OF WHAT'S GOING TO BE IN THE, THE REVISION REQUEST.

UM, AND SO, UH, HOPEFULLY THAT WILL GIVE YOU ALL A BIT MORE VISIBILITY INTO THE DIRECTION WE'RE HEADING AND, UH, YOU KNOW, WE CAN TAKE QUESTIONS AS WE'RE GOING THROUGH OR, UH, WELL IT'S, IT IS ONLY LIKE SIX SLIDES, SO LET ME GET THROUGH 'EM AND THEN, THEN WE WILL, WE'LL TAKE QUESTIONS.

SORRY, .

OKAY, SO I'M GONNA START WITH THE, THE SLIDE AS A, A CONCEPT REFLE REFRESHER.

SO, UM, THE CONCEPT IS THAT, UH, LARGE LOADS THAT INDICATE, UH, PRIOR TO THE BATCH STUDY THAT THEY WILL BE, UM, WILLING TO HAVE SOME OR ALL OF THEIR LOAD, UH, ENTERED AS CLR, UH, WILL POTENTIALLY RECEIVE HIGHER MEGAWATT ALLOCATIONS.

UM, WE'RE GONNA BE CREATING SORT OF A NEW MODIFIED, UH, CLR CONSTRUCT CALLED A PROVISIONAL CLR, UM, THAT WILL HAVE, UH, POTENTIALLY, UH, SOME CAPPING ON THE CLR BID CURVE, UH, INSTEAD, UH, BUT, UH, EFFECTIVELY, YOU KNOW, IT WILL ALLOW THESE LOADS TO POTENTIALLY CONNECT MORE MEGAWATTS, UH, OVER, YOU KNOW, SOONER THAN THEY WOULD HAVE IF THEY WERE STUDIED SOLELY AS FIRM LOAD.

UM, SO THAT'S, THAT'S THE STRUCTURE WE'RE GOING FORWARD WITH.

UM, AND SO I'M GOING TO GO AHEAD AND GET THE DETAILS NOW.

SO FIRST OF ALL, STRUCTURE OF REVISION REQUESTS, UM, I'M GOING TO CA CAVEAT EVERYTHING THAT I SAY FOLLOWING THAT FROM THIS SLIDE FORWARD AS THESE ARE DESIGN, UH, PRINCIPLES THAT ARE STILL BEING, UH, REVIEWED INTERNALLY.

UM, SO SOME OF THESE DETAILS MAY CHANGE BETWEEN TODAY AND WHEN WE FILE THE REVISION REQUESTS.

UM, WERE WERE THERE SOME AREAS WHERE WE'RE STILL DETERMINING WHETHER OR NOT WHAT WE ARE ARE DRAFTING IS, IS FEASIBLE? UM, SO I JUST, YOU KNOW, EVERY SINGLE SLIDE IS GONNA HAVE THAT FOOTNOTE ON IT.

UM, AND THAT'S BECAUSE, UH, IT'S ALSO THE REASON WE'RE NOT SHOWING LANGUAGE TODAY.

UM, OKAY.

SO, UH, THIS WILL CONSIST OF A PIGGER AND A COMPANION NPRR.

UM, AS WITH PIGGER 1 34 AND, UH, NPR 1325, UM, THE PROBABLY, UH, MOST OF THE PLANNING MEET WILL BE IN THE PIGGER AND THEN THE CHANGES TO SC METHODOLOGY AND, UH, THINGS LIKE DEFINITIONS AND THE AGREEMENT THAT WILL, WILL LOCK IN THE CLR, UH, ARE GONNA BE LOCATED IN THE NPRR.

AND THE WAY WE'RE STRUCTURING IT IS A MODULAR STRUCTURE WHERE EFFECTIVELY IT'S GOING TO KIND OF ADD ON TO PICKER 1 45 AND NPR 1325.

SO FOR EXAMPLE, IN PICKER 1 45, WE HAVE SECTION 9.2 0.2 THAT DEFINES THE SET OF INFORMATION THAT HAS TO BE PROVIDED TO GET INTO THE BATCH ZERO STUDY.

UM, WHAT WE'VE DONE IN KIND OF EACH OF THESE CASES IS ADDED ON A SECTION PLUS ONE NUMBER THAT WILL DEFINE ADDITIONAL INFORMATION OR ADDITIONAL STUDY PARAMETERS RELATED TO A PROVISIONAL CONTROLLABLE LOAD RESOURCE.

UM, SO THE IDEA IS IT WILL PLUG INTO PGA 1 45 BUT NOT BE TIED TO IT DIRECTLY IN THE EVENT.

YOU KNOW, SO THAT'LL ALLOW THEM BOTH TO MOVE TO JUNE BOARD IF, IF THERE'S, IF THAT'S POSSIBLE.

UM, BUT IT WILL NOT BOG DOWN PIGGER 1 45 BY BEING ADDED AS COMMENTS, UH, TO THAT, THAT PIGGER.

AND THE SAME FOR THE NPRR.

UM, SO THAT, THAT'S THE DIRECTION WE'RE HEADING.

KIND OF, IF YOU IMAGINE EVERYTHING IN SECTION NINE WILL KIND OF HAVE A LITTLE EXTRA SECTION ADDED TO IT THAT DESCRIBES HOW A PROVISIONAL CLR IS GONNA BE TREATED.

SO, UH, BEFORE WE TALK ABOUT THE PROCESS, UH, THE DEFINITION, SO I MENTIONED THAT WE ARE CREATING A NEW CONSTRUCT CALLED A PROVISIONAL CLR.

UM, THIS IS EFFECTIVELY ACL R, BUT WITH A A FEW KEY

[01:55:01]

DIFFERENCES.

UM, THE FIRST IS THAT IT WILL BE LOCKED IN FOR A SET PERIOD OF TIME UNTIL, UH, THE POINT AT WHICH THE LOAD CAN BE SERVED RELIABLY AS FIRM LOADS.

SO, UM, YOU KNOW, ONE OF THE FEEDBACK THAT WE HEARD FROM STAKEHOLDERS QUITE CLEARLY IS THAT THEY, THE DESIRE IS FOR A CLR TO BE A PATH TO CONNECT MORE MEGAWATTS SOONER, BUT HAVE AN EXIT PATH.

UM, AND SO PART OF THE B ZERO STUDY FOR, UH, THESE PROVISIONAL CLRS WILL BE TO IDENTIFY THAT EXIT DATE WHEN THE LOAD WOULD BE ELIGIBLE TO BECOME SOLELY FIRM LOAD AND DEREGISTER AS ACL R.

UH, THE SECOND DIFFERENCE WOULD BE THAT THERE WILL BE LOW POWER CONSUMPTION LIMITS THAT ARE DEFINED IN THE BATCH ZERO INTERCONNECTION STUDY.

SO THIS IS EFFECTIVELY IDENTIFYING HOW MUCH OF THE LOAD CAN RELIABLY BE SERVED AS FIRM AND THE REST OF IT WOULD NEED TO BE OFFERED IN, IN REAL TIME AS DISPATCHABLE TO SCED.

UM, SO, UH, THAT, THAT MIRRORS, YOU KNOW, HOW MUCH OF THE LOAD COULD BE SERVED AS FIRM IN FOR LOADS THAT ARE NOT WANTING TO BE CLR.

AND THE DIFFERENCE IS THAT THAT BECOMES SORT OF YOUR, YOUR FLOOR AS ACL R, UH, IF YOU'RE GONNA GO THIS ROUTE.

AND THEN THE FINAL, UH, DIFFERENCE BETWEEN A TRADITIONAL CLR AND THIS PROVISIONAL CLR, UM, WOULD BE THE, UH, THE BID CAPPING METHODOLOGY, UM, TO MITIGATE THE TRANSMISSION CONSTRAINTS.

AND SO WHAT THIS IS DOING IS IT'S ENSURING THAT THE SCED DISPATCH WILL ELECT TO DISPATCH THE LOAD DOWN IF IT'S NEEDED TO RESOLVE THE CONGESTION.

UM, BUT THERE IS MORE DETAIL IN THERE.

THE IDEA IS THAT IT WOULD BE DYNAMICALLY, UM, UH, SORT OF LAST IN LINE.

THIS LOAD WOULD SORT OF BE LAST IN LINE BEHIND ALL THE GENERATION THAT MIGHT BE ABLE TO RESOLVE THE DISPATCH.

UM, AND SO, UH, WHAT WE DON'T WANT TO HAVE HAPPEN IS, UH, THE CONSTRAINT IS ALLOWED TO VIOLATE, BUT, UH, WE'RE, WE'RE WANTING TO NOT DISPATCH THESE CLRS AHEAD OF THE GENERATION.

SO THERE'LL BE SOME ADDITIONAL METHODOLOGY AND, UH, I'VE GOT A, I'VE GOT A TEAM OF FRIENDS FROM THE COMMERCIAL OPS SIDE WHO ARE GONNA HELP ME WITH THAT.

WE'LL GET TO THAT SLIDE.

OKAY.

SO WHAT DOES THIS MEAN THEN, FOR THE BATCH STUDY PROCESS? SO EFFECTIVELY IT MEANS THERE'S GONNA BE SOME ADDITIONAL INFORMATION COLLECTED UPFRONT, SOME STEPS IN THE STUDY PROCESS AND THE COMMITMENT PROCESS.

AND THEN THE REFINEMENT STUDY WILL STILL BUILD THE FULL, THE, THE TRANSMISSION NEEDED TO SERVE THE FULL LOAD.

SO, UM, IF WE START AT BOX ONE, THERE WILL BE SOME EXTRA INFORMATION AND A DECLARATION OF INTENT TO REGISTER AS A CLR OR A PROVISIONAL CLR, UH, THAT WILL BE DUE TO ERCOT ALONG WITH EVERYTHING ELSE THAT'S COMING IN ON THE JULY 24TH DATE.

SO, UM, IF, IF YOU'RE WANTING, IF YOUR LOAD IS GOING THIS ROUTE, THERE'S JUST SOME ADDITIONAL DOCUMENTS AND INFORMATION IN TERMS OF MODELING PARAMETERS THAT WILL COME INTO ERCOT BY JULY 24TH.

ERCOT WILL STUDY THE LOAD IN THE BATCH ZERO STUDY.

I WANT TO EMPHASIZE THAT BEING ACL R, AT LEAST AS WE'RE DRAFTING IT, DOES NOT IMPACT YOUR ELIGIBILITY FOR, UH, BATCH ZERO INCLUSION AS AN ASSESSED LOAD.

IF YOU WERE NOT ELIGIBLE FOR INCLUSION AS AN ASSESSED LOAD, DECLARING INTENT TO BE A CLR IS NOT GOING TO CHANGE THAT.

UM, BUT ELIGIBLE LOADS CAN POTENTIALLY GET MORE MEGAWATTS SOONER IF THEY WANT TO GO THIS ROUTE.

AFTER BATCH ZERO, THERE'S GOING TO BE A STEP WHERE THE ILLE WILL HAVE TO, UH, UPDATE THEIR DECLARATION TO FORMALIZE THE AMOUNT OF, UH, THE FIRM LOAD AMOUNTS FROM THE BATCH ZERO STUDY AND TO AFFIRM THE INTENT TO REGISTER AS ACL R.

UM, AND THEN THE REFINEMENT STUDY REALLY, THERE'S NO CHANGE THERE.

THE REFINEMENT STUDY HAPPENS, UM, AND WE WILL STUDY THE FULL LOAD AMOUNT FOR, AGAIN, FOR INCLUSION, UH, TO ENSURE TRANSMISSION IS BUILT, UH, IN THE TRANSMISSION PLAN.

THE NEXT THREE STEPS ARE EFFECTIVELY EXISTING STEPS THAT HAVE TO HAPPEN TODAY IN ORDER TO REGISTER AS A CONTROLLABLE LOAD RESOURCE.

AND THESE WILL STILL NEED TO HAPPEN.

UH, SO THESE WILL INCLUDE THE CUSTOMER REGISTERING THE ILLE, REGISTERING AS A RESOURCE ENTITY DESIGNATING A QSE, UM, GETTING THE PROPER METERING IN PLACE, WORKING WITH ERCOT DEMAND INTEGRATION TO GET THE, UH, RIO SUBMISSIONS DONE TO GET THE CLR MODELED.

UM, AND, UH, ESTABLISHING THE REQUIRED TELEMETRY POINTS.

SO, UM, JUST LIKE ACL R, THIS IS A FULL REGISTRATION

[02:00:01]

AS A NERCOMP MARKET PARTICIPANT.

AND, UH, ALL THE TELEMETRY THAT WILL COME ALONG WITH THAT.

UM, THIS, UH, CAN BE DONE, WE BELIEVE IN PARALLEL WITH THE QSA REQUIREMENTS, BUT IT DEFINITELY HAS TO BE DONE PRIOR TO THE INITIAL ENERGIZATION, UH, POINT FOR THIS LARGE LOAD IN ORDER FOR THE NON FIRM AMOUNTS TO BE ALLOWED TO COME ONLINE.

UM, FINALLY, WE'LL, WE'LL VALIDATE ALL OF THAT HAS HAPPENED IN THE APPROVAL TO ENERGIZE PROCESS.

UM, SO I HAVE SOME MORE DETAILED SLIDES.

UH, I KIND OF VOICED OVER MOST OF THOSE, SO I'M GONNA JUST GO THROUGH THESE REAL QUICKLY.

UM, THE DECLARATION OF INTENT TO REGISTER, UM, WE'RE THINKING THAT WOULD BE A NOTARIZED DOCUMENT THAT'S SIGNED BY THE, UH, INTERCONNECTING LARGE LOAD ENTITY.

UM, THERE'LL BE SOME ADDITIONAL INFORMATION LIKE THE DESIRED MINIMUM FIRM LOAD AMOUNT SO, IN OTHER WORDS, IF YOU'RE A 500 MEGAWATT LOAD AND THE DESIGN OF YOUR FACILITY IS SUCH THAT A HUNDRED HAS TO BE FIRM, WE NEED TO KNOW THAT TO DETERMINE IF THE SYSTEM CAN RELIABLY SERVE THAT AMOUNT.

UM, IF IT GROWS OVER TIME, THE, YOU KNOW, IF YOUR FACILITY IS MODULAR, I THINK THAT THAT WOULD BE ACCOUNTED FOR AS WELL.

UM, FOR THE, SO IF WE MOVE OVER TO BOX TWO, I THINK THE ONLY OTHER DETAIL I WOULD ADD ABOUT HOW THIS IS GOING TO BE HANDLED IN THE BATCH ZERO INTERCONNECTION STUDY IS THAT WE WILL LOOK TO SEE IF THAT MINIMUM LOW POWER CONSUMPTION AMOUNT, IN OTHER WORDS, THE, THE PORTION OF YOUR DESIGN THAT HAS TO BE FIRM LOAD, UH, WHETHER THAT CAN BE RELIABLY SERVED IN EACH YEAR OF THE BATCH ZERO STUDY.

