[00:00:05]
THIS IS SUZIE CLIFTON WITH ERCOT.
IF YOU'RE ON THE WEBEX, COULD YOU CONFIRM? YOU CAN HEAR ME OKAY.
ALL RIGHT, WE'RE GONNA GO AHEAD AND GET STARTED IN THE ROOM.
UH, IF I COULD PLEASE ASK ALL OF YOU IN THE ROOM STANDING AROUND TALKING, WOULD YOU PLEASE TAKE YOUR SEATS? THANK YOU.
WE'RE TRYING TO GET STARTED AND THERE'S JUST A LOT OF CROSSTALK.
SO, UM, VERY QUICKLY, WHILE EVERYBODY'S TAKING THEIR SEATS, I'M GONNA GO THROUGH THE MEETING REMINDERS.
IF YOU ARE HERE TODAY AND IN THE MEETING ROOM AND A VOTING REPRESENTATIVE, YOU CAN HOLD YOUR CARD UP AND ELIZABETH MORALES IS OVER HERE IN THE CORNER OF THE ROOM.
SHE WILL ENTER YOU INTO THE CHAT, UM, OR YOU CAN ENTER YOURSELF IF YOU'RE IN THE MEETING ROOM.
OBVIOUSLY, IF YOU'RE ON THE WEBEX, YOU WILL NEED TO ENTER YOURSELF.
AND WE DO ASK THAT EVERYONE WAIT FOR THE CHAIR TO RECOGNIZE YOU BEFORE YOU BEGIN SPEAKING.
AND THEN IF YOU'RE A VOTING TAX REPRESENTATIVE.
AND ON THE WEBEX, AS WE APPROACH YOUR SEGMENT, PLEASE MAKE SURE YOU UNMUTE YOURSELF.
AND THEN AFTER YOU CAST YOUR VOTE, PLEASE RETURN TO THE MUTE FUNCTION.
UH, IF YOU'RE HERE TODAY, PLEASE MAKE SURE YOU COMPLETE THE SIGN IN SHEET OUTSIDE THIS MEETING ROOM SO WE CAN CAPTURE YOU FOR THE MEETING MINUTES AS BEING HERE ACTUALLY IN PERSON.
IF THE WEBEX ENDS FOR ANY REASON, GIVE US JUST A FEW MOMENTS TO RESTART THE WEBEX.
YOU SHOULD BE ABLE TO LOG IN WITH THE SAME MEETING DETAILS, AND IF THERE'S AN ISSUE WITH THAT WEBEX, WE WILL SEND SOMETHING TO THE TACT LIST SERVE.
AND WITH THAT, CAITLIN, WE DO HAVE A QUO AND READY TO BEGIN.
UH, IF WE COULD PLEASE ASK EVERYBODY IN THE MEETING ROOM TO MAKE SURE YOUR MIC IS MUTED.
THIS IS OUR, UH, REGULARLY SCHEDULED SORT OF TA MAY TECH MEETING.
[1. Antitrust Admonition]
UH, LET'S GO AHEAD AND DO THE ANTITRUST.TO AVOID RAISING CONCERNS ABOUT ANTITRUST LIABILITY.
PARTICIPANTS IN ERCOT ACTIVITIES SHOULD REFRAIN FROM PROPOSING ANY ACTIONARY MEASURE THAT WOULD EXCEED ER CO'S AUTHORITY UNDER FEDERAL OR STATE LAW.
AND THERE'S MORE INFORMATION ON THE WEBSITE ALT REPS AND PROXIES TODAY.
UM, IN THE CONSUMER SEGMENT IN THE RESIDENT FOR RESIDENTIAL, CONSUMER WILL HAS AT THE, AT OPEC HAS ALT REP SARAH KEMP, UM, AND THE COMMERCIAL CONSUMER.
NICK BECK IS GIVING HIS PROXY TO MARK DREYFUS AT 1:00 PM IN THE COOPERATIVE SEGMENT.
MIKE WISE FROM GOLDEN SPREAD HAS ALT REP JOE DAN WILSON, AND THE INDEPENDENT POWER MARKETER SEGMENT.
UM, SMIA AT SHELL HAS ALT REP SHANE THOMAS IN THE IRE SEGMENT.
JAY HARPO AT APG AND E HAS GIVEN HIS PROXY TO BILL BARNES IN THE IOU SEGMENT, EBY, JOHN HAS ALT REP DAVID BLANKENSHIP.
AND IN THE MUNICIPAL SEGMENT, DAVID KEY HAS ALT REP DIANA COLEMAN FOR CPS.
I THINK I'M GOING TO GO THROUGH THIS TWICE.
UM, SO WE ARE GOING TO TAKE THE RPG PROJECTS AT THE BEGINNING OF THE AGENDA TODAY.
WE HAVE A TWO HOUR WINDOW SCHEDULED.
UM, HOPEFULLY IT WILL NOT TAKE TWO HOURS, BUT THIS IS MOSTLY SO WE COULD MAKE SURE OUR SUBJECT MATTER EXPERTS FROM EACH TSP COULD BE HERE.
SO, UM, YOU KNOW, WE CAN TAKE UP TO TWO HOURS.
HOPEFULLY WE WILL NOT, MAYBE WE'LL TAKE LONGER, BUT WE WILL SEE.
WE WILL TAKE THOSE RPG PROJECTS UP IN ORDER AFTER THAT.
I THINK IT'LL BE PROBABLY A GOOD TIME FOR A FIVE TO 10 MINUTE BREAK.
UM, AND THEN WE'LL CONTINUE ON WITH OUR AGENDA AS IT'S LAID OUT ON THE WEBSITE.
ONE SWITCH, WE WILL TAKE UP THE A DR PILOT BEFORE THE COMBO BI COMBO BALLOT BECAUSE THERE IS A VOTING ITEM ON THAT.
UM, IDEALLY WE GET THROUGH ALL VOTING ITEMS BEFORE LUNCH.
WE COME BACK FROM LUNCH, RUN THROUGH THE ERCOT REPORTS, AND ARE READY TO START BATCH REVISION REQUEST, UH, BY TWO.
I WOULD LIKE TO GET THROUGH THE COMMENTS FILE TODAY FOR THE BATCH REVISION REQUESTS.
IF WE'RE READY TO TAKE A VOTE, THEN GREAT.
IF WE WANT TO GO HOME, PET DOGS, DRINK WINE, WHATEVER, AND COME BACK TOMORROW.
ALSO, MY EXPECTATION IS THAT WE PROBABLY WILL HAVE TOMORROW, BUT THAT WE WILL FINISH BEFORE LUNCH.
SO I'LL REPEAT MYSELF JUST SO EVERYBODY'S CLEAR.
OUR RPG PROJECTS FIRST AGENDA IS PLANNED.
THE ONE SWITCH IS A, A SMALL SWITCH, A DR PILOT BEFORE THE COMBO BALLOT.
SO WE HAVE VOTING ITEMS TAKEN UP.
[00:05:01]
DEFINITELY AFTER LUNCH, PROBABLY BETWEEN ONE AND TWO.TRY TO GET THROUGH ALL THE COMMENTS FILED TODAY.
DEFINITELY WRAP UP BY LUNCH TOMORROW.
UH, THEME OF THE MONTH IS STILL CLOSURE.
AND, UH, THE RICHARD ROSS THEME OF THE MONTH THAT WE DIDN'T ADD LAST MONTH OR LAST WEEK WAS CROSSING THE RUBICON.
YOU KNOW, ONCE YOU CROSS THAT RIVER, YOU CAN'T GO BACK.
I'M SURE PEOPLE ARE MORE EDUCATED THAN I AM, BUT FEEL FREE TO USE EITHER BOTH JULIUS CAESAR, NAPOLEON.
I LOOKED IT UP AND IT WENT BYE BYE.
SO I TOLD NED LAST NIGHT THAT I HAVE A REALLY GOOD MEMORY, BUT, UH, I, I USED TO BEFORE I HAD A CHILD, SO, ALL RIGHT, LET'S MOVE ON WITH OUR AGENDA.
UM, IF THERE ARE NO OTHER QUESTIONS, COMMENTS ABOUT AGENDA, ORDER OR QUOTES THAT I AM GETTING WRONG, ALL RIGHT.
[2. Approval of TAC Meeting Minutes (Vote)]
FIRST ARE MINUTES.UM, APRIL MINUTES ARE NOT READY FOR VOTE.
WE'RE GONNA POSTPONE THOSE TO JULY AND JULY.
WE'LL HAVE THREE SETS OF MINUTES.
UH, SO WE'LL HAVE APRIL 29TH, MAY 13TH, AND TODAY, TOMORROW.
SO THAT WILL BE A LOT OF WORK FOR SUSIE AND NED TO READ OVERNIGHT JULY 28TH.
UM, NOW WE'RE ONTO OUR MEETING UPDATES.
PROVIDE AN UPDATE ON, UH, BOARD AND PUC OPEN MEETINGS.
[3. Meeting Updates]
HAD ANY ERUPT BOARD MEETINGS.WE HAVEN'T HAD ANY PUC MEETINGS WHERE REVISION REQUESTS ARE, HAVE BEEN TAKEN UP.
I BELIEVE THE APRIL ERUPT BOARD REVISION REQUESTS WILL BE TAKEN UP AT THE, THE END OF THE MONTH OF THE PC OPEN MEETING.
IKA, IS THERE ANYTHING YOU'D LIKE TO ADD FOR US? YEAH, I HAVE ONE QUICK UPDATE.
WE JUST FILED A REQUESTING COMMENTS IN PROJECT 5 9 7 7 2 REGARDING T'S LOAD FORECAST ADJUSTMENT PROCESS.
AND THE COMMENTS ARE DUE JUNE 1ST AND COMMISSION WILL CONSIDER IT AT THE JUNE 18 OPEN MEETING.
WE ALSO FILED ANOTHER MEMO REQUESTING COMMENTS IN 5 5 9 9 9, UH, ASKING FOR COMMENTS OR CUTS TO GOOD CAUSE, EXCEPTIONS FOR THE TRANSMISSION PLAN AND CDR.
PLEASE FILE COMMENTS, BUT MAKE SURE PLEASE, THEY'RE NOT EXTREMELY LONG.
WE DON'T HAVE A LIMIT, BUT, UH, YEAH, THE DEADLINE IS AGAIN, JUNE 1ST.
THAT'S ALL I, OKAY, THANK YOU.
ANY QUESTIONS OR COMMENTS FOR IKA? ALL RIGHT.
[4. Review of Revision Request Summary/ERCOT Market Impact Statement/Opinions]
NEXT, WE'RE ON TO ANN WITH OUR REVIEW OF REVISION REQUEST SUMMARIES OR CROP MARKET IMPACT STATEMENTS AND OPINIONS.WHAT'S UP, BILL? UH, QUESTION ON THE LOAD FORECAST ADJUSTMENT.
UH, IT LOOKS LIKE THE TIMING, UH, IS GONNA BE PUSHED OUT TO MAYBE AUGUST FOR A FINAL DECISION ON WHAT THE ADJUSTMENTS WOULD LOOK LIKE.
I ASSUME THAT IS GONNA ALSO PUSH BACK THE RELIABILITY ASSESSMENT.
THAT'S WHY WE ARE WAITING COMMISSION TO DECIDE ON THE LOAD FORECAST AFTER THAT STAFF WILL FIRE REVISED TIMELINE FOR THE RELIABILITY STANDARD.
ANY OTHER QUESTIONS? I'M LOOKING AROUND THE ROOM THIS TIME.
NOW WE CAN GO TO ANN WITH OUR REVIEW OF REVISION REQUEST SUMMARIES OR CUT MARKET IMPACT STATEMENTS AND OPINIONS.
UM, WE HAVE SEVEN REVISION REQUESTS FOR T CONSIDERATION THIS MONTH.
UM, FIVE OF THEM ARE IN THAT GENERAL SYSTEM PROCESS IMPROVEMENTS, AND THEN TWO ARE IN STRATEGIC PLAN.
OBJECTIVE ONE, UM, IMPACTS TO NOTE ARE JUST PGR 1 45, HAVING THAT 300 TO 400 K BUDGETARY IMPACT AND THEN THE 3.6 TO 4.5 MILLION ANNUAL RECURRING O AND M.
UM, ERCOT IS IN SUPPORT OF ALL OF THE REVISION REQUESTS AND HAS PROVIDED POSITIVE MARKET IMPACT STATEMENTS.
THE IMM HAS NO OPINION ON ANY OF THE REVISION REQUESTS BEING CONSIDERED TODAY.
AND THE NPRS HAVE NO CREDIT IMPLICATIONS.
ANYTHING FOR ANNE? ALL RIGHT, LET'S MOVE.
I JUST POINT OUT WE'RE NOT PROJECTING THIS SCREEN ON THE, ON THE VIDEO BROADCAST.
WE'VE GOT THE ROOM, BUT NOT THE SCREEN.
WE HAVE THE ROOM ON THE WEBEX, BUT NOT THE, OR ON THE SWAG.
[00:10:05]
WELL, ARE WE TALKING ABOUT TWO DIFFERENT THINGS, BOB? BECAUSE YOU'RE TALKING ABOUT THE ROOM.ARE YOU TALKING ABOUT THE SWAG, THE SLIDE THAT'S NOT SHOWING ON THE BROADCAST? ON THE, THE SWAG.
AND YOU GUYS ARE ON THE WEBEX? YEAH.
'CAUSE THEY HAVE THE, THE ROOM.
IS THERE A SWAG BROADCAST ISSUE WE NEED TO RESOLVE? UM, GIMME JUST A FEW MINUTES TO FIND HIM.
CAN WE MOVE, CAN WE KEEP GOING? YES.
UM, BECAUSE THE, THE WEBEX IS WORKING THE SCREEN ON THE SWAG, IT'S NOT WORKING.
[5. Regional Planning Group (RPG) Projects (Possible Vote)]
GO TO RPG.UM, SO EVEN IF WE DECIDE TO PUT A PROJECT ON THE COMBO BALLOT, LET'S PAUSE AFTER EACH PROJECT AND DECIDE WHAT TO DO.
UM, SO LET'S GO TO BU AND WE WILL TAKE THESE UP IN ORDER.
SO LET'S GO TO THE FIRST PROJECT.
COULD Y'ALL CHECK YOUR MICS, PLEASE? MAKE SURE YOUR MICS ARE ALL MUTED EXCEPT FOR THE FRONT MORNING EVERYONE.
UM, I HAVE FIVE RPG PROJECTS TO GO THROUGH THIS MORNING AND TRY TO GET YOUR COMMENTS AND FEEDBACKS AND POTENTIAL, UH, ENDORSEMENT TO THE BOARD.
UM, I'LL START WITH THE FIRST PROJECT.
THAT'S THE CPS ENERGY COMBINED REACTIVE PLANNING PROJECT.
AND THE LOTUS 3 45 1 38 KV SWITCHING STATION AND AUTO TRANSFORMER EDITION TO THE EAST SIDE SWITCHING STATION PROJECTS.
THAT'S, THAT'S QUITE A HANDFUL.
OKAY, SO THIS IS A PROJECT SUBMITTED BY, UH, CPS.
UH, THIS WAS SUBMITTED, UH, FOR RPG REVIEW IN MAY OF 2025.
THE PRIMARY PURPOSE OF THIS RPG PROJECT IS TO ADDRESS, UH, ISSUES IN THE CPS AREA, PRIMARILY VOLTAGE AND THERMAL ISSUES.
UM, THIS IS A PROJECT SUBMITTED IN TWO PROJECTS.
C PS ACTUALLY SUBMITTED TWO TIER ONE PROJECTS LISTED HERE.
UM, THE ESTIMATED COST OF THE FIRST PROJECT IS $116.5 MILLION.
THE SECOND ONE IS $110 MILLION.
UM, THIS IS PRIMARILY TO ADDRESS THE RELIABILITY ISSUES IN THE BEAR COUNTY.
UM, ERCOT DECIDED TO CONDUCT A SINGLE INDEPENDENT REVIEW CONSIDERING ALL THE RELIABILITY ISSUES IDENTIFIED IN THE AREA.
WE, WE COMBINED THOSE TWO PROJECTS.
SO HERE'S THE OVERVIEW OF THE PROJECT NEED.
UM, BASED ON THE LAB ANALYSIS, WE IDENTIFIED SEVERAL VOLTAGE ISSUES, UH, THERMAL ISSUES ON 1 38, 3 45 KV LINES.
AND IN ADDITION TO THAT, THERE WERE ALSO LIKE, UM, UNSOLVED POWER FLOW CONDITIONS, UM, THROUGH, DUE TO THE, YOU KNOW, REACTIVE ISSUES OR THE VOLTAGE ISSUES IN THE AREA.
TO ADDRESS THESE ISSUES, ERCOT, UM, LOOKED AT FOUR DIFFERENT OPTIONS AMONG THE FOUR OPTIONS.
OPTION THREE A ADDRESSES THE PROJECT NEED, AND IT ALSO ADDRESSES THE ERCOT AND THE NERC CRITERIA IMPROVES THE LONG-TERM LOAD SERVING CAPABILITY.
AND IT WAS, YOU KNOW, THE OPTION THREE A WAS IDENTIFIED AS FEASIBLE, SOMETHING THAT CAN BE CONSTRUCTED TOO.
SO THE TABLE HERE, UH, SIMILAR TO ALL THE OTHER PROJECTS WE'VE DISCUSSED, HIGHLIGHTS THE COMPARISON FOR THE FOUR OPTIONS.
UM, AS YOU COULD SEE, OPTION FOUR, UH, THE ESTIMATED COST IS $477 MILLION.
I'LL GET INTO THE DETAILS A LITTLE BIT.
THE INITIAL COST WAS $238 MILLION.
UM, SO IN ADDITION TO THAT, OF COURSE, UH, THIS ADDRESSES THE LONG-TERM LOAD SERVING CAPABILITY, AND THIS WOULD REQUIRE APPROXIMATELY 14.3 MILES OF, UH, NEW RIGHT OF WAY.
AND THE ESTIMATED IN-SERVICE DATE FOR ALL THESE PROJECTS IS MAY OF 2031.
THE REQUIREMENTS OF THE PROTOCOL, UH, WE ARE REQUIRED TO LOOK AT THE SSO IMPACT SUB SYNCHRONOUS OSCILLATION, AND, UH, WE DID RUN THE STUDIES FOR THIS OPTION THREE A.
WE DID NOT IDENTIFY ANY ADVERSE IMPACT, UH, DUE TO SSO.
[00:15:01]
IN ADDITION TO THAT, WE ARE, AS PART OF THE PROTOCOL REQUIREMENTS, OUR PLANNING DATA REQUIREMENTS 3.1 0.3.UH, WE ARE REQUIRED TO LOOK AT THE SYSTEM CONGESTION AND SENSITIVITY ANALYSIS.
UM, BASED ON THE STUDIES WE PERFORMED FOR SENSITIVE OR CONGESTION ANALYSIS, UH, OPTION THREE EIGHT DID NOT CAUSE ANY ADDITIONAL CONGESTION IN THE STUDY AREA.
UM, ALSO THERE IS SENSITIVITY FOR GENERATION AND LOAD SCALING.
SO WE LOOKED AT POTENTIAL FUTURE GENERATION SENSITIVITIES, REMOVING THOSE, AND WE DID NOT SEE AN IMPACT ON THE PROJECT.
NEED, UH, THE LAST ITEM LOAD SCALING.
WE DID NOT PERFORM A LOAD SCALING BECAUSE WE DON'T, YOU KNOW, SCALE THOSE LOADS IN THE BASE BASE CASE.
IN ADDITION TO THAT, THIS IS A PROJECT DRIVEN BY REACTIVE NEED IN THE AREA.
WE PERFORMED A DYNAMIC STABILITY ANALYSIS FOR OPTION THREE A, UM, AND WE DID NOT IDENTIFY ANY, UH, ADVERSE IMPACT OR ADVERSE ISSUES RELATED TO DYNAMIC STABILITY WITH OPTION THREE A.
HERE'S THE OVERALL SUMMARY OF THE PROJECT.
UM, BASICALLY THIS IS TO CONVERT THE LOTUS 1 38 TO A 3 45 KV SUBSTATION AND LOOP AND ADJUST 3 45 KV LINES AND INSTALL A 270 MEGAWATT CAP BANK.
AND ALSO IN INSTALLED TWO STATCOMS TOTALING 600 MEGAWATTS.
UM, IN ADDITION TO THAT, THERE IS 14.3 MILES OF NEW RIGHT OF WAY, UH, APPROXIMATELY 43 MILES OF REBUILT OF 1 38 KV LINES.
SO ERCOT WILL RECOMMEND THE BOARD TO ENDORSE OPTION THREE A TO ADDRESS THE RELIABILITY ISSUES IN BEAR COUNTY AND THE SOUTH CENTRAL WEATHER ZONE.
UH, THE EXPECTED INSERVICE DATE FOR THIS UPGRADE IS OCTOBER, 2031.
UH, THE ESTIMATED COST IS $477.7 MILLION.
AS I SAID, THE INITIAL PROJECT THAT WAS SUBMITTED BY CPS, UH, COMBINED TWO PROJECTS.
UH, THE ESTIMATED COST IS $235 MILLION, BUT THERE WERE ADDITIONAL UPGRADES IDENTIFIED, INCLUDING THE NEED FOR A 3 45 KV LINE AND OTHER UPGRADES, UH, WHICH WAS PRIMARILY IDENTIFIED IN THE ERCOT INDEPENDENT REVIEW, UM, BASED ON RELIABILITY VIOLATIONS UNDER PEAK AND MAINTENANCE CONDITIONS.
UH, AGAIN, THE HIGHLIGHTED ONE IS THE NEED FOR A CCN FOR THE HILL COUNTRY TO HEIM 3 45 KV LINE ON A DOUBLE CIRCUIT STRUCTURE WITH ONE CIRCUIT IN PLACE.
UM, THAT'S APPROXIMATELY 14.3 MILES OF NEW RIGHT OF WAY.
HERE'S THE RECOMMENDATION, THE OVERVIEW OF THE PROJECT.
SO, UM, IT SHOWS ALL THE UPGRADES.
PLUS THE DOTTED, UH, GREEN LINE IS THE 3 45 KB LINE FROM HILL COUNTRY TO HEIM.
I BELIEVE THAT'S THE LAST SLIDE.
SO I'LL PAUSE HERE TO SEE IF THERE ARE ANY QUESTIONS ON THIS PROJECT.
UM, DID WE HAVE ANYONE FROM CPS THAT WANTS TO SPEAK TO THIS OR DO YOU WANNA WAIT FOR QUESTIONS? WE HAVE TWO FOLKS ONLINE AVAILABLE IF THERE'S ANY QUESTIONS.
WE HAVE, UM, MARCUS DE AND DAVID MILNER.
OKAY, SO BEFORE I GO TO QUESTION, CAN I MAKE A COMMENT? SO, OF COURSE, THE, THE FIVE PROJECTS BEFORE WE BROUGHT IT TO TAC WE STARTED THIS, UH, TAC COMMON PERIOD.
SO BASICALLY WHEN WE POSTED THIS PROJECTS, WE OPENED IT FOR A COMMENTS, YOU KNOW, PREPARING FOR THE TAC PRESENTATION.
UM, WE DID NOT RECEIVE SIGNIFICANT COMMENTS, BUT AFTER THE COMMENTS PERIOD, DURING, OKAY, I WAS, I WAS GOING TO SIGNIFICANT QUANTITY OF PROJECTS, WE, WE RECEIVED SIGNIFICANT QUALITY, BETH.
OKAY, LET, LET ME, LET ME REPHRASE.
SO DURING THE COMMENTS PHASE OR THE COMMENTS PERIOD, WE DID NOT RECEIVE SIGNIFICANT COMMENTS, BUT WHEN THE COMMENT PHASE WAS CONCLUDED, WE DID RECEIVE SUBSEQUENT COMMENTS.
SO THAT'S WHY YOU, YOU DIDN'T, YOU DIDN'T HAVE A OPPORTUNITY TO, LIKE, WE DIDN'T HAVE THE OPPORTUNITY TO ADDRESS THOSE COMMENTS.
SO THERE WERE COMMENTS OUTSIDE THE COMMENTS PERIOD WE OPEN.
RIGHT? AND I'M WILLING TO TAKE THOSE COMMENTS NOW AND ANSWER ANY QUESTIONS RELATED TO THAT.
SO I THINK, BETH, YOU'VE SENT SOME AROUND, BUT THEY WERE SORT OF AFTER THE COMMENT PERIOD, WHICH, WHICH IS FINE, BUT YOU KNOW, ERCOT DIDN'T HAVE TIME TO TO POST 'EM.
SO I THINK WE'LL JUST TAKE YOUR COMMENTS.
I I CAN JUST SAY IT OUT LOUD AS PROJECTS COME UP.
UM, I THINK WE HAVE NED IN THE QUEUE FIRST, UNLESS YOU'D LIKE TO YIELD, BUT LET'S GO, LET'S GO TO NED AND THEN BETH.
I WANTED TO CONFIRM BECAUSE I APOLOGIZE I MISSED THE COMMENT PERIOD.
[00:20:01]
REMEMBER WE TALKED ABOUT IT LAST TIME AND I DID NOT SEE THAT COME THROUGH, SO MY APOLOGIES FOR THAT.UM, SO IS THIS, IT LOOKS LIKE THIS IS A PURELY RELIABILITY BASED PROJECT, NOT A, THIS ISN'T DRIVEN BY ANY PARTICULAR LOAD.
UH, CPS SUBMITTED THIS AS A RELIABILITY PROJECT, EXCLUDING THE PROJECTED LOADS, THE LARGE LOADS IN THE AREA.
BUT WHEN WE DID THE INDEPENDENT REVIEW, WE DID ADD THOSE LOADS BASED ON FEEDBACK FROM OTHER TSPS AND PEOPLE WHO PROVIDED THAT FEEDBACK.
AND WAS THAT, I, I NOTICED ON ONE OF THE SLIDES EARLIER IT MENTIONED, UH, IT LOOKED LIKE THERE WAS ABOUT 178 MEGAWATTS OF LOAD ADDED.
IS THAT THE, IS THAT THE AMOUNT TO CONSIDER? YEAH, THAT THAT IS THE LOAD ADDITIONAL LOAD SERVING CAPABILITY.
SO WHAT THAT MEANS IS WHATEVER THE BASE LOAD, WE, WE DID A SENSITIVITY TO SEE HOW MUCH MORE LOAD IT CAN ACCOMMODATE.
SO THAT'S LIKE THE 178 IS THE INCREMENTAL LOAD ON TOP OF WHAT THE BASE LOAD WAS.
SO THIS IS, THIS GIVES YOU A SENSE OF HOW MUCH MORE MARGIN YOU HAVE FOR THE PROJECT.
AND SO AT ABOUT 478 MILLION YOU, YOU'RE ABLE TO SUPPORT 178 MEGAWATTS OF ADDITIONAL LOAD? UM, NO.
THERE, THERE IS, THERE IS BASE LOAD, RIGHT? THE, THE, THE PROJECT PRIMARILY THE A CPS PROJECT WAS NOT BASED ON THE LARGE LOAD.
MY UNDERSTANDING IS IT'S NOT BASED ON IT'S EX, IT'S PROJECTED, YOU KNOW, ISSUES, RELIABILITY, ISSUES WITH THE LOAD GROWTH THEY'RE ANTICIPATING.
SO I'M GONNA PAUSE HERE TO SEE IF CPS WANTS TO ADD ANYTHING MORE.
IS THERE SOMEONE FROM CPS THAT WANTS TO ADD DAVID OR MARCOS? WHAT WAS THE QUESTION? YEAH, UH, THE, LET, LET ME ASK A SPECIFIC QUESTION.
UM, THIS IS BETH GARZA, THE REPRESENTATIVE FOR RESIDENTIAL CONSUMERS.
I THINK THE SPECIFIC QUESTION NED WAS TRYING TO GET AT WAS HOW, HOW MUCH, IF ANY, LARGE LOAD WAS INCLUDED IN WHAT I WOULD DESCRIBE AS THE BASE EVALUATION FOR THIS PROJECT.
YEAH, SO THIS IS DAVID MILNER, CPS ENERGY.
SO THE CPS ENERGY STUDY DIDN'T INCLUDE ANY LARGE LOAD.
THE MAIN PROJECT DRIVER WERE LOCAL GENERATION RETIREMENTS.
AND SO THE, THE LARGE LOADS WERE ADDED SUBSEQUENTLY IN ERCOT ASSESSMENT? YES.
THERE WERE OTHER, I MEAN, IN THE STUDY OR THE NEIGHBORING TO THE STUDY AREA, THERE WERE SOME LARGE LOADS THAT WAS PROPOSED OR THAT WAS, YOU KNOW, INCLUDED IN THIS STUDY BASED ON FEEDBACK FROM SOME TSPS.
AND, BUT THAT'S NOT THE 178 MEGAWATTS.
CAN YOU, CAN YOU GIVE US SOME COLOR ON THE AGGREGATE AMOUNT THAT WAS INCLUDED? I, I DON'T HAVE THE NUMBERS, BUT I THINK MY, YOU KNOW, AS I SAID THIS, THOSE LOADS WERE IN, IN, IN THE STUDY OR OUTSIDE THE STA AREA PRIMARILY.
SO I CAN SEE IF, UM, I CAN HAVE SOMEBODY PULL UP THE NUMBERS.
SO, AND JUST TO BE CLEAR, THE REASON I'M ASKING THIS IS THE SAME, SAME THING I ASKED BACK IN MARCH WHEN WE WERE REVIEWING SOME OF THE PROJECTS THEN IS IT'S REALLY HELPFUL FOR, FOR I THINK TAC MEMBERS TO SEE AND UNDERSTAND, YOU KNOW, HOW SOME OF THESE PROJECTS ARE COMING IN SERVICE ALONG WITH LOADS THAT'LL BE COMING IN.
'CAUSE THAT HELPS US UNDERSTAND HOW THOSE COSTS WILL BE SPREAD OUT.
AND THAT'S, THAT'S REALLY WHAT I'M TRYING TO GET AT.
I, I, I THINK THAT'S A FAIR QUESTION.
SO ANYTIME THAT THE PROJECT IS DRIVEN BY THE NEED IS DRIVEN BY LARGE LOADS, WE TRY TO INCLUDE THAT.
BUT MY UNDERSTANDING IS, I'LL LET ROBERT SPEAK FOR THIS.
THIS IS, YOU KNOW, THE NEED WAS ESTABLISHED BY THE, BY THE RETIREMENTS.
AND BECAUSE WE ARE STUDYING THIS LOAD, YOU KNOW, WE, I MEAN WE ARE, BECAUSE WE ARE STUDYING THIS PROJECT, WE WANTED TO SEE THE IMPACT OF POTENTIAL LOADS IN OR IN OR NEARBY THE STUDY AREA.
SO I'M GONNA PAUSE HERE TO SEE ROBERT HAS SOME COMMENTS.