UH, IF IT CANNOT BE SERVED, THEN, YOU KNOW, THAT WOULD BE AN INDICATION THAT EVEN THE, THAT BASE AMOUNT OF, UH, FIRM LOAD CANNOT BE RELIABLY SERVED.

SO EVEN, UH, AS BEING A CLR WOULD NOT ALLOW YOU TO CONNECT.

BUT THE, THE REVERSE IS ALSO TRUE.

SO IF, IF YOU DESIGNATE, YOU KNOW, A HUNDRED MEGAWATTS MUST BE FIRM, AND WE, YOU KNOW, THIS, THE BATCH ZERO STUDY DETERMINES 150 COULD RELIABLY BE SERVED AS FIRM, THEN THAT WOULD BECOME YOUR ALLOWABLE FIRM LOAD AMOUNT, LOW POWER CONSUMPTION AMOUNT.

UM, SO, YOU KNOW, THERE'S STILL THAT RELIABILITY ASPECT.

WE WILL ALSO STUDY THE FULL REQUESTED AMOUNT FOR BOTH DETERMINING THE POTENTIAL TRANSMISSION UPGRADES AS WELL AS FOR THE STABILITY ANALYSIS.

UM, BECAUSE THE LOAD IS VARIABLE, WE NEED TO ASSESS, UH, THE IMPACT OF POTENTIALLY THE FULL CONSUMPTION AMOUNT ON THE SYSTEM, EVEN FOR THE EARLIER YEARS WHEN THE, THE FULL LOAD AMOUNT MAY NOT BE ABLE TO BE SERVED.

UM, DURING THE COMMITMENT PERIOD, AGAIN, THERE'S GONNA BE THAT UPDATE WITH THE DETAILS OF THE BATCH ZERO STUDY, UH, BEING INCLUDED IN THE AGREEMENT AND, UH, UH, AGREED TO BY THE, THE CUSTOMER.

UM, AND THEN AGAIN, IN THE REFINEMENT, WE'LL STUDY THE FULL REQUESTED AMOUNT TO ENSURE THE TRANSMISSION PLAN, UH, FULLY REFLECTS THE, UH, THE REQUESTED LOAD.

AND THEN, UH, AGAIN, EXISTING STEPS HAVE TO BE TAKEN TO REGISTER AS A CONTROLLABLE LOAD RESOURCE.

UM, AND THEN WE'LL VERIFY THAT DURING THE, UH, APPROVAL TO ENERGIZE PROCESS.

UM, SO WE DID HAVE ONE SLIDE.

UH, I, RYAN, IF YOU WANT TO TALK THROUGH ON THE, THE BID CAPPING METHODOLOGY THAT WE'RE CONSIDERING AND, UH, WOULD BE REFLECTED IN THE REVISION REQUESTS.

YES.

UH, THANKS AG RYAN KING MANAGER MARKET DESIGN AT ERCOT.

SO WHAT I'LL TRY AND DO HERE IS THIS, THIS IS KIND OF AN OVERVIEW OF, LET'S CALL IT THE CONCEPTUAL FRAMEWORK FOR THE DYNAMIC BIG CAPPING DESIGN, UH, THAT WE'RE PROPOSING AS PART OF, UH, THIS CONSTRUCT.

SO AS NOTED, THIS APPLIES TO THIS PROVISIONAL CLR CONCEPT.

SO I THINK WHAT I'LL DO IS JUST GO THROUGH THE STEPS AS OUTLINED ON THIS SLIDE, AND THEN I'M SURE THERE'LL BE A FEW QUESTIONS.

UM, SO AS AG MENTIONED BEFORE, THIS IS A, A KIND OF WAY OF DOING A LAST IN TIME OR LAST IN LINE, JUST IN TIME CONCEPT.

SO I'LL START ON THE, THE LEFT HAND SIDE HERE.

SO AFTER EACH SCED RUN CONCEPTUALLY, THERE'S GONNA BE A LIST OF BINDING TRANSMISSION CONSTRAINTS, WHICH ARE APPROACHING THEIR MAX SHADOW PRICE.

SO I HAVE A PARAMETER HERE, AN X PERCENT, AND I DID WANNA NOTE THAT THIS PERCENTAGE MAY NOT BE A SINGLE NUMBER, BUT RATHER IT MAY VARY DEPENDING ON THE, THE, THE TYPE OF CONSTRAINT.

AND THEN THESE ARE IDENTIFIED AS A, A POTENTIAL LIST OF TRANSMISSION CONSTRAINTS THAT CAN BE USED IN THIS BID, UH, CLR BID CAPPING PROCESS FOR THE NEXT SCED RUN.

SO THERE'S SOMETHING THAT HAPPENS IN THE PREVIOUS SCED RUN, AND THEN THE NEXT SCED RUN.

SO WE GET THIS LIST OF CONSTRAINTS DETERMINED

[02:05:01]

IN THE, THE, THE CURRENT SCED RUN, THE NEXT SCED RUN, UM, WHERE THE LIST OF CONSTRAINTS, UH, IDENTIFIED FOR THE BID CAPPING PROCESS FROM THE PREVIOUS SCED RUN MATCHES THOSE IN THE CURRENT SCED RUN.

THIS IS WHERE THE, THE THE, UM, BID CAPPING PROCESS APPLIES.

SO WHEN THO WHEN THE LISTS MATCH ANY CONSTRAINTS THAT MATCH, THEN ANY, UH, AND THAT SHOULD, PARDON ME, THAT SHOULD SAY, UH, PROVISIONAL CLR, ANY PROVISIONAL CLR WITH A HELPING SHIFT FACTOR.

AGAIN, THAT'S A, A PARAMETER.

SO WHAT WHATEVER THAT IS ON A GIVEN CONSTRAINT WILL HAVE ITS ENERGY BID CURVE CAPPED, UH, IN THE STEP TWO SCED RUN ACCORDING TO THE FORMULA THAT I'VE OUTLINED BELOW HERE.

SO THE BID CAP BAT, UH, PARDON ME, THE PROVISIONAL CLR BID CAP WILL BE STEP ONE SYSTEM LAMBDA, AND THEN IT WILL, UH, MINUS THE MAXIMUM OF THE MAX SHADOW PRICE ON THE CONSTRAINT TIMES THE SHIFT FACTOR, UH, LESS ONE PENNY.

NOW REMEMBER THAT THE, UM, IN THAT BRACKET, THOSE ARE NEGATIVE NUMBERS.

SO YOU HAVE TO KIND OF UNDERSTAND THE, THE WAY THE SIGNS WORK THERE, THAT THOSE WOULD BE ADDITIVE.

AND THEN BASICALLY, UM, IF FOLKS HAVE BEEN INVOLVED IN SOME OTHER, UH, CONTEXT, WE'VE UTILIZED SOMETHING LIKE THIS, NOT THE SAME, BUT SIMILAR IN PRINCIPLE IN NPR 1255, FOR EXAMPLE, ALTHOUGH, TO BE CLEAR, THAT WAS BASED ON MARKET POWER MITIGATION.

THAT IS NOT WHAT IS HAPPENING HERE.

BUT BASICALLY THAT ALLOWS, UM, CLRS TO BE, UH, JUST AVAILABLE TO SCAD TO HELP RESOLVE THE TRANSMISSION CONSTRAINT.

SO I'VE RAMBLED ON A LITTLE BIT HERE.

IT LOOKS LIKE WE HAVE A, A FAIRLY EXTENSIVE QUEUE.

I WILL JUST SEE IF S HAS ANYTHING THAT, THAT, UH, HE WANTED TO RAISE OVER AND ABOVE THAT.

IT'S GOOD.

OKAY.

YEAH, NOTHING FROM S SO WE'LL PASS THE BALL BACK TO AJI.

THANK YOU, RYAN.

SO BEFORE WE TAKE QUESTIONS, I THINK I JUST HAVE ONE MORE SLIDE.

SO LET'S GET THROUGH THAT AND THEN WE CAN, WE CAN OPEN UP THE QUEUE.

UM, I JUST WANT TO EMPHASIZE AGAIN THAT WHILE, YOU KNOW, WE, WE BELIEVE THAT THIS IS A VIABLE PATH FORWARD AND WE ARE, ARE STILL TARGETING THE APRIL 8TH DATE TO HAVE THIS FILED.

YOU KNOW, THERE, THERE ARE A NUMBER OF QUESTIONS THAT WE ARE STILL WORKING ON INTERNALLY.

AND THIS, AGAIN, AS PART OF THE REASON WHY WE DON'T HAVE LANGUAGE TO SHARE TODAY.

UM, YOU KNOW, SO IN THE B ZERO STUDY, IS THERE A STUDY SCENARIO POTENTIALLY FOR STABILITY WHERE WE MAY, UH, LIMIT THE MAXIMUM POWER CONSUMPTION OF THE, THE PROVISIONAL CLR? UM, THAT IS SOMETHING WE'RE STILL WORKING THROUGH.

UH, THE QUESTION OF CAN PCLR PROVIDE ANCILLARY SERVICES, I THINK IS STILL OPEN.

UM, YOU KNOW, THINGS FOR, HOW, HOW DOES THE CURRENT CLR PROCESS ENSURING THAT LINES UP WITH THE OVERALL BATCH STUDY PROCESS? UH, I THINK WE HAVE A, A PATH FORWARD THERE, BUT WE'RE, WE'RE STILL WORKING THE DETAILS THERE AND THINGS LIKE THE DETAILS FOR THE, UH, BID CAPPING PROCESS, YOU KNOW, THE, THE PERCENTAGES AND THE SLIDE THAT RYAN JUST TALKED THROUGH, UM, YOU KNOW, AND, AND IDENTIFYING THE SPECIFIC SYSTEM CHANGES AND ENSURING THAT THOSE ARE ACHIEVABLE BY THE POINT AT WHICH LOADS THAT, UM, WANT TO BE TREATED AS, AS PROVISIONAL CLRS IN THE BATCH STUDY WHEN THEY COME ON THE SYSTEM.

WE NEED TO HAVE SOME REALISTIC CHANCE OF HAVING THOSE, IF THERE ARE SYSTEM CHANGES NEEDED, HAVING THOSE IN PLACE.

UM, ONE LAST POINT BEFORE I OPEN IT UP IS THAT, YOU KNOW, I TALKED ABOUT HOW WE'RE, WE'RE, WE'RE WRITING THIS REVISION REQUEST IN A MODULAR FASHION.

UM, ONE OF THE ADVANTAGES OF DOING THAT IS SOMETHING THAT WE'VE HEARD FROM THIS, THESE WORKSHOPS IS THE DESIRE TO, WELL, COULD WE TREAT THESE LOADS THIS WAY IN THE PLANNING PORTION OF BATCH ZERO AND JUST NOT ALLOW THEM TO COME ONLINE, UH, UNTIL THE SYSTEM CHANGES ARE IN PLACE.

DOING THIS IN A MODULAR FASHION ALLOWS FOR THAT TO BE A POSSIBILITY THAT, YOU KNOW, IF WE, IF WE THINK ABOUT PICKER 1 45 AND SECTION NINE, YOU KNOW, SECTIONS 9.2 TO 9.5 ARE REALLY DEFINING THE PLANNING STUDY PORTION OF WHAT WE'RE DOING.

AND THEN 9.6 DEFINES THE INNER INITIAL ENERGIZATION AND ONGOING OPERATIONS PORTION BY PUTTING LANGUAGE IN 9.6 IN A, YOU KNOW, SEPARATE SECTION OF 9.6.

WE CAN POTENTIALLY LEAVE THAT GRAY BOX UNTIL THE SYSTEM CHANGES ARE THERE.

SO IT MAY ALLOW FOR THIS TO BE INCLUDED IN BATCH ZERO AS A STUDY, YOU KNOW, PART OF THE PLANNING STUDY AND STILL HOLD OFF ON THESE LOADS COMING ON THE SYSTEM UNTIL THE SYSTEM CHANGES ARE THERE.

SO, UM, YOU KNOW THAT THAT'S THE DIRECTION THAT WE'RE HEADED, BUT PLENTY OF OF OPEN QUESTIONS, UH, STILL TO RESOLVE.

SO, UM, MATT, I'M GONNA KICK IT BACK TO YOU AND, UH, WE'LL START THE QUEUE.

THAT'D BE GREAT.

AND JUST QUICK TIME CHECK.

SO IT'S 20 TILL NOON WE ARE HOPING TO TAKE, SO WE WILL HAVE A LUNCH TODAY.

OBVIOUSLY WE HAVE A LOT MORE TO COVER, BUT WE'LL SEE HOW MUCH

[02:10:01]

OF THIS WE CAN GET THROUGH IN TERMS OF QUESTIONS BY 12 OR 1210, UH, TO SEE IF WE CAN WRAP IT UP BEFORE LUNCH.

SO WE'LL START THE QUEUE AT BILL BARNES.

THANKS GUYS.

BILL BARNES, NRG.

REALLY APPRECIATE THE, THE MEAT ON THE BONE HERE THAT ALLOWS US TO KIND OF SEE WHERE THINGS ARE HEADED.

UH, A FEW QUESTIONS BACK ON SLIDE 17.

SO WHEN YOU GUYS PRESENTED THE CLR CONCEPTS BEFORE YOU HAD VERSION ONE A AND VERSION ONE B ONE B HAD WHAT YOU DESCRIBED AS NON SYNCHRONOUS GENERATION THAT'S NOT REGISTERED.

I'M JUST WONDERING WHY THAT CONFIGURATION COULDN'T PARTICIPATE HERE? IT CAN.

I MEAN, DOESN'T, IS NOT INTERESTED IN HOW YOU GIVE THE CLR THING.

OKAY.

UNLESS IT'S, UH, SYNCHRONOUSLY CONNECTED GENERATION.

GREAT.

THANK YOU.

APPRECIATE THAT CLARIFICATION.

I'LL JUST CLARIFY, BILL, I'M SORRY TO INTERRUPT, BUT I, I JUST TO CLARIFY, YOU KNOW, TO ADD TO WHATS SAID IS, UM, I I THINK THE INCLUSION OF ONE A ON TOP OF THIS WAS PROBABLY AN OVERSIGHT.

UM, THE, THE INTENT WAS TO CONDENSE THIS DOWN INTO ONE SLIDE OF, YOU KNOW, WE, WE FELT LIKE THE OTHER CONFIGURATION WAS STARTING TO CREATE CONFUSION WITHIN THE CONVERSATION.

AND SO THE, THE CLR FOR CLARITY IS A LOAD THAT REDUCES ITS CONSUMPTION FROM THE ERCOT SYSTEM BY LEAVING THE SYSTEM EFFECTIVELY.

AND WHAT HAPPENS AFTER THAT IS, YOU KNOW, KIND OF UP TO THE OPERATOR OF THAT LOAD, IF THAT MAKES SENSE.