UH, YES, ROBERT GOLAN ERCOT, SO THE EVALUATION STARTED OFF WITH THE 2024 RTP AS THE SEED CASE FOR THIS EVALUATION.
THERE WAS APPROXIMATELY 1900 MEGAWATTS WORTH OF LOAD ADDITION WITHIN THE BEXAR COUNTY.
THAT WAS BASED ON JUST LOAD GROWTH PROJECTIONS FOR THAT AREA FOR 2030.
ON TOP OF THAT, WHEN WE RECEIVE COMMENTS FROM THE TSPS, WE ADD OVER THREE GIGS OF LOAD OF LARGE LOADS, UM, IN THE LCRA TERRITORIES THAT WAS ABOUT NORTH
[00:25:01]
NORTHEAST OF THE BEXAR COUNTY.SO THEY WERE OUTSIDE OF THE AREA, BUT YOU KNOW, IT WAS APPROPRIATE TO ADD THOSE LOADS INTO THE EVALUATIONS.
WE WEREN'T ADDRESSING ALL THE NEEDS AND, UH, UH, ISSUES AND VIOLATIONS THAT WERE CAUSED BY ALL THAT LOAD NORTH OF BEXAR COUNTY.
UH, BUT WE WERE PRIMARILY FOCUSING ON, YOU KNOW, BEXAR COUNTY ITSELF AND WHAT, WHAT RELIABILITY UPGRADES WERE NEEDED.
HEY, HEY, ROBERT, AS, AS SOMEBODY, AS SOMEBODY WHO TRANSPLANTED TO AUSTIN 40 YEARS AGO, AND IN MY FIRST MONTH DID CALL IT BEARA COUNTY AND WAS CORRECTED.
I ACTUALLY JUST GOT LIKE THREE DIFFERENT IMS AT THE SAME TIME, SO I DO APOLOGIZE.
BEAR COUNTY
UH, THAT'S A BAD, THAT'S A BAD, BAD FOUL.
WE NED DO YOU HAVE MULTIPLE QUESTIONS AS USUAL? THINK THAT ANSWERS? NO, I THINK THAT ANSWERS THE, THE MAIN THING I WAS TRYING TO GET AT IT, THERE'S A RELIABILITY BASIS.
THERE'S THREE GIGAWATTS OF AN INCREMENTAL LARGE LOAD.
THE ONLY OTHER QUESTION I HAVE IS WHETHER THAT LOAD IS POSTED FINANCIAL SECURITY ASSOCIATED WITH THAT.
THAT'S A QUESTION FOR CPS OR ERCOT CPS THAT LOAD.
MY UNDERSTANDING IS THOSE ARE THE LOADS FOR WHICH MAKE IT IN THE RPG PROCESSES, BASED ON OFFICER LETTERS AT THE STATIONS OR THE LOADS THAT'S BEEN SUBMITTED TO EITHER THE 2024 OR 2024 RTP.
AND MOST OF THOSE LOADS ARE LCRA LOADS.
AND IN THE REPORT ITSELF ON THIS PROJECT, WHICH FRANKLY I WOULD SUGGEST THAT NEEDS TO BE PART OF THE TAC MATERIALS GOING FORWARD AS THE ACTUAL REPORT, UM, INCLUDED IN THE REPORT ARE THE LARGE LOAD INTERCONNECTION NUMBERS FOR ALL OF THE LCRA LOADS, NOT THE CPS LOADS.
SO FOR WHATEVER BETH'S DONE BETTER HOMEWORK THAN I HAVE.
UM, MY, STU MY, UH, WELL, CAN I, CAN I ASK NED TO FOLLOW UP? YOU WILL HAVE THE SAME QUESTION FOR EVERY PROJECT.
I THINK IT'S HELPFUL FOR US JUST TO UNDERSTAND, YOU KNOW, THE LOAD THAT'S ASSOCIATED WITH IT, THE TIMING YES.
RELATIVE TO THE IN-SERVICE DATES.
AND THEN IF YOU KNOW THE LOADS OF POSTED FINANCIAL SECURITY, I THINK THAT'S OKAY.
THOSE ARE THE THREE BIG THINGS.
THINGS WE JUST WANNA, AND JUST TO PUT ENCORE ON NOTICE IN MY REVIEW OF THE FIVE PROJECTS WE'RE DEALING WITH TODAY, THAT SPECIFIC QUESTION AND THE TOPIC IS WAY MORE IMPORTANT AND WAY MORE MEANINGFUL FOR THE THREE ENCORE PROJECTS THAT WE'RE GONNA TALK ABOUT.
BETH, LET'S GO TO YOUR QUESTIONS ABOUT THIS PROJECT.
UM, MY QUESTIONS ABOUT THIS PROJECT WERE, UM, WERE MINIMAL, FRANKLY, JUST CONFIRMING THAT, YOU KNOW, FOR THE EXTRA, UM, $243 MILLION IN, IN PROJECT COSTS.
WHAT WE'RE GETTING IS A NEW 14 MILE, 3 45 KV LINE AND REBUILDING 43 MILES OF, UM, OF RELATIVELY OLD TRANSMISSION LINES FOR, UH, MOST EXCEEDING 40 YEARS OLD WITH RATINGS INCREASING BY ROUGHLY 75%.
THAT'S WHAT WE'RE GETTING PRIMARILY FOR THAT INCREASED COST.
THE ISSUE ON THIS, THIS PROJECT SPECIFICALLY, WHICH IS A SIDE ISSUE PET PROJECT THAT I'M, I'M THINKING ABOUT, WE SPEND A, WE ARE SPENDING A LOT MORE IN PROJECTS TO SATISFY THE MAINTENANCE OUTAGE CRITERIA.
AND AT SOME POINT WE NEED TO, WE NEED TO THINK ABOUT WHETHER ALL OF THOSE EXTRA HUNDREDS OF MILLIONS OF DOLLARS ARE WORTH WHAT WE'RE, UH, WHAT WE'RE TRYING TO SATISFY HERE SINCE, UH, SAN ANTONIO WENT TO THE EFFORT TO HAVE THEIR EXPERTS ONLINE.
I'LL ASK MY QUESTION OUT LOUD THAT I SAID I WOULDN'T, TO ERCOT, WHICH WAS HAD TO DO WITH THE, UM, THE LOCATIONS OF THE VARIOUS REACTIVE CAPACITY.
THERE WERE A VARIETY OF ALTERNATIVES CONSIDERED IN THIS PROJECT.
AND THEN WHEN IT CAME DOWN TO IT, THE, THE INITIAL PROPOSAL BY SAN ANTONIO WAS DEEMED TO BE INFEASIBLE.
MY UNDERSTANDING WAS IT WAS DEEMED TO BE INFEASIBLE BECAUSE OF PHYSICAL, UH, LIMITATIONS AT VARIOUS SUBSTATIONS RELATED TO THE ADDITION OF VARIOUS, UM, UH, UH, UH, CAPACITOR ADDITIONS.
I, I, THAT STRUCK ME AS, AS STRANGE AS I WAS READING THE REPORT, THAT THE INITIAL PROPOSED PROJECT WAS THEN SUBSEQUENTLY DEEMED INFEASIBLE.
UM, IF, IF SOMEONE FROM SAN ANTONIO COULD ADDRESS THAT, I'D, I'D LOVE TO HEAR
[00:30:01]
THAT, THAT DESCRIPTION.DAVID MILNER, DO YOU WANNA YEAH, THIS IS DAVID.
UM, I THINK SOME OF THE, THE PRO THE PROJECT WAS DEEMED INFEASIBLE BECAUSE SOME OF THE LOCATIONS, UM, WHERE WE'RE PLANNING TO CITE CAPACITOR BANKS, UM, COULDN'T ACTUALLY ACCOMMODATE A CAP, A CAPACITOR BANK AFTER FURTHER ANALYSIS.
EITHER IT REQUIRED, UM, THE SUBSTATION FOOTPRINT TO BE EXPANDED OR JUST NO SPACE.
AND AND YOU WEREN'T AWARE OF THAT WHEN YOU SUBMITTED THE PROJECT? UH, I THINK THIS WAS, THIS PERTAINS TO, WHOOPS, OR DID THE LOCATIONS MOVE AROUND AS, AS THE PROJECT WAS BEING EVALUATED? HEY, GOOD MORNING.
CAN Y'ALL HEAR ME? IT LOOKS MY COLLEAGUE LOST CONNECTION.
SO YEAH, SO AS THE PROJECT WAS BEING EVALUATED, THE, SOME, THE INITIAL LOCATIONS WERE BASED OFF OF ESSENTIALLY WHAT THE STUDY RESULTS WERE INDICATED IN TERMS OF THE, UH, EFFECTIVENESS OF THE CAPACITORS.
AND SO, UM, YEAH, AS WE HAD, UH, OUR SUBSTATION ENGINEERING DO FURTHER ANALYSIS, UH, YOU KNOW, EITHER THE ACTUAL EXPANSION WAS INFEASIBLE FOR THE LOCATION OR IT WOULD REQUIRE, UH, YOU KNOW, TAKING POTENTIAL FUTURE DISTRIBUTION SPOTS.
SO, UH, OVER THE COURSE OF THAT, THERE WAS SOME ADDITIONAL BACK AND FORTH THAT ENDED UP, UH, RESULTING IN THE, YOU KNOW, CHANGES FOR THE LOCATIONS AND THE OPTION BEING FEASIBLE.
I, I'LL LET MARK MAKE HIS COMMENTS, BUT I, I FOR 1:00 AM AM PREPARED TO ACCEPT THIS AS A COMBO BALLOT ITEM.
UM, MY COMMENT IS, IS SIMILAR TO NED'S IN THAT FOR EACH OF THE, THE FIVE TRANSMISSION PROJECTS TODAY, BUT NOT JUST FOR TODAY, FOR, FOR ALL TRANSMISSION PROJECTS AS WE GO FORWARD AND, AND FOR THE OUTCOME OF THE BATCH STUDY, IT IS VERY IMPORTANT TO ME THAT WE HAVE TRANSPARENCY INTO THE LARGE LOADS THAT WERE, THAT WERE EMBEDDED INTO THESE ANALYSES.
AND THE, THE REASON FOR THAT IS BECAUSE WE ARE ABOUT TO, TO TRANSITION AWAY FROM DESIGN OF THIS, UH, BATCH PROGRAM TO A PERIOD OF COST ALLOCATION AND RATE MAKING.
UM, AND, AND AS WE'VE DISCUSSED FOR FOUR MONTHS IN THIS FORUM, THE LARGE LOADS WILL BE PAYING DIRECT COSTS RELATED TO THE TRANSMISSION EXPANSION THAT IS ASSOCIATED WITH THEIR PROJECTS.
AND, UH, THE COMMISSION POLICY ON THAT IS IN FLUX.
THE, THE COMMISSION DID RELEASE A REALLY NICE WHITE PAPER IN 5 8 4 8 4 ON, UH, TRANSMISSION COST AND THEIR, THEIR THOUGHTS ABOUT BOTH THE FOUR CP CHANGE AND THE DEMAND CHARGE THAT MIGHT BE USED TO COLLECT SOME OF THESE COSTS.
BUT AT SOME POINT THERE IS GOING TO BE A CONTESTED CASE PROCEEDING WHERE THE RUBBER'S GONNA HIT THE ROAD AND WE'RE GONNA FIND OUT WHO'S REALLY PAYING FOR WHAT, AND THEN THERE'S GONNA BE A SERIES OF T CRFS OR OTHER PROCEEDINGS AFTER THAT.
AND SO, UH, MY OBJECTIVE FOR THESE PROJECTS AND FOR PROJECTS GOING FORWARD IS THAT WE HAVE COMPLETE TRANSPARENCY INTO THE LARGE LOADS THAT WERE, UH, PART OF THE BASIS FOR THESE PROJECTS.
OKAY, ANY OTHER QUESTIONS OR COMMENTS ON THIS PROJECT? SO WE'D BE LOOKING TO ENDORSE THE COMBINED, UH, 25 RPG 17 CPS SYNERGY, UM, ARLO SWITCHING STATION AND AUTO TRANSFORMER EDITION AT EAST SIDE SWITCHING STATION PROJECT AND 25 RPG 13 CPS ENERGY, REACTIVE POWER PLANNING PROJECT OPTION THREE A.
CAN WE PUT THAT ON THE COMBO BALLOT? AND, AND LAST WORD, I, I WANNA THANK, SINCE WE'RE STARTING WITH CPS, I'LL THANK THEM FIRST AND OR ERCOT FOR PROVIDING AGE OF FACILITIES THAT ARE BEING REBUILD AS WELL AS RATING INCREASES EXPECTED ON THOSE REBUILD LINES.
I THINK THAT'S IMPORTANT INFORMATION TO BE INCLUDED, TO KNOW WHAT WE'RE GETTING FOR THE MONEY WE'RE SPENDING.
[00:35:01]
THAT, THAT NEW EFFORT, UH, THAT, THAT YOU'RE GOING THROUGH.I, AND THEN A COUPLE OF ANNOUNCEMENTS.
I'M TOLD THE, UH, SWAG IS WORKING NOW.
UM, IT WAS, WE WERE ALWAYS BROADCASTING THE ROOM AND THE AUDIO, BUT THE, THE SLIDES WEREN'T WORKING, BUT I, I BELIEVE THEY WERE WORKING NOW AND THE WEBEX WAS ALWAYS WORKING, SO IT CONTINUES TO WORK.
UM, AND THEN WE MISSED A PROXY, UH, SETH AND THE POWER MARKETER SEGMENT HAS GIVEN HIS PROXY TO IAN HALEY FOR THE MEETING.
SO WE ARE ON TO THE SECOND RPG PROJECT, WHICH IS, UH, ON CORAL CA, LCRA PROJECT.
I THINK WE'LL DO LIKE THE STANDING NED THEN BETH QUESTIONS, AND THEN WE CAN GO TO QUESTIONS AROUND THE ROOM FOR, FOR EACH OF THESE, THESE PROJECTS.
ALRIGHT, LET'S GO BACK TO BU THANK YOU.
THE SECOND PROJECT IS THE ENCORE AND LCRA MUSCOVY TO WAS LAKE 3 44, 1 38 KV PROJECT.
UH, AGAIN, OVERVIEW OF THIS PROJECT.
THIS WAS SUBMITTED BY ENCORE AND LCRA, UH, SUBMITTED THIS MUSCO, IT WAS LAKE PROJECT TO ADDRESS, UH, RELIABILITY NEEDS IN WILLIAMSON AND, UH, MILAM COUNTY.
UM, THIS IS A TIER ONE PROJECT WITH AN INITIAL ESTIMATED COST OF $381.83 MILLION.
AND THIS WOULD REQUIRE CCN BASED ON THE INITIAL SUBMITTAL.
AGAIN, ERCOT PERFORMED THIS ANALYSIS, UH, RELIABILITY ANALYSIS, AND WHEN WE LOOKED AT THIS RELIABILITY ISSUES, UH, WE VERIFIED THERE WERE SEVERAL ISSUES IN THIS STUDY AREA.
UH, SOME OF THE CON COUNTIES, INCLUDING THE BELL BASTROP, TRAVIS HAYES, CALDWELL, AND ROBERTSON COUNTIES.
WE, WE DID IDENTIFY SEVERAL ISSUES IN THE HUDDLE.
WE, WE, THE, THE STUDY AREA WAS BASICALLY DIVIDED INTO TWO, UH, ONE FOCUSING ON THE NORTH OF HARO, AND THE OTHER IS SOUTH OF HARO.
AND, UH, WE DECIDED TO DO AN INDEPENDENT REVIEW IN TWO PHASES.
UH, THIS PROJECT PRIMARILY, OR THE RECOMMENDATION HERE IS PRIMARILY FOCUSED ON STUDY AREA ONE, WHICH IS NORTH OF HARO.
AS YOU COULD SEE, THE TABLE HIGHLIGHTS SOME OF THE ISSUES IDENTIFIED IN STUDY AREA ONE, BASED ON THE RELIABILITY ISSUES.
THERE WERE SEVERAL OVERLOADS, THERMAL OVERLOADS, VOLTAGE ISSUES, AND UNSOLVED POWER FLOW CONDITIONS.
ALL RIGHT, SO LOOKING AT ALL THIS ISSUES, UM, THAT WE IDENTIFIED IN THE INITIAL RELIABILITY ANALYSIS, UM, THIS PROJECT, OBVIOUSLY THE SCOPE OF THE PROJECT WAS EXPANDED.
SO THE, THERE ARE THREE PARTS TO THIS PROJECT.
THE FIRST ONE IS THE ENCORE, LCRA MOSCOW WEST LAKE PROJECT, UM, THAT ADDRESSES SEVERAL POST CONTINGENCY THERMAL ISSUES, VOLTAGE ISSUES IN THE WILLIAMSON AND MILAM COUNTY.
UH, THAT'S DIRECTLY TIED TO THE LOAD GROWTH THAT IDENTIFIED, THAT WAS IDENTIFIED IN THE INITIAL SUBMITTAL.
UM, SO THE PRO COST OF THAT PART OF THE PROJECT IS, UH, REVISED $388.94 MILLION.
UM, ALSO SOME OF THE OTHER ISSUES WE IDENTIFIED IN THE NORTH OF HARO, UH, WE DID LOOK AT OTHER PROJECTS.
ONCOR DID SUBMIT, UH, SEVERAL OTHER RPG PROJECTS.
ONE OF THE PROJECTS IS THE, UM, 25 RPG 0 4 1, WHICH IS THE ENCORE SET ONE NORTH, CENTRAL AND SOUTH CENTRAL TEXAS RELI PROJECT.
UM, THERE WERE SEVERAL UPGRADES IDENTIFIED IN THAT PROJECT, SET OF PROJECTS.
SUBSET OF THE PROJECT ALSO ADDRESS SOME OF THE RELIABILITY NEEDS IDENTIFIED IN THE NORTH OF HA ISSUES.
SO THOSE, THOSE ISSUES, WHICH WAS NOT PART OF THE ORIGINAL SUBMITTAL, BUT, UH, WE DID IDENTIFY THOSE PROJECTS AS PART OF THE 2024 AND 2025 RTP STUDIES.
SO THOSE PROJECTS WERE, WERE MOVED TO THE MOSCOW WAS LAKE PROJECT AS TO ADDRESS SOME OF THE ISSUES IN THE NORTH CENTRAL.
IN ADDITION TO THAT, THERE WAS ALSO LOOKED AT, LIKE, WE ALSO LOOKED AT ADDITIONAL LOADS, POTENTIAL LOADS, UM, THAT IS PROJECTED TO, YOU KNOW, OR PROJECT OR, OR WAS SUBMITTED IN OTHER SUBMITTALS, INCLUDING THE LATEST, UM, RFI, UH, FOR 2026, WE DID SOME SENSITIVITIES.
WE DID IDENTIFY THAT WE NEED ADDITIONAL PIECES TO ADDRESS POTENTIAL LOADS BECAUSE WHEN WE ARE LOOKING AT A PROJECT ADDRESSING ALL THIS RELIABILITY ISSUES, WE WANTED TO BUILD THE MARGINS TO SEE THAT LIKE, YOU KNOW, THE PROJECT ADDRESSES ADDITIONAL POTENTIAL LOADS.
SO THAT'S THE LAST PIECE OF THE PROJECT.
UH, THERE WAS AN ADDITIONAL UPGRADE IDENTIFIED, WHICH, WHICH IS A NEW LINE, UM, THAT INCLUDED $465 MILLION.
[00:40:02]
SO FROM THE ORIGINAL $388 MILLION.WHEN YOU ADD ALL THOSE THINGS, YOU KNOW, THE PROJECT COST INCREASED.
UM, THAT'S, THAT'S THIS, THIS PROJECT IS ADDRESSING SEVERAL ADDITIONAL ISSUES THAT WAS ALREADY IDENTIFIED IN 20 24, 20 25 RTP, AND ALSO SUBMITTED AS, UH, PART OF OTHER PROJECTS.
SO WHEN I TALK ABOUT SET ONE, SET TWO PROJECTS, YOU'LL SEE THAT THIS PORTION IS REMOVED FROM THAT ENCORE SET ONE, SET TWO PROJECTS, AND WE WON'T BE, YOU KNOW, DISCUSSING THOSE PARTS IN THE OTHER PROJECT.
SO HERE'S THE COMPARISON OF THE OPTIONS.
UM,
AND WE SHORTLY LISTED FOUR OPTIONS AND BASED ON LOOKING AT ALL THE, ALL THE RELIABILITY NEED, LONG-TERM LOAD SERVING CAPABILITY, ADDITIONAL PROJECTED CONTRACTED LOADS, AND THE CCN REQUIREMENT, CONSTRUCTION FEASIBILITY, AND OTHER COST ESTIMATES, UH, WE RECOMMEND OPTION SEVEN A TO ADDRESS ALL THE RELIABILITY NEEDS.
ERCOT AND NER CRITERIA IMPROVE LONG-TERM LOAD SERVING CAPABILITY AND ALSO POTENTIAL FUTURE LOAD, UH, GROWTH IN THE AREA AND FEASIBILITY OF CONSTRUCTION.
SO OBVIOUSLY THE COST OF ALL THIS OPTIONS ARE SIGNIFICANTLY HIGHER THAN THE INITIAL PROJECT.
UM, THE, THE COST FOR THIS SHORTLISTED OPTIONS VARIES FROM TWO POINTS, 1.27 BILLION TO 1.45 OR $1.55 BILLION.
SO THE OPTION SEVEN IS HERE, IS LIKE THE SECOND MOST EXPENSIVE OPTION HERE, I THINK.
UM, THE RECOMMENDED OPTION IS $1.457 BILLION WITH AN ESTIMATED IN-SERVICE DATE OF, UH, DECEMBER, 2031 FOR BOTH THE LCRA AND ENCORE PORTIONS.
SO THERE ARE SEVERAL PARTS OF THIS PROJECT.
SO THE IN-SERVICE DATE, SOME PARTS MIGHT BE LIKE EARLIER THAN DECEMBER 3RD, 31 I THINK.
AGAIN, UH, SUB SYNCHRONOUS OSCILLATION ASSESSMENT, UH, WE DID NOT SEE ANY ADVERSE IMPACT WITH OPTION SEVEN.
A, UH, SIMILAR TO THAT, WE DID PERFORM THE CONGESTION ANALYSIS AND SENSITIVITY ANALYSIS FOR FUTURE POTENTIAL GENERATION AND OPTION SEVEN A DID NOT CAUSE ANY ADDITIONAL CONGESTION OR DID NOT HAVE AN IMPACT ON FUTURE POTENTIAL GENERATION, UM, THAT MIGHT BE ADDED TO THE STUDY AREA.
HERE'S THE OVERALL SUMMARY OF THE PROJECT.
SO BASICALLY APPROXIMATELY 159 MILES CIRCUIT MILES OF, UH, NEW 3 45 KB LINES, A HUNDRED MILES OF REBUILT OF THREE FOUR EXISTING 3 45 KB LINES, 45 MILES OF REBUILT OF 1 38 KB LINES, UH, CONSTRUCTION OF THREE NEW 3 45 1 38 KB STATION CONSTRUCTION OF ONE NEW 3 45 KB STATION.
AND, UH, INSTALL FIVE AUTO TRANSFORMER 3 45, 1 38 KB AUTO TRANSFORMERS AND ALSO INSTALL, UH, CAPACITORS, TOTALING 110 MEGAWATTS OF CAPACITOR BANK.
I, I THINK THERE ARE THE, THE DETAILED DESCRIPTIONS OR IN THE APPENDIX B I'M NOT GONNA GO THROUGH THIS, BUT I'LL JUST LIKE END WITH THIS RECOMMENDATION SLIDE, WHICH KIND OF HIGHLIGHTS, UM, THE PROJECT.
SO BASED ON THE REVIEWER CARD, WILL RECOMMEND BOARD ENDORSE THE OPTION SEVEN A TO ADDRESS RELIABILITY ISSUES IN BELL MILAM WILLIAMSON COUNTY AND ROBERTSON COUNTY IN THE NORTH CENTRAL, SOUTH CENTRAL AND EAST WEATHER ZONE.
UM, THE ESTIMATED IN-SERVICE DATE IS DECEMBER, 2031.
THE ESTIMATED COST IS 1.457 BILLION AND AS I SAID, THERE ARE THREE PARTS TO THE PROJECT.
UM, THE CCN FROM A CCN, THE MAJOR PORTION IS, UH, NEW 3 45 KV DOUBLE CIRCUIT LINE FROM MUSCOVY TO OS LAKE.
AND ALSO WE HAVE A NEW 3 45 KV LINE, UH, FROM SODO TO HURO SODO TO GABRIEL TO HURO.
THAT'S A DOUBLE CIRCUIT 3 45 KV LINE.
THOSE ARE THE MAJOR PORTIONS OF THE PROJECT.
SO I'LL GO BACK TO THIS, UM, I'LL PAUSE HERE TO SEE IF THERE ARE ANY QUESTIONS.
AND I THINK WE DO HAVE ENCORE AND LCRA FOLKS ON THE LINE.
UM, NED DO YOU WANNA START WITH YOUR QUESTION? SURE.
SO SAME THING I SAW IN THE SELECTED IN THE TABLE ON SLIDE FIVE.
YOU'VE GOT BASICALLY A GIGAWATT OF, UM, IMPROVED LONG-TERM LOAD SERVING CAPABILITY.
IT SAYS IT ALSO SUPPORTS NEW CONTRACTED LOADS, BUT I'M GUESSING THAT THERE, EACH ONE OF THE COMPONENTS THAT YOU WENT THROUGH THAT WERE KIND OF ADDED TOGETHER TO GET HERE ALSO HAD SOME LOADS ASSOCIATED WITH IT.
SO WHAT'S THE TOTAL LARGE LOAD THAT IS, I GUESS, BEHIND THIS SET OF,
[00:45:01]
UM, SET OF UPGRADES? AND DO WE HAVE SOME COLOR ON THE TIMING OF WINDOWS WILL COME ONLINE RELATIVE TO THE IN-SERVICE DATES OF THE FACILITIES? AND HAVE THEY POSTED, UH, FINANCIAL SECURITY? YES, SO THOSE ARE CAPTURED IN THE REPORT.SO I THINK THE ORIGINAL PROJECT SUBMITTED BY ENCORE WAS DRIVEN BY ROUGHLY AROUND 483 MEGAWATTS OF LARGE LOAD, UH, ENCORE AND LCRA.
AND, UH, WHEN WE LOOKED AT THE PROJECT, UM, THERE WERE OTHER PARTS OF THE PROJECT.
I THINK THE NUMBERS I HAVE IS, UH, ROUGHLY AROUND 4.1 GIGAWATTS OF ADDITIONAL LOAD IN THE NORTH OF AUTO STUDY AREA.
AND THE LAST PART OF THE PROJECT, WHEN WE TALKED ABOUT FUTURE LOADS, THE CONTRACTED LOADS, UH, WE DID A SENSITIVITY FOR ABOUT ADDING APPROXIMATELY 200 MEGAWATTS OF ADDITIONAL LOAD, UM, THAT DROVE THE LAST PIECE OF THE PROJECT.
SO I THINK THOSE, THOSE ARE THE, I BELIEVE THOSE NUMBERS ARE PART OF THE REPORT AND UM, THAT'S, I THINK THAT, I THINK THOSE ARE THE NUMBERS.
OKAY, SO WE GET TO ABOUT FOUR, 4.8 GIGAWATTS OF TOTAL, TOTAL LOAD THAT'S SUPPORTED THERE.
YES, THERE'S 4.8 TOTAL LOAD, BUT WHEN, YOU KNOW, WHEN YOU COMPARE THE, THERE ARE, WHEN YOU COMPARE THE STUDY, WHEN WE SAY STUDY EAST, NOT CENTRAL, SOUTH, CENTRAL, WHEN YOU COMBINE ALL THE LOADS THAT'S IN THE MODEL, THAT'S SIGNIFICANTLY HIGHER THAN WHAT WAS STUDIED IN THE 2024 AND 2024 RTP.
SO I, I'LL, I'LL, I'LL GO THROUGH THIS NUMBERS IN THE NEXT COUPLE OF PROJECTS, BUT THAT'S, THAT'S THE MODEL WE USE.
BETH, MY QUESTIONS HAVE TO DO WITH THE DIVISION OF THIS INTO THE NORTH OF HUDU, SOUTH OF HUDU.
UM, SO STARTING WITH, IF WE COULD GO BACK TO WHAT IS THIS SLIDE THAT HAS THE COMPONENTS, UH, OF THE COST? WAS THAT FOUR, UH, I'M SORRY, THE 382 OF INITIAL PROJECT SLIDE FOUR.
UM, AS I LOOK AT THAT FIRST PARAGRAPH, YOU KNOW, THE INITIAL, UH, MASS IF YOU WILL, OF THE, OF, OF THE SUBMITTED PROJECT WAS THAT LINE FOR 380.
NOW 389 MILLION WAS A LITTLE BIT LESS WHEN, WHEN PROPOSED, BUT IT'S BEEN AN OVER A YEAR.
UM, MY QUESTION HAS TO DO WITH, WERE THERE OTHER THINGS IN THAT INITIAL SUBMITTAL, I'M TRYING TO FIGURE OUT HOW MUCH MORE COSTS ARE WE, ARE WE LOOKING AT TO DEAL WITH THE SOUTH OF HUDU STUFF? UM, YOU KNOW, IT DOES THAT, DOES THAT FIRST PARAGRAPH REFLECT 90% OF WHAT WAS SUBMITTED IN THE INITIAL, UM, UH, PART OF THE INITIAL SUBMITTAL OR WAS IT 10%? UM, I ASSUME IT'S CLOSER TO 90 TO TEN FOUR.
YEAH, LET ME UNDERSTAND THE QUESTION.
SO ARE IS YOUR QUESTION WHETHER SOME OF THIS PROJECT WILL ADDRESS THE SOUTH OF HARO ISSUES? WELL, THAT'S ONE, THAT'S ONE QUESTION.
AND I'M JUST TRYING TO GET A HANDLE ON, IT'S LIKE YOU PARSED OFF A PUN A BUNCH, YOU PARSED OFF A PIECE OF THIS PROJECT, BUT SAID HERE, OUR $300 MILLION PROJECT IS NOW A BILLION AND A HALF.
HOW MUCH MORE IS LINGERING IN THE SOUTH OF HUN? IS THAT ANOTHER COUPLE HUNDRED MILLION OR IS IT ANOTHER BILLION DOLLARS? UM, OKAY.
THAT, THAT PART WE ARE IN THE PROCESS OF STUDYING THAT.
SO I DON'T HAVE AN ANSWER RIGHT NOW.
THAT'S, UH, THAT'S SOMETHING WE WILL SEE.