OKAY.

THANK YOU.

AND THEN SLIDE 21.

SO IN THE DESIGNATION OF INTENT, I'M JUST WONDERING WHY WE COULDN'T DO THAT IN THE INTERMEDIATE AGREEMENT.

WE ALREADY HAVE TO, IN UNDER THE PROPOSED COMMISSION RULE, WHICH I THINK IS IN PICKER 1 45, WE'RE ALREADY TELLING YOU WHETHER WE'RE A CLR OR WE'RE BYOG, IS THERE ANY REASON WHY WE CAN'T COLLAPSE STEP ONE INTO THE INTERMEDIATE AGREEMENT AND JUST DO, DO ALL OF THAT.

WE'LL ADD, ADD ALL THE INFORMATION TO BE SUBMITTED IF WE'RE ACL R.

THAT WAY THERE'S NOT ANOTHER FORM THAT WE HAVE TO FILL OUT.

SO UN UNFORTUNATELY, CHRISTINA HAS LEFT THE ROOM AND SHE'S, I PUNTED THIS QUESTION TO.

OKAY.

UM, SO I WILL BE HAPPY TO TAKE THAT BACK IN AND LOOK IF THAT'S FEASIBLE.

AND WE'RE CERTAINLY NOT , WE ARE ALREADY ANTICIPATING QUITE A BIT OF PAPERWORK COMING IN IN JULY, AND, UH, WE'RE CERTAINLY NOT LOOKING TO MAKE MORE FOR ANYBODY COMPLETELY UNDERSTAND THAT THIS CHRIS O'DONNELL, NICE TO MEET YOU.

PLEASURE.

I'M HERE WITH MY, UH, MY WIFE JUAN.

HEY CHRIS O'DONNELL, IF YOU CAN MUTE YOUR PHONE, WE'LL TRY TO MUTE IT AS QUICKLY AS WE CAN.

THANK YOU.

THANK YOU, CHRIS.

APPRECIATE THAT.

UH, WHICH BY THE WAY, CHRIS, UH, I HAVE MY, UH, MATT MARUS NUMBER ONE FAN MUG SO THAT ANYONE THAT UH, CAUSES DISRUPTIONS TO THE MEETING CAN CONTACT STEVE REY AND GET A MATT NESS NUMBER ONE FAN MUG.

NEXT, UH, SLIDE IS THE, THE, THE CAPPING PROCESS.

I THINK IT'S 24.

YEAH, THERE WE GO.

SO THE, THE GRAY BOX, SO AFTER EACH SCED RUN IS, DO WE THINK THAT'S GONNA HAPPEN IN STEP TWO OR SOME OTHER POST-PROCESS? UH, THIS IS AFTER SC COMPLETES.

OKAY.

THE BASE POINTS, EVERYTHING HAS GONE OUT.

THERE'LL BE A POST PROCESS, I MEAN, TIED TO THE SC PROCESS.

WE WILL LOOK AT ALL THE, UM, CONSTRAINTS THAT ARE BINDING OR VIOLATED THAT ARE ABOVE THE X PERCENT OF THE, THAT CONSTRAINTS MAX SHADOW PRICE.

AND THE CONSTRAINTS WE ARE LOOKING AT IS COMING FROM THE STEP TWO DISPATCH RUN.

SO IF THERE'S A PRICING RUN, WE ARE NOT LOOKING AT THAT.

WE'RE LOOKING AT THE STEP TWO DISPATCH RUN, IT COMES OUT OF THAT AND THE CLR OPERATOR, WE'LL JUST HAVE TO TAKE WHATEVER CAP.

THERE'S NO, LIKE, UM, YOU'RE NOT, LIKE YOU'RE TERING IT BACK TO THE CLR OPERATOR IN ADVANCE.

SO THEY GET A, LIKE A GLIMPSE AT WHAT IT'S GONNA BE OR IT JUST, IT YOU, YOU JUST ACCEPT THE OUTCOMES.

SO IF I KIND OF SEQUENCE THIS AND THIS ONE, NOTHING IS HAPPENING, RIGHT? IT'S IN, WHEN WE DO THE CAPPING, WHICH IS IN THE NEXT SCHEDULE, YOU PASSING IT OVER, WE COULD DO SOMETHING, UM, WE COULD SAY THAT, HEY, YOUR CLR BIDS ARE CAPPED.

UH, BUT IT'LL COME OUT WITH THE RESULTS.

THE OTHER WAY OF DOING IT IS WE ALREADY HAVE A CURTAILMENT FLAG.

WE COULD PURPOSE THAT AND TELL THEM THAT, HEY, YOU'RE BEING CURTAILED, THAT WOULD BE GREAT.

AWESOME.

AND THEN THE WORDS HERE SAYS, ANY, ANY BATCH CLR WITH A HELPING SHIFT FACTOR? YEAH.

NEGATIVE, NEGATIVE SHIFT FACTOR.

OKAY.

THAT'S WHAT HELPING MEANS.

SO WHEN YOU'RE, YOU'RE CAPPING IT, YOU'RE REDUCING THE BID.

MM-HMM .

ANY PART OF THE ENERGY BID CURVE, THIS IS, REMEMBER THIS IS AFTER 1188 IMPLEMENTATION.

SO ANY PART OF THE BID CURVE THAT IS ABOVE THAT VALUE WILL BE

[02:15:01]

KIND OF SET TO THAT VALUE.

OKAY.

THE BIG CAP VALUE.

OKAY.

GOT IT.

AND I THINK YOU'RE LOOKING FOR FEEDBACK ON SLIDE 25.

LAST COMMENT FROM ME SO FAR.

SECOND BULLET, I'M JUST, FROM OUR PERSPECTIVE, IF WE'RE DOING A CLR FOR A LARGE LOAD, IT'S, IT'S THERE TO SERVE THE LARGE LOAD, WE WOULD NOT, THERE WOULD BE NO INTEREST IN SELLING ANCILLARY SERVICES AND THAT MIGHT, YOU'RE PROBABLY GONNA WANT GRID CONNECTED, UH, YOU KNOW, BATTERIES TO PROVIDE ANCILLARIES VERSUS ONES THAT ARE BEING USED TO OPERATE AS A CLR FOR THE PURPOSES OF THE LARGE LOAD.

JUST THAT'S OUR FEEDBACK.

THANKS.

I I JUST WANNA EMPHASIZE AGAIN WHAT S SAID THAT, YOU KNOW, THE, WE A SYNCHRONOUSLY CONNECTED BATTERY IS NOT ELIGIBLE FOR UH, C TO BE PART OF A CLR CONSTRUCT, JUST .

CORRECT.

BUT, BUT I ALSO HEARD YOU CAN OPERATE AS A CLR WITH NON SYNCHRONOUS BATTERIES THAT AREN'T REGISTERED AND POTENTIALLY OPERATE AS A CLR SELLING ANCILLARY SERVICES.

I'M JUST SAYING THE PURPOSE, IF YOU'RE ESSENTIALLY CO-LOCATING NON SYNCHRONIZED GENERATION TO OPERATE AS ACL R, IT'S NOT SELLING ANCILLARIES.

YEAH, THANKS.

AND TO KEEP THE DESIGN SIMPLE, THAT'S WHERE WE'RE HOPING TO KIND OF EXCLUDE, NOT HAVE TO WALK OUT ALL THOSE ISSUES.

SO, ALRIGHT, UH, NEXT IN LINE, UH, IS BROTH.

HEY, ON THAT PRICE CAP, UH, SLIDE, SO LET'S SAY A CLR SIGNED UP FOR 200 MEGAWATTS.

SO THEN EVERY SCHEDULED RUN THEY WOULD GET, UM, SO THERE IS A PRICE CEILING FOR HOW MUCH THEY CAN BE, YOU KNOW, SO WHEN THEY GET A CURTAIL WHEN SIGNAL, THEN IT SETTLES THEM WITH THE AMOUNT OF MEGAWATT THAT IS CURTAILED TO FOR THAT SPECIFIC PRICE.

I'M TRYING TO UNDERSTAND THE MECHANICS ON HOW THIS WORKS.

UM, SO, SO THE SETTLEMENT IS JUST BASED ON THE LMP.

SO WHATEVER THE LMP IS, RIGHT, UH, THEY'LL BE SETTLED AT A NODAL PRICE NUMBER ONE.

SO THAT TAKES CARE OF THE SETTLEMENT PART.

ALL THAT WE ARE DOING HERE IS WHEN WE ARE DOING RUNNING THE OPTIMIZATION FOR THAT PARTICULAR CLR, IT'S BIT TO BUY ENERGY.

UM, LET'S SAY IT'S A FLAT CURB OF $200.

YEAH.

AND LET'S SAY THAT THE CAP, THEY SUBMITTED SOMETHING AT $5,000 PER MEGAWATT, YOU REDUCE THAT FOR ALL THE 200 MEG.

WE'LL REDUCE THAT.

YEAH, I UNDERSTAND THAT.

AND LET THE OPTIMIZATION FIGURE OUT WHAT, WHETHER TO CURTAIL IT, NOT CURTAIL IT OR WHATEVER IT IS.

OKAY.

I GUESS THE SECOND QUESTION I HAVE, UH, ON PARTICIPATION AG IS THAT, SO IF I HAVE, LET'S SAY BASE LOAD AND ALLOCATABLE LOAD, I CAN EXTEND THEM.

SO LET'S SAY I HAVE A RANDOM 500 MEGAWATTS OF BASE LOAD.

NOW I CAN SUBMIT AND ATTEST THAT THE, FOR ME TO HAVE ADDITIONAL 500 MEGAWATTS OF CLR ATTACHED TO THAT BASE LOAD.

I I, I'M GIVING IT FROM A TECHNICAL PERSPECTIVE.

SO LET'S SAY YOUR TOTAL REQUESTED AMOUNT WAS A THOUSAND MEGAWATTS AND THROUGH THIS PROCESS YOU GOT A FIRM, UM, YEAH.

UM, THING OF 500 MEGAWATTS AND YOU WANNA DO ANOTHER 500 MEGAWATTS AS ACL R.

THERE ARE TWO WAYS YOU CAN REGISTER WITH ERCOT, YOU CAN MODEL TWO LOADS.

ONE IS JUST A REGULAR LOAD AT 500.

THE OTHER ONE IS A LOAD THAT'S, IT'S A CLR WHERE IT'S LOW POWER CONSUMPTION IS ZERO AND MAXIMUM POWER CONSUMPTION IS 500.

OR YOU COULD CLUB IT TOGETHER AND SAY THAT THE LPC IS 500, MPC IS A THOUSAND.

SO I GUESS MY QUESTION WAS OTHER WAY AROUND.

SO IF I ALREADY HAVE A BASE LOAD, RIGHT, CAN I FIRE AN EXTENSION APPLICATION? SHOULD I GO THROUGH THE TSP TO GET THAT 500 MEGAWATTS AS A CLR LOAD? YOU KNOW, UM, YEAH, SO IF YOU'RE ASKING, YOU KNOW, IF YOU HAVE A OPERATIONAL SITE THAT ALREADY HAS 500 MEGAWATTS, FOR EXAMPLE, COULD YOU FILE A NEW LARGE LOAD INTERCONNECTION REQUESTS TO ADD ANOTHER 500 MEGAWATTS, UH, AS CLR LOAD WITH EFFECTIVELY A MINIMUM POWER, A LOW POWER CONSUMPTION OF ZERO BASICALLY? YEAH.

UH, THE ANSWER IS YES.

HOWEVER, UH, YOU, THERE IS NOTHING IN OUR FORTHCOMING REVISION REQUEST FOR CLR THAT WOULD MAKE THAT LOAD MORE ELIGIBLE TO BE IN BATCH ZERO THAN A FIRM LOAD REQUEST.

SO IT WOULD NEED TO MEET ALL THE PROPOSED CRITERIA IN PICKER 1 45 TO BE ELIGIBLE TO BE STUDIED IN BATCH ZERO, IF THAT MAKES SENSE.

SO, YEAH.

SO, BUT YES, IT IS POSSIBLE.

OKAY.

SO IF THERE IS A LOAD THAT MEETS

[02:20:02]

BADGE ZERO CRITERIA, FOR EXAMPLE, FOR X MEGAWATTS, NOW CAN I, UH, ADD Y MEGAWATTS AS CLR TO THAT LOAD AND WILL I BE SUBJECTED TO X PLUS Y FOR THE FINANCIAL CRITERIA, EVEN THOUGH THIS IS ACL R? SO I'M GONNA, I'M GONNA PHONE, PHONE A FRIEND HERE.

SO THE, THE FINANCIAL, THE DOLLARS PER MEGAWATT I BELIEVE IS ON THE TOTAL REQUEST.

SO IF YOU INCREASE THE REQUESTED MEGAWATTS, YOU KNOW, TO TRY AND ADD CLR ON TOP OF IT, THAT WOULD ALSO INCREASE THE OBLIGATIONS FOR, UH, UH, FINANCIAL SECURITY THAT FOR INCLUSION BECAUSE WE ARE EVENTUALLY TRYING TO GET FIRM.

SO THAT'S, WELL PROBABLY.

OKAY.

THANK YOU.

ALRIGHT, WE, UH, SO CIRCLE BACK TO BILL BARNES' QUESTION, UH, CHRISTINA'S BACK IN THE ROOM.

THE QUESTION FROM YOU, BILL, WAS COULD THE, UH, ATTESTATION TYPE AGREEMENT FOR CLR OPERATIONS BE INCLUDED IN THE INTERMEDIATE AGREEMENT? CHRISTINA SWITZER, SENIOR REGULATORY COUNSELOR, ERCOT, MY THINKING RIGHT NOW IS THAT THEY WOULD NEED TO BE TWO SEPARATE, UH, ONE, ONE IS AN ATTESTATION RELATED TO THE MEETING, THE INTERMEDIATE AGREEMENT.

THIS WOULD BE A FORM THAT DECLARES INTENT TO BE ACL R, YOU KNOW, THIS, THIS CONCEPT OF PROVISIONAL CLR AND MEET THOSE REQUIREMENTS.

SO I THINK THE ATTESTATIONS, THE, THE ATTESTATION FOR THE INTERMEDIATE AGREEMENT IS DOING SOMETHING DIFFERENT THAN THIS FORM WOULD DO, UM, AS I'M THINKING ABOUT IT RIGHT NOW.

BUT WE CAN, WE CAN THINK, TAKE THAT BACK AND THINK ABOUT MAYBE THERE'S A WAY TO BRING THOSE TWO TOGETHER.

OKAY.

YEAH.

JUST SUGGESTING A WAY TO POSSIBLY STREAMLINE STREAM.

YEAH.