BUT I THINK, YOU KNOW, THE, AS AS THE LOAD INCREASES, LIKE, YOU KNOW, IT'S CHANGING ON A MONTHLY BASIS OR LIKE, YOU KNOW, IT'S, IT'S RAPIDLY CHANGING, SO THAT MAKES IT MORE COMPLEX, RIGHT? SO IF WHATEVER WE ARE SEEING TODAY, YOU KNOW, BY THE TIME WE DO THE STUDY, I'M, I'M REAL RELUCTANT TO SAY WHAT THE, HEY PROBABLY, I THINK ANOTHER THING BETH, SORRY, BEHIND YOU, IT'S CHRISTIE.
UM, ONE THING I'D LIKE TO ADD, I KNOW THE CONCERNS ABOUT ADDITIONAL NEW LARGE LOADS MOVING FORWARD AND I WOULD LIKE TO, YOU KNOW, INVITE YOU ALL TO THE LARGE LOAD WORKING GROUP THIS WEEK WE'RE GONNA BE STARTING DISCUSSIONS ABOUT KIND OF WHERE DO WE SEE PLANNING GOING FORWARD AND THE ROLE OF RPG IN THE PROCESS AS WE EVOLVE WITH THE NEW COMMISSION RULES, THE EVOLVING GRID, HOW DOES ALL THAT FIT WITH THE BATCH PROCESS? AND I THINK WHAT YOU'LL FIND IS WHAT WE'LL BE RECOMMENDING IS THAT GOING FORWARD AFTER HOPEFULLY THE APPROVAL OF THIS REVISION REQUEST WITH THE APPROVAL OF COMMISSION RULES, BEING ABLE TO UTILIZE AN RPG FOR NEW LARGE LOADS SOLELY FOR THAT, THOSE LARGE LOADS ARE GONNA HAVE TO GO THROUGH THE BATCH PROCESS.
AND SO WE'RE GONNA HAVE TO REVISIT, YOU KNOW, ANY ONES THAT ARE CURRENTLY IN FLIGHT AND WHAT WE DO WITH,
[00:50:01]
UM, NEW SUBMITTALS GOING FORWARD.SO I THINK THAT WILL HELP TO ADDRESS SOME OF THE CONCERNS THAT I THINK YOU HAVE LOOKING AT, YOU KNOW, FUTURE PROJECTS TO ADDRESS LARGE LOAD GROWTH.
AND, AND I APPRECIATE THAT, CHRISTIE.
'CAUSE THAT'S MY REAL, THAT'S AS FROM A CONSUMER PERSPECTIVE, YOU KNOW, MUCH, MOST OF THE BATCH ARGUMENT HAS BEEN WHO'S IN AND WHO'S OUT AND, AND FRANKLY I DON'T REALLY CARE, I DO CARE VERY MUCH ABOUT THE INTERACTION OF THE RESULTS OF THE BATCH STUDY AND WHAT THAT MEANS FOR TRANSMISSION EXPANSION.
SO I THANK YOU FOR, THANK YOU FOR SHARING THAT.
UM, TO HONE IN ON THE LOAD ISSUE, UH, I ASKED IT PRETTY SPECIFICALLY,
SO IF YOU LOOK AT THE OPTIONS COMPARISON, WHEN YOU ADD THAT ADDITIONAL LOAD, SOME OF THE OPTIONS DID NOT MEET THE REQUIREMENTS.
SO OPTION SEVEN A AND OPTION FOUR A MET THOSE LARGE LOADS.
SO PART OF THAT IS DRIVEN BY THOSE ADDITIONAL CONTRACTED LOAD.
AND THAT A, AGAIN, THAT'S ANOTHER AREA WHERE, NOT INCLUDED IN THE DETAILS OF YOUR SLIDES, BUT IT IS EMBEDDED IN THE REPORT.
UM, YOU KNOW, IT'S 600 MEGAWATTS OF ENCORE LOAD AND 3,573 MEGAWATTS OF LCRA LOAD, UM, WITH 11 LARGE LOAD IDENTIFIERS FOR THE LC, UH, LOADS INCLUDED IN THE REPORT.
UM, AND THIS, I DON'T INTEND IT TO BE A GOTCHA QUESTION 'CAUSE IT, BUT I JUST THOUGHT OF IT THIS MORNING IN THE SHOWER, SO I'M GONNA ASK IT NOW,
UM, YOU'RE SOLVING PART OF THE PROBLEM THAT INITIALLY WAS PRESENTED.
WHAT WAS YOUR MOTIVATION FOR DOING THAT TODAY INSTEAD OF WAITING FOR A COMPREHENSIVE RECOMMENDATION FOR THE WHOLE PROBLEM? YEAH, THIS IS, THIS IS SOMETHING WE TALKED ABOUT.
SO THERE IS, IF, IF YOU LOOK AT THIS PROJECTS, YOU KNOW, ESPECIALLY THE LOAD GROWTH, UM, THERE IS AN URGENCY TO MOVE SOME OF THE PROJECTS TO ADDRESS THE, THE RELIABILITY NEEDS.
SO ONE OF THE THINGS I WOULD POINT OUT TO, LIKE I HAVE TO GO BACK TO SEE WHICH ONE IT IS, WHETHER IT'S HOSPITAL 50 66 OR PROBABLY THE PREVIOUS ONE THERE IS, UM, I THINK ONE OF THE THINGS THAT CAME OUT IS LIKE, YOU KNOW, WE NEED TO DO EVERYTHING TO MAKE SURE LIKE, YOU KNOW, WE INTERCONNECT THIS LOADS AND SERVE THIS LOAD IN AN EXPEDITED MANNER.
I THINK THAT'S ONE OF, ONE OF THE THINGS THAT CAME, CAME THROUGH THAT, UH, I, I GOTTA GO AND LOOK THE LANGUAGE, BUT THERE IS LANGUAGE IN THERE EITHER IN THE, IN THE, IN THOSE ONE OF THOSE BILLS OR EXISTING, UH, YOU KNOW, PCD RULES, WHICH I THINK THE OTHER THING YOU SHOULD ADD BU IS THAT, YOU KNOW, WE HAVE TO TAKE EACH ONE AT A TIME AND THIS PIECE WAS READY TO MOVE FORWARD AND IF WE WAIT FOR THE GOOD OF ALL, YOU KNOW, THE WAY THE GRID IS INTERCONNECTED, WE'RE GONNA BE LOOKING AT THE WHOLE STATE AND THAT'S WHERE WE'RE GOING TO IN THE BATCH PROCESS.
AND SO THIS PORTION OF IT WAS MORE VETTED AND READY TO MOVE FORWARD.
UM, AND SO, YOU KNOW, WITH THE SAKE OF, YOU KNOW, NOT HOLDING EVERYTHING BACK, LET'S MOVE FORWARD WHAT WE CAN NOW.
AND, AND, AND I THINK THE OTHER PART IS ALSO LIKE WE, WE'VE BEEN SEEING THESE ISSUES IN, UH, IN THE LAST COUPLE OF RPG CYCLE, RIGHT? SO 20 24, 20 25 WE'RE SEEING THIS PROJECTS AND EVERY INDICATION OR THE, THE LOAD PROJECTIONS WE ARE GETTING IS, YOU KNOW, THE LOAD IS PROJECTED TO GROW HIGHER THAN WHAT WAS STUDIED IN 2024 OR 2025.
IT'S ALSO BASED OFF OF FEEDBACK WE'VE GOTTEN FROM OUR OPERATIONS AREA.
WE REGULARLY MEET WITH THEM TO SEE WHAT THINGS THEY'RE SEEING IN OPERATIONS, MAKE SURE WE'RE PICKING IT UP AND PLANNING.
AND THIS HAS BEEN AN AREA OF FOCUS FOR THEM AS WELL.
[00:55:01]
THIS IS REALLY LOUD, SARAH WITH OPEC.UM, I THINK MY QUESTION WAS JUST CLARIFYING THE R PT NOTES THAT THE, I GUESS THE NINE, ABOUT 1900 MEGAWATTS OF CONFIRM LOAD, THAT'S THE RRP RTP LOAD AND THEN THE 2200 OF TSPA TESTED LOAD, THAT'S WHAT YOU'RE SAYING AS ADDITIONAL CONTRACTED LOAD.
THE FOR THIS IS, THIS IS GOING BACK TO WHAT'S IN THE CURRENT DEFINITION OR IN THE, IN THE PLANNING GUIDES.
THIS IS CALLED THE SUBSTANTIATED LOAD.
ONE IS, YOU KNOW, THE, THE LOADS THAT HAVE CONTRACTS AND THEN THE OFFICER LEVEL LOADS THAT THAT'S INCLUDED IN, IN THIS REVIEW.
THE OTHER CONTRACTED LOAD I'M TALKING ABOUT, THAT'S AN ADDITIONAL LOAD THAT WAS NOT SUBMITTED INITIALLY AS PART OF THE STUDY.
THAT'S SOMETHING WE, WE DID A SENSITIVITY TO ADD ADDITIONAL CONTRACTED LOAD, WHICH WAS NOT PART OF THAT.
AND THEN SO UNDER THE, I GUESS THE EXISTING, THAT MEANS THEY'RE NOT INCLUDED IN THE BATCH PROCESS 'CAUSE THEY'RE ALREADY, UM, PA I GUESS PAST THAT STEP.
THEY'RE NOT THE, YEAH, SO I, I QUESTION THAT'S SOMETHING WE ARE WORKING ON, LIKE, YOU KNOW, WHAT LOAD GOES INTO THE BATCH ZERO, THAT'S AN ONGOING PROCESS THAT ERCOT IS LOOKING AT.
SO I CAN'T COMMENT ON WHAT'S IN THE BATCH PROCESS OR WHAT'S IN THE, IF I, I MIGHT HAVE NOT UNDERSTOOD YOUR QUESTION CORRECTLY, SO NO, YOU'RE GONNA, I MAY NOT HAVE ASKED IT WELL.
UM, SO THE, THE 2200 OF TSPA TESTED LOAD AND THEN THE 1900 OF CONFIRMED LOAD, IS THAT HAVE ALREADY MOVED FORWARD IN THE CURRENT RPG PROCESS OF INTERCONNECTION? OR IS, IS THAT STILL LIKE IN THE INTERCONNECTION QUEUE WAITING TO BE CONNECTED? I THINK THIS IS SOMETHING I'M GONNA SEE IF ENCORE WANTS TO ADD MORE COLOR TO THAT LOAD OR, YEAH.
UM, MARTHA HENSON WITH ENCORE.
SO JUST KIND OF GOING BACK TO THE BEGINNING WHEN, WHEN WE SUBMITTED THIS PROJECT AS BU STATED, WE HAD JUST SHY OF 500 MEGAWATTS OF ENCORE LOAD TO SUPPORT THE SUBMITTAL DURING THE PENDENCY OF THE ERCOT INDEPENDENT REVIEW, ENCORE ADDED ADDITIONAL 300 MEGAWATTS OF, UM, LOAD TO THE SUBMITTAL.
UH, MOST OF THAT LOAD IS CONTRACTED WITH ENCORE.
THEY HAVE AN EXECUTED FACILITY FACILITIES EXTENSION AGREEMENT WITH THE COMPANY.
UM, I'D ALSO INVITE LCRA TO PROVIDE ANY OTHER DETAILS ABOUT THE LOAD THAT THEY PROVIDED TO THE ORIGINAL SUBMISSION AS WELL.
THIS IS SAND KAR WITH LCRA PLANNING.
AS THE STUDY SCOPE WAS BEING DEVELOPED, UH, L-C-R-A-T-C SAW L-C-A-T-C LAWS WERE JUST SOUTH OF THAT REGION, BUT HAVE, WERE BEING IMPACTED BY THE RELIABILITY ISSUES IDENTIFIED AS PART OF THE, UH, LIMBER MUSCO PROJECT.
SO AT THAT POINT, UH, L-C-R-T-C ALSO INCLUDED, UH, SOME OF ITS, UH, LARGE LOADS THAT WERE CONTRACTED AS WELL AS, UH, UH, SOME OFFICER LEVEL LOADS AT THAT POINT.
I THINK THOSE NUMBERS ARE CALLED OUT IN THE REPORT.
UH, I BELIEVE IT'S, UH, 3003 5 7 3, UH, MEGAWATTS.
UH, AND, AND WE ALSO PROVIDED THE LLI NUMBERS THAT ARE ASSOCIATED WITH THEM, UH, AS A REFERENCE.
ARE WE GOOD ON QUESTIONS? PROBABLY.
DID YOU FINISH YOUR SLIDES ON THIS ONE? YEAH, I, I THINK I FINISHED THIS PRESENTATION.
SO THE RECOMMENDATION HERE OKAY.
FOR ATTACK, OKAY, SO WE'D BE LOOKING TO ENDORSE THE 25 RPG 0 0 9 ENCO, LCRA AT TSC, MUSK GOBY AND VOS LAKE 3 45 1 38 KB PROJECT OPTION SEVEN A.
IS THIS A COMBO BALLOT ITEM OR A SEPARATE BALLOT ITEM? CONSUMERS, ARE WE LISTENING?
FEELS LIKE, YOU KNOW, FEELS LIKE A SEPARATE BALLOT MIGHT BE APPROPRIATE.
JUST 'CAUSE IT'S, IT'S A BILLION FREAKING DOLLARS.
I MEAN A BILLION DOLLARS IS A LOT OF MONEY.
I MEAN, IT'S, IT, THE OTHER ONES ON THE, OKAY, SO WE'RE GONNA AT SOME POINT PUT IN THE TECH PROCEDURES, THE BETH GARZA BILLION DOLLAR
I'M, IF I'M THE ONLY VOICE THAT'S, I, YOU KNOW, I'M HAPPY TO, THAT'S, YOU KNOW, I'M HAPPY TO, UH, IT'S A SEPARATE OR COMBO.
[01:00:01]
THIS TIME, BUT THE THIRD TIME.AND WHAT WE COULD DO IF, IF IT MAKES SENSE, COREY, WHAT WE COULD DO IS WE COULD SET IT ASIDE, GO THROUGH ALL THE PROJECTS, AND THEN COME BACK AND KIND OF SEQUENTIALLY AND DO A, DO A $3 MILLION BALLOT.
I'M, I'M, I'M NOT TRYING TO CAUSE PROBLEMS YOU YOU'D LIKE TO DO.
I'D RATHER DO IT, JUST PUT IT ON THE COMBO BALLOT THAN HAVE A RPG COMBO BALLOT.
I, IF I'M, DO WE NEED A SEPARATE BALLOT ON THIS? ARE THERE ANY ABSTENTIONS OR NOS? I WOULD SUPPORT A SEPARATE FOR THIS HIGH AMOUNT.
MOTION FROM BOB HILTON, SECOND FROM DAVID DA.
DAVID HAD HIS FINGER HIGHER IN THE AIR, AARON, SO, OKAY.
WE'RE COMING UP WITH ALL KINDS OF NEW PROCEDURAL RULES HERE.
YEAH, I'D, I'D RATHER JUST TAKE THE SEPARATE BALLOT THAN HAVE LIKE A RANDOM REAL COMBO BALLOT RPG COMBO BALLOT.
SO, WELL I WAS THINKING JUST A SERIES OF RPG BALLOTS ALL AT ONCE, BUT THAT'S OKAY.
AGAIN, I HATE THIS, BUT YES, WE'LL GET THROUGH IT.
I'LL DOUBLE CHECK MY MOTION AND MAKE SURE THAT SHORT NOVEL DESCRIBES WHAT Y'ALL ARE ENDORSING.
OPTION SEVEN A FOR THE ENCORE LCRA MUSKOGEE DEVOS LAKE PROJECT.
AND THEN JUST A REMINDER, IN CASE ANYONE'S CONFUSED WHEN Y'ALL VOTE ON THE COMBO BALLOT THAT CARRIES THE SAME WEIGHT AS AN INDIVIDUAL BALLOT.
SO IF, IF THERE'S ANY MISTAKEN BELIEF THAT THIS IS SOMEHOW MORE OFFICIAL THAN COMBOING FIVE ITEMS, 10 ITEMS, A HUNDRED ITEMS, THEY ALL CARRY THE SAME WEIGHT.
SO YEAH, ANNIE, I KNOW, BUT IT'S SIMPLE.
LISTEN BOY, IT'S, YEAH, IT'S SYMBOLIC.
COREY, THEN SO IS MY COMMENTARY
I KNOW, I KNOW IT WAS RECEIVED.
SO SO IS THE AMOUNT OF SLEEP YOU'VE BEEN GETTING.
WELL WE WILL START UP WITH THE CONSUMERS, WITH GARRETT.
[01:05:01]
FEHRENBACH YOU WITH US? I'LL SWING BACK TO NICK BETH? YES.YES, THANK YOU JOE, DAN FOR MIKE.
ONTO OUR INDEPENDENT GENERATORS.
UH, MARK ME DOWN AS AN UPPERCASE X.
CAITLIN, CAN I GET ONE OF THOSE UPPERCASE XES ALSO? SURE.
NO FEES FOR THE FIRST ONES ONTO THE IPMS. JEREMY? YES, THANK YOU.
THANK YOU IAN FOR SETH? YES, THANK YOU.
AND THEN IAN FOR MORGAN STANLEY.
THANK YOU, UH, SHANE FOR RASHMI? YES SIR.
UM, NICK, I GOT YOUR YES IN CHAT.
YES, THANK YOU, UH, DAVID FOR EBY.
YES, THANK YOU AND DIANA FOR DAVID.
MOTION CARRIES WITH ONE ABSTENTION.
I'M SO GLAD WE DIDN'T HAVE THAT ON THE COMBO BALLOT.
THANK YOU JEN, EVERYBODY THANK JEN FOR JUSTIFYING THAT EXERCISE.
ALRIGHT, ANYTHING ELSE ON THE SECOND PROJECT? OKAY.
BU YOU, YOU HANGING IN THERE? ALL RIGHT, WE ARE GONNA GO TO OUR THIRD RPG PROJECT.
UM, THIS IS ANOTHER ENCORE PROJECT, SO WE'LL DO, DO THE SAME THING.
WE'LL DO BU ENCORE IF THEY HAVE ANYTHING BEFORE.
NED BETH O OTHER QUESTIONS? SOUND GOOD? ALL RIGHT, TAKE IT AWAY PU.
THE THIRD PROJECT IS THE ENCORE COMBINED SET ONE NORTH AND CENTRAL TEXAS RELIABILITY PROJECT AND THE SET TWO NORTH AND CENTRAL RELIABILITY PROJECT.
THOSE ARE TWO DIFFERENT PROJECTS SUBMITTED BY ENCORE.
SO THESE PROJECTS, UM, ADDRESS VARIOUS LIBRARY ISSUES, UM, ESPECIALLY IN THE NORTH, NORTH CENTRAL AND THE EAST WEATHER ZONES, OR, UM, SO THIS, THE SET ONE AND SET TWO NORTH AND CENTRAL PROJECTS.
UM, THIS, THESE PROJECTS WERE SUBMITTED BY ENCORE BASED ON, UH, THE PROJECTS IDENTIFIED IN THE 2024 AND 2025 RTP.
UH, THIS IS A COMBINED PROJECT, AS I SAID, UH, SET ONE.
THE THE SET ONE PROJECTS THE TOTAL ESTIMATED COST WAS $1.79 BILLION, AND THE SET TWO PROJECT IS $1.33 BILLION.
THERE'S A LOT OF ELEMENTS TO THAT PROJECT.
UM, SO THE COMBINED ESTIMATE IS, UH, AROUND ROUGHLY AROUND THREE POINT, UH, 1 BILLION TO THREE POINT LESS THAN $3.2 BILLION.
SO ERCOT DECIDED TO PERFORM A SINGLE, UM, ERCOT INDEPENDENT REVIEW BY COMBINING THESE TWO PROJECTS.
SO THE BACKGROUND ON THIS IS THE, THE SET ONE PROJECTS AS SUBMITTED BY ENCORE OR PROJECTS IDENTIFIED IN BOTH 2024 AND 2025 RTP.
THE SET TWO PROJECTS WERE INCLUDED IN THE 2024 RTP, UM, AND SUBSET OF THE PROJECTS WERE IDENTIFIED IN 2025.
SO BASICALLY THE DIFFERENCE IF YOU HAVE BEEN FOLLOWING THE LAST FEW RPG CYCLE, RTP CYCLES, AND, UH, THE, THE LOAD PROJECTIONS IN THE AREA, IF YOU LOOK AT THE TABLE, GIVES THE COMPARISON OF WHAT WAS STUDIED IN THE ERCOT INDEPENDENT REVIEW.
THIS, THIS PARTICULAR REVIEW VERSUS WHAT WAS INCLUDED IN THE 2024 VERSUS 2025 RTP.
[01:10:01]
UH, 2025 IS THE ONE WHERE WE DID THE ERCOT ADJUSTED, UH, FORECAST.UM, SO IF YOU LOOK AT THE TOTAL LOADS IN THIS THREE WEATHER ZONES, UM, 2024, IT WAS 58 GIGAWATTS, 2025, UH, 55 GIGAWATTS.
BUT THIS PROJECT, WHEN WE STARTED LOOKING AT ALL THE LOADS THAT'S SUBMITTED IN THE STUDY AREA, THAT LOAD ADDED TO BE LIKE 71 GIGAWATTS.
SO BASICALLY THIS IS 16 GIGAWATTS, UH, MORE THAN WHAT WAS STUDIED IN THE 2025 RTP AND ROUGHLY 13 GIGAWATTS MORE THAN WHAT WAS STUDIED IN THE 2024 RTP.
AGAIN, THE, THE PROJECT EVALUATION, UM, THIS IS AGAIN, BROKEN INTO THREE DIFFERENT, UH, BUCKETS OR GROUPS.
THE FIRST GROUP IS WHAT WE CALL LIKE, UH, WHAT THE WAY WE APPROACH THIS COMBINED RPG REVIEW IS WE SAW LIKE NEEDS TO MOVE SOME OF THE PARTS AS INTO OTHER ONGOING RPG REVIEWS.
SO THE GROUP ONE HERE IS, UH, SET UP PROJECTS THAT WAS CARRIED OVER TO THE ENCORE SOUTH DFW LOAD INTEGRATION PROJECT.
THAT PROJECT WAS, UM, YOU KNOW, THIS WAS, THIS WAS ENDORSED.
I THINK THE SECOND PART, THE GROUP TWO PROJECT IS, IS PART OF TODAY'S RECOMMENDATION OF THE GROUP THREE.
GROUP TWO IS, UM, THERE IS SET OF PROJECTS WHERE THE SET ONE AND SET TWO PROJECTS.
WE LOOKED AT THE LOAD PROJECTIONS, WE DID A COMPARISON, WE WHAT ON THE NEED, WHAT WAS IDENTIFIED IN 2024 AND 2025.
AND BASED ON THOSE REVIEWS AND COMPARISON, WE ARE RECOMMENDING A SET OF PROJECTS, BECAUSE THIS IS COMMON.
THIS ARE PROJECTS THAT SHOWED UP IN EITHER 2024 AND 2025, OR IT MIGHT HAVE SHOWED UP IN 2024.
BUT WHEN YOU LOOK AT THE PRO TOTAL PROJECTED LOAD THAT'S BEING STUDIED IN THE ERCOT INDEPENDENT REVIEW, THAT EXCEEDS EITHER 2024 OR 2020 FAIL FORECAST.
SO THE RELIABILITY NEEDS, OR BASED ON EITHER 2024 OR 2025.
SO THAT'S THE GROUP OF PROJECTS UNDER SET TWO OR GROUP TWO, I APOLOGIZE.
AND GROUP THREE IS A SET OF PROJECTS.
AND IF YOU LOOK AT THE WHOLE COMBINED, UM, THE SET ONE AND SET TWO PROJECT, THERE WERE PORTIONS OF THE PROJECT, WHICH OTHER TSPS, UM, PROPOSED COMMONS, AND THEY PROPOSED PROJECT ALTERNATIVES.
SO ONE OF THE, THOSE PROJECTS WERE LIKE, YOU KNOW, PUT IN A SEPARATE GROUP, GROUP THREE, AND WE DID A TRADITIONAL, LIKE TYPICAL ERCOT INDEPENDENT REVIEW TO EVALUATE THOSE POTENTIAL COMPETING OPTIONS.
THAT'S THE GROUP THREE HIGHLIGHTED HERE.
SO BASICALLY, UM, BRASS AND TNP COMMENTED ON A SPECIFIC PORTIONS OF THE PROJECT WHERE THEY PUT OUT LIKE PROJECT ALTERNATIVES, AND WE DID, UH, PERFORM AN INDEPENDENT REVIEW FOR THAT PROJECT.
SO AGAIN, UH, FOR ALL THIS PROJECTS, WE DID AN SSO ASSESSMENT.
UM, WE DID NOT SEE ANY IMPACT FOR SSO BASED ON ALL THE SET OF PROJECTS THAT WILL BE, UH, REC OR PROPOSED FOR, UM, ENDORSEMENT TODAY.
AND SIMILAR TO THAT, UH, WE DID, UH, PERFORM THOSE CONGESTION ANALYSIS AND SENSITIVITY ANALYSIS.
THERE WAS NO ADDITIONAL CONGESTION, OR WHEN YOU LOOKED AT THE FUTURE POTENTIAL GENERATION, UH, IT DID NOT HAVE ANY IMPACT REMOVING OR, UH, LOOKING AT THOSE POTENTIAL GENERATION SENSITIVITIES.
SO THIS, I'M GOING, I'M GONNA COVER THIS GROUP THREE PROJECT.
THIS IS A PROJECT WHERE THERE WERE COMPETING OPTIONS.
SO THEY BASICALLY, THERE WERE TWO SET OF PROJECTS, OPTION ONE AND OPTION TWO.
UM, SO ONE IS THE ENCORE PROPOSAL OR THE SUBMITTAL, AND THE OTHER ONE IS THE ONE I HIGHLIGHTED, THE, UH, SUBMITTED BY PROCESS AND TNMP.
SO IF YOU LOOK AT THAT PROJECT, THE ESTIMATED COST, UH, BETWEEN THE COMPARISON IS $56 MILLION VERSUS $80 MILLION.
AND WHEN WE LOOKED AT THE RELIABILITY NEED, LONG-TERM LOAD SERVING CAPABILITY AND COST ESTIMATES, UM, THE CONSTRUCTION FEASIBILITY, AT THE END OF THE DAY, WE STILL RECOMMEND OPTION ONE, UH, WHICH WAS PROPOSED BY ENCORE FOR THIS PROJECT.
SO WE DID SIMILAR TO THAT, WE, WE DID NOT ANY, WE DID NOT SEE ANY ISSUES WHEN, WHEN IT CAME TO SSO OR THE OTHER SENSITIVITIES FOR THIS GROUP THREE, OPTION ONE.
SO TODAY, UH, THE RECOMMENDATION IS, AS I SAID, THE GROUP ONE WAS COMBINED WITH THE, WITH THE DFW SOUTHERN DFW PROJECT.
THAT'S, UH, THAT WAS ALREADY APPROVED.
UM, THIS ONE HERE COMBINES THE GROUP TWO AND GROUP THREE UPGRADES.
SO THERE'S A LOT OF, UH, ELEMENTS TO THIS, BUT AT A HIGH LEVEL,
[01:15:01]
UM, THIS IS, THESE ARE SOME OF THE, YOU KNOW, KEY OR HIGH LEVEL OVERVIEW OF THE, THE, THE MAJOR COMPONENTS OF THE PROJECT HERE.SO I'LL, I'LL, I'LL WALK THROUGH SOME OF THE THINGS.
UH, CONSTRUCT A NEW SUBSTATION THREE, UH, TRANSFORMERS.
THIS IS A 3 45 KV SUBSTATION AT 3 45, 1 38 KB TRANSFORMERS REBUILD FIVE EXISTING STATIONS AND ONE TRANSFORMER THAT INCLUDES, UH, 3 45 KB AND 1 38 KB SUBSTATION REBUILDS AND CONSTRUCT, UH, FIVE NEW, 3 45 KB AND 1 38 KB LINES.
UH, ROUGHLY 115 MILES OF, UH, TWO NEW 3 45 KB LINES, AND THREE NEW 1 38 KV LINES, APPROXIMATELY 32.9 MILES.
UM, THOSE ARE THE C THOSE WERE REQUIRED AS THE CCN AND UPGRADE SEVERAL MILES OF EXISTING 1 38 AND 3 45 KV, ROUGHLY AROUND 290 MILES OF 3 45 KV LINES, AND 233 MILES OF 1 38 KV LINES.
SO, UM, THE DETAILS ARE IN APPENDIX B.
UH, IT'S A LENGTHY DESCRIPTION.
I'M NOT GONNA WALK THROUGH ALL OF THOSE.
UM, BUT HERE'S THE RECOMMENDATION FOR, UH, FOR TODAY, BASED ON THE REVIEW, ERCOT RECOMMENDS THE GROUP TWO AND GROUP THREE UPGRADES TO ADDRESS THE RELIABILITY NEEDS IN NORTH, NORTH, CENTRAL AND EAST WEATHER ZONE.
UH, THE EXPECTED IN-SERVICE DATES, AS I SAID, THERE ARE SEVERAL PARTS OF THE PROJECT INCLUDING REBUILD, UH, BUILDING, REBUILDING STATIONS, BUILDING NEW SUBSTATIONS AND NEW LINES.
SO IT VARIES, UM, BETWEEN 2028 AND 2034, UM, THE ESTIMATED COST OF THOSE GROUP TWO AND GROUP THREE UPGRADES COMBINED IS $2.363 BILLION.
UM, LET'S SAY THE ORIGINAL COST WAS 3.2 AROUND LA AROUND LIKE 800 OR 890 SOME MILLION WAS MOVED TO THE OTHER PROJECT, LIKE THE DFW SOUTH PROJECT, AND THAT WAS, THAT WAS A SEPARATE, UH, APPROVAL.
UM, AND THEN HIGHLIGHTS SOME OF THE CCN MILES.
I'M NOT GOING TO WALK THROUGH THOSE.
UM, AGAIN, I WILL, OKAY, I'LL, I'LL STOP HERE.
IF WE NEED TO GET TO THOSE DETAILS, THOSE ARE IN THE APPENDIX.
SO IF YOU GO THROUGH THIS PROJECTS, WE HAVE THIS ALL THE LIMITS OF THE PROJECT.
SO IN ORDER TO SAVE TIME, I WILL PAUSE HERE AND TAKE QUESTIONS.
OKAY, SO LET'S DO OUR STANDING, STANDING NED AND BETH QUESTIONS, AND THEN GO TO, UH, SHANNON AND THE QUEUE.
OKAY, SO BU I SAW THERE WAS 16 GIGAWATTS OF INCREMENTAL LARGE LOAD INCLUDED IN THIS, OR AM I MISREADING THAT, THAT SLIDE FROM, I THINK IT WAS ON SLIDE THREE.
SO I WANTED TO MAKE THIS CLEAR.
SO THERE WERE LARGE LOADS INCLUDED IN BOTH 2024 AND 2025 RTP, THE 16 GIGAWATTS AND 13 GIGAWATTS REFERRED HERE.
IT'S WHAT IS ON TOP OF WHAT WAS ALREADY INCLUDED IN THE 2024 OR 2025 RTP FOR THOSE STUDY AREAS, RIGHT? IT'S NOT ONE AREA.
ALL THOSE AREAS COMBINED THE PROJECTION FOR 20 24, 58, 58 GIGAWATTS, THERE WERE LARGE LOADS INCLUDED IN 2024.
AND SIMILARLY, THERE WERE LARGE LOADS INCLUDED IN 2025.
THE FORECAST, OF COURSE, WE DID THE ERCOT ADJUSTED FORECAST.
THE LOADS DROPPED A LITTLE BIT 55, BUT, AND THE ARE FOR THE RP RPG PURPOSE INDEPENDENT REVIEW.
WHEN WE ADDED ALL THOSE LOADS AT FULL UP, I MEAN, WHATEVER THE CONTRACT OR OFFICE LEVEL LOAD LEVELS, WE ENDED UP WITH 71.
SO THE 16 GIGAWATTS IS COMPARING TO THE 2024 OR 2025 RTP AND 13 GIGAWATTS IS COMPARING TO THE 20 25, 20 24 RTP.
SO IT'S THE DELTA FROM 55.4 GIGAWATTS TO 71.9.
AND, UM, I GUESS THE OTHER QUESTION, STANDING QUESTION IS, I, I SAW THE SET OR THE THIRD PIECE WAS A 2030 IN SERVICE DATE, BUT THE REST OF IT WAS SPREAD OUT BETWEEN 2028 AND 2034.
UM, WHERE DOES THAT SIT RELATIVE TO THE LOAD RAMP THAT IS ASSUMED HERE? SO THAT I, I THINK IN, IN THE REPORT WE DID IDENTIFY THAT LIKE, YOU KNOW, IF THE LOAD SHOWS UP BEFORE THE PROJECT, ENCORE WILL WORK ON SOME CONGESTION MANAGEMENT PLAN.
SO, UM, I DON'T HAVE A, YOU KNOW, THERE'S, THERE'S A LOT OF LOAD.
SO WE, WE WILL HAVE TO WORK WITH ENCORE BASED ON WHEN THIS LOADS ARE PROJECTED TO BE IN SERVICE, AND WE WILL HAVE TO, YOU KNOW, SEE WHAT PROJECTS ARE BUILT.
SO THAT, THAT'S SOMETHING I THINK THAT'S GOING TO BE WORKED OUT.
UM, BUT WE'LL PAUSE HERE TO SEE IF
[01:20:01]
ENCORE WANTS TO COMMENT ON ANYTHING.YEAH, I WOULD JUST SAY, UH, I DON'T THINK WE HAVE VISIBILITY YET INTO THE SPECIFIC LOAD RAMPS.
UM, YOU KNOW, IT'S MY UNDERSTANDING THAT BASED ON THE CUT POINTS THAT ERCOT HAS ESTABLISHED IN THEIR COMMENTS TO THE BATCH STUDY PICKER, THAT THIS PROJECT WON'T MEET THE THRESHOLDS TO AUTOMATICALLY BECOME A VALID STUDY.
SO THE WAY I THINK THIS MOVES FORWARD, I'M HAPPY TO BE CORRECTED BY SOMEONE FROM ERCOT, BUT THE, THE PROJECTS, ASSUMING THEY MOVE FORWARD THROUGH T AND BOARD, UH, WOULD BECOME PROJECTS THAT CAN BE EVALUATED THROUGH THE BATCH STUDY PROCESS.
AND AT THAT POINT, THE RESULTS OF THAT STUDY WILL BE WHAT ALLOCATES MEGAWATTS TWO PROJECTS AND CUSTOMERS, UH, YOU KNOW, IN AN LCP TYPE CONSTRUCT, UH, WHICH IS SORT OF, I THINK YOUR LOAD RAMP QUESTION THERE.
SO THE SHORT OF IT IS, I DON'T THINK WE FULLY KNOW AS WE SIT HERE TODAY.
IT, THAT'S, IT'S GOOD TO UNDERSTAND THAT THIS IS, IS, IF I'M PARAPHRASING, IT'S THIS IS GIVING AN OPTION FOR CONSIDERATION IN THE BATCH ALLOCATION, AND THEN THAT'S REALLY WHAT WILL SET, I MEAN, I GUESS
IS THAT THE WAY TO ENCORE DIDN'T PROPOSE THIS PROJECT TO BE, YOU KNOW, UH, REVIEWED OR ALL OR UTILIZED IN THE BATCH STUDY PROCESS, PER SE.
WE SUBMITTED THIS PROJECT BEFORE THE BATCH STUDY PROCESS GOT INITIATED, BUT DUE, BUT DUE TO THE TIMING, I THINK THE EFFECT WILL BE THAT, UM, YOU KNOW, THESE PROJECTS WILL BE CONSIDERED FOR ALLOCATING MEGAWATTS IN THE BATCH STUDY PROCESS.
DOES THAT MAKE SENSE? THAT THAT DOES THAT, THAT'S, AND I'M HAPPY TO BE CORRECTED BY PROBABLY OR ANYONE ELSE IF THEY SEE IT DIFFERENTLY.
I DON'T WANNA SPEAK FOR ERCOT HERE.
YEAH, I, I THINK ONE, WE, WHEN WE DECIDE TO MOVE FORWARD WITH LIKE A, THE BATCH ZERO STUDY, ANY APPROVED PROJECTS AND TRANSMISSION SOLUTIONS, WE, WE PLAN TO CARRY OVER TO THE BATCH STUDY.
OKAY, BETH, UM, THANKS FOR, I DUG INTO THE LOAD QUESTION MYSELF, SO THANKS FOR, FOR GETTING DIGGING INTO THAT AND YOUR, YOUR RESPONSE.
UH, MARTHA, THE, MY SNAR I'LL ASK MY S SNARKY QUESTION JUST 'CAUSE I DON'T HAVE A FILTER.
YOU KNOW, AT SOME POINT IT FEELS LIKE, YOU KNOW, THE ENCORE SYSTEM WILL BE COMPLETELY REBUILT BY ALL OF THESE PROJECTS.
UM, THE, UH, THIS IS ALMOST 500 MILES OF REBUILT CIRCUITS, BUT AS YOU LOOK AT THE AGE OF THOSE CIRCUITS, AGAIN, APPRECIATE THE INFORMATION BEING GATHERED AND, AND PUT INTO THE REPORT.
THESE LINES ARE, ARE, THERE'S SOME LINES THAT ARE AS OLDER THAN I AM, WHICH MEANS THEY'RE TOO DAMN OLD TO BE IN SERVICE.
AND, UM, BUT THE AVERAGE AGE, IT'S APPROACHING 50 YEARS ON THE CIRCUITS THAT ARE GETTING REBUILT, INCREASED RATINGS ARE LIKE 150% INCREASE IN RATINGS.
SO THE, THE VOLUME, YOU KNOW, JUST FROM A VOLUME OF MORE CAPABILITY, IT'S SIGNIFICANT ACROSS A WIDE SWATH OF THE AREA IS HOW I INTERPRET THIS, THIS PROJECT.
UM, THE LARGE LOAD IMPLICATIONS OF THAT SHOULD BE THAT WE NOW, YOU KNOW, WE'RE PLANNING FOR A BIGGER SYSTEM TO BE ABLE TO HANDLE MORE STUFF AND HOW WE ALLOCATE TO THE MORE STUFF IS YET TO BE DECIDED.
UM, SO THAT'S, THAT'S THE ONLY ISSUE.
THIS IS ONE WHERE, UH, BECAUSE IT STARTED AS COMBINED 3.3 $0.1 BILLION PROJECT, WE MOVED $700 MILLION INTO A PROJECT THAT WE'VE ALREADY ENDORSED AND WE'RE NOW LEFT WITH THE $2.3 BILLION OF, OF COST.
AND THAT ALL SEEMED TO BE PRETTY STRAIGHTFORWARD AND, AND SUBSTANTIATED.
OKAY, SHANNON? YEAH, COULD WE GO TO THE MAP PAGE? I HAD A QUICK QUESTION.
I DON'T KNOW IF THIS IS ERCOT OR ENCORE WOULD BE BEST TO ADDRESS IT.
THE REBUILD OF VENUS TO NOTICE ALL MAKES SENSE.
I WAS A LITTLE SURPRISED TO SEE NO UPGRADES FROM NOTICE ON DOWN TO NAVARRO.
AND THE REASON I'M A LITTLE SURPRISED BY THAT IS WE SEE THAT FOR, UM, IT'S A BINDING CONSTRAINT OVER ON, UH, LOAD INTERCONNECTIONS WE'RE TRYING TO DO ON THE BRAAS SYSTEM.
AND IT'S, IT'S, IT'S AN OLD 10 72 RATING WHEN THE, ALL THE REST OF THE FROM NOTICE TO VENUS IS, YOU KNOW, SOON TO BE 5,000 AMP CONDUCTOR.
IT SEEMS SURPRISING NOT TO HAVE TAKEN THAT ALL THE WAY BACK TO THE NAVARRO SWITCHING STATION.
ANY COMMENTS FROM ERCOT OR ENCORE ON THAT?
[01:25:02]
GO AHEAD.I'LL, I'LL, I'LL DEFER TO ENCORE.
MARTHA, DO YOU WANT YEAH, THIS IS
UM, WHAT WE PROPOSED IN THIS RRP G IS PURELY WHAT WAS IDENTIFIED IN 2024 R TP AND IN THAT CASE THAT NOTICE TO NOVEMBER LINE WAS NOT IN IT.
SO WE'LL CONTINUE TO LOOK AT THIS TRANSMISSION LINE AND PROPOSE A SEPARATE PROJECT AS NEEDED, BUT THE IDEA BEHIND THIS RPG WAS JUST TAKE WHAT'S IN THE 24 RTP AND PROPOSE THAT.
OKAY, ANY OTHER QUESTIONS OR COMMENTS FOR ERCOT OR ENCORE BU ANYTHING ELSE ON THIS PRESENTATION? NOPE, I AM GOOD TO, OKAY.
THIS IS OUR THIRD PROJECT, UH, LOOKING TO ENDORSE THE COMBINED 25 R PG OH 40 ONCOURSE AT ONE NORTH AND CENTRAL TEXAS RELIABILITY PROJECT AND 25 R PG OH 42 ON CORSET TWO NORTH AND CENTRAL TEXAS RELIABILITY PROJECT GROUP TWO AND GROUP THREE UPGRADES.
CAN WE PUT THIS ON THE COMBO BALLOT OR ARE WE DOING THE, THE BILLION DOLLAR SEPARATE BALLOT RULE, OR DO WE HAVE ANYONE THAT WANTS TO ABSTAIN? I THINK COMBO MAKES SENSE BECAUSE THIS IS LARGELY, CAN YOU SAY THAT INTO THE MIC? I THINK COMBO MAKES SENSE BECAUSE THIS IS LARGELY PREVIOUSLY PLANNED SPEND.
IT'S NOT INCREMENTAL TO THIS CONVERSATION COMBO THUMBS UP AS LONG AS WE RECOGNIZE IT.
YEAH, I THINK, I THINK WE CAN HAVE THOSE CON THOSE CONVERSATIONS.
UM, BETH, YOU KNOW, I, I THINK WE, WE'VE, I'VE, MARTHA AND I, WHEN WE TALKED TO THE BOARD, UM, YOU KNOW, TRY, TRY TO POINT OUT THE QUANTITY AND QUALITY MEAN MEANING AMOUNT OF PROJECTS THAT ARE COMING THROUGH RPG THAT WE'RE DISCUSSING ATTACK VERSUS BEFORE.
UM, AND I, I THINK, YOU KNOW, YOU'VE, YOU'VE RAISED AWARENESS, WHICH IS GOOD, AND, AND PRABU, I THINK HAS, HAS RAISED AWARENESS TOO THROUGH THE, THE NEW PROCESS.
AND I, I KNOW THAT GROUP IS REALLY BUSY.
I WAS SORT OF AMAZED AND IMPRESSED THAT THEY ACTUALLY DID POST THE, THE PROJECT SO WE CAN ADVANCE.
SO I, I THINK WE ARE, WE ARE DOING, YOU KNOW, WHAT, WHAT WE CAN TO MAKE SURE PEOPLE KNOW THESE ARE BILLIONS OF DOLLARS AND, AND WE'RE SPENDING THE REQUISITE TIME.
UM, BUT I THINK THAT'S A CONVERSATION WE SHOULD CONTINUE TO HAVE OF THE ONLY ISSUE I HAVE IS, AND, AND, BUT COREY SAID IT, I MEAN, THE VOTE IS A VOTE.
UM, BUT THERE'S A LOT OF, YOU KNOW, APPROVING THE MINUTES HAS A LITTLE DIFFERENT IN IMPLICATIONS THAN ENDORSING A $2.3 BILLION PROJECT.
AND I, YOU KNOW, I THINK THE TIME AND EFFORT TO HAVE A SEPARATE BALLOT ON A REALLY EXPENSIVE, REALLY IMPORTANT THING THAT TOOK UP SOME TIME AND THAT WE DELIBERATED ON, UM, IS, IS WORTHWHILE.
BUT I'M, I, YOU KNOW, I'M HAPPY TO BE THE, THE VOICE IN THE WILDERNESS.
WELL, MAYBE, MAYBE NOT THIS TIME BECAUSE WE DIDN'T PREPARE FOR IT, BUT MAYBE IN FUTURE MEETINGS WE DO TAKE UP A RPG BALLOT OR SOMETHING SEPARATELY FROM THE BALLOT THAT HAS THE MINUTES.
UM, BUT FOR NOW, CAN WE PUT THIS PROJECT ON THE COMBO BALLOT? YES.
SO LET'S PUT THIS ON THE COMBO BALLOT.
UM, AND LET'S MOVE ON TO OUR, OUR FOURTH PROJECT, WHICH IS A ENCORE PROJECT AS WELL.
SO SAME, SAME ORDER, UH, BU ENCORE, IF THEY HAVE ANYTHING BEFORE.
UM, ANY OTHER QUESTIONS IN, IN THE ROOM OR ON THE PHONE? OKAY, THANK YOU.
UH, THE NEXT ONE IS THE ENCORE COMBINED SET ONE NORTH, CENTRAL AND SOUTH CENTRAL TEXAS RELIABILITY PROJECT AND THE ENCORE SET TO NORTH CENTRAL AND SOUTH CENTRAL TEXAS RELIABILITY PROJECT.
UM, THIS, OKAY, AGAIN, UM, JUST BEFORE I START, THIS IS, THIS IS SIMILAR TO THE PREVIOUS PROJECT, THE APPROACH, THE STUDY APPROACH.
UM, THERE'LL BE LIKE DIFFERENT GROUPS OF PROJECTS.
SO I'LL WALK THROUGH SOME OF THE THINGS.
THIS, THIS SET OF PROJECTS ARE COMING FROM THE 2024 AND 2025 RTP, SIMILAR TO THE PREVIOUS PROJECT.
UM, INITIALLY ONCORE SUBMITTAL, THERE IS, UH, 2, 2, 2 PROJECTS THAT THE SET ONE PROJECTS, THE ESTIMATED COST IS $943 MILLION
[01:30:02]
AND WILL REQUIRE CCN.AND THE SET TWO PROJECTS IS FOUR $40.79 MILLION.
AND THAT WOULD ALSO REQUIRE CCN.
SO AGAIN, THIS IS ALSO ADDRESSING VARIOUS ISSUES IDENTIFIED IN THE 20 24 1 25 RTP, UH, PRIMARILY IN THE NORTH CENTRAL, SOUTH CENTRAL, AND THE EAST WEATHER ZONES.
AGAIN, ERCOT DECIDED TO DO A SINGLE, UH, COMBINED RPG REVIEW FOR THESE TWO SET OF PROJECTS.
THE, THE, THE STUDY AREAS ARE SIMILAR TO WHAT WE TALKED IN THE PREVIOUS.
I'M NOT GONNA SPEND A LOT OF TIME THOUGH AGAIN, THE NEED OF THOSE PROJECTS ARE EITHER, UH, SET ONE PROJECTS OR BOTH 2024 AND 2025.
AND, YOU KNOW, SUBSTANTIVE, THE PROJECTS WERE ALSO INCLUDED IN 2025.
UM, AGAIN, WHEN YOU LOOK AT ALL THE LOADS, THAT'S PART OF THE ERCOT INDEPENDENT REVIEW.
UM, WE LOOKED AT THE NUMBERS HERE, SO AGAIN, IT'S A LITTLE BIT HIGHER.
THE, THE, THE DIFFERENT WEATHER ZONES LISTED HERE.
AS YOU COULD SEE, THE COMPARISON BETWEEN THE 20 24, 20 25 AND THE ERCOT INDEPENDENT REVIEW, ERCOT INDEPENDENT REVIEW NUMBERS WERE SIGNIFICANTLY HIGHER.
UM, BASICALLY IT WAS, UM, 18 GIGAWATTS HIGHER THAN WHAT'S IN THE 2020 OR, OR 2024 RTP AND 19 GIGAWATTS HIGHER THAN WHAT WAS IN THE 2025 RTP.
SO, UH, SIMILAR TO THE LAST PROJECT HERE, WE GROUPED THE PROJECTS INTO 3D THREE DIFFERENT BUCKETS.
ONE OF THE GROUP ONE IS SOMETHING YOU ALREADY HEARD TODAY, IT'S PART OF THE MUSCOVY WAS LAKE PROJECT.
UH, THERE IS A PORTION OF THE PROJECT THAT WAS MOVED TO THAT INDEPENDENT REVIEW, WHICH WAS MORE RELEVANT TO STUDY THERE.
AND WHAT WE ARE TALKING HERE IS, UH, THE GROUP TWO AND GROUP THREE PROJECTS.
OKAY, SO THE, AGAIN, THE GROUP TWO IS SET UP PROJECTS THAT WAS, UM, BASED ON THE NEED IDENTIFIED IN EITHER 2024 AND 2024 RTP.
SO WE DID AN EVALUATION OF COMPARING THE LOADS THAT WAS STUDIED IN 20 24, 20 25, AND THE, AND THE ERCOT INDEPENDENT FORECAST AND LOOK AT THE RELIABILITY NEEDS IN THE STUDY AREA.
AND WE CONFIRM, YOU KNOW, THE PROJECTIONS ARE MUCH HIGHER THAN WHAT WAS STUDIED IN EITHER 2024 OR 2025.
AND ALL THIS PROJECTS GROUPED AS GROUPED THREE GROUP TWO SET OF PROJECTS WILL BE ENDORSED BASED ON THE NEEDS IDENTIFIED IN 2024 AND 2025, AND THE REVIEW OF THE ERCOT INDEPENDENT, UH, REVIEW LOAD LEVELS.
OKAY, UH, GROUP THREE, GROUP THREE IS, UH, ERCOT IS CONDUCTING A REVIEW FOR THE UPGRADES OF THE, THE PROJECT SUBMITTED BY TEAM.
THIS IS EXPECTED TO BE COMPLETED IN THE, SO BASICALLY THIS PROJECT WE ARE, WE'RE NOT THERE TO MAKE THE RECOMMENDATION ON THE GROUP THREE.
SO THERE IS A SET OF PROJECTS THAT'S GOING THROUGH THE NORMAL OR THE ERCOT INDEPENDENT REVIEW DUE TO COMMON SUBMITTED BY TSPS OR OTHER COMPETING PROJECTS.
THAT OPTIONS, WE ARE LOOKING, SO WE'RE NOT MAKING A RECOMMENDATION ON THE GROUP THREE TODAY.
UH, NO IMPACT ON SSO ON THE GROUP TWO PROJECTS.
AND AGAIN, WE DID NOT SEE ANY ISSUES RELATED TO CONGESTION OR, UH, WE DID NOT SEE ANY ADVERSE IMPACT WITH THE SSR OR FUTURE GENERATION SCREENINGS.
SO HERE'S THE SUMMARY OF THE GROUP THROUGH GROUP TWO UPGRADES.
UM, BASICALLY THIS IS CONSTRUCTING NEW, UH, 3 45 KB LINE.
WHAT WOULD REQUIRE APPROXIMATELY 14 MILES OF NEW RIGHT OF WAY RE REBUILD 67 MILES OF EXISTING 1 38 KV AND REBUILD 2 3 45 1 38 KV STATION AND UPGRADE 1 3 45 1 38 KV STATION.
I THINK THAT THE ESTIMATED COST FOR ALL THIS UPGRADES IS $381 MILLION.
AGAIN, THERE ARE SEVERAL PARTS OF THE PROJECT, UH, THAT'S LISTED IN THE APPENDIX.
SO, UH, DEPENDING ON THE, THE, WHICH, DEPENDING ON THE, ON THE UPGRADES, THE ESTIMATED IN-SERVICE DATE IS 20, ANY TIME BETWEEN 2028 AND 20 20 34.
OBVIOUSLY THERE IS A PORTION OF THE PROJECT THAT WILL REQUIRE CCN FOR THE 14 MILES OF NEW RIGHT OF WAY OF 3 45 KV.
I BELIEVE THAT'S THE LAST SLIDE HERE.
I WILL, I'LL PAUSE WITH, UM, THE RECOMMENDATION AND OVERVIEW OF LIKE THE PROJECTED NEW ONE OR 3 45 KV LINE, 14 MILES PLUS THE HIGHLIGHT HIGHLIGHTED LINES OR UPGRADES OF EITHER 3 45 OR 1 38 KV REBUILDS.
READY FOR QUESTIONS? THANK YOU.
[01:35:01]
OKAY.YOU WANNA ADD ENCORE ANYTHING BEFORE QUESTIONS? NOPE.
SO $381 MILLION AND THIS SUPPORTS AN ADDITIONAL 19 GIGAWATTS IN ADDITION TO WHAT WAS, UH, STUDY PREVIOUSLY.
SO THAT'S, I NEED TO BE CAREFUL THERE BECAUSE WHAT WE SAW IS WE DID A COMPARISON BETWEEN 20 24, 20 25, AND THE PROJECTED LOAD IS 19 GIGAWATTS, 18 OR 19 GIGAWATTS GREATER THAN THAT.
THIS PROJECT SET OF PROJECTS DOESN'T ADDRESS ALL THE NEEDS OF THE 19 GIGAWATTS.
SO WHAT WE ARE SAYING IS, YES, WE NEED THIS PROJECTS, THIS SET OF PROJECTS THAT'S COMING OUT OF 20 24, 20 25.
IN ORDER TO ADDRESS ALL THOSE 19 GIGAWATTS OR 18 GIGAWATTS, WE WILL NEED ADDITIONAL UPGRADES ON TOP OF THIS.
SO THIS IS THE AMMO BUSH? YES.
AM I WOULD HOPE IT, I HOPE IT'S A LARGER, UH, LARGER ENTREE THAN THAT, BUT YEAH, MR. JOKE, NUD, IT WAS A, IT WAS A, A SNACK JOKE.
I'M STARTING TO THINK ABOUT LUNCH.
OH MAN, WE GOT A LONG WAY BEFORE LUNCH.
ALRIGHT, BETH, UH, SAME, SAME QUESTION.
THAT NED RAISED THE, THE, THE SAME ISSUE AND JUST POINTING OUT THAT THERE'S, GIVEN THE MAGNITUDE OF DOLLARS IN THE INITIAL SUBMITTAL, THE, A BIG SLUG OF IT, HALF OF IT GOT SLID OVER TO THE MUSKOGEE VOSS LAKE PROJECT THAT WE ALREADY ENDORSED.
LEAVES HALF OF THE, YOU KNOW, HALF OF IT, A QUARTER OF WHICH IS REFLECTED IN THIS PROJECT.
AND SO THERE'S ANOTHER 400 MILLION PLUS OR MINUS YEAH.
THAT IS STILL OF PROJECTS THAT ARE STILL UNDER REVIEW AND THAT WILL COME BACK IN SOME OTHER FORM.
BE IS HOW I WOULD, I WOULD DESCRIBE IT.
I'M, I'M OKAY WITH THIS ON THE COMBO.
YOU'RE OKAY WITH THIS ON THE COMBO BALLOT BECAUSE IT'S LESS THAN A BILLION.
AND THE CRITERIA OF THESE ARE ALL, YOU KNOW, RTP PROJECTS COMING THROUGH THE RPG PROJECTS, UH, AS PROJECTS.
SO THESE WERE ALL PROJECTS, THESE WERE ALL THE R TRANSMISSION PROJECTS IDENTIFIED AS PART OF THE REGIONAL TRANSMISSION PLANNING PROCESS AND CONFIRMED.
I THINK WE'RE, WE'RE ALL GONNA HAVE TO ADJUST OUR WAY OF THINKING MAYBE AFTER BATCH, BUT, WE'LL, DO YOU WANT A SEPARATE BALLOT, JEN? NO, NO, I JUST WANTED TO EMPHASIZE THAT THAT'S ALSO WHERE I FIND MYSELF IS HOW THIS INTERSECTS WITH THE BATCH STUDY IS THE PART WHERE I HAVE HESITANCY TO MAKE SURE THAT RESIDENTIAL AND SMALL COMMERCIAL CUSTOMERS DON'T END UP FOOTING THESE BILLS.
AND SO LIKE THAT CONVERSATION WILL HAPPEN.
IT'S NOT HAPPENING HERE RIGHT NOW.
UM, SO WE WOULD BE LOOKING TO ENDORSE THE COMBINED 25 RPG OH 41 ON COURSE AT ONE NORTH CENTRAL AND SOUTH CENTRAL TEXAS RELIABILITY PROJECT AND 25 RPG OH 43 ON COURSE AT TWO NORTH CENTRAL AND SOUTH CENTRAL TEXAS RELIABILITY PROJECT GROUP TWO UPGRADES, AND WE CAN PUT THIS ON THE COMBO BALLOT.
SO WE ARE ONTO OUR LAST RPG PROJECT.
UH, THIS IS LCRA AND CENTERPOINT, SO THANK YOU ENCORE.
UM, SO WE'LL DO THE SAME THING BU EL AND CENTERPOINT IF YOU WANT TO ADD ANYTHING BEFORE QUESTIONS.
AND THEN WE'LL DO NED BETH, UH, AND THEN OPEN IT UP TO QUESTIONS IN THE ROOM AND ON.
I'LL SAY, I DON'T HAVE ANY QUESTIONS ON YOU, DON'T HAVE ANY QUESTIONS ON THIS ONE.
NED, WILL YOU HAVE THE SAME QUESTION ON THIS ONE? TPD? YES, MAYBE NO.
SO THIS IS THE LAST PROJECT, THE LCRA AND CENTER POINT, UH, EUCLID, UH, 7 65 KVS TRANS SUBSTATION AND TRANSMISSION LINE EDITION PROJECT.
THE OVERVIEW ON THIS PROJECT, UH, LCRA AND CENTERPOINT JOINTLY SUBMITTED THIS PROJECT TO ADD THIS EUCLID 7 65 KV SUBSTATION AND TRANSMISSION LINE EDITION AND BACK IN JANUARY, 2026.
UH, THIS IS, UM, A TIER ONE PROJECT WITH AN ESTIMATED COST OF, UM, $1.831 BILLION.
[01:40:01]
UH, THE PRIMARY NEED OF THIS PROJECT IS COMING FROM 2025 RTP TO ADDRESS THE RELIABILITY NEEDS AND GROWTH IN THE CENTRAL TEXAS AREA AS A MAP, WHICH SHOWS, UH, WHAT CAME OUT OF THE 2025 RTP.SO MOVING ON THE PROJECT NEED AGAIN, UH, THE 2025 RTP DEVELOPED THE, WHAT WE CALL THE STEP PLAN.
AND WE, WHEN WE LOOKED AT THIS PLAN, WE DID IDENTIFY ADDITIONAL EXPANSIONS TO THE 7 65 KV.
AND, UH, THIS PORTION OF THIS, THE EUCLID STATION PLUS A NEW LINE FROM EUCLID TO HILL G IS ONE OF THE THINGS THAT'S COMING OUT OF THE 2024 RTP.
AGAIN, THE LOAD LEVELS, UH, FOR THIS PROJECT, UH, WE USE SIMILAR LOAD LOAD FOR EAST NORTH, CENTRAL AND SOUTH CENTRAL WEATHER ZONE.
UH, THIS TABLE REFLECTS THE SAME COMPARISON I SHOWED IN THE PREVIOUS, UM, STUDY, UH, THE, THE PROJECT AREA SIMILAR TO WHAT WE STUDIED IN THE PREVIOUS ONES.
SO, UH, FOR THIS STUDY, YOU KNOW, OBVIOUSLY THIS IS RELYING ON 2025 R-T-P-R-T-P DID, UH, WELL IN AS PART OF THE 2024 RTP, WE DID AN EXTENSIVE ANALYSIS ON THE 7 65 KV, UH, STEP PLAN PLUS ADDITIONAL NEED.
UM, ONE OF THE SECTIONS THAT WERE BASED ON THE JUST OR THE LOAD FORECAST IN 2025, WE DID IDENTIFY THE NEED FOR THE EUCLID STATION AND THE SUBSEQUENT TRANSMISSION 7 65 KV ADDITION TO THE STEP PLAN, UM, THAT WE DID HAVE SEVERAL DISCUSSIONS, STAKEHOLDER DISCUSSIONS THROUGH RPG.
UM, AS A C EFFECT OF THIS EFFORTS, ORCA HAS PROPOSED THIS, UH, EUCLID 7 65 KV STATION AND THE TRANSMISSION LINE EDITION OF, BASED ON THE 2024 RTP STUDY.
UM, THIS IS A SIGNIFICANT PROJECT.
SO AGAIN, UH, SSO SCREENING, WE DID PERFORM THE SSO SCREENING FOR THE 7 65 KV SUBSTATION EDITION AND TRANSMISSION EDITION.
WE DID NOT SEE ANY SSO IMPACT, UH, TO THE EXISTING OR THE PLANT GENERATION IN THE AREA.
SO I, UH, THIS WAS A SIGNIFICANT PROJECT.
SO WE DID LOOK AT THE DYNAMIC STABILITY ANALYSIS.
UM, BASICALLY WE LOOKED AT, UH, THE, THE SELECTED, UH, LIMITED CONTINGENCY ANALYSIS IN THE STUDY AREA AND ALSO LOOKED AT, YOU KNOW, THE IMPACT OF EXISTING STABILITY.
SO, UM, BASED ON THIS ANALYSIS, UM, WE DON'T SEE ANY ISSUES WITH ADDING THIS LG 7 65 KV LINE.
UM, AND WE DO NOT, AT THIS POINT, WE DO, WE DO NOT SEE AN IMPACT ON THE WEST STABILITY LIMIT, UH, THAT WAS IDENTIFIED IN THE PREVIOUS STUDY, WHICH IS THE 7 65 KV STEP PLAN STUDY.
SIMILARLY, WE DID, UH, PERFORM THIS, UH, SENSITIVITY FOR CONGESTION ANALYSIS AND SENSITIVITY ANALYSIS.