AND IT'S, YOU'RE ALREADY REQUIRED TO DISCLOSE IF YOU'RE GONNA OPERATE A CLR OR BYOG UNDER THE INTERMEDIATE AGREEMENT, BUT YEAH, THERE'S MORE CONTENT YOU PROBABLY HAVE TO POINT TO A DIFFERENT FORM TO FILL OUT, SO.

YEP.

OKAY.

THANKS.

THANK YOU.

VERY GOOD.

ERIC GOFF, UH, ERIC GOFF, UH, THESE QUESTIONS ON BEHALF OF INFINIUM.

UM, SO, UM, INFINIUM, UM, IS INTENDING TO USE THIS PROGRAM AND WANTS TO MAKE SURE THAT THEY'LL BE ABLE TO LATER THIS YEAR.

AND SO IN TERMS OF THE, UM, PARTICULAR EXAMPLES HERE THAT COULD REQUIRE SYSTEM REQUIREMENTS, THEY'VE EXPRESSED A WILLINGNESS TO TAKE ON CONTRACTUAL OBLIGATIONS TO KEEP THEIR BIDS TO BUY BELOW CERTAIN LEVELS UNTIL THE SYSTEM REQUIREMENTS ARE IN PLACE.

I'VE EXPRESSED THAT BEFORE TO SOME OF YOU ALL.

I JUST WANNA EXPRESS IT AGAIN HERE.

UM, IF THE TIMING OF THIS IS, YOU KNOW, THE IMPACT ANALYSIS IS, IS MODEST, WHICH IT IT MIGHT BE, THERE MIGHT NOT BE AN ISSUE TO, TO REQUIRE THAT.

AND SO FOR THAT REASON, WE REALLY WANNA FOCUS ON WHEN ANSWERING YOUR LIST OF QUESTIONS, UH, THE IMPLEMENTATION CAPABILITIES OR IS THERE A PHASE ONE AND PHASE TWO OR ANYTHING LIKE THAT IN ORDER TO HAVE SOME OF THE, THE CAPABILITIES ONLINE SOONER OR ALTERNATIVELY HAVE A MANUAL PROCESS THAT HAS CONTRACT CONTRACTS AROUND IT.

YOU'RE WELCOME TO COMMENT ON THAT IF YOU WANT TO, BUT I, I, I DON'T HAVE AN ANSWER TO THAT AT THIS TIME.

OKAY.

THEN THE SECOND QUESTION, UM, IS IF A LOAD HAS A, IN THEIR, UM, REQUEST, UM, HAS A MCL OF LET'S SAY 50 MEGAWATTS, BUT YOU CAN ONLY SERVE 20 RELIABLY, WOULD YOU REJECT THE LOAD FROM THE BATCH? WOULD YOU, WOULD THEY STILL GET A TRANSMISSION PLAN? UM, YEAH, SO THEY, THEY WOULD NOT, NOT GET REJECTED FROM THE BATCH, BUT THEIR ALLOCATION IN THAT YEAR WOULD BE ZERO UHHUH.

UM, BECAUSE THEY'RE, WHAT THEY'VE INDICATED TO US IS THEIR LOW POWER CONSUMPTION MINIMUM CAN'T BE RELIABLY SERVED.

RIGHT.

AND SO, UH, THAT, YOU KNOW, SO IF, IF FOR EXAMPLE, A LOAD WANTS TO BRING, YOU KNOW, THEY NEED 50 MEGAWATTS IN YEAR ONE AND WE CAN'T DELIVER THAT TILL YEAR THREE, THEN FOR YEARS ONE AND TWO, THE ALLOCATION WOULD BE ZERO.

BUT THEN IN YEAR THREE, UM, THEN THEY, YOU KNOW, THEY COULD HAVE THEIR 50 PLUS WHATEVER THEY WANNA BRING FOR CLR.

SO THAT OKAY.

THAT'S, THAT'S THE APPROACH WE'RE TAKING.

SO AND SO THEN YES, THEY WOULD BE INCLUDED IN THE TRANSMISSION PLAN THAT COMES OUTTA THE BATCH.

CORRECT.

OKAY.

UM, ONE OTHER THING BEFORE WE MOVE ON TO THE NEXT QUESTION, I I, I'M GOING TO WALK BACK JUST SLIGHTLY WHAT I SAID ABOUT NOT BEING READY TO SPEAK ON YOUR FIRST QUESTION.

UM, ONE THING I DO WANT TO EMPHASIZE IS THAT ALL OF THIS IS CONTINGENT ON NPR 1188 AND THE ASSOCIATED SYSTEM CHANGES BEING IMPLEMENTED.

RIGHT.

UM, THERE IS NO PATH FOR THESE LOADS TO ENERGIZE PRIOR TO THAT BEING DONE AS WELL.

SO I AGREE, I JUST WANT TO, IT'S NOT CLEAR FROM THE SLIDES, I JUST WANT TO VERBALLY STATE IT.

YEAH.

AND SO

[02:25:01]

IT'D BE IDEAL AS IF THESE CLR CHANGES COULD BE FINISHED CONCURRENTLY WITH 1188 FROM LIKE AN IMPLEMENTATION PERSPECTIVE.

ALL RIGHT.

NEXT LINE IS SAM BRANDON.

SO FOR THE, UM, FOR THE SCENARIO WHERE A CLR SUBMITS A LCP OF ZERO AND IS IN BATCH ZERO, I JUST WANTED TO CONFIRM THAT THE DELIVERY OF FIRM, UM, TRANSMISSION TO THAT PROJECT IS NOT GONNA BE TREATED ANY DIFFERENTLY THAN ANY OTHER PROJECT IN THAT BATCH.

IS THAT RIGHT? SORRY, I, I JUST WANNA MAKE SURE I UNDERSTAND.

SO WHEN YOU SAY A LOAD COMMISSIONING PLAN OF ZERO, YOU MEAN, OH, SORRY.

NO, I MEANT THE LOW, THE LOW POWER CONSUMPTION POINT IS ZERO.

SO, SO BASICALLY IF I SUBMIT A PROJECT THAT HAS A LPC OF ZERO, THAT'S NOT GOING TO, UM, CHANGE HOW FIRM SERVICE WILL EVENTUALLY BE DELIVERED FOR THAT SITE.

CORRECT.

THE, THE STRUCTURE IS, IS DESIGNED SUCH THAT THE FULL REQUESTED AMOUNT WOULD BE SERVED EVEN IF THE CUSTOMER INDICATES THE ENTIRETY OF IT IS FLEXIBLE, BUT THAT ALSO WOULD, YOU KNOW, COME WITH AN OBLIGATION WHEN IT IS ENERGIZED TO POTENTIALLY BE CURTAILED ALL THE WAY DOWN TO ZERO MEGAWATTS BY.

SURE.

YEAH.

AND I, AND I CERTAINLY, YOU KNOW, IT GOES WITHOUT SAYING THAT THAT THAT IT'LL BE PHYSICALLY FEASIBLE.

UM, IT'S JUST, YOU KNOW, IF YOU'RE CONCERNED ABOUT AVOIDING THIS ISSUE OF YOUR LPC CREATING, UM, YOU KNOW, AN INABILITY TO SERVE YOU IN ONE YEAR, YOU COULD BASICALLY JUST HAVE AN LPC OF ZERO AND THAT WOULD GET YOU THAT SERVICE EARLIER, BUT THEN YOU JUST HAVE TO MANAGE IT UNTIL FIRM SERVICE IS DELIVERED.

YEAH, I WOULD SAY THAT THAT IS TRUE KIND OF REGARDLESS OF, UH, OF WHAT, WHAT YOUR MINIMUM LPC IS, IS DEFINED AS IS MM-HMM .

YOU KNOW, IT'S REALLY THE OBLIGATION FOR THAT FLEXIBLE AMOUNT IS FOR IT TO BE REGISTERED WITH ERCOT AS A CONTROLLABLE LOAD RESOURCE, RESPOND TO DISPATCH AND UH, YOU KNOW, THE, THE OBLIGATIONS THAT GO ALONG WITH THAT REGISTRATION.

YEP.

MAKES SENSE.

THANKS.

ALRIGHT, NEXT UP HARSH AG, COULD YOU TALK ABOUT HOW YOU PLAN TO RESOLVE VOLTAGE VIOLATIONS IF YOU IDENTIFY A VOLTAGE ISSUE AS A RESULT OF THE LOAD? UH, CANNOT MITIGATE THAT.

SO HOW WOULD THAT WORK OUT? I THINK THAT KIND OF GETS ROLLED INTO THAT.

ARE THERE SCENARIOS THAT MIGHT IMPACT THE MAXIMUM POWER CONSUMPTION? UM, I THINK IT ALSO DEPENDS ON IF WE'RE TALKING ABOUT, UH, STEADY STATE OR DYNAMIC, YOU KNOW, VOLTAGE ISSUES, YOU KNOW, POTENTIALLY THERE MAY BE GTCS THAT ARE CREATED AS WELL.

UM, BUT UH, I THINK WE CAN BRING A MORE DETAILED ANSWER THAN THE NON-ANSWER I JUST GAVE RIGHT THERE TO THE NEXT SPEAKER.

NO, UNDERSTAND.

AND I WAS JUST TRYING TO THINK ABOUT, WOULD THE COMMISSIONING PLAN THEN SAY THAT YOU HAVE TO INSTALL THIS, SAY CAPACITOR BANK BEFORE YOU CAN BE A CLR OR NOT, WHATNOT? YEAH, THAT, THAT IS A POSSIBLE, UH, OKAY.

POSSIBLE OUTCOME.

AND THEN THE OTHER QUESTION I HAD WAS, UM, YOU WILL IDENTIFY TRANSMISSION UPGRADES SO THAT THAT LOAD CAN BECOME FIRM EVENTUALLY.

AND AS EACH UPGRADE GETS COMPLETED, WOULD THEN THE LPC GET REVISED? YES.

YEAH.

SO THAT, AND THAT'S, YOU KNOW, YOU MAY REMEMBER FROM THE LAST MEETING WE REVISED THIS GRAPH THAT WAS KIND OF SHOW, YOU KNOW.

OKAY.

IF, IF A UPGRADE COMES IN IN THE LATER YEAR THAT ALLOWS PART OF THE LOAD TO BE CONFIRMED, THAT WOULD, WHAT, WHAT WOULD BE REFLECTED IN THE AGREEMENT? UM, THAT IS SIGNED DURING THE COMMISSION.

THE COMMITMENT PERIOD IS LPC BY YEAR.

AND SO IF THERE'S AN UPGRADE COMING IN THE FUTURE, THEY'RE ALLOW IT TO GO UP, THEN THAT WOULD BE ALLOWED IN THAT YEAR.

OKAY.

THANK YOU.

ALL RIGHT, NEXT UP EVAN NEIL, I HAVE A NEW PLAN.

I HAVE A COUPLE QUESTIONS.

UM, SO THE FIRST ONE, I GUESS IT'S KIND OF RELATED TO WHAT BILL WAS TALKING ABOUT WITH WHERE YOU REGISTER THE PCLR.

AND I GUESS I'M JUST STILL KIND OF CONFUSED, LIKE WHAT ARE WE GAINING BY HAVING THAT REGISTRATION HAPPEN PRIOR TO BATCH? THE, THE MAIN REASON THIS NEEDS TO OCCUR BEFORE THE BATCH IS GONNA BE FOR THE STABILITY STUDIES.

SO, UM, THE WAY WE ARE THINKING ABOUT THE, UM, BATCH ZERO INTERCONNECTION STUDY IS THAT THE LIMITS IDENTIFIED IN THE STUDY STATE WILL INFORM HOW IT IS THE AMOUNT THAT IS STUDIED IN THE STABILITY SCREENING FOR EACH CALENDAR YEAR.

AND SO FOR A CLR IT POTENTIALLY COULD BE APPROVED UP TO THE FULL AMOUNT.

AND SO THAT FULL AMOUNT WILL NEED TO BE REFLECTED IN EACH YEAR OF THE STABILITY STUDY.

SO THAT'S WHY WE NEED TO KNOW THAT DESIGNATION AHEAD OF TIME.

[02:30:03]

OKAY.

I THINK THAT MAKES SENSE, BUT MAYBE, MAYBE I'M NOT FOLLOWING ENTIRELY.

SO I GUESS YOU'RE SAYING THAT YOU'LL GET AN OUTCOME THAT COULD BE WHAT YOU REQUESTED, NOT WHAT YOU'RE LIMITED OUT ON A STEADY STATE THERMAL BASIS, AND THEN YOU WOULD STUDY THAT IN STABILITY.

BUT I GUESS HOW IS THAT CHANGING THE OUTCOME OF THE STABILITY? I MEAN I, YOU'D STILL HAVE THE SAME ASSUMPTIONS AROUND VOLTAGE IN THE AREA.

WOULD YOU NOT LIKE, I GUESS YOU LIKE JUST TAKE A GIGAWATT LOAD FOR EXAMPLE, THAT'S LIMITED TO 500 ON THERMAL, LIKE WOULDN'T IT STILL BE LIMITED TO THE SAME STABILITY AMOUNT REGARDLESS OF WHAT THE STEADY STATE IS? 500 OR A THOUSAND? YOU WOULD STILL JUST KNOCK IT DOWN TO THE 400 AVAILABLE ON A VOLTAGE SIDE.

I CAN MAYBE JUMP IN ON THIS.

SO IN, IN YOUR EXAMPLE, EVAN, UM, IN UH, I'LL SAY NON CLRS, HOW WE WOULD LIKE TO STUDY THAT IN BATCH IS NOT STUDY THE FULL 1000 IN THE STABILITY.

UH, 'CAUSE THAT MAY CREATE A WHOLE BUNCH OF PROBLEMS. AND, AND SO WE WILL STUDY THAT IN STABILITY ANALYSIS AT 500 MEGAWATTS BECAUSE THERM THERMALS LIMITED AT 500.

SO WE WANT TO STUDY THE STABILITY AT 500.

HOWEVER, IF THERE IS A POSSIBILITY THAT THAT LOAD COULD BE A THOUSAND BECAUSE IT'S ACL R, SO SOME, SOME DAYS IT MAY BE A THOUSAND, THEN WE NEED TO IDENTIFY AHEAD OF TIME IF THERE ARE STABILITY CONSTRAINTS THAT COULD DRIVE A NEW GTC BEING ADDED TO THE SYSTEM.

AND SO IF IT IS A CLR INSTABILITY, WE WILL STUDY IT AT THE FULL 1000 SO THAT WE CAN IDENTIFY ARE, ARE THERE POTENTIAL STABILITY CONSTRAINTS FOR WHICH WE NEED TO IMPLEMENT A NEW GTC.

SO THAT GOING INTO THE QSA, WE, WE, WE HAVE THAT PICTURE OF, OH, I I THINK I MIGHT HAVE A STABILITY CONSTRAINT HERE.

THAT IS SUPER HELPFUL AND I THINK IT ACTUALLY HELPED GET TO WHERE I WAS TRYING TO GO.