UM, SO, UH, BASED ON THE CONGESTION ANALYSIS, WE DID IDENTIFY AN ADDITIONAL CONGESTION IN THE STUDY AREA.
UM, BUT AS PART OF THE TYPICAL PLANNING ANALYSIS, WE WILL START EVALUATING THOSE CONGESTION IN THE SUBSEQUENT PLANNING STUDIES, UH, SEE WHETHER, YOU KNOW, IT MAKES ECONOMICAL OR IT, IT JUSTIFIES AN ECONOMIC PROJECT TO RELIEVE THOSE CONGESTION BECAUSE THIS IS MORE RELATED TO THE DY FOR THE RELIABILITY ANALYSIS.
UM, NO IMPACT ON FUTURE GENERATION STUDY.
UM, THIS IS THE GENERATION SENSITIVITY.
UM, UM, I THINK, UM, SO WE DO NOT DO A LOAD SCALING BECAUSE WE, WE DON'T DO THIS LIKE, YOU KNOW, WE DON'T BREAK THE STUDY AREAS BY DIFFERENT ZONES.
SO WE HAVE LIKE ONE COMPREHENSIVE MODEL WE USE FOR PLANNING.
AGAIN, SUMMARY OF THE PROJECT, UH, THIS WOULD ADD A NEW 131 MILES OF NEW 7 65 KB LINES, SINGLE CIRCUIT LINE, UM, BETWEEN EUCLID AND LG.
UH, AS PART OF THIS, BUILD THIS NEW STATION, UH, 7 65 KV STATION AND ADD NEW 7 65 KV TRANSFORMERS, AS WELL AS LOOP EXISTING 3 45 KV LINES INTO THIS NEW 7 65 KV STATION.
AND AS PART OF THIS, UH, WE NEED TO UPGRADE SOME EXISTING THREE 40 V KB STATIONS, UM, TO BE COMPATIBLE WITH THE 7 65.
SO WE'RE INCREASING THE BREAKER RATINGS, 80 KA AND AS I SAID, THERE ARE TWO NEW, APPROXIMATELY TWO MILES OF LINES THAT WERE LOOPED INTO THE NEW 7 65 KB STATION.
SO BASED ON THE REVIEW, ERCOT WILL RECOMMEND THE BOARD ENDORSE THE INCLUDE 7 65 KV STOP STATION AND THE TRANSMISSION LINE EDITION PROJECT AS IDENTIFIED UNDER 2024 RTP TO ADDRESS THE
[01:45:02]
LOAD GROWTH IN ESPECIALLY THE CENTRAL TEXAS AREA.UH, THE EXPECTED IN-SERVICE DATE IS JUNE 30TH, 2031.
AND OF COURSE, THE ESTIMATED IN ESTIMATED COST IS 1.831 BILLION, AND THIS LINE WILL REQUIRE A CCN.
IT'S 131 MILES OF, UH, NEW TRANSMISSION LINE, UM, BUILT JOINTLY BY YES, UM, LCRA AND CENTERPOINT.
UH, AGAIN, THESE ARE THE, THIS IS THE RECOMMENDATION, THE RATINGS OF THE NEW TRANSMISSION LINE.
UH, ONE MORE THING TO ADD IS, YEAH, THERE, THERE WILL BE LIKE REQUIREMENTS TO ADD, LIKE ADDITIONAL REACTORS TO SUPPORT THE VOLTAGE FOR THE LINE AND OPERATIONS.
SO THAT WILL BE DETERMINED AS, UH, WE AS THE TSPS PERFORM THEIR OWN STUDIES AND, YOU KNOW, MAKE THOSE DESIGN RECOMMENDATIONS.
SO HERE'S, HERE'S THE BREAKDOWN.
UM, THE LIKE 131 MILES, LIKE SPLIT BETWEEN LCRA AND CENTER POINT.
AND, UH, YEAH, I'LL PAUSE HERE.
BETH, LET'S START WITH, UH, NED AND THE LOAD NUMBERS.
YEAH, SO I'M GUESSING SINCE THIS IS A 7 65, THERE'S NOT A DIRECT, UH, YOU KNOW, NOT AS MUCH OF A DIRECT LINK TO ANY PARTICULAR LOADS.
IT'S LOOKING MORE AT THE AGGREGATE AND IT LOOKED LIKE IT WAS THE SAME 19 GIGAWATTS THAT WE WERE TALKING ABOUT PREVIOUSLY.
SO WHEN WE'RE THINKING ABOUT THAT LOAD GROWTH, IT'S, IT'S THIS PLUS THE PROJECT WE JUST LOOKED AT AND PROBABLY OTHER STUFF THAT'S ALL SERVING THAT SAME LOAD GROWTH.
IS THAT THE FAIR TAKEAWAY? YES.
THERE, THERE IS NOT, YOU KNOW, PARTICULAR LOAD THAT'S DRIVING, BUT IT'S THE AGGREGATE OF ALL THE LOADS IN THE CENTER TEXAS, ESPECIALLY IN THE, IN THE LCRA FOOTPRINT THAT'S, UH, DRIVING THE NEED FOR THE PROJECT, I THINK.
AND CERTAINLY AS WE GET MORE OF THESE COMING THROUGH, UH, I'LL JUST ECHO THE COMMENTS YOU SAID PREVIOUSLY AND, AND I THINK BETH AND, AND MARK HAVE, HAVE ECHOED IS, YOU KNOW, HAVING MORE, MORE TRANSPARENCY OF THAT AND KINDA LINING THOSE UP WILL BE REALLY HELPFUL TO US.
AND I THINK IT'S ALL IN SERVICE OF THE SAME THING JEN FLAGGED IS MAKING SURE THE COST IS, UH, ALLOCATED APPROPRIATELY.
OKAY, WE'LL DO BETH AND UH, JEN THEN EVAN, I INITIALLY WASN'T GONNA SAY ANYTHING 'CAUSE I DON'T HAVE ANYTHING UNIQUE ABOUT THIS PROJECT COMPARED TO ANY OF THE OTHER 7 65 PROJECTS GOING FORWARD, AND THEY'RE GONNA GET THEIR OWN SORT OF OVERALL SCRUTINY, I ASSUME.
UM, WHAT I'M STRUCK WITH BY THE CUMULATIVE DISCUSSION THAT WE'VE HAD ON ALL OF THESE PROJECTS IS HOW IMPORTANT THE REGIONAL TRANSMISSION PLANNING PROCESS IS FOR IDENTIFYING THE NEW PROJECTS NEEDED THAT THEN APPEAR MANIFEST AS REGIONAL PLANNING GROUP PROJECTS.
SO I JUST WANTED TO HIGHLIGHT AND EMPHASIZE THAT POINT.
UM, I'M VERY EXCITED ABOUT NEW 7 65 SPECIFICALLY HOOKING INTO EXISTING 7 65.
SO I WANT US TO ALL JUST LIKE TAKE A MOMENT TO BE EXCITED ABOUT THE NEW GRID THAT WE WILL HAVE.
OKAY, EVAN, I'M VERY EXCITED FOR THE NEW GRID.
UM, OKAY, BUT I DO HAVE A QUESTION.
UM, SO NOTABLY THIS RPG WAS SUBMITTED IN JANUARY OF THIS YEAR AFTER THE DECEMBER 15TH DATE OUTLINED IN PICKER 1 45.
AND SO I KNOW WE JUST TALKED ABOUT SOME OF THE ENCORE PROJECTS ABOUT HOW THAT, UM, ASSUMING WILL ALLOW SOME OF THOSE LARGE LOADS DRIVING THAT TO GET INTO BATCH ZEROS ALLOCATED.
I WOULD JUST TAKE IT THAT NONE OF THE LARGE LOADS JUSTIFYING THIS TRANSMISSION UPGRADE WOULD THEN MEET THAT CRITERIA TO BE INCLUDED IN BATCH ZERO.
IS THAT CORRECT? YEAH, I, I THINK THAT'S, UH, THAT'S, UH, YOU KNOW, I, I WILL, I'LL, I'LL LET THE, YOU KNOW, BA BATCH DISPATCH ZERO DISCUSSIONS TO HAPPEN SEPARATE FROM THIS.
I DON'T, I DON'T KNOW IF YOU HAVE ANYBODY TO COMMENT ON THAT AG DO YOU WANT, I I DON'T WANT TO PUT YOU ON THE SPOT, BUT I THINK THAT NO, NO PROBLEM.
AND, AND WE WILL, I THINK, ADDRESS THIS MORE THIS AFTERNOON, BUT EVAN, COULD YOU JUST REPEAT THE QUESTION PLEASE? YEAH, I'M JUST, YOU KNOW, WE JUST TALKED ABOUT THE OTHER RPGS THAT WERE SUBMITTED PRIOR TO DECEMBER 15TH CUTOFF IN FIGURE 1 45, AND I THINK WE CONFIRMED THAT THE LARGE LOADS DRIVING THE TRANSMISSION FOR THOSE UPGRADES WOULD BE INCLUDED IN BATCH ZERO, BUT NOTABLY THIS ONE WAS SUBMITTED AFTER DECEMBER 15TH.
AND SO I JUST WANNA CONFIRM THAT THE LARGE LOADS DRIVING THIS WOULD NOT BE INCLUDED IN BATCH ZERO
[01:50:01]
IF NOT QUALIFYING VIA ANOTHER PATHWAY, CORRECT? YEAH, THE, UH, INCLUSION IN AN RPG SUBMITTED AFTER DECEMBER 15TH, UH, IS NOT A VIABLE PATH, UH, UNDER THE CURRENT DRAFT LANGUAGE.AND I, I DON'T KNOW IF IT WAS SAID, BUT DO WE HAVE A ESTIMATE FOR HOW MANY LARGE LOADS WOULD NOT BE THEN INCLUDED? I DON'T HAVE THAT NUMBER, UM, BUT I WILL, I'M JUST LOOKING AT SOMEBODY HERE, BUT I DON'T THINK, UH, WE HAVE THAT INFORMATION.
SHANNON, KIND OF FOLLOWING ON EVAN'S QUESTION, YOU KNOW, WITH THE ENCORE PROJECTS, WE, Y'ALL WILL BE APPROVING THOSE AND THEN THAT TRANSMISSION WILL GO INTO THE BATCH ZERO ALONG WITH THE LOADS IS ALLOCATED.
SO THEN YOU'VE, YOU'VE AT LEAST GOT SOMEBODY PAYING FOR IT.
THE QUESTION I WOULD HAVE HERE IS IF YOU DON'T LET THE LOADS COME IN TO BATCH ZERO ALLOCATED, BUT SEPARATELY APPROVE THE TRANSMISSION, YOU'VE GOT A DISCONNECT.
LIKE, WHO PAYS FOR THIS? AND SO YOU NEED TO HAVE THE LOADS COMING COME IN ALONG WITH IT IN ORDER TO BE ABLE TO HAVE THE PEOPLE PAYING FOR IT THAT IT WILL SERVE.
YEAH, BUT, BUT SHANNON, THERE AREN'T ANY LOADS HANGING OFF THE 7 65 SYSTEM.
AND SO THAT, UH, YOUR, YOUR POINT BREAKS DOWN AT THAT LEVEL BECAUSE YOU GOTTA BUILD OUT ALL, WHICH IS PART OF THE OTHER RPG ENCORE PROJECTS IS BUILDING OUT ALL THAT UNDERLAYMENT, REBUILDING AND REBUILDING THAT UNDERLAYMENT THAT GETS IT DOWN TO SERVING LOADS.
BETH, THERE IS ACTUALLY A LOT OF LOAD OVER AT THE LCRA INTO THIS.
UM, JIM LEE, CENTER POINT ENERGY, JUST PROBABLY MAYBE, UM, THIS MAY HELP, BUT, UM, THE EUCLID 7 65 PROJECT, I THINK WAS ROOTED IN THE 2025 RTP, AND SO IT'S SIMILAR TO THE EASTERN BACKBONE.
THERE'S NOT A LIST OF LARGE LOAD PROJECTS IN IN THAT RT.
I MEAN, IT IT'S BASED ON THE RDB, SO IT'S, IT'S NOT THE SAME AS WHAT THE TWO ENCORE PROJECTS THAT WE JUST SAW THIS, THIS WAS VERY MUCH MORE CLOSELY ALIGNED TO THE 7 65 STEP EASTERN BACKBONE PROJECT, WHICH WAS ROOTED IN AN RT P.
SO JUST WANTED TO ADD THAT THAT'S CORRECT FOR THE LARGE LEVEL QUESTIONS, TRAVIS? OKAY.
ANY OTHER QUESTIONS OR COMMENTS? LCRA WANNA ADD ANYTHING? NO.
SO WE WOULD BE LOOKING TO ENDORSE THE 26 RPG 0 0 1 L-C-R-A-T-S-C AND, UH, CENTER POINT HOUSTON EUCLID 7 65 SUBSTATION AND TRANSFORMATION TRANSMISSION LINE ADDITION PROJECT IS IDENTIFIED IN THE 2025 RTP.
THIS IS A COMBO BALLOT ITEM? YES.
LET'S ADD THIS TO THE COMBO BALLOT.
FIRST OF ALL, I, I LIKE QUESTIONS.
I LIKE THAT WE ASK QUESTIONS AND THINK THEY'RE A GOOD THING, BUT I DID WANT TO GET SOME CLARITY ON THE NEW RPG COMMENT PROCEDURE, MAYBE FROM BU AND FROM YOU, CAITLIN.
HOW, HOW SHOULD WE APPROACH THIS FOR NEXT T WHEN THIS COMES UP? IS THERE A DEADLINE FOR QUESTIONS SUBMITTAL, OR, UM, HOW, HOW SHOULD WE APPROACH THAT? SO I BELIEVE THE PROCESS IS BU'S GROUP WILL POST THE PRESENTATION SEVEN DAYS AHEAD, AND THEN QUESTIONS THAT THEY RECEIVE WITHIN TWO BUSINESS DAYS, THEY CAN THEN POST.
I THINK WE WANT TO ENCOURAGE THAT SO THAT SUBJECT MATTER EXPERTS CAN BE PREPARED.
WE ARE NEVER GONNA PRECLUDE QUESTIONS, YOU KNOW, AT, AT THE TABLE OR, OR ONLINE ATTACK, BUT I THINK THAT IS, YOU KNOW, IN, IN SOME OF THESE CASES WE'RE GETTING THE SAME QUESTION OVER AND OVER.
AND SO IF ERCOT CAN SORT OF BETTER INFORM THEIR PRESENTATION AND, AND YOUR SUBJECT MATTER EXPERTS CAN BE BETTER PREPARED, I THINK WE WANT TO DO THAT.
BUT I, WE'RE, WE'RE NOT GONNA PRECLUDE LATER QUESTIONS OR, OR QUESTIONS AT THE, THE TABLE.
AND I AGREE WITH THAT APPROACH.
[01:55:02]
FOR KIND OF NEXT TIME IS, UH, ROBERT SUBMITTED, LIKE NOTICE ABOUT THE PROJECTS AND THAT SCHEDULE YOU LAID OUT TO THE RPG EXPLODER LIST.I THINK MAYBE ALSO INCLUDING TAC MEMBERS ON THAT LIST AS WELL, UH, OR THE TAC EXPLODER WOULD PROBABLY GIVE GREATER NOTICE AND ENCOURAGE EARLIER QUESTIONS.
CURIOUS ABOUT THOUGHTS THERE? I THINK THAT'S PROBABLY RIGHT BE, YOU KNOW, I, I HEARD THAT BETH HAD QUESTIONS, BUT I DIDN'T GET TO SEE THEM MYSELF BECAUSE I DON'T, I DON'T THINK I'M ON THE RPG EXPLORER.
THEY WENT TO RPG, SO, SO I THINK HAVING THOSE GO TO TAC IF THEY'RE QUESTIONS FOR TAC IS MAKES SENSE.
WE CAN DO THAT, RIGHT ANNE? YEAH, ANYONE CAN SEND, I'D ALSO REITERATE MY EARLIER REQUESTS THAT ERCOT INCLUDE, NOT THAT WE'RE GONNA REVIEW THE, NOT THAT IN THE MEETING WE NEED TO REVIEW THE 25 PAGE DOCUMENTS FOR ALL OF THESE, BUT I THINK AS PART OF TAC MATERIALS, WE SHOULD HAVE THE FULL ERCOT REPORT, UM, IN ADDITION TO THE PRESENTATION.
SO IN, IN AN APPENDIX OR SOMETHING JUST INCLUDE, YOU KNOW, IT JUST LIKE WE DO WITH THE NPRS, RIGHT? ALL OF THE MATERIALS ARE LOCKED INTO A ZIP FILE THAT ARE, ARE CONSOLIDATED AND EASY ACCESS.
I, I SAY THAT BECAUSE I CAN'T GO TO AN RPG SITE ON THE WEBSITE AND GRAB ALL OF THOSE REPORTS EASILY.
UM, SO HAVING THAT FOR TECH I THINK WOULD BE, UH, UH, BU AND ROBERT, IS THAT SOMETHING WE, WE COULD JUST INCLUDE WITH THE RPG MATERIALS THAT ARE POSTED TO THE ATTACK PAGE? YOU MAY NOT BE ABLE TO COMMIT TO A SEVEN DAY IN ADVANCE, WOULD BE MY GUESS, BUT
MAYBE, MAYBE WE CAN WORK AWAY HOW TO, HOW TO DO THAT.
SO, UM, CHAIR IF I MAY, SO I DO HAVE LIKE 20 MINUTES I THINK, BUT I'M NOT GONNA TAKE THAT.
SO BEFORE I LEAVE, I, I JUST WANTED TO, YOU KNOW, YOU KNOW, ACKNOWLEDGE MY TEAM.
THERE ARE LIKE A LOT OF PEOPLE WHO WORK BEHIND THESE PROJECTS AND, UM, YOU KNOW, PEOPLE WHO HAVE BEEN FOLLOWING THE RPG, WE HAD LIKE A LOT OF DISCUSSIONS, THESE PROJECTS HAVE GONE THROUGH SEVERAL ATIONS OF UPDATES, SO I WANT TO CALL OUT SOME NAMES.
UM, WANT TO ROBERT FOR LEADING THE RPG.
THESE ARE COMPLEX PROJECTS, AS YOU ALL KNOW.
THERE'S SEVERAL PROJECTS, UH, WE'VE BEEN ABLE TO PROCESS THROUGH RPG, UH, SOME OF THE KEY PEOPLE, ROBERT, ESPECIALLY THESE SET OF PROJECTS, UH, TRAVIS ING LEE, UM, TANZA, BEN, I MIGHT BE MISSING SOMEBODY ELSE.
SO THANK YOU FOR ALL THE, ALL THE HARD WORK, ESPECIALLY THE LAST FEW DAYS.
LIKE, YOU KNOW, TRYING TO GET ALL THE MATERIALS FOR T AND THE BOARD, YOU KNOW, THEY, THEY DID A, YOU KNOW, INCREDIBLE JOB BEHIND THE SCENES.
DO YOU WANNA DO IN FRONT OF THE SCENES TOO? I MEAN, JUST, YEAH, THESE WERE LARGE, COMPLICATED PROJECTS WITH MANY MOVING PIECES THAT SOMEHOW PEOPLE KEPT TRACK OF AND HERE WE ARE TODAY.
YOU KNOW, TO OUR EARLIER CONVERSATION, THERE'S A LOT MORE OF THESE AND HIGHER DOLLAR AND YOUR TEAM HAS DONE A, A REALLY GOOD JOB BU AT, AT GETTING US MATERIALS, YOU KNOW, PRETTY FAR IN ADVANCE CONSIDERING THE WORKLOAD YOU HAVE.
AND, UM, I WOULD THANK THE TSPS TOO.
THAT WAS SORT OF A TWO HOUR WINDOW.
WE ASKED SUBJECT MATTER EXPERTS TO BE AVAILABLE.
I KNOW IT'S, UH, A LOT FOR THE, THOSE TEAMS AND THE, THE REGULATORY TEAMS TO BE PREPARED FOR QUESTIONS.
AND I THINK EVERYONE DID A GREAT JOB ALL.
WAIT, I WOULD PROPOSE WE TAKE A SHORT, A 10 MINUTE BREAK AND THEN DO, YOU KNOW, ANOTHER 45 MINUTES WORTH OF WORK BEFORE LUNCH? SO TAKE, TAKE A QUICK BREAK, COME BACK.
[6. Revision Requests Tabled at TAC (Possible Vote)]
ALL THE, COULD WE PUT ALL THE REVISION REQUESTS ON THE COMBO BALLOT AND BE DONE WITH THEM? NO, BEFORE A BREAK? YEAH, NOBECAUSE WE'D HAVE TO GO THROUGH SEVERAL REPORTS.
SO LET'S, LET'S TAKE A FIVE MINUTE, LET'S, LET'S ACTUALLY START BY 1140 AND THEN WE CAN DO THE COMBO BALLOT BEFORE LUNCH.
SO LET'S, LET'S TAKE A, A SHORT BREAK BE ACTUALLY BACK BY 1140.
AND THEN LET'S HAVE THAT COMBO BALLOT AT LEAST, MAYBE ONE MORE OR CUT REPORT BEFORE LUNCH.
THE FOUR 15 PRS REPORT AS AMENDED BY THE FIVE 12
[02:00:01]
ERCOT COMMENTS.AND ALSO TO RECOMMEND APPROVAL OF NPR 1306 AS RECOMMENDED BY PRS IN THE FOUR 15 PRS REPORT.
CAN WE PUT BOTH OF THESE ON THE COMBO BALLOT? YES, PLEASE GO AHEAD BLAKE.
UH, BLAKE HOLDS SPEAKING FOR WMS IN THE INTEREST OF EFFICIENCY.
WE HAD TWO OTHER REVISIONS RELATED TO 1306 THAT, UH, WMS ENDORSED THE COP MGRR OH FIVE TWO AND V-C-M-R-R OH FOUR FIVE.
UH, THESE REVISIONS REALLY JUST REMOVED THE REFERENCE TO DIGITAL CERTIFICATE AND EACH OF THE REVISIONS, UH, MADE IT MORE GENERAL.
THEY'RE, THEY'RE BOTH NO IMPACT REVISIONS.
I'M CURIOUS IF WE COULD ALSO ADD THOSE TO THE COMBO BALLOT.
NOW I, YOU KNOW, I I HOPE THEY'RE ALL GOING TO COMBO BALLOTS, SO I DON'T MATTER, I DON'T THINK IT MATTERS IF WE PUT IT ON THE COMBO NOW OR LATER, BUT, UM, BUT SURE.
SO IT WOULD BE A, DO WE, HOW DO WE SAY THAT ACRONYM? IT'S A COP M-G-R-R-O 55 0 52 AS RECOMMENDED BY THE WMS IN THE FIVE EIGHT WMS REPORT.
AND THE V-C-M-R-R 45 IS RECOMMENDED BY WMS IN THE FIVE EIGHT WMS REPORT? YES, MA'AM.
CAN WE PUT ALL FOUR OF THOSE ON THE COMBO BALLOT? OKAY, LET'S DO IT.
AND YOU ADD RMS, WE CAN ADD RMSS RMSS IS ALSO RELATED.
UM, AND THAT IS THE R-M-G-R-R 180 4 AS RECOMMENDED BY RMS IN THE FIVE 12 RMS REPORT.
IS IT FIVE FIVE REVISION REQUESTS? OKAY.
SO WE'LL PUT THOSE ALL ON THE COMMA BALLOT.
[7. RMS Report (Vote)]
W WE'RE TO R-M-S-R-M-S-D ONE TWO REPORT ON ANYTHING ELSE? I HAVE A REALLY QUICK, UM, REPORTS, SORRY, IT'S A VERBAL REPORT.JOHN HAD TO STEP AWAY, SO HE ASKED ME TO DO IT.
WE REALLY MADE SOME GOOD PROGRESS WITH THE MERGER OF THE TEXAS SET AND THE LOW PROFILING GROUP.
AND, UH, THEY'RE REALLY NEAR COMPLETION OF THEIR WORK FOR THE LOAD PROFILING GUIDE.
SO REALLY THAT'S, IT'S BEEN O OVER A YEAR AND IT'S REALLY BEEN A LOT OF HARD WORK AND WE ARE ALSO MOVING FORWARD WITH THE TEXAS MARKET TEST PLAN AND WE'RE TAKING KOTS APPROACH ON THAT AND MAKING IT AN NPRR.
ANY QUESTIONS FOR DEBBIE? ABOUT, ABOUT RMS? AND WE HANDLED THE VOTING ITEM ALREADY.
[8. WMS Report (Vote)]
BLAKE, WOULD YOU LIKE TO PRESENT WMS REPORT? UH, YES.IT'S JUST A VERBAL REPORT AS WELL.
UM, JUST WANTED TO GIVE SOME NOTICE ABOUT OUR JUNE 3RD MEETING.
ERCOT REQUESTED FOLKS TO COME PREPARED WITH THEIR OPINIONS ON NPR 1296, THE RESIDENTIAL DEMAND RESPONSE PROGRAM.
I IMAGINE THE MAJORITY OF OUR FIRST PART OF THE AGENDA WILL, WILL HANDLE THAT DISCUSSION, UH, AS WELL AS THERE MAY BE ANOTHER, DON'T WANNA STEAL BEST THUNDER, BUT THERE MAY BE ANOTHER ITEM LA ADDED LATER IN THE AGENDA TODAY THAT WE'LL DISCUSS.
UM, AND THEN SECONDLY, THE SECOND PART OF OUR AGENDA, WE'RE GOING TO HAVE A WORKSHOP ON FIRM FUEL SUPPLY SERVICE AND THE REVISIONS NEEDED TO HANDLE, UH, THE MOST RECENT RULEMAKING THERE.
SO, UH, PROBABLY A LONGER AGENDA ON JUNE 3RD, BUT WANTED TO GIVE FOLKS NOTICE ABOUT THAT.
I'M VERY CURIOUS ABOUT THE ITEM NOW.
[10. ERCOT Reports (Part 1 of 2)]
WE HAD ONE LITTLE AGENDA SWITCH.WE'RE GONNA GO TO THE A DR PILOT GOVERNING DOCUMENT BECAUSE THAT IS A VOTING ITEM AS WELL.
AND THEN LET'S GO TO THE COMBO BALLOT.
UM, CATHERINE GROSS WITH ERCOT, I WAS GONNA GO OVER SOME UPDATES TO THE A DR GOVERNING DOCUMENT THAT WE WANTED TO ASK FOR A TECH ENDORSEMENT OF, AND THEN ALSO GIVE A BRIEF UPDATE ABOUT THE PILOT PROGRAM AND ABOUT, UM, OUR MOVING THAT PILOT PROGRAM INTO PROTOCOLS.
UM, SO HOW DO I GO? YOU JUST HAVE TO CLICK ON THAT SCREEN JUST TO ACTIVATE IT AND THEN THE MOUSE WHEEL AND STUFF.
SO, UM, A QUICK UPDATE ON THE GROWTH OF THE EIGHTER PILOT PROJECT.
UM, YOU CAN SEE THAT JUST, UM, IN THE LAST YEAR THERE'S BEEN
[02:05:01]
A LOT OF A, A TREMENDOUS AMOUNT OF GROWTH.UM, WE'RE NOW AT, UM, 236 MEGAWATTS, UM, ENROLLED.
UM, AND THAT'S OF A 500, UM, SYSTEMWIDE MEGAWATT CAPACITY, UH, CAP.
AND THEN FOR ECRS, UM, GETTING CLOSE TO FILLING THE 100 MEGAWATT CAP, UM, WE'VE GOT 78 MEGAWATTS.
AND THEN FOR NON SPIN, ABOUT HALF OF THAT IS, IS FILLED.
AND CURRENTLY THERE ARE NINE AIDERS, UM, THAT ARE QUALIFIED TO PARTICIPATE.
AND SO, UM, UH, THE MAIN REASON THAT, UM, WE ARE COMING HERE TODAY IS TO ASK FOR ENDORSEMENT OF, UM, A COUPLE OF CHANGES TO THE GOVERNING DOCUMENT.
UM, THIS FIRST ONE IS REALLY WHAT, UM, I GUESS MOTIVATED US COMING HERE TO, TO ASK FOR SOME CHANGES TO THE GOVERNING DOCUMENT.
UM, THERE IS A SECTION IN THE GOVERNING DOCUMENT THAT TALKS ABOUT, UM, A CAP ON, UM, THE TOTAL RESPONSE CAPABILITY OF ALL EIGHT ERS ASSIGNED TO ANY SINGLE SIM LOAD SHALL BE CAPPED AT A HUNDRED PERCENT OF THE RATING OF THE SIM LOAD.
AND, UM, AS WE WERE GETTING CLOSER TO THAT CAP FOR SOME AIDERS, UM, WE TALKED WITH OPERATIONS AND REALIZED THAT THAT, UM, THAT CAP IS ACTUALLY NOT NEEDED.
UM, A LOT OF THESE AGGREGATIONS, IF YOU'RE THINKING OF INDIVIDUAL PREMISES THAT ARE SPREAD OUT, UM, THEY ARE ONLY LOOSELY RELATED TO THE SIM LOAD WHERE THEY'RE MODELED AT.
UM, SO HAVING THIS CAP IS ACTUALLY NOT SERVING AN OPERATIONAL, UM, NECESSITY.
AND SO, UM, THERE'S TWO SPOTS IN THE GOVERNING DOCUMENT THAT HAVE THIS LITTLE PARAGRAPH THAT WE WANTED TO REMOVE.
UM, IF THERE ARE, UM, ANY OPERATIONAL CONCERNS OR CONCERNS WITH PHYSICAL SYSTEM LIMITS, THOSE CAN STILL BE ADDRESSED, UM, THROUGH THE ADA PROCESS AND THROUGH UPDATING THE DODA FORMS. UM, AND I SEE THERE'S A QUESTION FROM BOB HILTON.
YEAH, JUST REAL QUICKLY, YOU KNOW, UH, ON THESE, UM, AND I MAY HAVE MISSED THIS OR MAY NOT KNOW IT 'CAUSE I'M NOT AS FAMILIAR WITH THIS PROGRAM, BUT, UH, IN THE ANCILLARY SERVICES AND EVERYTHING, IS THERE STATISTICS ON, ON COMPLIANCE ON THOSE TO, UH, DISPATCH INSTRUCTIONS AND COMPLYING WITH WHAT IS NEEDED FOR ECRS AND NONS SPIN? I AM NOT AWARE OF ANY NONCOMPLIANCE ISSUES THAT WE'VE HAD WITH THOSE.
RYAN, DO YOU, RYAN? SO, UH, WE DO PUBLISH, UM, UH, I'M BLANKING ON THE EXACT ACRONYM, BUT BASICALLY IT'S A COMPLIANCE WITH DISPATCH METRIC THAT ALL, UH, CONTROLLABLE LOAD RESOURCES ARE SUBJECT TO.
AND, UH, ADR R AS A LR ARE SUBJECT TO THAT.
I, I CAN'T PULL ANY, UH, STATISTICS, UH, OFFHAND BUT THE, I DON'T THINK WE'VE SEEN LIKE A SYSTEMIC ISSUE WITH COMPLIANCE.
AND 'CAUSE YOU KNOW, THERE WAS TALK RIGHT HERE ABOUT RAISING SOME OF THESE LIMITS OR GETTING RID OF SOME OF THESE LIMITS AND I'D BE REALLY INTERESTED IN THAT BEFORE WE REALLY DID THAT.
DO YOU WANNA GO TO MORE QUESTIONS, PHIL? SURE, YEAH.
HEY CATHERINE, ON THIS SLIDE IS IT, ARE THIS STILL MAINLY UM, BATTERIES? YES.
OKAY, AND THEN, UM, SO AS I SAID, THE SIM LOAD RATING CAP IS THE, THE MAIN CHANGE.
UM, BUT AS WE ARE LOOKING AT THE GOVERNING DOCUMENT, SINCE WE'RE GONNA HAVE TO COME TO THE BOARD TO ASK FOR THEM TO APPROVE THAT CHANGE, WE LOOKED FOR ANYTHING ELSE THAT NEEDED TO BE UPDATED.
UM, THERE IS CURRENTLY ON OUR WEBSITE, YOU CAN LOOK UP IF YOU'RE INTERESTED AND SEE HOW CLOSE WE ARE GETTING TO THE PARTICIPATION LIMITS.
SO HERE WHERE IT SAYS TOTAL, YOU CAN COMPARE THAT TO WHAT THE CAP IS.
BUT WE THOUGHT IT WOULD BE HELPFUL IN THE GOVERNING DOCUMENT JUST TO ADD A LITTLE SENTENCE TO LET PEOPLE KNOW IF YOU WANNA KNOW WHAT THE CURRENT, UM, PARTICIPATION LEVELS ARE, GO TO OUR WEBPAGE TO FIND OUT THOSE, THOSE UPDATES.
SO THAT'S BEEN ADDED INTO THE GOVERNING DOCUMENT.
AND THEN FROM, UM, I THINK TWO, I GUESS THE LAST TIME THAT WE UPDATED THE CAPS, THERE WAS ONE SPOT WHERE WE MISSED, UM, UPDATING A REFERENCE.
SO THAT HAS ALSO BEEN UPDATED AND THE RED LINE VERSION OF THE GOVERNING DOCUMENT IS ALSO AVAILABLE WITH THE MATERIALS FOR TODAY.
UM, SO FOR NOW, UM, WE CONTINUE TO WORK ON SEEING HOW, UM, THE PILOT IS OPERATING.
UM, WE ARE CURRENTLY WORKING THROUGH DESIGN QUESTIONS THAT WILL NEED TO BE ANSWERED AS WE MOVE THE PILOT INTO PROTOCOLS AND WE ARE WORKING ON THAT NOW, HAVING A LOT OF MEETINGS, ALSO TALKING WITH UM,
[02:10:01]
DSWG ON THOSE ISSUES AND MEETING INDIVIDUALLY WITH STAKEHOLDERS.AND WE ARE CONTINUING TO DO THAT THROUGH, UH, NEXT QUARTER.
AND THEN FOR, UM, THE LAST QUARTER OF 2026, OUR GOAL IS THAT WE WOULD HAVE AN NPRR PACKAGE READY, UM, THAT WE CAN SHARE.
AND SO TO MOVE THE WHOLE PILOT COMPLETELY INTO THE PROTOCOLS.
UM, BILL, DO YOU HAVE A QUESTION? YEP.
DEFINITELY SUPPORT, UM, MAKING THIS A FORMAL PRODUCT IN THE PROTOCOLS.
ONE QUESTION I HAD IS JUST GOING THROUGH THIS PROCESS, IS THERE FURTHER AUTOMATION BEING CONTEMPLATED, LIKE PROCESSING THE DOTA AND ALL THAT? 'CAUSE THAT'S PAINFUL.
I THINK THAT WE ARE LOOKING AT THAT WOULD BE GREAT.
UM, HAVING A MUCH MORE STREAMLINED PROCESS BECAUSE IT IS A LOT OF, IT'S AN EXCEL SPREADSHEET AS YOU KNOW, THERE'S BACK AND FORTH OF YEP.
UM, SENDING FROM THE QSC TO, TO THE DSP AND THEN, THEN WE GET INVOLVED AND SO THERE'S A LOT OF BACK AND FORTH WITH, UM, BLOCKING OFF OR REJECTING INDIVIDUAL EASY IDS AND IT'S HARD TO KEEP TRACK OF THAT.
AND SO WE ARE LOOKING AT AN AUTOMATED PROCESS FOR THAT.
I'M HAPPY TO MAKE A MOTION FOR THIS OR COMBO BALLOT IF YOU NEED IT.
ARE YOU DONE WITH YOUR PRESENTATION? YES.
HI, MITCH FROM, FROM BASE POWER HERE, JUST, UM, KIND OF TO ALSO PARTIALLY ANSWER BILL'S QUESTION.
WE DID JUST HAVE A DEMAND SIDE WORKING GROUP MEETING YESTERDAY WHERE, UM, SOME OF THE KIND OF POTENTIAL UPDATES TO THE A DER PROGRAM AS WELL AS, UM, MOVING FORWARD SOME KIND OF DESIGN QUESTIONS AS WELL AS AUTOMATION AROUND THE, THE DO DEFORM WAS DISCUSSED.
UM, SO THE, UH, THE DEMAND SIDE WORKING GROUP I THINK IS WHERE A LOT OF THOSE DISCUSSIONS ARE GOING TO BE HELD IN THE FUTURE.
AND ALSO JUST HIGHLIGHTING, UM, THAT WE HAD ONE OF THOSE MEETINGS YESTERDAY, UH, FOR INTERESTED PARTIES.
ALL RIGHT, SO WE WOULD BE LOOKING TO ENDORSE THE, UM, A DER PILOT PROJECT, GOVERNOR DOCUMENT AS PRESENTED.
CAN WE PUT THAT ON THE COMBO BALLOT? LET'S PUT IT ON THE COMBO BALLOT.
[9. Combo Ballot (Vote)]
TO OUR COMBO BALLOT.UM, BEFORE WE TAKE IT UP OR BEFORE WE GET STARTED, UM, WE, WE JUST SPOKE ABOUT, UM, PR 1 45 AND NPR 1325, LESS THAN A WEEK AGO.
UM, SO I WOULD ASK IF WE CAN PUT WAIVING NOTICE OF PR 1 45 AND NPR 1325 ALSO ON THE COMBO.
AND THEN I KNOW BILL HAS A OTHER REQUEST.
I MADE THIS SUGGESTION LAST WEEK.
UM, IT WOULD BE TO HELP GO AHEAD.
TO HELP STREAMLINE OUR EFFORTS AFTER LUNCH.
UM, I DON'T BELIEVE 1325 IS CONTROVERSIAL AT ALL.
THERE HAVE BEEN NO OPPOSING COMMENTS FILED IN ANY WAY.
I WOULD SUGGEST WE PUT THAT ON THE COMBO BALLOT AS WELL.
SO THAT WOULD BE, UM, RECOMMENDED.
1325 AS RECOMMENDED BY FIVE SIX PRS REPORT AS AMENDED BY ERCOT FIVE 11 COMMENTS AND THE THREE FOUR IMPACT ANALYSIS.
I DON'T THINK WE NEED THE IA, WE DON'T NEED THE I A QUESTION MARK.
HOW DID WE APPROVE THE IA? PRS APPROVED IT.
SO WE DON'T HAVE TO DO THE IA.
CORY, DO YOU OBJECT TO THAT? RECOMMENDED APPROVAL OF 1325 IS RECOMMENDED BY FIVE SIX PRS REPORT IS AMENDED BY, OR FIVE 11 COMMENTS.
I'M JUST LOOKING FOR CLOSURE AT LEAST ON PART OF THIS.
PROBABLY A LITTLE LATE ON THAT ONE.
I WAS A, THE PROBLEM IS THERE IS A, WE WOULD BE JULIUS CAESAR, AND THEN IF SOMETHING HAPPENS WITH FIGURE 1 45, WE CAN'T UNAPPROVE 1325.
I KNOW, I, I HEAR THE CONCERN.
[02:15:01]
MAYBE OVERLY SO THAT WE WILL VOTE OUT A VERSION OF PICKER 1 45 EITHER TODAY OR TOMORROW BEFORE MIDNIGHT.I DON'T KNOW WHAT IT WILL LOOK LIKE OR WHAT'S GONNA BE IN IT, BUT I I'M CONFIDENT THAT WE'RE NOT GONNA SEND 1325 TO THE BOARD ON ITS OWN.
AND IF ANYONE DISAGREES WITH THAT, WELCOME TO HEAR THOUGHTS.
IT'S MAY 15TH COMMENTS, NOT MAY 11TH COMMENTS.
DOES THAT CHANGE YOUR MIND IN ANY WAY? BILL BARNES
ARE PEOPLE OKAY WITH THAT ON THE COMBO COMBO BALLOT? OKAY.
AND WILL YOU BE MAD AT US? NO, NO.
UM, IN THE MOTION FOR THE L-C-R-A-R-P-G PROJECT, SHOULD IT SAY 2025.
SO WE NEED A MOTION AND A SECOND ON THE COMBO BALLOT.
BOB BILL, I ALREADY GAVE YOU ONE, DAVID.
SO HIS FINGER WAS HIGHER THAN MINE, THOUGH.
HIS FINGER WAS HIGHER AGAIN, BUT, AND AARON DIDN'T EVEN TRY THIS TIME.
CHILDREN
WELL, WE CAN WORK THAT OVER LUNCH.
AND THE SECOND ARE BOB HILTON AND BILL BARNES ARE, AND THEY MAY BE MAD AT EACH OTHER ALSO, BUT I DON'T, I DON'T KNOW.
BUT THERE'S A DISPUTE IN THE IO IOU SEGMENT THAT WE WILL RESOLVE OVER LUNCH.
OUR MOTION TO APPROVE THE COMBO BALLOT.
WE WILL START UP WITH THE CONSUMERS, WITH GARRETT? YES, SIR.
NICK FARBA YOU WITH US? I CAN TAKE YOU IN CHAT AGAIN.
THANK YOU, SARAH FOR WILL? YES.
ONTO OUR INDEPENDENT GENERATORS.
AND THANK YOU SHANE FOR RASHMI.
THANK YOU, DAVID FOR ABBY? YES.
I THINK WE CAN FINISH ALL THESE OR WORKOUT REPORTS BEFORE LUNCH.
ANY, ANY QUESTIONS OR COMMENTS ABOUT WHAT WE VOTED ON? ANY ANYTHING? OKAY.
[10. ERCOT Reports (Part 2 of 2)]
LET'S GO TO, UM, MAGGIE, WITH THE FFSS SETTLEMENT REPORT.YEAH, YOU MIGHT HAVE TO CLICK ON THE LEFT SCREEN JUST TO ACTIVATE IT, AND THEN ONCE YOU'RE DONE, YOU SHOULD, MOUSE WHEEL OR ARROWS WILL WORK.
MAGGIE SHANKS FROM ERCOT SETTLEMENTS, AND THIS IS THE FIRM FUEL SUPPLY SERVICE SETTLEMENT REPORT FOR THE 20 25 20 26 SEASON.
SO, JUST SOME BACKGROUND ON THIS REPORT.
UM, AT THE END OF EVERY SEASON, WE ARE REQUIRED TO PROVIDE A REPORT TO TACK, UM, RELAYING THE SETTLEMENT DOLLARS THAT WERE PAID FOR FIRM FUELS, UH, SUPPLY SERVICE ON APRIL 29TH.
A SECONDARY REPORT WAS PROVIDED THAT, UH, DESCRIBES THEIR REASONS FOR DEPLOYMENT, AND THAT WAS, UH, YOU COULD FIND THOSE MATERIALS ON THE APRIL 29TH TECH MEETING.
UH, SOME BACKGROUND ON THIS SEASON, WE DID HAVE
[02:20:01]
32 GENERATION RESOURCES AWARDED AS PRIMARY FFF SSRS.THE CLEARING PRICE WAS AT $12,240 PER MEGAWATT, AND WE DID HAVE A TOTAL OF 4254.6 MEGAWATTS PROCURED.
UH, DURING THE SEASON, WE DID DECERTIFY AND RECERTIFY FOR FF SSRS.
SO AFTER THAT RECERTIFICATION IT DROPPED.
UM, THE MEGAWATT PROCURE DROPPED SLIGHTLY TO 4250.4 MEGAWATTS.
THE TOTAL COST OF THIS SEASON, THE PROJECTED COST WAS A LITTLE BIT OVER $52 MILLION.
THE STANDBY PAYMENT AT THE END OF THE SEASON WAS A LITTLE BIT UNDER $51 MILLION.
AND THE REASON FOR THE DIFFERENCE BETWEEN THE $52 MILLION BUDGET OR PROJECTED BUDGET AND THE $51 MILLION STANDBY FEE THAT WAS PAID IS SOME RESOURCES, UM, HAD THAT STANDBY FEE REDUCED BECAUSE OF THEIR AVAILABILITY FACTOR.
SO THEY HAD SOME OF THAT MONEY, UM, REDUCED.
WE ALSO, AS I MENTIONED BEFORE, HAD FOUR FFF SSRS THAT WERE DE-CERTIFIED, UH, DURING THE SEASON BETWEEN DECEMBER 23RD AND JANUARY 9TH.
THEY WERE LATER RE-CERTIFIED ON JANUARY 10TH.
SO THAT ALSO WAS A REASON FOR THAT LOWER STANDBY FEE, TOTAL COST.
UM, AND THE REASON FOR THOSE, UH, DECERTIFICATIONS WAS BECAUSE THOSE FOUR RESOURCES DID NOT MEET THE 50% AVAILABILITY FACTOR THAT YOU ARE, UH, SUPPOSED TO MAINTAIN WHENEVER YOU ARE APPROVED FOR THIS, UM, CONTRACT.
WE DID NOT HAVE ANY FUEL REPLACEMENT COSTS THIS SEASON, EVEN THOUGH THERE WERE FUEL REPLACEMENTS THAT WERE APPROVED, WE JUST DIDN'T RECEIVE ANY DISPUTES FOR THOSE AMOUNTS.
SO WE DID NOT HAVE TO PAY ANY ADDITIONAL AMOUNT FOR FUEL REPLACEMENT COSTS.
AND THERE WAS ABOUT $5.7 MILLION THAT WILL BE CLAWBACK TOTAL FOR THIS SEASON.
AND THOSE CLAWBACKS BEGAN ON THE TRIP STATEMENTS ON MAY 12TH, AND THEY'LL CONTINUE ON UNTIL SEPTEMBER 9TH.
RELATED TO THE CLAWBACKS, WE DID HAVE EIGHT RESOURCES THAT RECEIVED CLAWBACK CHARGES.
SEVEN OF THOSE WERE RELATED TO THE AVAILABILITY FACTOR OF THEM.
SO THE LONGEST AVAILABILITY DURING A WATCH WAS 26 HOURS.
THE SHORTEST UNAVAILABILITY WAS ONE HOUR, AND THE AVERAGE BETWEEN THE TWO WATCHES FOR THOSE SEVEN RESOURCES THAT WERE CLAWED BACK WAS ABOUT 9.6 HOURS OF UNAVAILABILITY.
ONE RESOURCE DID RECEIVE CLAW BACK CHARGES RELATED TO THREE DIFFERENT PARAGRAPHS.
SO THEY WERE, THEY FAILED TO STAY ONLINE DURING A WATCH FOR A FUEL RELATED ISSUE, AND THEY FAILED TO GENERATE, UH, THE REQUIRED TOLERANCE, AND THEY WERE ALSO UNAVAILABLE DURING CERTAIN HOURS OF THE WATCH.
SO ONE RESOURCE DID HAVE THEIR ENTIRE STANDBY PAYMENT CLAWED BACK FOR THE ENTIRE SEASON.
AND THESE ARE JUST PROTOCOL REFERENCES IF YOU WANTED TO SEE THE EXACT LANGUAGE RELATED TO THE CLAWBACK.
ANY QUESTIONS OR COMMENTS FOR MAGGIE? I HAVE ONE.
DEBBIE IS, OR MAYBE THIS IS FOR BLAKE.
IS THIS THE DRIVER FOR YOUR WORKSHOP? CAN YOU, CAN YOU TALK INTO A MIC FOR THE PHONE PEOPLE? SORRY.
IS THIS THE DRIVER FOR YOUR WORKSHOP, BLAKE? NO, MA'AM.
THE, THE PUC RECENTLY EXPANDED ELIGIBILITY REQUIREMENTS FOR, UH, FIRM FUEL SUPPLY PARTICIPATION, AND THAT WILL BE THE FOCUS OF OUR WORKSHOP, IS TO TALK THROUGH NEW PROTOCOLS TO, UH, ENACT THAT EXPANDED ELIGIBILITY.
YEAH, I BELIEVE THIS IS MAGGIE.
THIS IS REQUIRED AFTER THE, THE SEASON? YES, CORRECT.
LET'S MOVE ON TO THE POTENTIAL PRICE CORRECTION WITH MATT.
HELLO, MY NAME'S MATT YOUNG WITH ERCOT.
I'M GONNA BE GOING OVER A POTENTIAL PRICE CORRECTION FOR THE REAL TIME MARKET.
UH, THE SUMMARY IS BASICALLY WE HAD A ENERGY OFFER CURVES THAT WERE GENERATED BY SCED FOR QUALIFIED FACILITIES THAT WERE INCORRECT.
UM, OUT OF THE 20 PLUS DAYS THAT WE LOOKED AT, THERE WERE FIVE OPERATING DAYS THAT MET CRITERIA FOR BOARD REVIEW.
SO TYPICALLY, WHEN, UH, RESOURCE SUBMITS AN OUTPUT SCHEDULE, ERCOT WOULD CREATE AN ENERGY OFFER CURVE FOR THAT RESOURCE, UH, SIMILAR TO THE ONE SEEN HERE.
[02:25:01]
SCHEDULE IS 50 MEGAWATTS, THEN THE, UH, PROXY ENERGY OFFER CURVE WOULD BE AT THE FLOOR OF NEGATIVE TWO 50 FROM LSL UP TO THAT TARGET.AND THEN ABOVE THAT, UP TO HSL WOULD BE AT THE REALTIME SYSTEM WIDE OFFER CAP.
UM, FOR QUALIFIED FACILITIES, WE HAVE SPECIAL LOGIC.
UM, A QUALIFIED FACILITY IS CONSIDERED A SMALL POWER PRODUCTION FACILITY OR QUALIFYING CODE GENERATION FACILITY UNDER REGULATORY QUALIFICATION.
UM, THE, UH, RESOURCES ARE TREATED AS A MUST TAKE OR MUST RUN FACILITY, MEANING ERCOT ACCOMMODATES THEIR OUTPUT RATHER THAN DISPATCHING THEM ECONOMICALLY.
UM, AND WHEN A RESOURCE THAT IS DESIGNATED AS A QUALIFIED FACILITY SUBMITS AN OUTPUT SCHEDULE, THEN THE CREATION OF THEIR ENERGY OFFER CURVE HAS ONE KEY DIFFERENCE THAN NORMAL, WHICH IS THAT THE TARGET MEGAWATT FOR THAT PROXY OFFER CURVE IS ACTUALLY THEIR TELE THIRD MEGA MEGAWATT OUTPUT.
AND SO ERCOT DISCOVERED THAT THERE WAS A SOFTWARE DEFECT ON JANUARY 29TH AFFECTING THE REAL TIME MARKET.
UH, THE DEFECT OCCURRED BETWEEN DECEMBER 17TH, 2025 AND JANUARY 29TH, 2026.
ERCOT CORRECTED THE DEFECT IMMEDIATELY.
AND, UH, AS I EXPLAINED, UH, SCED WAS BASICALLY FAILING TO GENERATE THE CORRECT ENERGY OFFER CURBS FOR THOSE QUALIFIED FACILITIES, OR CAUGHT ISSUED A MARKET NOTICE ON FEBRUARY 5TH TO PRESERVE THE BOARD OF DIRECTORS' ABILITY TO REVIEW PRICES.
THE NOTICE COVERED OPERATING DAYS JANUARY 6TH THROUGH JANUARY 29TH, UH, 30 DAYS FROM THAT NOTICE.
UM, BUT THERE WAS A CHANGE IN THE OPTIMIZATION ENGINE ON THE, ON JANUARY 8TH THAT RESULTED IN US NOT BEING ABLE TO ACTUALLY DETERMINE CORRECT PRICES FOR THE SIXTH AND SEVENTH.
THE RESULTS, UH, SHOWED THAT THERE WERE FIVE DAYS THAT MET THE CRITERIA REQUIRED TO SEEK BOARD APPROVAL.
UH, SHOWN HERE THERE WAS, UH, FOUR PARTIES THAT MET THE CRITERIA, UH, FOR CRITERIA ONE AND TWO PARTIES FOR CRITERIA TWO CRITERIA BEING THAT THE IMPACT TO ANY SINGLE COUNTERPARTY BEING 2% OR GREATER THAN 20,000 OR 20% AND GREATER THAN 2000.
UM, THIS TABLE JUST SHOWS THE, UH, MAXIMUM ABSOLUTE VALUE IMPACT TO A SINGLE COUNTERPARTY FOR EACH OPERATING DAY AS WELL AS PERCENTAGE, THE LARGEST BEING ON JANUARY 25TH FOR $74,000 TO A COUNTERPARTY.
UH, THE MAXIMUM ESTIMATED CHANGES TO CHARGES DUE TO ERCOT ARE SHOWN IN THIS TABLE, UM, THE LARGEST ONE, AGAIN, BEING THE 25TH, WITH A NEGATIVE IMPACT OF 284,000 ROUGHLY.
AND, UH, JUST TO BE CLEAR, NEGATIVE AMOUNTS ARE INCREASED PAYMENTS TO MARKET PARTICIPANTS WHILE POSITIVE AMOUNTS ARE INCREASED CHARGES.
AND OUR NEXT STEPS ARE TO PRESENT THIS TO THE BOARD FOR APPROVAL FOR THE, UH, THE JUNE BOARD SPECIFICALLY.
THANK YOU, MATT, ARE THERE ANY QUESTIONS FOR MATT ON HIS PRESENTATION? BLAKE? HEY, MATT.
I'M, I'M CURIOUS, WHAT, WHAT WAS THE OUTPUT SCHEDULE SET TO? WAS IT A A RANDOM NUMBER OR WAS IT A, THE, UH, IT REALLY DOESN'T MATTER WHAT THESE QUALIFYING FACILITIES SET THEIR OUTPUT SCHEDULE TO.
THEY COULD HAVE SET IT TO ANYTHING.
UM, THE PROTOCOLS SPECIFY THAT, UH, WE USE A TELEMETRY TO OUTPUT AS THE TARGET MEGAWATT, CORRECT.
I, I, I GUESS MY QUESTION COULD BE A LITTLE BIT BETTER.
WHAT DID SCED TREAT THAT OUTPUT? OUTPUT SCHEDULE AS? OH, SCED WAS USING WHATEVER THEY SUBMITTED FOR THEIR OUTPUT SCHEDULE.
AND IT WASN'T JUST ONE RESOURCE, IT WAS ALL QUALIFIED FACILITIES.
SO IF THEY, FOR INSTANCE, IF THEY SUBMITTED THEIR OUTPUT SCHEDULE AS 50 MEGAWATTS, SCED WAS GENERATING AN OFF CURVE WITH THE TARGET MEGAWATT OF 50 MEGAWATTS INSTEAD OF THEIR TELEMETRY MEGAWATTS.
SO, YOU KNOW, TER WAS 30, IT SHOULD HAVE BEEN USED IN 30 INSTEAD OF EXACTLY.
NEXT UP IS LUIS WITH THE 2027 AS METHODOLOGY TIMELINE DISCUSSION.
I AM GONNA BE TALKING ABOUT THE 2027 ANCILLARY SERVICE METHODOLOGY TIMELINE, UM, MOSTLY HERE TO MAKE SURE THAT WE GET THE RIGHT STAKEHOLDERS INVOLVED IN THE PROCESS AND UNDERSTAND WHERE TO START LOOKING FOR MATERIAL AS WE WORK THROUGH THIS.
UH, SO, UH, WHAT I HAVE UP HERE, UH, WE, WE, WE TEND TO SHARE SOMETHING VERY SIMILAR EVERY YEAR, BUT REALLY TODAY
[02:30:01]
IS HERE AT THE KICKOFF, TRYING TO MAKE SURE WE GET THIS OUT THERE AND GET THE WORD THAT THIS PROCESS IS, IS STARTING, UH, TO START GET, UH, STAKEHOLDER FEEDBACK.UM, AND, AND WE'RE WORKING THROUGH THE 2027 AS METHODOLOGY.
UH, WE ARE WORKING TO GET BOARD AND PUC APPROVAL YOU SEE THERE BY SEPTEMBER 15TH FOR THE BOARD.
AND THEN WE WILL DECIDE, UH, NOVEMBER, DECEMBER, WHEN IT GETS TO THE PUC AFTER THAT.
UM, WHAT I'VE PROVIDED HERE IS OUR TYPICAL TIMELINE WHEN WE DO GET REVIEW AND, AND FEEDBACK FROM THE MARKET.
SO WE ARE GOING TO WORKING GROUPS HERE STARTING IN, IN JUNE.
UM, WHAT WE DO AS AN OVERVIEW IN JUNE IS, IS TALK ABOUT THE METHODOLOGY, TALK ABOUT FEEDBACK THAT WE'VE HAD IN THE PAST, THINGS THAT WE'RE WORKING ON, THINGS THAT WE'RE LOOKING FORWARD TO, AND THINGS THAT WE'RE LOOKING TO GET BACK AS FEEDBACK FROM THE MARKET.
IF THERE IS ANY ADDITIONAL FEEDBACK THAT WAS NOT PROVIDED TO US, UH, LAST YEAR, AS WE WORK THROUGH THAT FEEDBACK, WE GET INTO JULY.
WE START WORKING THROUGH THE PROPOSED METHODOLOGY, THINGS THAT WE ARE WORKING ON THAT, THAT WE THINK WE CAN SOLVE IN THIS YEAR'S TIMELINE, THIS YEAR'S METHODOLOGY, UH, AGAIN, BASED ON PRIORITIZATION AND FEEDBACK WE GET FROM STAKEHOLDERS.
UH, SO WE WOULD BE SHOWING PROPOSED METHODOLOGY IN JULY, UH, HOPEFULLY THEN TO SET UP FOR VOTING IN AUGUST AT THE SUBCOMMITTEE MEETINGS.
UM, NOW, UH, WHAT WE'VE DONE, AGAIN, WHAT WE DO IS WE TRY TO BRING THOSE, THOSE DEEPER DIVE DETAILS TO THE WORKING GROUPS.
YOU KNOW, THINK ABOUT METHODOLOGY, THINK ABOUT CRITERIA, THINK ABOUT PARAMETERS, KIND OF, YOU KNOW, THE NITTY GRITTY THINGS.
AND THEN WE TRY TO GIVE HIGH LEVEL DETAILS TO, TO, UM, YOU KNOW, BRING THOSE BACK TO THE SUBCOMMITTEES, MAKE SURE THAT, THAT THAT UNDERSTANDING IS CORRECT AND, AND, AND GOOD TO GO.
UM, SO REALLY, I'M JUST HERE TO MAKE SURE EVERYBODY SEES THE TIMELINE, KNOWS THAT IT'S COMING, AND, AND SENDS THEIR APPROPRIATE, UH, RESOURCES TO THE MEETINGS AS, AS WE SEE, AS YOU SEE FIT.
CAN WE TAKE SOME QUESTIONS? SURE.
ABOUT YOUR CONTROVERSIAL TIMELINE.
OKAY, LET'S GO, LET'S GO TO BETH.
THIS, THIS WAS THE, UH, SURPRISE THAT, UH, BLAKE WAS ALLUDING TO EARLIER.
UM, AND, AND I HAD SHARED THIS WITH LUIS PROBABLY VERY LATE LAST NIGHT, EARLY THIS MORNING,
AND SO, UM, WOULD SUGGEST KIND OF GOING THROUGH THE PROCESS IN MAYBE A LITTLE DIFFERENT ORDER THAN WE'VE DONE PRIOR.
AND, AND I, MY SUGGESTION WOULD BE THAT IN JUNE, ERCOT COME TO THE SUBCOMMITTEES WMS AND ROS TO LAY OUT THEIR ISSUES AND LET THE SUBCOMMITTEES DECIDE WHICH WORKING GROUPS NEED TO DIG INTO SPECIFICS.
UM, PART OF THAT IS JUST AS, AND MY CONCERN, FRANKLY, WAS THAT, UM, YOU KNOW, COMING TO, IN AUGUST, COMING TO A VOTE AT THE SUBCOMMITTEE LEVEL WITHOUT SOME OF THE KEY DETAILS BEING HASHED OUT FOR THOSE ENTITIES THAT WERE MOST CONCERNED IS PROBABLY PROBLEMATIC FROM MY PERSPECTIVE.
SO THAT'S A VERY SPECIFIC, UM, SUGGESTION I'VE MADE.
UM, LUIS HAS HAD LIKE SIX HOURS TO THINK ABOUT THAT MAYBE.
UM, AND OTHERS MAY OBJECT OR HAVE OTHER, OTHER PERSPECTIVES ON THAT, BUT THAT'S, THAT'S A SUGGESTION.
I'VE ALSO, I'VE RUN THAT, UH, SUGGESTION PAST BLAKE AND SANDY, UM, AND THEY BOTH SEEMED AMENABLE TO IT AS THE SUBCOMMITTEE CHAIRS.
SO, BLAKE, WHAT DO YOU THINK? I SEE YOU IN THE QUEUE.
LET'S GO AHEAD AND TAKE YOU UP.
I, I THINK THAT COULD BE A GOOD APPROACH TO ALLOW THE SUBCOMMITTEE TO GIVE SOME DIRECTION FOR WMWG TO, TO SPEAK ON AND, AND LUIS A SUGGESTION OR AN OFFER FOR OUR JUNE 3RD MEETING.
IT'S GONNA BE A LONG ONE ANYWAYS.
WHAT'S ONE MORE THING? UH, BUT I THINK THERE'S ROOM, UH, THAT WE COULD AT LEAST HAVE AN INITIAL DISCUSSION THERE.
IF, IF Y'ALL BE READY BY THEN.
UM, WE COULD DO THAT AND THEN KEEP THE SIMILAR SCHEDULE.
I THINK THAT COULD PLAY OUT WELL.
SO I THINK SOME OF THE QUESTIONS I HAVE FROM WHAT I'VE HEARD, OR WHAT, WHAT, WHAT THINKING THROUGH THIS SINCE, UH, BETH HAD GIVEN ME A HEADS UP IS, UH, DO WE THINK THE SUBCOMMITTEES HAVE THE TIME IN THE LONG DISCUSSIONS TO TALK ABOUT ALL THE DETAILS? TYPICALLY, WHAT WE BRING IN THE VERY EARLY DISCUSSIONS IS 20, 30 SLIDES, 40 SLIDES OF REAL IN THE WEEDS, DETAILS OF PARAMETERS AND HOW WE'VE DEVELOPED THE METHODOLOGY WHERE WE'VE COME FROM.