UM, AND SO JUST TO BE CLEAR, THOSE GTCS THAT COULD BE IDENTIFIED, ARE YOU SAYING THAT WOULD HAPPEN IN THE STABILITY SCREENING OR THAT HAPPENS IN, 'CAUSE I THOUGHT THAT WOULD BE A QSA THING, RIGHT? I I THINK IT, THE, THE, UM, BATCH STUDY WOULD IDENTIFY A POTENTIAL STABILITY CONSTRAINT AND, AND THEN WHEN YOU GET TO THE QSA, YOU ARE IDENTIFYING WHAT, WHAT EXACTLY IS MY GTC? OKAY LI KIND OF SIMILAR TO HOW WE DO GENERATORS TODAY WHERE IT'S GENERATOR INTERCONNECTION STUDY SAYS, HEY, WE, WE HAVE A STABILITY ISSUE HERE THAT, YOU KNOW, YOU NEED TO, UH, PAY ATTENTION TO.

SO WHEN, WHEN WE GET TO THE QSA, THEN THAT, THAT GTC WORK THAT THAT HAPPENS DURING THE QSA.

YEAH, I, I APPRECIATE THAT AND I THINK THAT'S THE RIGHT WAY OF THINKING.

I THINK I WOULD JUST GO BACK TO MY POINT AND WHAT I THINK WE JUST WORKED OUT IS THAT WE'RE NOT GONNA REALLY KNOW WHAT THE RESULT IS UNTIL AFTER BATCH, RIGHT.

AND WE'RE TRUING UP SCREENING OR, UH, STABILITY STUDIES AND WE'RE DOING THE QSA TO IDENTIFY LIMITS AS THAT LOAD IS TRYING TO COME ONLINE WHENEVER IT DOES CHOOSE TO COME ONLINE.

'CAUSE WE'RE NOT GONNA KNOW IF IT DECIDES TO BE A CR IN YEAR ONE OR YEAR TWO OR, OR WHATNOT.

AND SO I GUESS MY, MY POINT IS IS THAT, YOU KNOW, IF, IF THE OUTCOME IS A TRANSMISSION SYSTEM FROM BATCH, I'M STRUGGLING TO UNDERSTAND WHY WE NEED TO BE JUMPING THROUGH ALL THESE HOOPS IN BATCH RATHER THAN TREATING THE CLR PATHWAY AS, ALRIGHT, YOU GOT YOUR FIRM PATHWAY NOW HOW CAN WE GET ONLINE SOONER? WHICH IS GONNA BE SOMETHING THAT IS INHERENTLY LIMITED TO SOMETHING LIKE THE QSA THAT IS STUCK AFTER BATCH.

AND SO I, I AM GUESSING, I'M NOT SAYING THAT WE CAN'T PUT IT IN BATCH OR IN THE FRONT OF IT, I'M JUST STRUGGLING TO FIGURE OUT WHAT WE'RE GAINING BESIDES MORE WORK RIGHT NOW WHEN THE OUTCOME SEEMS TO BE THE, THE SAME.

DOES THAT MAKE SENSE? I THINK IT WHAT, UM, WHAT ERCOT IS GAINING IS THAT IDENTIFICATION OF THOSE STABILITY CONSTRAINTS THAT COULD POTENTIALLY GO IN THAT, THAT NEED TO BE IDENTIFIED IN, UH, THE QSA.

YEAH, I I WOULD ALSO ADD TO THAT, THAT, YOU KNOW, THERE'S BEEN, UM, EXPRESSED DESIRE FROM STAKEHOLDERS IN THIS FORUM, THE, THAT THERE BE SOME VISIBILITY INTO THE ACTUAL ABILITY FOR THAT CLR TO EVER REACH THOSE HIGHER MEGAWATTS.

AND IF THAT'S NOT ASSESSED IN ADDITION TO THE RELIABILITY NEED TO ASSESS IT THERE, THERE'S ALSO NO WAY TO KNOW THAT INFORMATION WITHOUT ASSESSING IT.

SO, UM, YOU KNOW, I PROBABLY SHOULD HAVE ADDED THAT TO MY ISSUES STILL TO BE WORKED OUTSIDE, BUT IS, YOU KNOW, THE LEVEL OF INFORMATION THAT CAN BE COMMUNICATED BACK TO THE CUSTOMER

[02:35:01]

ON, YOU KNOW, THE RESULTS OF THE, UH, UH, ANALYSIS, UH, IN TERMS OF HOW IT WOULD IMPACT THE HIGHER MEGAWATT LEVELS, UM, AS JEFF STATED IN THE LAST WORKSHOP, YOU KNOW, WE'RE NOT GONNA BE ABLE TO DO AN 87 60 TYPE ANALYSIS, BUT THERE IS LIKELY, YOU KNOW, SOME ABILITY, YOU KNOW, MUCH LIKE WITH A GENERATION INTERCONNECTION TO IDENTIFY AT LEAST THE TYPE OF CONSTRAINT THAT IS POTENTIAL TO HOLD DOWN THE CLR.

SO I THINK THERE IS VALUE TO BOTH PARTIES THERE.

SO THIS THANKS, I APPRECIATE THAT.

AND, AND SO I GUESS THE IDEA IS THAT IT HELPS INFORM THE DECISION OF WHETHER OR NOT THEY WANT TO MOVE FORWARD WITH THE FIRM AGREEMENT OR NOT, OR SORRY, THE, THE NON-REFUNDABLE AGREEMENT AND, AND I, I GET THAT ARGUMENT.

I GUESS JUST ONE OTHER THING THAT I'LL POINT OUT THAT I'M A LITTLE CONCERNED ABOUT THINKING ABOUT THIS IS HOW PICKER 1 27 COMES INTO PLAY.

IF WE'RE ADDING A BUNCH OF GENERATION TO THE CASES, YOU KNOW, WE'RE HAVING TO DO THAT FOR THE STABILITY CASES AS WELL AND THAT IS GONNA HAVE A, A SIGNIFICANT IMPACT ON THE OUTCOME OF THOSE CASES.

AND SO TO THE POINT WE WERE TALKING ABOUT JEFF, IS IF WE HAVE TO IDENTIFY LIMITS THERE, WE'RE GONNA BE IDENTIFYING DIFFERENT LIMITS THAN WHAT WE IDENTIFY IN THE QSA, WHICH IS WHAT IS THE ACTUAL, I THINK, THING THAT SHOULD BE BINDING THAT'S GONNA REFLECT OPERATIONS IN, IN REAL TIME.

AND SO I WOULD JUST BE CONCERNED THAT WE WOULD BE SETTING OURSELVES UP FOR A PATH WHERE WE ARE GONNA INTRODUCE NEW RELIABILITY CONSTRAINTS THAT WILL NOT JUST IMPACT THE CLRS THAT ARE TRYING TO CONNECT, BUT IMPACT OTHER LOAD CUSTOMERS AS WELL.

AND I THINK THAT'S, THAT'S AN OUTCOME WE NEED TO BE REALLY CAUTIOUS OF.

UM, SO I'LL DROP THAT TOPIC AND I HAVE JUST ONE OTHER QUESTION, HOPEFULLY IT'S A LITTLE EASIER IS, SO WE'RE GIVING THE CLRS THE OPTION TO NOT BE A CLR ANYMORE.

ONCE THE FIRM TRANSMISSION IS IN PLACE, WILL THEY THEN SWITCH BACK TO A ZONAL PRICE WHEN THAT HAPPENS? I THINK THE ANSWER IS UNDER THE CURRENT, UH, PROTOCOLS.

YES.

HOWEVER, YOU KNOW, I THINK THAT THAT'S ANOTHER AREA THAT PROBABLY BEARS LONGER TERM DISCUSSION.

AGREE.

YEAH.

THE GOAL, THE GOAL HERE IS, IS TO FIGURE OUT HOW THESE LOADS CAN BE ACCOMMODATED IN BATCH ZERO.

OKAY, THANKS.

WELL LET'S DO ONE MORE QUESTION THEN WE'LL TAKE OUR LUNCH BREAK AND, UH, WE'LL HOLD PEOPLE IN THE QUEUE WHERE THAT WE LEFT OFF.

SO LAST QUESTION BEFORE LUNCH, SANDEEP SHARMA? SURE.

UH, THANK YOU MATT SANDEEP, UH, NEXT ERA.

I THINK I GOT A LOT OF ANSWERS TO MY QUESTION FROM THIS CONVERSATION, BUT I JUST WANT TO CONFIRM ON THIS SLIDE.

IF THERE IS NO STABILITY ISSUES ON THE VERY FIRST YEAR, YOUR MPC COULD BE 1100, RIGHT? SORRY, 1000 MEGAWATTS, RIGHT? IF THERE ARE NO STABILITY CONCERN, YEAH, AND I WOULD, I AGAIN EMPHASIZE THAT THE IMPACT OF THE STABILITY ISSUES ON WHAT WOULD WE DON'T, WE HAVE NOT DETERMINED YET HOW THAT'S GOING TO IMPACT IF THERE'S A LIMIT ON THE MAXIMUM POWER CONSUMPTION OR NOT.

OKAY.

OKAY.

AND THEN ON SLIDE NUMBER 20, I THINK IF YOU GO TO SLIDE NUMBER 20, SANDY OVER HERE EVAN, UH, COULD YOU BACK SURE.

JUST TO MAKE SURE, SO THE RAMP THAT YOU'RE SEEING THERE, THE RAMP THAT YOU'RE SEEING THERE IN AN EXAMPLE IS ONE WHERE THAT'S THE CUSTOMER'S DESIRED RAMP.

SO IN YEAR ONE, THE CUSTOMER'S NOT DESIRING THE, THE FULL 1000.

OKAY.

BUT WHAT YOU'RE ASKING IN YOUR CASE, IF IF THEY HAD WANTED THE FULL 1000, WOULD THEY BE ELIGIBLE FOR IT? IS THAT WHAT YOU'RE ASKING? RIGHT.

NO, NO, NO.

SO I THINK WHAT I WAS ASKING WAS, IF AFTER THE BAT STUDY, IF YOUR LPC OR YOUR FIRM SERVICE IS A HUNDRED MEGAWATTS, I'M BASICALLY USING THE DARK BLUE AS WHAT COMES OUTTA THE BAT STUDY, RIGHT? IF THAT IS THE FIRM SERVICE THAT A LOAD CUSTOMER GETS IN THE FIRST YEAR, AND THEN THE SECOND YEAR HE'S GETTING A HUNDRED, NOTHING INCREMENTAL.

THIRD YEAR IT'S JUMPING TO 300 IS THERE, AND IF THERE IS NO STABILITY ISSUES, I UNDERSTAND THE STABILITY ISSUES, UH, CONCERNS AROUND STABILITY ISSUES, CAN THE CUSTOMER ACTUALLY ENERGIZE ALL THE WAY TO 1000 MEGAWATTS IN THE FIRST YEAR PROVIDED 900 MEGAWATT IS COMPLETELY DISPATCHABLE.

I THINK WE'LL HAVE TO TALK ABOUT THAT MORE INTERNALLY.

THE, THE IT THE INTENT IS FOR THE CUSTOMER TO COME WITH THEIR DESIRED RAMP SCHEDULE AND FOR THIS TO BE A PATH FOR MORE OF THAT DESIRED RAMP SCHEDULE TO BE ACCOMMODATED FASTER.

UM, AND SO I I THINK MY SORT OF HIGH LEVEL RESPONSE BACK WOULD BE IF

[02:40:01]

THE CUSTOMER IS DESIRING TO CONNECT A THOUSAND MEGAWATTS IN THE FIRST YEAR, THEN THAT NEEDS TO BE COMMUNICATED IN THE FRONT OF BATCH, UH, THE BATCH STUDY.

IT'S NOT INTENDED TO BE, WELL, YOU FIND YOUR FIRM LOAD AMOUNT AND THEN YOU CAN CONNECT, YOU KNOW, KIND OF AS MUCH AS YOU WANT RIGHT AWAY THERE.

IF THAT'S THE DESIRED RAMP, THEN THAT NEEDS TO STILL BE SUBMITTED ALONG WITH THE, UH, OTHER BATCH LOAD INFORMATION.

OKAY, THANK YOU.

YEAH.

AND SORRY, I FORGOT WE'RE GONNA LOSE AG FOR PART OF THE TIME AFTER LUNCH, SO LET'S JUST KEEP MUSCLING THROUGH, SEE HOW MANY WE CAN GET THROUGH IN THE NEXT 20 MINUTES.

SO, UH, BOB WHITMEYER.

YEAH, SO ONE OF THE THINGS GOING TO THE JUNE BOARD IS NOER 2 82, WHICH REQUIRES VOLTAGE RIDE THROUGH, WHICH EFFECTIVELY REQUIRES BATTERIES AT LARGE LOADS.

ARE WE ASSUMING THOSE ARE NOT SYNCHRONIZED TO THE GRID AND STILL PROVIDING YEAH.

HELP, HELP ME OUTSIDE, UM, FOR PROVIDING VOLTAGE RIGHT THROUGH AND, UM, FREQUENCY, RIGHT THROUGH AND, AND SSO MITIGATION, THEY HAVE TO BE SYNCHRONOUSLY CONNECTED TO THE GRID.

NOW THE QUESTION IS WHAT DO THEY REGISTER WITH ERCOT NOW, AS PER THE CURRENT PROTOCOLS, THEY HAVE TO, IF THERE'S, DEPENDING ON THEIR SIZE AND IF THE TRANSMISSION CONNECTED, THEY HAVE TO REGISTER WITH ERCOT AS AN ESR.

UM, IT, IT, IT'S, IT'S A LITTLE, I DON'T KNOW THE ANSWER THERE YET BECAUSE THEY MAY NOT BE PARTICIPATING IN THE MARKET.

THEIR WHOLE SOLE PURPOSE IS TO, UM, BALANCE OUT THE LOAD AND PROVIDE VOLTAGE SUPPORT.

SO THERE IS A LITTLE BIT OF A GRAY AREA.

UM, SO WE NEED TO HAVE A LITTLE BIT MORE DISCUSSIONS ON THAT, BUT THEY ARE SYNCHRONOUSLY CONNECTED TO THE GRID.

THAT, THAT WAS MY THOUGHT AND THAT WAS WHAT WAS BOTHERING ME ABOUT THE STATEMENT THAT THEY CAN'T HAVE A SYNCHRONOUSLY CONNECTED BATTERY.

I THINK WHAT WE MEAN IS THAT SYNCHRONOUSLY CONNECTED BATTERY CANNOT BE THE PATH FORWARD TO ACL R.

YES.

RIGHT? YES.

BECAUSE WE DO NOT MODEL HYBRID RESOURCES.

AND THE THING IS, WE DON'T KNOW IF THE CLR CAN, IF, IF THAT COMBINATION CAN REALLY PROVIDE THE CLR SERVICE IF THEY DON'T HAVE STATE OF CHARGE BECAUSE CLR DOESN'T REQUIRE STATE OF CHARGE TELEMETRY AND ALL THAT.

SO WE DON'T WANT TO GO THERE.

WE HAVE NEVER DONE THAT.

YEAH, AND, AND I'M NOT TRYING TO, I'M JUST TRYING TO MAKE SURE WE GOT ALL THE BASES COVERED.

THANK YOU.

ALL RIGHT.

UH, BLAKE KING.

HELLO.

YES, BLAKE, GO AHEAD.

UH, IS THERE A MAXIMUM LCP OR MAXIMUM RATIO OF LCP TO MCP CONTEMPLATED IN THIS SORT OF CONCEPT? I BLAKE, I'M, I'M NOT ENTIRELY SURE I UNDERSTAND YOUR QUESTION.

ARE YOU ASKING IF THERE IS SOME, SOME, LIKE SOME PERCENTAGE OF THE LOAD HAS TO BE FLEXIBLE? UH, CORRECT.

UH, I, I DON'T BELIEVE THAT IS CURRENTLY CON CONTEMPLATED.

I THINK IT CAN BE, UM, YOU KNOW, AS, AS MUCH AS A HUNDRED PERCENT LOAD MAY BE FLEXIBLE OR A SMALLER, YOU KNOW, A LARGE PERCENTAGE MUST BE FIRM.

UM, BUT JUST, YOU KNOW, KEEP IN MIND THAT, UM, THE CURRENT, YOU KNOW, WHAT THE DIRECTION WE'RE GOING IS THAT IF THE FIRM AMOUNT CANNOT BE SERVED IN A GIVEN YEAR, THEN IT, YOU KNOW, YOU'VE TOLD US THAT THAT IS THE MINIMUM AMOUNT THAT CAN BE, THAT MUST BE FIRM.

IF THAT CANNOT BE RELIABLY SERVED IN A GIVEN YEAR, THEN IT WILL BE ALLOCATED ZERO MEGAWATTS.

SO, UM, YEP.

YEAH, IT'S JUST SOMETHING TO KEEP IN MIND IN, IN THE CONTEXT OF WHAT I JUST SAID.

GOT IT.

AND, AND SO YEAH, THE THING THAT I'M THINKING ABOUT IS IF THERE'S, IF THERE'S VALUE THAT ACCRUES TO BEING ACL R, BUT YOU ONLY REALLY HAVE TO BE FLEXIBLE FOR ONE MEGAWATT.

IT'S JUST, IT'S AN INTERESTING SORT OF FREE OPTION TO, YOU KNOW, TO ASK FOR FLEXIBLE CAPACITY ABOVE WHAT YOU ALREADY HAVE.

IT'S JUST, IT'S JUST KIND OF AN INTERESTING CONCEPT.

I WANTED TO JUST MAKE SURE I WAS UNDERSTANDING IT CORRECTLY.

THANKS.

ALRIGHT, THANK YOU.

WOW, PEOPLE ARE FALLING OFF FOR THE LUNCH QUEUE HERE.

THANK YOU FOR YIELDING TO LUNCH TO EVERYBODY AND ANYBODY, UH, BILL BARNES, YOU'RE NEXT.

YEAH, THIS IS, IT'S KIND OF SIMILAR TO THE LAST FEW QUESTIONS SANDEEP MENTIONED IS JUST THE, THE CONCEPT OF HAVING A-A-C-L-R WHERE YOU'RE, YOU'RE, YOU DON'T NEED ANY FIRM LOAD.

YOU'RE WILLING TO TAKE ZERO AND YOU COULD FLEX UP, YOU KNOW, OR CONSUME AS MUCH AS POSSIBLE WHEN THERE ARE NO CONSTRAINTS ON THE SYSTEM.

IS THAT AN OPTION? HOW WOULD THAT BE TREATED IN BATCH ZERO? HAS ERCOT CONTEMPLATED A VARIATION OF A CLR WHERE IT'S JUST A HUNDRED PERCENT NON FIRM LOAD? THE, THE

[02:45:01]

ANSWER TO THAT LAST QUESTION BILL, THAT YES, YOU KNOW, I THINK I, HOPEFULLY IT'S CONSISTENT WITH WHAT I GAVE TO SAM A FEW MINUTES AGO, IS THAT IS A POSSIBLE, YOU CAN TELL US THAT THE ENTIRETY OF THE LOAD IS FIRM, UM, BUT THAT ENTIRETY OF THE LOAD CANNOT BE UNDEFINED.

SO, UM, IF THAT MAKES SENSE, LIKE, YOU KNOW, WHATEVER THE TOP OF THAT THAT FLEXIBLE, UH, IS, YOU KNOW, IT CANNOT BE LIMITLESS.

IT NEEDS TO BE DEFINED AHEAD OF BATCH ZERO SO THAT WE CAN ACCURATELY REFLECT THAT IN THE STABILITY STUDIES AS WELL.

THIS FEELS LIKE THERE MAY BE A EXPEDITED PATH FOR THOSE TYPES OF CLRS, BUT I'M JUST THINKING ABOUT THAT.

THANKS.

ALRIGHT, THANK YOU BILL.

ALRIGHT, IT'S WORTH THE BUILD.

THERE'S SOME FUN, FUN IMS GOING AROUND ON THIS STUFF.

OKAY, WE ARE GONNA BREAK FOR LUNCH RIGHT NOW.

AND SO YEAH, 1215 TO ONE 15 WILL BE LUNCH AND WHEN WE COME BACK WE'LL BE TAKING UP AGENDA ITEM FOUR, THE ELIGIBILITY MARCH 4TH DISCUSSION.

SO WE STAND RECESS FOR LUNCH.

THANK Y'ALL.

[4. Deep dive: Eligibility/March 4 Discussion]

ALRIGHT, FOR THOSE OF YOU AT HOME, WE'RE GONNA START WITH AGENDA ITEM FOUR.

UH, AGAIN, WE'LL HIT WITH THE ELIGIBILITY, JUST KINDA THE DEEP DIVE ON THE ELIGIBILITY IN THAT MARCH 4TH TIMELINE.

UH, AFTER THAT WE'LL HIT THE YEAR SIX TRANSMISSION PLANNING OPTIONS AND THEN WE'LL SKIP DOWN TO AGENDA ITEM SEVEN, THE BRING YOUR OWN GENERATION, UM, OPTION.

AND AT THAT POINT WE'LL BE DONE.

SO I'M GUESSING MAYBE AN HOUR EACH OF THESE.

SO WE'LL PROBABLY GO IN, I SAID MAYBE THREE 30, MAYBE IT'S MORE CLOSER TO FOUR, BUT WE'LL SEE HOW IT GOES.

SO I'LL TURN IT OVER TO JEFF AND WE'LL START WITH SLIDE 10.

ALRIGHT.

ALL RIGHT, THANKS MATT.

SO, UM, THIS, THIS TOPIC IN PARTICULAR, WE HEARD IT TODAY, UH, WE, BY FAR THIS HAS BEEN THE TOPIC THAT HAS, UM, LISTED THE MOST NUMBER OF COMMENTS IS THE, THE STUDY VALIDITY AND HOW WE, UH, ARE THINKING ABOUT THAT.

SO I WANTED TO EXPLAIN THAT A LITTLE BIT MORE TODAY ON OUR, OUR THINKING ON THE, THE MARCH 4TH, UM, AND WHY WE PICKED THAT AND REALLY WHAT, WHAT THAT MEANS.

UM, AND AGAIN, OUR MOTIVATION FOR, FOR HAVING A, A RULE LIKE THIS IN PICKER 1 45, IT, IT IS REALLY TO MAKE SURE THAT THE BASE LOAD THAT WE ARE, UH, SETTING IN BATCH ZERO DOES NOT EXCEED THE TRANSMISSION SYSTEM RELIABILITY LIMIT.

SO IT, IT'S REALLY ABOUT MAKING SURE THAT, THAT WE CAN SERVE RELIABLY ALL THE LOAD THAT WE ARE SAYING IS BASE LOAD IN BATCH ZERO.

UM, AND SO, UM, IF WE WERE TO DO SOMETHING LIKE WHAT I THINK STAKEHOLDERS ARE PROPOSING IS THIS OPTION A HERE WHERE IT IS KIND OF AUTOMATIC STUDY VALIDATION FOR ALL, ALL, ALL PREVIOUS STUDIES.

SO WE, WE DEEM THAT THEY ALL THOSE STUDIES, UM, THAT WE'VE APPROVED THAT PRIOR TO BATCH ZERO, THAT THOSE ARE DEEMED VALID.

UM, WHAT THAT CREATES IS A SITUATION WHERE, UM, WE, WE HAVE ESSENTIALLY ALL, ALL THE LOADS IN AN AREA, THIS IS JUST A MA MADE UP EXAMPLE HERE.

UH, ALL, ALL THE LOADS IN IN THIS AREA ARE DEEMED, UM, TO HAVE VALID STUDIES.

UM, BUT WE MAY HAVE AREAS WHERE ALL, ALL OF THE LOADS THAT ARE THEN DEEMED VALID WHERE THE TRANSMISSION SYSTEM CANNOT RELIABLY SERVE ALL OF THOSE LOADS.

SO IF I JUST TAKE, TAKE THIS AS EXAMPLE AND, AND, YOU KNOW, MAKE UP SOME NUMBERS HERE.

SO LET, LET'S SAY THAT I, I HAVE, AND I'LL TAKE THIS LOWER AREA AS AN EXAMPLE, IF I HAVE EACH OF THOSE LOADS ARE SAY 400 MEGAWATTS, UH, BUT THIS AREA CAN ONLY, THE TRANSMISSION SYSTEM CAN ONLY RELIABLY SERVE A THOUSAND MEGAWATTS.

UH, I HAVE NOW DEEMED VALID STUDIES THAT WOULD, UH, HAVE 1200 MEGAWATTS OVER THE THOUSAND MEGAWATTS.

AND, AND HOW WE COULD GET TO THERE IS THAT, UH, ALL, ALL OF THESE, THE, THE STUDIES FOR EACH OF THESE LOADS MAY NOT HAVE INCLUDED THE OTHER LOADS.

SO IF I HAVE A STUDY THAT HAS TWO OF THEM, BUT NOT NOT THE THIRD, THAT STUDY'S GONNA SHOW THAT, YEAH, I CAN RELIABLY SERVE ALL THE LOADS, BUT, BUT IT, IT'S NOT GONNA SHOW ALL THREE OF THOSE LOADS.

AND SO WE DON'T REALLY KNOW IF WE CAN RELIABLY SERVE ALL OF THOSE LOADS.

AND, AND SO THAT'S HOW WE GOT INTO THAT, THAT'S HOW WE COULD GET INTO THAT SITUATION.

AND SO WHAT OUR PROPOSAL IS, UH, SO WE HAVE A PROCESS TO CATCH THIS IN THE EXISTING LLIS PROCESS, BUT I I, IF WE HAVE A KIND OF A FLOOD OF LOADS THAT COME IN BETWEEN NOW AND THAT, THAT JULY 10TH CUTOFF DATE, THEN, THEN WE COULD GET INTO THAT SITUATION.

SO OUR, OUR PROPOSAL IS ANYTHING THAT IS BEFORE MARCH 4TH IS GETS THAT AUTOMATIC STUDY VALIDATION.

[02:50:01]

UH, BUT WE ARE NOT, UH, NOT GOING TO AUTOMATICALLY, BUT WE STILL WILL LOOK AT STUDIES, UH, THAT COME IN BETWEEN MARCH 4TH AND, AND JULY 10TH.

AND, AND SO THERE MAY BE SOME OF THESE LOADS THAT WE LOOK AT AND WE SAY, WELL, I CAN ONLY SERVE A THOUSAND MEGAWATTS IN THIS AREA AND I ALREADY HAVE TWO THAT CAME IN BEFORE MARCH 4TH THAT ARE EIGHT 800 TOTAL.

AND, AND SO I NEED TO RE-LOOK AT THIS, THIS LOAD HERE THAT, THAT CAME IN AFTER THAT DATE.

AND SO MAYBE THAT LOAD DOESN'T GET THEIR FULL ALLOCATION IN BATCH ZERO.

UH, SO AGAIN, IT IS REALLY ABOUT TRANSMISSION SYSTEM RELIABILITY IS, IS HOW WE'RE THINKING ABOUT THIS.

UM, AND, AND THIS SLIDE KIND OF DE DETAILS KINDA WHAT, WHAT DOES THAT MEAN? WHAT, WHAT, WHAT DOES THAT LOOK LIKE? UM, I'M GONNA GO TO A SLIGHTLY SIMPLIFIED VERSION OF THAT, WHICH IS ANYTHING THAT COMES IN BEFORE MARCH 4TH, THEN WE ARE DEEMING THOSE STUDIES TO BE COMPLETE AND VALID.

SO THEY GET AU THAT AUTOMATIC VALIDATION.

IT ANYTHING THAT COMES IN BETWEEN MARCH 4TH AND JULY 10TH, THOSE STUDIES, WE, WE MAY STILL DEEM THOSE STUDIES AS VALID.

SO IT'S, IT DOESN'T MEAN THAT THEY HAVE, THEY'RE AUTOMATICALLY NOT DEEMED VALID, IT JUST MEANS THAT WE ARE GOING TO DO A CHECK ON THOSE.

UM, AND THEN ANYTHING AFTER JULY 10TH, REALLY WE'RE AT, AT THAT POINT WE'RE NO LONGER ACCEPTING CURRENT THE CURRENT LLIS STUDIES, UH, BECAUSE WE, WE NEED TO CREATE THIS, UH, KIND OF BATCH BATCH, UH, FILTER AND, AND FUNNEL THAT EVERYTHING NEEDS TO GO THROUGH BATCH GOING FORWARD.

AND SO WE'LL NO LONGER AFTER JULY 10TH, UH, IS DRAFTED IN PICK 1 45, WE'LL NO LONGER ACCEPT STUDIES.

AND, AND SO IF YOU'RE NOT IN BATCH ZERO BY, UH, BY THE JULY 10TH, IF YOU DON'T MEET THOSE REQUIREMENTS, THEN YOU NEED TO WAIT FOR BATCH ONE, WHICH WOULD START IN MARCH OF NEXT YEAR.

AND IF YOU DON'T MEET THE REQUIREMENTS BY MARCH OF NEXT YEAR, THEN YOU'RE NOT AT BATCH ONE.

YOU WOULD NEED TO WAIT IN BATCH TWO AND, AND SO ON GOING FORWARD.

UM, AND THEN, UM, WANTED TO ADDRESS SOME OF THE FAQS THAT WE'VE HAD ON THIS, UH, BECAUSE I I DO THINK THAT THERE'S SOME CONFUSION.