WE, LAST YEAR WE SWITCHED TO PROPO, UM, PROBABILISTIC.
SO WE'RE GONNA GO THROUGH ALL THAT BACKGROUND AGAIN.
DOES, DOES THAT MAKE SENSE TO BRING SO TO WMS AND ROSS? AND IT'S ONE OF THE REASONS WE STICK TO WORKING GROUPS.
SO THEN THAT GETS, KIND OF, GETS FILTERED UP TO THE SUBCOMMITTEES.
NOW I UNDERSTAND, YOU KNOW, WMS AND ROSS ACTUALLY ARE HAPPENING EARLY IN, IN BOTH OF THESE MONTHS.
UM, AGAIN, I'D, I'D ASK, IS THAT OKAY? IS THAT APPROPRIATE? ARE YOU LOOKING FOR SOMETHING MORE SUMMARIZED?
[02:35:01]
CAN I OFFER MAYBE JULY IS THE TIME WHAT, MAYBE THE LET THE WORKING GROUPS DIGEST SOME OF IT FIRST? THAT'S WHAT I WOULD SUGGEST.IS JULY, THINKING ABOUT THAT, UM, WWG GETS A CRACK AT IT.
WE WILL HAVE A JULY 8TH WMS MEETING, BETH, WHERE THEY COULD RAISE OR FLAG ISSUES OR CONCERNS.
WE'D HAVE A CHANCE TO WEIGH IN.
THEN THEY GET ANOTHER CRACK AT IT JULY 27TH.
UM, I, I THINK THAT COULD ALSO WORK WELL.
I THINK, YOU KNOW, THE ISSUE IS, I DON'T KNOW THAT, AND MAYBE IT'S JUST A WORK GROUP, UM, YOU KNOW, DIRECTION ISSUE, BUT IT SEEMED LIKE WE WERE HAVING VERY SPECIFIC METHOD METHODOLOGICAL QUESTIONS, DISCUSSIONS ABOUT THE METHODOLOGY AT THE SUBCOMMITTEES, AND EVEN AT TAC MM-HMM
AND, AND I'M ALL ABOARD, LET'S HAVE THOSE DISCUSSIONS EARLY.
UM, AND SO, UM, THAT, THAT, I'M TRYING TO FIGURE OUT HOW TO BEST ACCOMPLISH THAT.
BUT WHAT YOU JUST DESCRIBED, BLAKE SEEMS TO BE A, A WORKABLE, UH, A WORKABLE APPROACH.
I, YOU KNOW, I, I THINK IT'S A WAY TO MAKE OUR DISCUSSION SHORTER AND MORE SUMMARIZED.
UM, AND SO I CAN WORK WITH AMANDA ON HIGHLIGHTING THE ISSUES THAT SHE THINKS WE NEED TO WEIGH IN ON.
UM, AND I, I PREFER THAT APPROACH MORE NOW.
SO WE'D ADD THE JULY WM, S AND ROSS, BASICALLY.
AND I THINK SO THEN THEY COULD GIVE ANY DIRECTION THAT NEEDS TO GO BACK TO THE JULY WORKING GROUPS.
AND, AND IF THERE'S ANY FEEDBACK IN BETWEEN, THEN THAT CAN STILL COME TO US.
BUT I THINK TO ME, THAT GIVES THE GROUPS A LITTLE BIT MORE TIME TO DIGEST, HAVE THAT DISCUSSION WITH SUBCOMMITTEES, AND THEN GIVE US THE FEEDBACK SO WE CAN WORK IT INTO THE PROPOSAL THAT WE BRING IN JULY.
AND I APPRECIATE YOU GUYS ACTUALLY LOOKING AT THE MEETING CALENDAR TO MAKE THAT RECOMMENDATION AS CLEARLY.
ARE WE GOOD ON CALENDAR? MAYBE LET'S GO TO ERIC.
ERIC GOFF ON BEHALF OF DETECTIVES BUYERS ALLIANCE.
UM, AT THE SEPTEMBER BOARD MEETING LAST YEAR, THERE WAS A INTERACTION BETWEEN SOME OF THE BOARD MEMBERS AND THE IMM AND THE CHAIRMAN OF THE COMMISSION AROUND, UM, THE FEEDBACK AND THE PROCUREMENT STRATEGY.
UM, AND CHAIRMAN GLEASON SAID, LET'S KEEP IT THIS WAY FOR THIS YEAR AND RECONSIDER THE METHODOLOGY NEXT YEAR.
ARE WE DOING THAT? WE ARE TAKING THE FEEDBACK THAT WE HAD FROM THE IMM LAST YEAR AND THE PUC AND WE'RE WORKING TO MAKE SURE THAT WE SHOW THAT IN THE METHODOLOGY AND HOW THAT THOSE PARAMETERS MAY IMPACT.
SO WE ARE SHOWING THAT, THAT WE'RE STARTING AND HAVE BEEN WORKING ON THAT, THOSE METHODOLOGIES.
UM, CHAIRMAN GLEASON ALSO USED THE PHRASE IN THAT, UM, DISCUSSION, UM, REVISITING CONSERVATIVE OPERATIONS.
AND I THINK THAT'S A BROADER CONVERSATION THAN JUST THE ANSWERING SERVICES PROCUREMENT METHODOLOGY, BUT IS INTERRELATED.
UM, AND I WOULD HOPE THAT AT THESE JULY MEETINGS OF THE WORKING GROUPS, EXCUSE ME, OF THE SUBCOMMITTEES.
UM, WE ALSO TAKE UP THAT MATTER GENERALLY BECAUSE OF IT'S INTERRELATED.
I KNOW THIS IS A BIG DISCUSSION.
WE'VE BEEN TALKING ABOUT IT FOR A LONG TIME.
BUT, UM, GIVEN THE COMMENTS AT LAST SEPTEMBER'S BOARD MEETING, I THINK IT WOULD BE PRUDENT FOR US JUST TO PLAN TO HAVE THAT DISCUSSION.
I THINK THE, WHAT I'LL JUST SAY, YOU HIT IT ON THE NAIL, THE NAIL ON THAT IS SO THAT DISCUSSION IS BROADER THAN JUST AS MM-HMM
BUT THERE ARE SOME PARAMETERS IN THE AS METHODOLOGY THAT WE ARE REVIEWING TO, TO SHARE THE SCENARIOS AND HOW THOSE WILL IMPACT THE METHODOLOGY.
UM, SO BLAKE SANDE, CAITLIN, I HOPE THAT AT THOSE MEETINGS WE CAN JUST BE TEEING UP THE BIGGER DISCUSSION AND HOW IT'S ALL INTERRELATED.
I APPRECIATE THE COMMENTS BY ERIC AND, AND BETH AND APPRECIATE EVERYONE'S FLEXIBILITY TO MOVING THIS INTO, UM, INTO WORKING GROUPS WHERE, OR INTO SETTINGS WHERE, UH, CONSUMERS ARE MORE PRESENT.
UM, I HAD A SPECIFIC QUESTION ON, IN, IN THE COMMISSION'S REVIEW OF THE ANCILLARY SERVICES, ONE OF THE REQUIREMENTS BY THE 2027 METHODOLOGY WAS REEVALUATING THE, THE, UM, THE, THE TARGET RESERVE LEVELS BASED ON, UM,
[02:40:01]
WATCH EMERGENCY ALERT LOAD SHED.IS THAT PART OF THE CHANGES THAT YOU'RE REFERRING TO IN THIS BULLET? WE ARE WORKING ON EVALUATING WHAT THE SCENARIOS WOULD LOOK LIKE BY MODIFYING THE TARGETS.
SO WE'RE, WE'RE, WE'RE, WE DEVELOPED THE TOOL LAST YEAR TO BUILD SCENARIOS AND BE FLEXIBLE.
AND WE HEARD THE FEEDBACK FROM WHERE WE LANDED LAST YEAR ON THINGS THAT WERE POTENTIAL GAPS OR THINGS THAT WE WANTED TO CONTINUE TO LOOK AT.
AND WE STARTED THERE AND PICKED THOSE UP AND SAYING, YOU KNOW, THIS IS WHERE WE'RE GOING TO TRY TO MOVE FORWARD AND SHOW WHAT QUANTITIES WOULD LOOK LIKE IF THOSE PARAMETERS WERE CHANGED.
'CAUSE I THINK THE SPECIFIC DIRECTION WAS ESTIMATES OF COSTS AND PROBABILITIES OF EXPERIENCING THOSE DIFFERENT THINGS.
SO AS LONG AS THAT'S STILL THE PLAN, I JUST WANTED TO CONFIRM THAT.
BILL, STRONGLY SUPPORT THAT SUGGESTION THAT TARGET RESERVE LEVELS ARE ONE OF THE BIGGER IMPACTS ON HOW MUCH WE PROCURE AND IT'S NOT ALWAYS SUPER TRANSPARENT AS TO WHAT'S GOING ON.
SO THAT FULLY SUPPORT THAT INCLUSION.
ALSO, WE'LL MENTION THAT, UM, WE'LL BE LOOKING SPECIFICALLY FOR DURATION LIMITS, HOW YOUR URINALYSIS, UH, IS IMPACTED BY THE DRE AND LIMITS THE PROCUREMENT QUANTITIES ARE IMPACTED BY DURATION LIMITS.
UM, I ACKNOWLEDGE ERIC'S COMMENT ABOUT THE COMMENTS MADE LAST SEPTEMBER, BUT A LOT'S CHANGED SINCE THEN.
PARTICULARLY WE'RE SEEING INCREASED RUX DUE TO, UM, CONCERNS ABOUT, UM, LIMITED STATE OF CHARGE.
AND SO THE BEST WAY TO SOLVE THAT PROBLEM IS THROUGH A MARKET SOLUTION, WHICH IS THE PER PROCUREMENT OF ANCILLARY.
SO THAT'S ONE THING WE'RE GONNA BE FOCUSED ON.
SO I WOULD LOVE TO SEE, AS PART OF THIS ANALYSIS, HOW MUCH OF YOUR REC ACTIVITY THAT HAS OCCURRED IS DUE TO THOSE CONCERNS.
AND IF YOU CAN QUANTIFY THAT AS PART OF THIS ANALYSIS, THAT WOULD BE GREATLY APPRECIATED.
'CAUSE THAT'S GONNA BE A BIG INPUT INTO THE DECISION MAKING.
THE OTHER QUESTION I HAD, WHICH I DON'T, I DON'T THINK IS THE CASE, BUT WANT TO CONFIRM, WE ARE, WE ARE NOT GONNA BE INCLUDING DRS IN 2027 AT ALL.
IT'S GONNA BE IMPLEMENTED AFTER THAT.
SO WE'RE NOT GONNA TALK ABOUT DRS QUANTITIES UNTIL 28 AND BEYOND.
IKA, CAN I ASK JEFF TO COME AS WELL JUST TO PLEASE COME OKAY.
TO SUPPORT WHAT, UH, LUIS WAS SAYING.
WE'VE BEEN WORKING TOGETHER 2027.
I JUST ASKED IMM TO COME AND ALSO TELL HIS PART OF THE STORY HOW WE HAVE BEEN WORKING TOGETHER WITH ERCOT AND IMM REGARDING 2027 AS METHODOLOGY.
SO, UH, APOLOGIZE, THANKS JEFF FOR NOT BEING HERE.
I HADN'T PLANNED ON SPEAKING HERE TODAY, BUT, BUT HAPPY TO.
UM, SO WE'VE BEEN IN CONTACT AND WORKING DIRECTLY WITH, UH, ERCOT STAFF AND ACTUALLY, UM, WITH PEC STAFF, UH, IN THESE MEETINGS AS WELL FOR A FEW MONTHS NOW.
JUST TRYING TO HAMMER OUT, UH, WHAT SPECIFICALLY WOULD BE USEFUL IN TERMS OF, UM, I GUESS, UH, SIMULATION PERMUTATIONS, UH, THAT WOULD REFLECT DIFFERENT TYPES OF, I DON'T KNOW IF YOU WOULD CALL IT POLICY, BUT, BUT STUDY PARAMETERS.
UM, LOOK, LOOKING AT, YOU KNOW, PERHAPS ONE IN 10 VERSUS, UH, AVOIDING A WATCH.
AND THERE ARE SOME OTHER ASPECTS TO IT AS WELL.
SO, YOU KNOW, I'M, I'M ALWAYS HAPPY TO SAY OR REPORT WHEN WE'RE HAVING A VERY POSITIVE INTERACTION WORKING WITH, UM, ERCOT STAFF.
I DON'T KNOW IF YOU WANT ME TO GO INTO ANY DETAIL.
I DON'T IF THAT'S APPROPRIATENESS NECESSARILY, BUT, YEAH.
SO, SO, SO IT'S BEEN A GREAT PROCESS.
I THINK WE'VE BEEN DOING IT FOR ABOUT THREE MONTHS NOW OR SO.
UM, AND IT'S BEEN TERRIFIC AND WE'LL CONTINUE TO WORK WITH THEM GOING FORWARD.
I'M SORRY, I'M, I'M JUST CONFUSED ABOUT THE TIMING HERE.
ARE, ARE WE EXPECTING TO SEE THE RECOMMENDED CHANGES, UM, PRIOR TO, UM, THE WMS THAT'S ON JUNE 3RD? SO LIKE, SAY, UH, WEEK AHEAD OF THAT, THE MAY WHATEVER, 23RD OR WHATEVER, WHATEVER DAY THAT WORKS OUT TO BE THE 27TH.
MAY 27TH IF WE'RE TALKING ABOUT IT, WE'RE WE MOVED THAT TO THE JULY MEETING.
I APPRECIATES THAT, BUT SO AM I NOT GONNA SEE SOMETHING UNTIL JUNE 10TH, 10TH, JUNE 10TH OF THE FIRST TIME, IS TALKING ABOUT IT AT PDC WG.
SO WE'RE GONNA BE COVERING AN OVERVIEW OF THE METHODOLOGY THAT WE HAVE TODAY AND POTENTIAL CHANGES THAT WE WANT TO MAKE AS A CATCH UP ON JUNE 17TH.
UM, I'VE HEARD WE WANT TO ADD THE JULY ROSS
[02:45:01]
AND WMS MEETINGS AS POTENTIAL, UH, CATCHUPS AND SUGGESTIONS ON, ON METHODOLOGY THAT THE GROUP, THEY, THEY WOULD LIKE TO SEE AS A SUBCOMMITTEE.AND THEN WE WOULD BRING THOSE PROPOSALS ON JULY 22ND AS A FIRST.
SO I'LL SEE IT MAYBE IN WRITING LIKE A WEEK BEFORE JULY 22ND.
AND PROBABLY AS A TEASER, THERE WILL BE SOMETHING IN THE IMM STATE OF THE MARKET REPORT.
BUT THERE'LL BE ROBUST CONVERSATION AT THE JUNE WORKING GROUPS AND THE JULY SUBCOMMITTEES BEFORE THE 22ND.
JUST TRYING TO FIGURE OUT WHAT DAYS TO SET ALARMS FOR, TO, YOU KNOW, GO SCRAPE FOR THESE THINGS.
I WAS TELLING ANN JUNE 3RD ON GILMORE GIRLS IS THE DATE LUKE AND LOLE DON'T GET MARRIED.
SO IT'S THE DATE NOW WE'RE NOT DOING ANCILLARY SERVICES.
ANY OTHER QUESTIONS? YOU GOT THE WORD.
LET'S, LET'S FINISH OUR CUT REPORTS.
THIS IS IMPORTANT, BUT YOU KNOW, IT'S BETWEEN YOU AND LUNCH, TIKA.
SORRY, YOU HAVE THE WORST SPOT OF THE DAY, BUT WE CAN DO THIS.
UM, SO THIS, THIS IS A UPDATE.
THE ERCOT REPORT IS, IS DUE THIS AUGUST.
SO ERCOT IS LOOKING FOR SOME FEEDBACK.
NIKA ISS HERE TODAY, AND THEN SHE'LL BE BACK IN IN JULY.
BUT IT'S IMPORTANT WE GET THROUGH THIS TODAY AND, UH, BE ABLE TO GIVE HER ANY FEEDBACK BY THE END OF THE MONTH.
THANK YOU VERY MUCH FOR THAT SETUP.
YOU HAVE HEARD OF THIS TOPIC BEFORE, I THINK, UH, PUC STAFF WAS HERE SOMETIME LAST YEAR, LATE LAST YEAR, TO SET UP THIS, UH, PARTICULAR WORK THAT THE PUC IS REQUIRED TO DO UNDER PURA.
THERE IS AN OPEN PROJECT ON IT.
THERE WAS A SCOPE OF WORK THAT WAS OUTLINED.
THERE IS A TIMELINE FOR, UH, WORKING THROUGH THIS PROCESS SO THAT PUC CAN MAKE ITS RECOMMENDATIONS BY END OF THIS YEAR.
SO THE, THE MATERIALS THAT I HAVE TODAY IS ABOUT 12 SLIDES, BUT WHAT I'M HOPING TO DO IS QUICKLY GIVE YOU A BACKGROUND OF WHAT THIS IS, TALK ABOUT WHAT WAS OUTLINED IN THE SCOPE SHARE WHERE WE ARE TODAY.
UH, GIVE YOU A TIMELINE SO YOU CAN PROVIDE ANY FEEDBACKS OF THINGS WE SHOULD THINK OF OR CONSIDER AS WE ARE WORKING ON THE ANALYSIS.
WE'LL TAKE THOSE, WE'LL WORK ON THEM.
AND, UH, IN AROUND LATE, WHEN YOU HAVE YOUR JULY MEETING, WE'LL TRY TO BRING BACK OUR FINDINGS, UH, AND WORK, UH, AND AFTER THAT WORK THROUGH OUR REPORT.
SO THAT'S THE OVERALL PROCESS.
LIKE I MENTIONED, THERE IS A REQUIREMENT IN PUR A, WHICH REQUIRES TO EVALUATE BY DECEMBER 1ST, WHETHER AN ALTERNATIVE APPROACH TO, UH, ALLOCATE ANCILLARY SERVICE AND RELIABILITY COSTS MAY PRODUCE A NET SAVINGS TO CONSUMERS COMPARED TO WHAT WE DO TODAY.
UM, THAT IS AN ACTIVE PROJECT.
I HAVE LINKED IT, IF ANYBODY WOULD LIKE TO TAKE A LOOK AT IT.
UH, WITHIN THAT STUDY SCOPE, THERE IS A TIMELINE WHICH GIVES A CUT TILL END OF AUGUST, UH, TO, UH, WORK WITH THE TAC AND PRODUCE A REPORT.
SO, AGAIN, LIKE I MENTIONED, OUR PURPOSE TODAY IS TO REALLY SHARE WITH YOU WHAT THAT WORK IS, SECURE INPUT AS WE WORK ON THE ANALYSIS.
I DID PRINT OUT AT THE TAIL END WHAT THE OVERALL TIMELINE FOR THIS EFFORT LOOKS LIKE.
SO THIS IS NOT THE ONLY TIME FOR STAKEHOLDERS TO PROVIDE INPUT, UH, AFTER WHAT, AFTER A COURT IS DONE IN THAT SEPTEMBER TO NOVEMBER TIMEFRAME.
ALL ALSO, THE VOC STAFF IS PREPARING TO ENGAGE WITH YOU ALL.
SO AGAIN, BEFORE I GET INTO THE GUTS OF THE WORK, CERTAIN WORDS YOU WILL HEAR ME TALK ABOUT AS I GET INTO THE DECK.
AND YOU WILL ALSO SEE SOME OF THESE REFLECTED IN THE REPORTS THAT WE PRODUCE.
UH, THE, THE, THE COLUMN ON YOUR LEFT FOCUSES ON THE ALLOCATION METHODS.
BASE CASE IS THE CURRENT METHOD, THE LOAD RATIO SHARE ALLOCATION.
WE CAN, UH, WE COIN THE TERM METHOD A TO TALK ABOUT, UH, UH, METHOD THAT FOCUSES ON ALLOCATING COST BASED OFF OF ERRORS IN OUR FORECAST OR ERRORS IN FORECAST DURING THE HIGH RELIABILITY RISK COVERS.
THIS PARTICULAR METHOD IS SUPPOSED TO ALLOCATE THOSE COSTS ON A SEMI-ANNUAL BASIS, UH, UH, ACROSS DISPATCHABLE, NON DISPATCHABLE, AND LOAD THOSE
[02:50:01]
THREE BUCKETS.IT'S, IT'S VERY SIMILAR TO METHOD A IN TERMS OF THE ALLOCATION PRINCIPLE, BUT IT USES, IT ALLOCATES THOSE COSTS BASED OFF OF FORECAST ERROR ACROSS ALL HOURS.
AND THE LAST METHOD, METHOD C AS FOCUSES ON USING A QSE CAPACITY SHORT ALLOCATION APPROACH TO ALLOCATE THOSE COSTS.
SO IN THAT METHOD, THE COSTS ARE FIRST CHARGED TO CAPACITY SHORT QCS, AND THEN ANY RESI, ANY RESIDUAL IS THEN ALLOCATED BY LOAD RATIO SHARE.
SO THOSE ARE THE ALLOCATION METHODS.
NOW, COUPLE OTHER TERMS AS I GET INTO THE DECK AND AS YOU LOOK AT THE SCOPE, PRIMARY EFFECTS.
SO WHAT IS THE PRIMARY COST OF, UH, MY PRIMARY IMPACT OF REALLOCATING THE COSTS WE'VE SEEN HISTORICALLY? SECONDARY EFFECT, ONCE YOU REALLOCATE THE COST, WHAT SHOULD YOU THINK AS FAR AS, UH, UM, MARKET PARTICIPANT BEHAVIOR CHANGES? HOW COULD THOSE COSTS IMPACT CREDIT AND SETTLEMENTS? UM, AND EVENTUALLY WHAT, WHAT, HOW WOULD THEY IMPACT YOUR CONSUMER COST, UM, AS A WHOLE? SO, PRODUCTION SCOPE FOR THE WORK WE ARE DOING ALL FOR ANCILLARY SERVICES, NOT DRRS, BECAUSE RIGHT NOW WE ARE, IT IS STANDARD DEVELOPMENT.
AND ALL OF THE RELIABILITY SERVICES, UH, THE HISTORY THAT WE ARE LOOKING AT WAS ALSO OUTLINED IN THE SCOPE.
SO 2024 AND 2025 DATA IS WHAT WE WILL BE LOOKING TO USE FROM HERE.
I'LL SWITCH TO SHARING SOME MORE DETAILS.
FIRST, I'LL FOCUS ON METHOD A AND METHOD B, THEN I'LL REQUEST MAGGIE'S HELP FOR METHOD C.
SO IN METHOD A AND METHOD B, LIKE I MENTIONED, THE PRIMARY, UH, UH, APPROACH IS TO ALLOCATE COST BASED OFF OF OPERATIONAL RISK FOR WHICH THOSE SERVICES ARE PROCURED AS A REMINDER REGULATION.
AS WE, THE QUANTITIES FOR REGULATIONS ARE BASED OFF OF ERROR IN OUR FORECAST.
THE FIVE MINUTE FORECAST THAT WE HAVE.
UH, SO THIS IS REALLY THE ALLOCATION CATEGORIES END UP BEING LOAD AND NON DISPATCHABLE.
'CAUSE IT'S THE NET LOAD FORECAST ERROR THAT WE ARE WORKING WITH FOR RRS.
THESE, UH, PRODUCT, THIS PRODUCT IS PARTICULARLY PROCURED, UH, TO ENSURE WE HAVE SUFFICIENT FREQUENCY RESPONSE FOR THE LOSS OF OUR LARGEST TWO UNITS.
THIS COST HAS, WE'VE ALLOCATED IT TO DISPATCHABLE RESOURCES BY VIRTUE OF THE LARGEST TWO UNITS.
SPIN, AGAIN, ARE BOTH DRIVEN BY NET LOAD UNCERTAINTY.
ONE IS INTRA NET LOAD UNCERTAINTY.
THE OTHER ONE IS SUSTAINED UNCERTAINTY PLUS FORCED OUTAGES.
SO IN CASE OF ECRS, AGAIN, THE ALLOCATION LOOKS SIMILAR TO REGULATION LOAD AND NON DISPATCHABLE.
IN CASE OF NONS SPEND, BY VIRTUE OF FORCED OUTAGES ALSO BEING PART OF THE QUANTITY DETERMINATION, ALL THREE BUCKETS IS WHAT WE WOULD BE LOOKING TO APPLY THOSE COSTS TO.
AS FAR AS RELIABILITY SERVICES GO IN BOTH METHODS A AND METHOD B, THEY WOULD BE AS I ASSIGN A HUNDRED PERCENT TO LOAD.
NOW WITH THIS, I KNOW THERE ARE QUESTIONS I'LL REQUEST TO HOLD THEM AND I'LL, I'LL TRY TO TAKE THEM, UH, TOWARDS THE END METHOD DAY.
UH, HERE'S, IF WE LOOK AT, UH, THE FOUR FORECAST ERRORS, UH, SOLELY DURING THOSE HIGH RELIABILITY RISK COVERS, WHAT WOULD THE, UH, REALLOCATION OF COSTS LOOK LIKE? NOW FOR THE PURPOSES OF HIGH RELIABILITY RISK HOURS, THERE WAS SOME GUIDANCE IN THE SCOPE ITSELF.
UH, SO THE FIRST SET OF HOURS THAT WE'VE SELECTED WERE BASED OFF OF SEASONAL RAMP HOURS.
AND WE'VE SHOWN THEM HERE, THE SECOND SET OF HOURS WERE TIED TO ANY LOW RESERVE HOURS.
AND THERE WAS A SPECIFIC DEFINITION FOR LOW RESERVES IN THE SCOPE.
AT LEAST IN 20 24, 20 25, NONE OF THE HOURS MET THAT SPECIFIC DEFINITION.
SO REALLY THIS ANALYSIS THAT YOU SEE HERE IS PRIMARILY TIED TO THE SEASONAL RAMP HOURS THAT YOU'RE SEEING IN THIS TABLE.
UM, WE'VE SHARED, UH, IF WE AGGREGATE UP ALL THE COSTS DIRECTIONALLY, WHERE, HOW WOULD THE SPLITS LOOK LIKE FOR ALL FOUR ANCILLARY SERVICES, UH, REGULATION, R-R-S-E-C-R-S AND NONS SPEND.
UH, WE'VE, WE'VE TRIED TO SHARE BOTH PERCENTAGES AND DOLLAR AMOUNTS, SO YOU HAVE THOSE FOR REFERENCE.
I'LL SWITCH TO METHOD B FOR A MINUTE, AND THEN I'LL TALK ABOUT WHAT YOU'RE SEEING BETWEEN THE TWO.
SO REMEMBER, METHOD B USES THE SAME ALLOCATION PRINCIPLE, BUT IT APPLIES ACROSS ALL HOURS.
NOW IF YOU LOOK AT THE PERCENTAGES, UM, DIRECTIONALLY OR, OR QUANTITATIVELY, THE SPLITS DON'T CHANGE BY MUCH BETWEEN THE TWO APPROACHES.
THERE'S A SLIGHT DIFFERENCE IN ECRS AND NONS SPIN, BUT OVERALL, UH, THE, THE SPLITS LOOK VERY SIMILAR.
LET ME TRY TO TAKE SOME OF THOSE AND THEN BRING MAGGIE OVER.
JOHN HUBBARD, JOHN HUBBERT WITH TIC ON, UH, SLIDE FOUR.
THE, UM, WHEN TALKING ABOUT THE RRS ALLOCATION, IT'S, RIGHT NOW IT LOOKS LIKE IT'S ALL ALLOCATED TO DISPATCHABLE, BUT THERE ARE SOME LARGE
[02:55:01]
NON DISPATCHABLE INTERCONNECTS THAT RS ALSO HELPS WITH, ESPECIALLY DURING INTERVALS WHERE THERE IS LOW DISPATCHABLE IN THE SYSTEM.UM, SO I'M CURIOUS WHY IT'S JUST DISPATCHABLE ALLOCATION AND NOT, UM, BROADER.
SO, SO FAR, UH, I I LEAN ON THIS ONE MORE SO TOWARDS THE DIRECT DEFINITION OF HOW RRS QUANTITIES ARE SET.
THOSE ARE SET FOR THE LOSS OF OUR LARGEST TWO UNITS.
YOU ARE RIGHT, UH, ON THE SYSTEM IN REAL TIME.
THOSE LARGEST TWO UNITS CAN CHANGE.
BUT OUR, OUR PRIMARY REQUIREMENTS ARE BASED OFF OF WHAT WE CONSIDER THE TWO UNITS.
UH, AND THAT'S THE, THE UNDERLYING REASON RIGHT NOW, AT LEAST IN OUR MINDS.
I'D SAY THE REAL TIME CHARACTERISTICS MAY MATTER MORE THAN JUST THE DEFINITIONAL PART.
SO ON METHOD A AND B, YOU'RE SHOWING IT'S BOTH DISPATCHABLE, NON DISPATCHABLE AND LOAD ON THE LOAD SIDE.
WILL IT STILL STAY AT THE QSE LEVEL OR ARE WE TALKING ABOUT IT ACTUALLY GOING TO THE SITE OR THE METERS? FROM A SETTLEMENT'S PERSPECTIVE, I WOULD THINK IT WOULD GO DOWN TO THE QSCS.
BILL, ARE BATTERIES IN A DISPATCHABLE CATEGORY? YES.
AND THEN WHEN YOU'RE ALLOCATING TO GENERATION EITHER DISPATCHABLE OR NON DISPATCHABLE, IS IT JUST GENERATION RATIO SHARE, OR HOW ARE YOU ACTUALLY ALLOCATING IT? SO LIKE A LARGE NUKE PLANT WOULD PAY THE MOST.
I DON'T KNOW IF THAT MAKES SENSE.
SO, UH, WHEN WE TALK ABOUT THE SECONDARY EFFECTS, I CAN SHARE WHAT WE ARE LOOKING TO DO.
SO THIS IS MORE OF AGGREGATING UP TO DATA AND SIMPLY ALLOCATING IT, UH, AT SYSTEM LEVEL.
BUT WHEN WE WERE TALKING ABOUT THINKING THROUGH SECONDARY EFFECTS AND HOW WOULD THEY TRICKLE DOWN, SO WE'VE BEEN TALKING EXACTLY ABOUT THAT.
WHAT MAKES MOST SENSE? IS IT A RATIO OF THE GENERATOR, THE SIZE OF THE GENERATOR OR NOT? SO FAR WE HAVE BEEN CONTEMPLATING MORE TOWARDS WHAT'S THE REAL TIME HSL, UM, OKAY.