SO, SO, YOU KNOW, ONE THING I THINK THAT WE'VE HEARD IS, HEY, IS IS MARCH 4TH A RETROACTIVE CUTOFF DATE IN PGA 1 45 FOR STUDIES? AND THE ANSWER TO THAT IS NO, IT, IT IS NOT A RETROACTIVE CUTOFF DATE.

LOADS CAN STILL QUALIFY TO HAVE THEIR STUDIES DEEMED VALID AFTER MARCH 4TH, UH, BETWEEN MARCH 4TH AND AND JULY 10TH.

UM, BUT THAT WE, BUT WE WILL DO A CHECK TO SEE IF THERE ARE ANY OTHER LOADS THAT HAVE MET THE, UH, THE MET THE STUDIES AND THE PLANNING GUIDE SECTION 9.5 CRITERIA.

WE WILL DO THAT CHECK TO SEE IF THOSE STUDIES ARE VALID, BUT IT'S, UH, QUITE POSSIBLE THAT WE COULD DO THAT CHECK AND WE COULD SAY, NO, THE STUDY IS GOOD.

SO EVEN THOUGH IT CAME IN JUNE 1ST, THIS STUDY IS STILL GOOD BECAUSE THERE AREN'T ANY OTHER LOADS THAT MET THAT CRITERIA.

AND SO YOU COULD HAVE JUNE 1ST STUDIES, YOU COULD HAVE JULY 9TH STUDIES THAT COME IN THAT WOULD STILL BE DEEMED VALID UNDER THIS PROCESS.

AND I WANTED TO MAKE THAT CLEAR.

UM, AND I THINK WE, WE'VE HEARD ALSO THAT THERE'S THIS UNCERTAINTY THAT IF A PROJECT IS MEETING THOSE REQUIREMENTS LATER, THEN, UH, AFTER MARCH 4TH, THEN HOW WOULD THEY KNOW IF THEIR STUDY IS BEEN DEEMED VALID? AND SO WE'VE TAKEN THAT FEEDBACK AND, UH, ARE GOING TO, UM, START PRODUCING A STUDY REPORT.

SO WE, OR, OR A REPORT.

SO WE'VE ALREADY, UM, UH, ALREADY AT, AT ONE POINT, UH, I THINK A COUPLE WEEKS AGO WE PROVIDED TSPS A LIST OF THE, UH, LLI STUDIES AND KIND OF HOW WE SEE THEM, UH, IN, IN THE, UH, WHERE, WHERE THEY'RE AT IN THE CURRENT PROCESS.

UH, WE WILL ADD TO THAT REPORT AND PROVIDE THAT ON A, UM, I, I'LL SAY A PERIODIC BASIS, UH, DON'T WANNA COMMIT TO A FREQUENCY AT THIS POINT, BUT IT, IT'S OUR INTENTION TO UP THE FREQUENCY OF THAT SO THAT WE'RE PROVIDING THAT ON A, ON A REGULAR BASIS, UH, PROVIDING THAT REPORT TO THE INTERCONNECTING TSP SO THAT THEY KNOW, UH, AND THEY CAN COMMUNICATE TO THEIR, THEIR CUSTOMERS WHAT, WHAT THE STATUS IS OF THOSE PROJECTS.

SO IF YOU KNOW THAT, HEY, I CAME IN AFTER MARCH 4TH, UH, YOU KNOW, I I IF I CAME IN MARCH 30TH, IF I CAME IN TODAY, THEN I WILL KNOW IF THAT STUDY IS GOING TO BE CONSIDERED DEEMED VALID OR IF THERE ARE OTHER THINGS THAT, THAT HAVE CHANGED.

AND, AND THEN ANOTHER QUESTION THAT WE'VE GOTTEN QUITE A BIT IS, UH, WILL THE CURRENT LLIS PROCESS WILL THAT CONTINUE FOR PROJECTS THAT DON'T QUALIFY TO BE IN BATCH ZERO? AND THE ANSWER TO THAT IS NO.

SO I, ON JULY 10TH, THAT PICKER ONE 15 PROCESS WILL CEASE TO EXIST AS DRAFTED IN, IN PICKER 1 45 RIGHT NOW.

UM, AND AND SO GOING FORWARD, ALL LLI PROJECTS WILL NEED TO GO THROUGH

[02:55:01]

A BATCH PROCESS, UM, WHETHER THAT'S BATCH ZERO OR A SUBSEQUENT BATCH, IN ORDER TO BE, UH, QUALIFIED TO BE INCLUDED IN, UH, THE LOAD FORECAST IN ORDER TO BE THAT, THAT THEN DRIVES PLANNING IN ORDER, IN ORDER TO BE CONSIDERED IN, IN ANY, UH, LOAD FOR ENERGIZATION FORWARD, YOU'LL NEED TO GO THROUGH THE BATCH PROCESS GOING FORWARD.

UH, SO WITH THAT, LET ME PAUSE AND, AND SEE WHAT QUESTIONS THERE ARE.

ALL RIGHT.

THERE ARE A COUPLE.

SO WE'LL START WITH COLIN XO.

COLIN, IF YOU'RE ONLINE, WE DON'T HEAR YOU YET.

I, ALL RIGHT, COME BACK TO COLIN BROTH.

GO AHEAD.

HEY JEFF, THANK YOU SO MUCH.

SO I GUESS MY QUESTION IS, IN BIGGER ONE 15, YOU'RE ALREADY DOING THIS, THAT'S WHERE THE STUDIES ARE COMING, RIGHT? SO THE NEW DIMENSION IS THE RPG PROJECTS THAT YOU ARE EVALUATING AGAINST? I, YEAH, I, I WOULD SAY THAT'S NOT A, A NEW DIMENSION THAT'S REALLY A LEGACY DIMENSION IS THAT THERE WERE, UM, SO AGAIN, RRPG, UM, HAS AND UM, AND CONTINUES TO BE A PROCESS FOR PROJECT, UH, TRANSMISSION PROJECT, UH, APPROVAL AND ENDORSEMENT.

UM, THERE WAS A LEGACY, UH, ALLOWANCE IN THE, THE INTERIM PROCESS WHERE WE WOULD SAY THAT, THAT THOSE STUDIES COULD BE ACT AS THE STUDIES FOR LARGE LOAD PROJECTS THAT WERE INTERCONNECTING LONGER THAN TWO YEARS.

UM, BUT THAT AS OF FIGURE ONE 15, THAT'S NO LONGER, THAT'S NO LONGER A, A VALID PATHWAY FOR THOSE.

SO ALL, ALL, ALL, ALL THESE PROJECTS NEED TO GO THROUGH THE LLIS PROCESS GOING FORWARD, .

SO I GUESS, BUT WE'RE, YEAH, WE, WE ARE TRYING TO ACKNOWLEDGE, SORRY TO CUT OFF, WE, WE, WE ARE TRYING TO ACKNOWLEDGE THAT, THAT AT ONE POINT THAT WAS A, A, UH, VALID PATHWAY, ALTHOUGH IT NO LONGER IS.

SO I GUESS MY QUESTION IS BEFORE OR ON, OR BEFORE MARCH 4TH, YOU STILL CONSIDERED THESE RPG PROJECTS WHEN YOU APPROVED THEM? YEAH, AND, AND, UM, AND I, A APOLOGY, APOLOGIZE, AGS NOT HERE, BUT I THINK THERE'S SOME, THERE ARE SOME NUANCES TO THAT THAT I THINK PROBABLY NEED AG TO HELP ADDRESS, BUT, UM, BECAUSE HE'S MORE FAMILIAR WITH THE HISTORY ON THAT THAN I AM, UH, UNLESS EVAN, IF YOU KNOW OFF THE TOP OF YOUR HEAD.

BUT, UM, UH, BUT YEAH, I THINK THAT THERE WAS KIND OF THIS, THIS PATH WHERE, UH, FOR PROJECTS THAT WERE ENERGIZING MORE THAN TWO YEARS OUT, THAT THEIR, THE RPG COULD KIND OF COUNT AS, AS THEIR INTERCONNECTION STUDIES.

UM, BUT I THINK THAT THEY'RE, UH, RECOGNIZED WHEN WE DRAFTED PIGGER ONE 15, THAT THERE WERE FLAWS IN, IN THAT PROCESS.

UH, AND SO THAT'S WHY ONE 15 EFFECTIVELY SHUT THE DOOR ON THAT.

BUT, BUT THERE MAY BE SOME THAT ARE KIND OF HANGING OUT THERE THAT WERE, UH, PRE-IMPLEMENTATION OF PGA ONE 15.

UM, AND, AND SO I THINK WE'RE, WE'RE TRYING TO ALLOW FOR SOME ALLOWANCE OF THAT.

I, OKAY.

I THINK THE OTHER QUESTION I HAVE IS WITH REGARDS TO WHEN YOU'RE SEEING MARCH 4TH, IT'S THE EMAIL FROM TSP THAT THIS LOAD HAS MET 9.4 AND 9.5, NOT ACKNOWLEDGEMENT.

IS THAT ACCURATE OR HOW ARE YOU SEEING THIS? YEAH, UM, AND I APOLOGIZE 'CAUSE I NEED AG TO ANSWER THAT SPECIFICALLY, BUT MAYBE WE CAN LOCK THAT.

YEAH, I'LL HOLD OFF AND THEN COME BACK TO THAT IF, IF WE CAN MAKE A NOTE OF THAT.

OKAY.

YEAH, I HAD ANOTHER QUESTION.

I FORGOT I, I'LL COME BACK WHEN AG COMES.

SORRY.

THANKS.

ALRIGHT.

YEAH, WE'LL PARK THAT NOW.

UH, COLIN, WERE YOU ABLE TO GET YOUR AUDIO WORKING? ALRIGHT, WELL, HEARING NONE, WE WILL MOVE ON.

WE'RE GONNA TAKE YOU OUTTA THE QUEUE FOR NOW, BUT YOU CAN ALWAYS TYPE YOUR QUESTION IN AND WE'LL GET TO IT THAT WAY.

ERIC GOFF, YOU'RE NEXT.

SO IN THE NEXT SLIDE, SLIDE 11, UM, IF YOU DON'T MEET THE CRITERIA FOR BATCH ONE, UM, BECAUSE YOU HAVEN'T GOTTEN STUDIES APPROVED YET, BUT THIS, THE PROCESS IS ENDING ON JULY 10TH, DO YOU ENVISION THAT BATCH ONE WILL DO MORE OF THE ACTIVITY TO APPROVE STUDIES THAT WE'RE NOT DOING AT BATCH ZERO? SO I, I THINK BATCH ONE, UM, WILL BE THE STUDY.

LET ME SAY IT THIS WAY.

ALL, ALL LOADS SHOULD BE ELIGIBLE.

THIS IS, AS WE'RE THINKING ABOUT IT NOW, HAVEN'T DRAFTED THAT PICKER YET, UHHUH .

BUT AS WE'RE THINKING ABOUT IT NOW, BATCH ONE IS OPEN TO ANY NEW LARGE LOADS THAT, UM,

[03:00:01]

THAT HAVE NOT GONE THROUGH BATCH ZERO.

SO THEY CAN GO THROUGH THE COMPLETE PROCESS WITHIN BATCH ONE.

YOU CAN GO THROUGH THE, YEAH, SO WHETHER YOU'VE STARTED THE OLD PROCESS OR WHETHER YOU COME IN IN FEBRUARY OF 27, YOU'RE BRAND NEW, NEVER REQUESTED BEFORE.

OKAY.

UH, I MEAN THERE, THERE ARE STILL THINGS THAT THE TSPS WILL NEED TO DO AHEAD OF TIME BECAUSE WE'LL NEED TO KNOW THINGS LIKE POINT OF INTERCONNECTION AND THOSE SORTS OF THINGS.

BUT THE IDEA IS THAT ANYTHING NEW, ANYTHING NOT INCLUDED IN BATCH ZERO IS, WILL BE ELIGIBLE TO BE INCLUDED IN BATCH ONE.

SO THE REASON FOR THAT LAST LINE PROJECT'S NOT INCLUDED IN BATCH ONE IS JUST BECAUSE THEY CHOSE NOT TO BE IN BATCH ONE.

YEAH.

SO I THINK WHAT WE'RE TRYING TO DO IS POINT TO, UH, WE'RE, WE'RE TRYING TO ILLUSTRATE HERE IS THAT THERE IS AN ONGOING BATCH PROCESS AND THERE WILL BE LOADS THAT DON'T QUALIFY TO BE IN BATCH ONE BECAUSE MAYBE THEY DIDN'T MEET THE INTERMEDIATE AGREEMENT REQUIREMENTS AS, AS THEY END UP BEING DEFINED IN 58 41 MAY.

MAYBE THEY, IT'S A NEW IDEA THAT THEY COME UP WITH IN APRIL OF 2027.

IT, IT'S, YOU KNOW, THERE ARE, THIS IS AN ONGOING PROCESS AND SO WE'RE TRYING TO ILLUSTRATE THAT OKAY, THIS, THIS IS AN ONGOING THING.

GREAT, THANK YOU.

ALRIGHT, NEXT UP BLAKE KING.

UH, HELLO? YES, GO AHEAD.

UH, SO IS THE, IS THE SORT OF NOT AUTOMATIC VALIDITY, IT SOUNDS LIKE IT'S JUST PURELY RELATED TO THESE SORT OF RACE CONDITIONS WHERE, WHERE PROJECTS ARE TYING.

SO IT SOUNDS LIKE IT'S, IT'S MORE OF A JUST KIND OF PUTTING, PUTTING INTO LANGUAGE THE TUDY MECHANISM THAT EXISTS TODAY.

IS THAT CORRECT? IS THAT KIND OF HOW I SHOULD, SHOULD THINK ABOUT IT? YEAH, YEAH.

NO, THAT, THAT'S IT.

IT'S EXACTLY THE TU ISSUE THAT WE HAVE TODAY IN THE ONE 15 PROCESS.

UM, I THINK WHAT MAKES IT SLIGHTLY DIFFERENT IS THAT, UM, IN THE ONE 15 PROCESS, ONCE YOU'VE MET 9.5, THEN YOU ARE, UM, NO LONGER, YOU KNOW, SUBJECT TO THAT, THAT, UM, RE STUDY THAT, THAT RE STUDY ISSUE.

I THINK THAT, AND, AND THAT'S FINE HISTORICALLY IF WE HAVE, YOU KNOW, ONE OF THESE COMING IN EVERY FEW WEEKS THAT, THAT IS MEETING THESE REQUIREMENTS.

BUT IF, IF WE GET TO A POINT HERE WHERE WE'RE GETTING MULTIPLE OF THESE EVERY WEEK, THEN IT MAY NOT, WE MAY NOT HAVE TIME TO CATCH ALL OF THOSE.

SO, SO IN OTHER WORDS, THE PROCESS IS TODAY, YOU MEAN NINE FIVE, YOU, THE TSP THEN TELLS ERCOT, THEN WE GO AND LOOK AND SEE WHAT, WHAT OTHER STUDIES ARE IN THE AREA THAT MAY BE IMPACTED.

UH, AND, AND, AND AGAIN, THAT, THAT WORKS FINE IF IT'S HAPPENING, YOU KNOW, ONCE A MONTH OR SO.

BUT IF THAT'S, IF THAT STARTS TO HAPPEN FREQUENTLY, THEN WE MAY NOT BE ABLE TO CATCH ALL OF THOSE.

GOT IT.

SO, SO PUT ANOTHER WAY IT, BEFORE, WHENEVER THERE WAS JUST SORT OF THIS MUST STUDY DESIGNATION, ERCOT WAS IN CONTROL OF WHEN STUDIES MET THAT THRESHOLD, RIGHT? SO ERCOT COULD SORT OF DO THE DILIGENCE BEHIND THE SCENES AND SEE, BUT WITH NINE FIVE IT'S MORE AT THE TSPS DISCRETION ON WHEN THEY SEND YOU THE EMAIL.

IS THAT THE BETTER WAY TO THINK ABOUT IT? I THINK IT'S MORE, UH, SO I THINK THAT THAT'S, UH, THAT IS, UM, TRUE BOTH TODAY AND, AND, UM, AND GOING FORWARD IT WHERE, WHERE IT'S THE NINE FIVE, IT'S WHEN THEY TELL US THAT THAT A PROJECT HAS MET NINE FIVE, I THINK THE DISTINCTION HERE IS THAT THE LEVEL OF ACTIVITY HAS SIGNIFICANTLY RAMPED UP AS WE HAVE TALKED ABOUT THIS, UH, TRANSITIONING TO BATCH ZERO.

AND SO WE HAVE A, A, UM, SIGNIFICANT AMOUNT OF LOADS THAT ARE TRYING TO REACH THAT NINE FIVE MILESTONE AND IT, IT'S NOT AT A PACE WHERE WE CAN KEEP UP WITH, YOU KNOW, LOOKING AT THOSE AND, AND, UM, PROACTIVELY TELLING TSPS THAT, HEY, ANO ANOTHER LOAD HAS MET THIS REQUIREMENT IN THE AREA OF YOUR STUDIES.

AND, AND SO YOU NEED TO, YOU KNOW, THESE OTHER LOADS ARE, ARE NO LONGER, UM, YOU KNOW, THEIR STUDIES ARE NO LONGER VALID.

SO WE HAVE A PROCESS TO THAT TODAY, THAT PROCESS IS NOT DESIGNED TO, UH, UH, KIND OF NO MOVE IT AT THE PACE AT WHICH THINGS ARE MOVING NOW.

GOT IT.

OKAY.

AND IF I'M, IF I CAN BE GREEDY, SORRY TO BELABOR THE POINT, JUST ONE THING I'VE, I'VE HEARD FROM SOME TSPS THAT THEY'RE NOT REALLY SURE IF THE, UH, 2026 R-T-P-R-F-I STUFF THAT'S GOING ON RIGHT NOW, IF THAT'S CONNECTED TO ANY SORT OF PROJECT APPROVAL STATUS, UM, IT ARE THEY CONNECTED.

IT DOESN'T SEEM LIKE THEY ARE DIRECTLY, BUT I WAS WONDERING IF YOU YOU HAD ANY CLARITY ON ON THAT? YEAH, MY, MY VIEW IS THAT THEY ARE NOT CONNECTED, UH, BECAUSE THE, THE CRITERIA FOR THE 2026 RTP IS NOT THE SAME CRITERIA AS LAID OUT IN EITHER PICKER ONE 15 PROCESS OR THE

[03:05:01]

PICKER 1 45 GOING FORWARD.

GOT IT.

THAT'S SUPER HELPFUL.

THANK YOU, JEFF.

ALRIGHT, NEXT ANDRES.

HI EVERYONE, THIS IS ANDRES WITH CYPRESS CREEK.

UM, ON THIS SLIDE, UM, CAN YOU PLEASE CLARIFY, JEFF AT THE BOTTOM, UH, THAT, UH, RED CIRCLE THAT SAYS THE GRID CANNOT RELIABLY SUPPLY ALL THE APPROVED LOADS.

LIKE WHAT EXACTLY DOES THAT MEAN? LIKE, ARE, ARE WE TALKING STEADY STATES STABILITY? LIKE ARE WE LOOKING AT N MINUS ONE BASE CASE VIOLATIONS? YEAH, IT, IT, IT COULD BE ANY OF THOSE CONDITIONS.

OKAY.

SO WITH THAT SAID, UM, AND I'M SORRY FOR BRINGING THIS BACK UP, BUT LIKE IF SOME, I, I UNDERSTAND SOME AREAS MIGHT HAVE STUDIES APPROVED PRIOR TO MARCH 4TH, THEY'RE INCLUDED AS BASE LOAD.

AND THEN I ALSO UNDERSTAND SOME LOADS THAT CAME AFTER MARCH 4TH, BEFORE JULY 10TH.

MIGHT OR NOT, MIGHT NOT BE, UH, VALID, BUT I GUESS THE POINT I'M, I'M TRYING TO MAKE HERE IS IF, IF RAKU CAN USE SCOPE PF, UH, TO DO GENERATION RE-DISPATCH AND KEEP THE MEGAWATTS FIXED FOR ALL LOADS THAT COMMIT, UH, AND SOLVE THE TRANSMISSION VIOLATIONS IN THE REFINEMENTS, UM, AS, AS, AS, AS, AS, AS YOU SAID EARLIER, WHY CAN'T WE USE, UH, SCOPE F IN, IN THIS SITUATION TO KEEP ALL THESE LOADS FIXED AND AND THEN SOLVE THE GRID RELIABILITY ISSUES BY THE DISPATCH? YEAH, YEAH.

SO LET, YEAH, LET ME CLARIFY.

SO, UM, THAT IS A TOOL, BUT THAT TOOL DOES NOT GUARANTEE THAT THERE ISN'T ENOUGH GENERATION TO SOLVE THAT.

SO IF I TAKE LIKE THIS EXAMPLE HERE ON THE LEFT, WE'RE, WE'VE GOT LIKE A RADIAL LINE HERE.

THERE'S NO GENERATION YOU CAN RE-DISPATCH, RIGHT? IT IS JUST, I'VE GOT SIX LOADS THAT ARE HANGING OFF OF THIS RADIO LINE AND, AND SO IF I LET TOO MANY LOADS CONNECT TO THAT RADIAL LINE, THEN MAYBE I CAN'T, THERE'S NO RE-DISPATCH I CAN DO, RIGHT? I'M JUST GONNA OVERLOAD THAT LINE IF I LET TOO MANY CONNECT.

SO, SO YOU KNOW, SU SUPPOSE THAT THESE ARE ALL, ALL SIX OF THESE ARE 100 MEGAWATT LOADS AND THIS IS A 400 MEGAWATT LINE.

IF, IF I LET SIX LOADS CONNECT THERE, THERE'S NO RE-DISPATCH.

I JUST HAVE 600 MEGAWATTS CONNECTED TO A 400 MEGAWATT LINE.

AND SO I'M, I'M JUST GONNA BE OVERLOADED INTO REAL TIME.

I'M JUST GONNA HAVE TO SHED LOAD, I'M, I'M GONNA HAVE TO ROTATE THESE GUYS.

AND, AND SO I, I THINK THAT'S THE, THE DANGER THAT WE'RE TRYING TO KIND OF STAY OUT OF HERE IS, YOU KNOW, I I I DON'T WANT TO ALLOW MORE LOADS IN AS BASE LOAD THAN WHAT I CAN RELIABLY SERVE.

AND, AND SO I HAVE TO MAKE SOME SORT OF JUDGMENT AS TO WHICH LOADS I CAN RELIABLY SERVE.

AND I'M GONNA DO THAT BASED ON, UH, KIND OF WHEN THEY, WHEN THE STUDIES GOT APPROVED THAT, THAT THAT'S THE IDEA.

I SEE.

AND DO YOU SEE LOADS LIKE, UM, AND I'M SORRY YOU'VE EXPLAINED THIS IN, IN, IN, IN OTHER WORKSHOPS, BUT LIKE, ARE LOADS CLOSER TO THE JULY 10TH A BIGGER RISK THAN LOADS ACHIEVING THE, THE, THE STUDIES AND AGREEMENTS CLOSER TO MARCH 4TH? LIKE IS THERE A DIFFERENCE ON THAT? LIKE IF I HAVE A LOAD THAT'S STILL YEAH.

ON, IN IN PENDING STUDIES? YEAH, I, I IT'S MORE RISK.

I, I THINK THAT'S FAIR.

YEAH.

I THINK THE CLOSER YOU ARE TO MORE MARCH 4TH AND THE MORE LIKELY IT IS THAT, THAT YOUR STUDY WOULD DEEM BE DEEMED VALID BE BECAUSE AS YOU KNOW, AGAIN, AS WE GO FORWARD, YOU, YOU'RE GONNA HAVE MORE AND MORE LOADS THAT ARE GONNA MEET THAT, THAT, UM, THAT NINE FIVE CRITERIA AND, AND, AND WE'RE GONNA LOOK AT THOSE FIRST AND THEN THEY WILL DE BE DEEMED VALID AND THEN ANYTHING COMES AFTER THAT, WE'LL HAVE TO CONSIDER THAT LOAD.

GOT IT.

THANK YOU.

APPRECIATE IT.

ALRIGHT, NEXT.

KILLING.

HEY, YES, MY QUESTIONS ARE ON SLIDE 12, MAINLY AROUND BATCH ONE.

SO DOES THAT 3 1 20 27 START DATE, IS THAT FIRM OR IS THAT STILL IN FLUX? IT'S A GOOD QUESTION THAT I WOULD SAY THAT'S DRAFT RIGHT NOW, UH, BE BECAUSE IT'S, UM, UL ULTIMATELY THAT WILL BE DETERMINED BY THE NEXT, UH, FIGURE THAT WILL COME.

UH, BUT I WOULD SAY BASED ON THE DATES OF, UH, HOW THE, THE DATES THAT WE HAVE LAID OUT IN FIGURE 1 45, I I WOULD SAY THAT IS THE TARGET DATE IS MARCH 1ST.

UH, BUT THE, UH, THERE, THERE WILL BE A SUBSEQUENT FIGURE THAT DEFINES WHEN BATCH ONE STARTS AND THAT WOULD BE MORE DEFINITIVE.

SO IT, IT'S SORT OF IN PENCIL AT THIS POINT.

OKAY.

YEAH.

AND THEN I GUESS FOLLOW UP ON, I GUESS RELATED QUESTION FOR BATCH ONE, WILL THE REQUIREMENTS BE THE SAME FOR BATCH ZERO? OR I, I GUESS MY UNDERSTANDING WAS THAT

[03:10:01]

THERE WILL NOT BE A STUDY REQUIREMENT AND THAT THE BATCH ONE WILL BE THE STUDY FOR THESE LARGE LOADS IS, AM I CORRECT IN THAT ASSUMPTION? YEAH, SO, UH, I THINK THE, UM, THE THINKING RIGHT NOW, AGAIN, THIS WILL BE DEFINED IN A SUBSEQUENT FIGURE, BUT, UH, THE THINKING RIGHT NOW IS THAT, UH, TO GET INTO BATCH ONE, THERE WILL NOT NEED TO BE ANY SORT OF PREVIOUS STUDY THAT WAS PERFORMED.

UM, IT, WITH THE ASTERISK THAT WE, WE DO NEED THE TSPS, UH, THEY WILL NEED TO TELL US WHAT THAT POINT OF INTERCONNECTION IS AND TO WHAT WHATEVER STUDIES THAT THEY NEED TO DO THAT WILL, WILL NEED TO BE DONE BUT DON'T, WILL NOT HAVE TO HAVE IT CURRENT THINKING, WHAT WILL NOT HAVE TO HAVE A PREVIOUS STEADY STATES OR STABILITY STUDY OR ANYTHING LIKE THAT TO GET INTO BATCH ONE.

SO, SO BATCH ZERO IS A LITTLE DIFFERENT IN THAT REGARD, BUT BATCH ONE IS YOU COULD, UH, YOU KNOW, THE THEORETICALLY COME IN ON FEBRUARY 28TH WITH, UH, YOU'VE GOT YOUR POI FROM YOUR, UM, YOUR TSP, YOU'VE SIGNED YOUR INTERMEDIATE AGREEMENT.

YOU COULD BE KIND OF BRAND NEW LLI NUMBER AT THAT POINT AND STILL SHOW UP AND BE INCLUDED IN BATCH ONE.

OKAY.

THANK YOU.

ALL RIGHT, NEXT, SAM JUNG, UH, SAM JUNG FROM EP.

UM, SO I, I WOULD ASSUME THAT TOWARDS MAY, JUNE TIMEFRAME, YOUR, UM, ERCOT IS GONNA HAVE A LOT OF STUDIES SUBMITTED TO, UH, BE REVIEWED BY ERCOT.

UM, DOES ERCOT HAVE CONFIDENCE THAT THESE STUDIES WILL BE, YOU KNOW, REVIEWED, YOU KNOW, BEFORE JULY, JULY 10TH TIMEFRAME? OR SHOULD YOU KNOW, I GUESS TSPS AND THE LOAD DEVELOPERS SUBMIT THEIR STUDIES BEFORE JULY 10TH AND THEN JUST HOPE THAT ERCOT HAS TIME TO REVIEW THEM ALL? YEAH, SO WE'RE, WE ARE, UM, WE'RE BRINGING ON ADDITIONAL RESOURCES TO BE ABLE TO, UH, REVIEW ALL THOSE STUDIES.

SO WE ARE ANTICIPATING, AS, AS YOU'RE SAYING THAT, THAT WE WILL GET, UM, A A LOT OF STUDIES THAT ARE COMING IN, UM, AND, AND SO WE, WE ARE BRINGING EXTRA RESOURCES ONLINE, UM, TO HELP US WITH THAT.

OKAY.

BUT THERE'S NO LIKE, SAY CUTOFF DATE ON WHEN THE STUDY SHOULD BE SUBMITTED TO HAVE LIKE A PROPER TIME FOR REVIEW NEXT MAYBE COMMENTS BACK AND FORTH? YEAH, THE, THE, THERE'S NOT, WE, WE DIDN'T WANT TO, UM, PRESUPPOSE THAT.

UH, SO WE, I MEAN, THERE MAY BE STUDIES THAT DO GET SUBMITTED IF STUDIES SUBMITTED ON JULY 9TH.

IT'S, UM, THERE'S LOW LIKELIHOOD THAT WE'LL BE ABLE TO REVIEW THAT.

UM, BUT UH, BUT WE DID NOT WANT TO PRESUPPOSE A, A CUTOFF DATE ON THAT.

ALL RIGHT.

THANK