UH, COMPLETELY AGREE WITH JOHNS HUBBARD.
AGAIN, IT'S TWICE WE'RE BROWSED TODAY, MAN.
DON'T ACT LIKE THAT'S SHOCKING.
LIKE THE AMOUNT OF RESPONSIVE THAT YOU GUYS PROCURE, WHICH I AGREE WITH YOUR CRITERIA, IS HEAVILY INFLUENCED BY INERTIA ON THE SYSTEM AT THE TIME.
SO I, THIS, I WOULD CONSIDER THIS INCORRECT.
LIKE YOU NEED TO INCORPORATE THAT THE IMPACTS ON INERTIA AND WHAT, WHEN YOU TRIP UNITS AND YOUR, YOU KNOW, YOUR FREQUENCY DECAY IS ALMOST ENTIRELY DEPENDENT ON INERTIA ON THE SYSTEM AT THE TIME.
THAT IS LIKE, SO I WOULD RECOMMEND YOU FIGURE OUT HOW TO INCORPORATE THAT IN HERE.
CAN YOU TAKE A COUPLE MORE? YES, LET'S DO IT.
OH, DID I GO WRONG ORDER BOB? OH, SORRY.
EITHER WAY, IT DOESN'T MATTER.
AND KIND OF GO TO WHAT BILL'S TALKING A LITTLE BIT.
I'M NOT NECESSARILY AGREEING WITH YOU, BUT THE CONCEPT OF THAT IS IF, IF YOU LOOK AT, AT ALL OF THESE, YOU CAN SAY THAT THE DEFINITION DOESN'T NECESSARILY MAKE SENSE 'CAUSE ECRS AND NON SPIN AND EVERYTHING ELSE ALSO TAKES INTO CONSIDERATION FORCED OUTAGE RATES AND OTHER THINGS LIKE THAT.
SO I, I DON'T AGREE WITH THAT PIECE EITHER.
SO YOU CAN, YOU KNOW, I AGREE WITH YOU DISAGREEING WITH THAT ON YOUR ASPECT THERE YOU'RE TALKING ABOUT, BUT I DISAGREE WITH IT ALL THE WAY UP AND DOWN THE LADDER, THAT, THAT YOU CAN'T NECESSARILY GO BY THAT DEFINITIONAL.
YOU'VE GOT TO LOOK AT OPERATIONAL.
IT'S WHAT I THINK WAS SAID DOWN THERE ON THE END.
SO, UH, THAT'S SOMETHING I THINK YOU NEED TO TAKE INTO CONSIDERATION.
AND IF YOU LOOK AT THAT ORDER OF PREFERENCE HERE AND THE WAY YOU DO THIS MM-HMM
ECRS ACTUALLY YOU USE TO BACKFILL RRS IN THE END ANYWAY WHENEVER IT GOES.
SO, SO I DON'T KNOW IF YOU'RE LOOKING AT THOSE ASPECTS WHERE THESE ALL MIX IN TOGETHER ANYWAY, SO, SO SOMETHING TO KEEP IN MIND IS THE WAY THE LANGUAGE IN THE SCOPE IS WRITTEN, IT DOES BOX US IN TO DOING CERTAIN ALLOCATIONS OF THE WAY WE HAVE IN METHOD A AND METHOD B.
'CAUSE IT DOES TALK ABOUT BASING IT OFF OF THE, THE RISKS FOR WHICH WE PROCURE THESE SERVICES.
SO I NATURALLY DO HAVE TO TIE IT BACK TO THE ANCILLARY SERVICE METHODOLOGY.
WE WILL TRY TO, AT LEAST IN CASE OF THE FEEDBACK THAT BILL GAVE, I DO WANT TO GO AND SEE IF THERE IS A WAY WE CAN REFLECT THE, THE RELATIONSHIP BETWEEN INERTIA AND THE TWO LARGEST UNIT AND, AND THE IMPACT ON INERTIA BY HAVING THE BUNCH OF NON, NON DISPATCHABLE THAT WE DO.
SO THAT WAS AT LEAST HOW I TOOK AWAY
[03:00:01]
THAT FEEDBACK TO MEAN RIGHT NOW ALL I'M SAYING IS, IS ALONG WITH THAT, WHEN YOU'RE LOOKING AT THE OTHERS MM-HMMYOU NEED TO TAKE IN THE FORCED OUTAGE RATES AND HOW THAT PLAYS INTO THE OTHER ONES ALSO, WHICH YOU DIDN'T MENTION.
SO FORCED OUTAGE IS IN THE NONS SPIN BECAUSE THAT'S EXACTLY WHERE IT GOES.
SO THE, SO THE PERCENTAGE OF THE PRO PROCUREMENT VOLUME THAT IS DRIVEN BY FORCED OUTAGES IS DRIVING THIS 28% NUMBER THAT YOU'RE SEEING ALLOCATED TO DISPATCHABLE RESOURCES.
NED, NED, YOU'RE STILL UP? YEAH.
UH, TIKA, WHEN, WHEN YOU'RE LOOKING AT, WHEN THIS ON A, UH, ARE YOU TRYING TO ESTIMATE ANY SECONDARY EFFECTS ON, SAY, COST TO LOAD OF, UM, SAY DISCOURAGING INVESTMENT IN GENERATION BY ALLOCATING COSTS TO GENERATION? THEN I, I HOLD THAT TILL MAGGIE'S DONE.
I HAVE A SLIDE THAT GOES INTO QUITE A BIT OF DETAIL ON THAT SECONDARY.
I REQUEST MAGGIE TO COME AND MAYBE SPEND SOME TIME TALKING ABOUT THE CAPACITY SHORT APPROACH.
SO METHOD C, WE LOOKED AT ALLOCATING THE ANCILLARY SERVICE AND RELIABILITY SERVICE COSTS USING A CAPACITY SHORT METHOD.
SO WHAT WE DID WAS WE TOOK THE REC CAPACITY, SHORT ADJUSTMENT PERIOD CALCULATIONS THAT WERE IN EFFECT PRE RTC SINCE THIS STUDY WENT FROM 2024 TO 2025.
SO THAT WAS THE DATA WE DID HAVE AVAILABLE AND UH, WE DID MAKE SOME MINOR MODIFICATIONS TO THOSE CALCULATIONS AS WELL.
SO JUST AN OVERVIEW, HOW DOES THE CAPACITY SHORT CALCULATION WORK? SO FIRST WE WILL CALCULATE A QS E'S CAPACITY SHORTFALL ON A 15 MINUTE INTERVAL BASIS USING THEIR REALTIME LOAD, UH, COP CAPACITY TRADES AND DC TIES AND DETERMINE WHAT THEIR SHORTFALL IS PER INTERVAL.
AND THEN WE WILL TAKE THOSE, UM, AS COSTS OR OUR OR RELIABILITY SERVICE COSTS AND ALLOCATE THOSE COSTS IN PROPORTION TO, UH, WHAT THEY WERE SHORT PER INTERVAL.
AND IF AFTER WE'VE CALCULATED THOSE CAPACITY SHORT CHARGES, IF THOSE ARE NOT ENOUGH TO COVER THE TOTAL COST OF THE SERVICE, THEN WE WILL UPLIFT THE, REMAIN THE REMAINING AMOUNT TO LOAD RATIO SHARE.
SO THAT'S A OVERVIEW OF HOW THE CALCULATION WORKS.
A COUPLE OF MODIFICATIONS WE MADE TO THE EQUATION.
AND, UM, YOU CAN ACTUALLY SEE THOSE ON SLIDE 13 IN THE APPENDIX AS WELL.
UM, WE, IF YOU'RE LOOKING AT THE EQUATION, THE BILL DETERMINANT, UH, FOR R MAKE COAL AMOUNT, IF YOU WOULD JUST REPLACE THAT AMOUNT WITH THE ANCILLARY SERVICE OR RELI OR RELIABILITY SERVICE THAT YOU'RE LOOKING TO CALCULATE, YOU JUST REPLACE IT IN THE EQUATION THERE.
AND THE SAME FOR THE MEGAWATT QUANTITY, YOU WOULD USE THAT MEGAWATT QUANTITY FOR THE ASSOCIATED SERVICE IN PLACE OF THE RU CAPACITY TOTE FOR IRRS.
UH, THE HSL WE USED, WE USE THAT IN PLACE OF THE HIGH ANCILLARY SERVICE LIMIT FOR THE ADJUSTMENT PERIOD BECAUSE TODAY WE USE THE, UM, HASSELL SNAP AT THIS, AT THE SNAPSHOT.
AND SINCE THIS SERVICE, WHENEVER WE'RE ALLOCATING AS COSTS AND THE OTHER RELIABILITY SERVICE COSTS, WE DIDN'T HAVE THE SNAPSHOT DATA SINCE IT, UH, DOESN'T MAKE SENSE TO HAVE IT.
SO, UH, WE JUST USE THE HSL IN THAT PLACE.
AND FINALLY, SINCE RU COSTS ARE CONSIDERED A RELI A RELIABILITY SERVICE COST, WE JUST PULLED THOSE COSTS STRAIGHT OUT OF OUR SYSTEM WHENEVER WE WERE LOOKING AT THE TOTAL COSTS SINCE, YOU KNOW, THE SYSTEM ALREADY DID THE MATH FOR US AND THAT WAS THE MOST ACCURATE CALCULATION SINCE IT ALLOCATED IT USING THE, UH, PROTOCOLS IN EFFECT AT THAT TIME.
SO THOSE FOR THE RUT COSTS, WE DIDN'T USE ANY OF THE MODIFIED CALCULATIONS.
ERIC JACKSON IS GONNA COME OUT AND CHECK ON HIM ALONG WITH JOSE CARLO THE THIRD, LEMME GET THAT MUTED HAPPENED WITH WARD GOING INTO SECOND.
IT MIGHT BE MORE FUN THAN THIS
UM, SO, SO WHAT WE DID WAS WE TOOK THOSE COSTS AND USED THESE QSE CLASSIFICATION CATEGORIES JUST BECAUSE A LOT OF THE, UM, DATA THAT'S USED IN REC CAPACITY SHORT IS ACTUALLY ON A QUEASY PORTFOLIO BASIS.
SO IT WAS DIFFICULT TO USE THE DISPATCHABLE, NON DISPATCHABLE LOAD CATEGORIES.
SO WE USED GENERATOR RETAILER UTILITY AND POWER MARKETER.
SO A GENERATOR IS A QSE THAT REPRESENTS ONLY GENERATION A RETAIL IS A QSE THAT REPRESENTS ONLY LOAD A UTILITY REPRESENTS BOTH GEN AND LOAD, AND THEN A POWER MARKETER DOES NOT REPRESENT EITHER.
AND THESE ARE THE PRELIMINARY RESULTS FOR ANCILLARY SERVICES.
AND THIS IS, UH, SUMMARIZES BOTH FOR 2024 AND 2025 COSTS.
[03:05:01]
THE ANCILLARY SERVICE COSTS USING THE CAPACITY SHORT METHOD AND LOOKED AT HOW THOSE QUEASY CLASSIFICATIONS WOULD BE, YOU WOULD SEE THAT ON AVERAGE IT WOULD BE ABOUT 6% WOULD GO TO GENERATORS.UM, ABOUT 33% WOULD BE SPLIT BETWEEN POWER MARKETERS AND RETAILERS, AND ABOUT 25 TO 27% WOULD GO TO UTILITIES.
THEN I'LL HAVE ONE MORE SLIDE AND THEN I CAN TAKE SOME QUESTIONS.
AND THIS NEXT SLIDE IS SHOW SHOWS THAT SAME, UM, THOSE SAME RESULTS FOR RELIABILITY SERVICES.
UH, WE HAVE BSS IS BLACKSTAR, ERS IS, UH, EMERGENCY RESERVE SERVICE.
FFSS IS FIRM FUEL SERVICE RMR AND RUCK.
WE DID NOT HAVE ANY VOLTAGE SUPPORT COSTS.
AND, UM, JUST A COUPLE THINGS TO NOTE.
RMR, SINCE WE ONLY HAD COSTS FROM MARCH TO DECEMBER OF 2025, THAT'S WHAT THOSE COSTS ARE BASED ON.
AND IN THE ERS BUCKET, BECAUSE THE ERS COSTS ARE CALCULATED ON A, ON A SEASONAL VALUE, WE DID NOT HAVE DECEMBER, 2025, UH, SEASONAL AMOUNT YET SINCE THAT CONTRACT HAS NOT SETTLED.
AND, UH, FOR THESE COSTS, YOU'RE LOOKING AT ABOUT FOUR TO 6% WILL GO TO GENERATORS.
ABOUT 35 TO 38% WILL GO TO POWER MARKETERS AND RETAILERS, AND THEN ABOUT 22 ISH PERCENT TO UTILITIES.
CAN YOU, YOU SAID YOU DEFINED UTILITY HERE THOUGH, AS SOMEONE WITH LOAD AND GEN? YES.
CAN WE NOT DO THAT
YEAH, WE MAY WANT TO CHANGE THE WORDING ON THAT.
YOU'RE, YOU'RE GONNA GET A BUNCH OF COMMENTS THAT YOU DON'T NEED WITH THE USE OF THE WORD UTILITY.
AND ALSO, UM, CAN WE USE ALL OF THE COLORS INSTEAD OF THREE SHADE OF BLUE
WE CAN, UH, LOOK, NEXT TIME WE PRESENT THIS, WE CAN CHANGE DIFFERENT COLORS TOO, ALL OF THE RAINBOW.
AND DO WE HAVE A SUGGESTION ON WHAT WE WOULD WANNA REPLACE UTILITY WITH OR I'LL JUST CALL IT LOAD AND GEN.
JUST KEEP IT SIMPLE CALL, CALL IT GENERATOR AND RETAILER OR SOMETHING.
LET'S, NED, ARE YOU GOOD? NEVER.
UH, I DO HAVE A, A COUPLE COMMENTS.
UM, FIRST OFF, ON UTILITY, MAYBE YOU CONSIDER, UM, YOU KNOW, BALANCED PORTFOLIO, UH,
UH, THE, UH, AND THEN OTHER COMMENTARY IS, UM, THIS IS THE FIRST TIME I THINK I'VE SEEN RMR AND R REFERRED TO AS A RELIABILITY SERVICE.
AND THAT IT SEEMS CONCEPTUALLY DIS VERY DIFFERENT FROM SAY, BLACKSTAR ERS AND FIRM FUEL, WHERE IT'S A, YOU KNOW, THOSE ARE PROCURED SERVICES THAT ACTUALLY HAVE DEFINED NEEDS, WHEREAS RMR AND RUCK ARE BY DEFINITION OUT OF MARKET ACTION.
SO I CONCEPTUALLY WOULD SUGGEST SEPARATING THOSE OUT AND CALLING THEM SOMETHING DIFFERENT.
I DON'T EVEN KNOW IF IT FITS WITHIN THE SCOPE.
THEN IF, UH, WE'RE TALKING ABOUT THIS, YEAH, THE SCOPE SPECIFICALLY CALLS OUT THE RELIABILITY SERVICES WE NEED TO REVIEW AND THOSE TWO WERE LISTED ON IT AS WELL.
MAGGIE, THIS IS AN INCREDIBLY INTERESTING EXERCISE AND A NICE BRIEF DISTRACTION FROM THE BATCH DISCUSSIONS.
IF YOU'RE DEMAND RESPONSE ONLY T DEMAND RESPONSE, I DON'T KNOW THE ANSWER OFF THE TOP OF MY HEAD, SO I'D HAVE TO GO BACK AND LOOK.
AND THEN THE CRR PEOPLE, ARE THEY IN HERE AT ALL? UH, POWER MARKETERS OR LIKE IF YOU'RE A QSE THAT ONLY HAS CR ONLY SHOP IS IN THE POWER MARKETER.
YEAH, SO IF YOU'RE A, HOW DO YOU MEASURE THEIR ACTIVITY? SO IF YOU'RE A QSE THAT ONLY HAS TRADES, YOU'RE A POWER MARKETER.
BUT IF YOU'RE A CRR ACCOUNT HOLDER, THAT'S NOT PART OF THIS SINCE THE R CAPACITY SHORT DOESN'T HAVE ANY CRR, UM, DATA IN IT.
OKAY, BOB? YEAH, SORRY I'M BACK IN.
YEAH, I'M JUST REAL CURIOUS ON THESE PARTICULAR ONES ON HOW, I MEAN YOU'VE GOT THE PERCENTAGES OUT THERE, BUT I'M REALLY CURIOUS ON HOW YOU BROKE CAME TO THOSE.
THIS IS LIKE ON, ON SAY RMR, HOW YOU CHARGE A GENERATOR FOR RMR. HOW DID THEY CAUSE THAT, YOU KNOW, WHAT IS THE CAUSE FOR THEM TO BE CHARGED FOR THAT? UH, I'M CURIOUS ON HOW YOU GOT TO SOME OF THESE PLACES CHOSE TO RETIRE.
YEAH, SO WE LOOKED OR YEAH, BECAUSE THEY CHOSE TO RETIRE, SO CHARGE
[03:10:01]
'EM MOREYEAH, SO WE LOOKED AT, WE USED THE R CAPACITY SHORT ADJUSTMENT PERIOD EQUATIONS.
SO WE JUST PULLED THE DATA STRAIGHT FROM OUR SYSTEM, CALCULATED WHAT YOUR, WHAT THE QSCS SHORTFALL WOULD BE AT EVERY SETTLEMENT INTERVAL, ALLOCATED THOSE COSTS.
AND THEN WE PULLED THE REGISTRATION DATA TO DETERMINE WHAT CLASSIFICATION THE QSE WOULD BE AND THEN ALLOCATED THOSE COSTS INTO THESE DIFFERENT BUCKETS.
SO IT WAS BASED ON THE DATA, UM, IN THE SYSTEM FOR THE DIFFERENT, YOU KNOW, TRADES GENERATION LOAD, DIFFERENT THINGS LIKE THAT.
BUT YOU DID MENTION IT WAS COST CAUSATION.
IS THAT, IS THAT FITTING IN HERE OR ARE YOU JUST DOING THIS A DIFFERENT WAY? DID I MISS SOMETHING? WELL, WE, SO THE SCOPE OF WORK FOR METHODS D WAS TO LOOK AT IT BASED ON A CAPACITY SHORT APPROACH.
I MEAN, WHETHER OR NOT WE WANT TO ADOPT THIS BECAUSE IT'S, YOU KNOW, MAYBE THE CERTAIN, UH, RELIABILITY SERVICE IS NOT RELATED TO, YOU KNOW, HAVE ANY INBOUND BALANCE PORTFOLIO.
BUT THAT WOULD BE, I GUESS, A DISCUSSION AT A LATER TIME.
THIS WAS JUST, UH, HOW WE WERE TOLD AND SUPPOSED TO LOOK AT THE CAPACITY SHORT APPROACH.
OKAY, MR. WHITMEYER, YOU'RE GOOD? OKAY.
IKA, ARE WE, WE CONTINUING YOU'RE BACK TWO SLIDES, I THINK.
THIS ONE'S THE MORE DENSE ONE, THE NEXT ONE SUMMARY.
SO, UH, IT SHOULD GO, THAT ONE SHOULD GO QUICKER.
BUT, UH, NOW THAT YOU'VE HEARD, UH, THE FIRST ASPECT OF THIS WORK, WHICH WAS AROUND GOING BACK AND DOING AN EXERCISE WHERE WE REALLOCATED THE COST BASED OFF OF SOME OF THE METHODS, THE THREE METHODS THAT WERE OUTLINED IN THE SCOPE, THE NEXT PHASE OF THIS ANALYSIS, UH, SWITCHES TO EVALUATING HOW THESE ALTERNATIVE ALLOCATION BEHAVIORS COULD AFFECT MARKET BEHAVIOR.
UH, HOW COULD THE SETTLEMENT TIMING CHANGE, UM, IMPACT SETTLEMENTS, CREDIT EXPOSURE, AND, UH, AND OF, AND OF COURSE DIG TO THAT ULTIMATE QUESTION OF, UH, CONSUMER COSTS AND WILL THERE BE A DIFFERENCE OR A CHANGE OR A REDUCTION, UH, IN THAT? SO IN, AS A PART OF THE SECONDARY EFFECTS, UM, THERE ARE REALLY THREE DIFFERENT BUCKETS THAT HAVE BEEN OUTLINED FOR THE MARKET PARTICIPANT BEHAVIOR BUCKET, WHERE WE ARE LOOKING TO SEE HOW THESE COULD CHANGE OPERATIONAL TRADING, MAINTENANCE OR INVESTMENT DECISIONS.
WE HAVE, UH, INVOLVED A CONSULTANT, UH, TO HELP US IN THINKING THROUGH THOSE OUTCOMES.
UH, ON THE RIGHT SIDE IN THE BLUE BOX, YOU I'VE, I'VE STARTED, I'VE, I'VE LISTED OUT AT LEAST THE ANGLE THROUGH WHICH THE CONSULTANT IS LOOKING TO HELP US IN THINKING THROUGH, UH, HOW COULD THE MARKET PARTICIPANT BEHAVIOR CHANGE? AND THERE ARE A VARIETY OF, UH, UH, AREAS THAT THEY'RE LOOKING TO, UH, GET INTO SO THAT THEY CAN THINK THROUGH THIS IMPACT ALL THE WAY FROM, UH, MODELING THE COST SIGNALS.
UM, THINKING ABOUT HOW THOSE RISK DRIVERS THAT WE'VE ALLOCATED THESE ANCILLARY SERVICES TO COULD MODIFY BEHAVIOR.
UH, HOW COULD, UH, UH, WHAT PRACTICAL ACTIONS COULD MARKET PARTICIPANTS TAKE? WHAT IS THE COST, UH, OF TAKING THOSE ACTIONS? AND THEN WHAT COULD THE PRACTICAL OUTCOMES BE OR WHAT COULD THE POTENTIAL OUTCOME BE? THEY WILL LOOK TO SEPARATE NEAR TERM IMPACTS AND LONG-TERM IMPACTS, UM, AS A PART OF THEIR WORK.
UH, WE ARE DEEP IN THE MIDDLE OF THIS PARTICULAR ANALYSIS RIGHT NOW, SO I DON'T HAVE ANY MORE, UH, ANY INSIGHTS TO SHARE FROM IT.
BUT I LOOK TO, I HOPE TO BRING THOSE BACK WHEN I COME AGAIN IN JULY.
UH, WE LOOK TO BRING AS MUCH DIRECTIVE AND QUALITATIVE INFORMATION AS WE CAN.
I AGAIN, SEE A SET OF QUESTIONS.
LET ME GET THROUGH THE LAST SLIDE, SET IT UP, AND THEN MAYBE WE CAN COVER THOSE.
SO THE, UH, THE SUMMARY, UH, IS THINGS, UH, THAT THIS IS THE WORK WE ARE DOING IN RESPONSE TO, UH, UH,
WE ARE HERE TO SEEK FEEDBACK, UH, FROM TAC BASED OFF OF, UH, UH, AT LEAST THE SCOPE OF THE ANALYSIS WE ARE DOING, THE ASSUMPTIONS WE PUT IN.
I APPRECIATE WHAT WE'VE HEARD SO FAR.
IF THERE ARE ANY MORE, PLEASE FEEL TO SEND THEM.
YOU CAN SEND THEM DIRECTLY TO ME, UH, MAY 29TH BY MAY 29TH.
SO BY END OF THIS MONTH, WE WILL CONTINUE TO DO QUALITY REVIEW ON OUR ANALYSIS, UH, THE CHANGES THAT WE THINK WE CAN MAKE WITHIN THE SCOPE.
UH, WE WILL ADD ABSOLUTELY LOOK TO WORK, UH, THROUGH THOSE BASED OFF OF YOUR FEEDBACK.
UH, WE'LL CONTINUE TO WORK ON THE SECONDARY EFFECTS AND WE HOPE TO BE BACK WITH OUR, UH, FINDINGS AND UPDATES TO THIS WORK, UH, ON JULY 29TH.
UH, I SEE THERE ARE QUESTIONS.
[03:15:01]
THINGS.FIRST, WHO, WHO IS THE CONSULTANT? I DON'T KNOW THINK I'VE HEARD THE NAME OF WHO THAT CONSULTANT IS.
HAS IT BEEN NAMED? AM I HAVE TO SHARE? IS IT SECRET OR, I THINK I GOT A THUMBS UP.
'CAUSE THIS IS GONNA BE REALLY, REALLY IMPORTANT.
'CAUSE THIS IS WHERE THE RUBBER MEETS THE ROAD.
WHEN YOU GET TO DOWN TO IT ALL IS, IS ADDING IN ALL THE RISK FACTORS AND EVERYTHING ELSE AND CHANGING THE WAY WE ACTUALLY DO IT.
'CAUSE WHEN YOU THINK ABOUT IT, THE REASON WE HAVE EVERYTHING AND HAVE THE ANCILLARY SERVICE AND EVERYTHING ELSE IS ULTIMATELY TO SERVE LOAD.
AND IN THE END, THAT'S ULTIMATELY WHO PAYS FOR IT.
IT'S A MATTER OF HOW IT GETS THERE AND WHAT RISKS AND EVERYTHING ELSE GETS THROWN ON IT.
SO I THINK THIS IS GONNA BE A REALLY IMPORTANT AND KEY PIECE OF THIS, THE SIGNING FACTOR IN MY MIND.
GARRETT, I'VE BEEN THINKING ON IT AND IT MAY BE WHEN YOU COME BACK.
BUT AS, AS I'VE LOOKED AT THIS ON METHOD B, I, I DON'T THINK I'M SMART ENOUGH TO BE ABLE TO COMPREHEND WHAT THE DAILY ALLOCATION REALLY DOES.
I ALSO DON'T KNOW THAT I CAN ANSWER IT, BUT I CAN DEFINITELY LOOK TO GET BACK TO YOU.
ANY QUESTIONS OR COMMENTS? ONE MORE SLIDE.
SO FEEDBACK BY THE 29TH, AND THEN YOU'LL COME BACK IN JULY, UNLESS I HAVE A SURPRISE UP MY SLEEVE AS WELL.
UM, YOU KNOW, JUNE IS THE MONTH THAT HAPPENS AND THEN WE WILL, SO FEEDBACK TO YOU.
AND THEN JULY IS REALLY, YOU ONLY HAVE A COUPLE DAYS BEFORE THE REPORT TO AUGUST, SO THAT'S MORE OF AN UPDATE.
WE WILL HAVE A MONTH, END OF AUGUST IS WHEN THE, OH, END OF AUGUST.
I HAVE A PLAN FOR AFTER LUNCH.
DO YOU WANNA HEAR MY PLAN OR DO YOU WANT ME TO SURPRISE YOU? UM, SO WE'LL, WE'LL TAKE LUNCH AND THEN WE'LL START OUR DISCUSSION ON FIGURE 1 45 AFTER LUNCH.
WE'LL, YOU KNOW, OPEN THE FLOOR OR WHATEVER.
AND AS ALWAYS, PEOPLE CAN MAKE MOTIONS WHENEVER THEY WANT ABOUT WHATEVER THEY WANT.
BUT I WOULD, YOU KNOW, REQUEST THAT WE LET PEOPLE GET THROUGH COMMENTS JUST SO EVERYBODY CAN BE HEARD BEFORE WE VOTE.
BUT, YOU KNOW, CALL THE QUESTION AS A MOTION PEOPLE CAN MAKE.
UM, I'LL, I'LL SAY THE ORDER AND THEN I'LL SAY IT AGAIN AFTER LUNCH.
I SORT OF GROUPED COMMENTS TOGETHER, SO IT'S NOT A CHRONOLOGICAL, BUT WE WOULD FIRST HAVE ERCOT PRESENT ON ERCOT COMMENTS.
SO WE HAD ERCOT MAY 15, 15TH ERCOT MAY 18TH, WHICH MADE JUST A ONE CORRECTION AND THEN, OR, OR ERCOT MAY 19TH THIS MORNING, I THINK WHEN CORY WOKE UP AT FIVE IN THE MORNING.
AND THEN, UM, THE ERCOT MAY 18TH REVISED IMPACT ANALYSIS.
AND THEN THE COMMENTS, FOR THE MOST PART, I THINK PEOPLE WERE REALLY COOPERATIVE IN, IN NARROWING THEIR ASKS.
SO I THINK EACH COMMENTER CAN, CAN GET THROUGH THEIR COMMENTS IN FIVE MINUTES OR LESS, MAYBE THREE MINUTES OR LESS.
UM, THE SECOND GROUP I HAD AFTER ERCOT WAS THE ISSUE OF THE STUDY SUBMISSION DATES AND THEN ROLLING INTO THE INCLUSION OF THE RPG PROJECT.
SO THE PEOPLE I HAVE IN THAT GROUP ARE RELIANT WISE, ENERGY, CHOA, TIBA, AND SAILFISH.
AND THEN GROUP THREE I HAVE GOING INTO THE NET METERING ISSUE.
SO I HAVE VISTA DATA CENTER COALITION, BKV, AND THEN THE, UM, AT THE END OF THAT GROUP, I WOULD TAKE THE OLLI COMMENTS THAT HAVE SORT OF A, A BUNCH OF COMMENTS IN THEM.
GROUP FOUR, I WOULD GO INTO MORE OF THE PCLR ISSUES.
SO WE WOULD DO THE EGEN AND LUMINARY COMMENTS.
GROUP FIVE GOING INTO THE W PUN.
UM, THAT'S SORT OF A NARROW ISSUE.
AND THEN GROUP SIX, UM, FOLKS TALKING ABOUT THE, THE CRITERIA.
SO THE FEES, THE DEVELOPMENT REQUIREMENTS, THINGS LIKE THAT.
IS CHAD SEALEY BUYING HIS DINNER? CHAD SEALEY? YES.
WHAT, UM, JUST SO I CAN PREPARE MY SPEECH, HOW MANY, HOW LONG DO I HAVE EACH, EACH COMMENT SUBMITTER
[03:20:01]
GETS? WE CAN SAY IN FIVE MINUTES.'CAUSE THEN I FEEL LIKE THE PEOPLE THINK THEY NEED TO TAKE THAT LONG.
YOU KNOW, I LESS IS MORE FIVE MAX.
I CAN DO THREE FIVE, BUT ESPECIALLY I TRIED TO SORT OF DO THE ORDER AS PEOPLE PLAYED COMMENTS AFTER, OR YOU KNOW, WHO, WHO'S BEEN THE MOST SIGNIFICANT SPEAKER.
SO YOU'RE THE FIRST IN YOUR GROUP, SO YOU CAN TAKE A LITTLE BIT LONGER, BUT IF PEOPLE HAVE ALREADY MADE YOUR POINT, YOU DON'T HAVE TO MAKE IT AGAIN.
BUT YEAH, FIVE, I THINK THE PLAN, BY THE WAY, I DON'T THINK YOU NEED MORE THAN FIVE, RIGHT? NED? CAN YOU HANDLE IT IN FIVE OR LESS? I WILL ENDEAVOR TO MEET THE CHAIR'S REQUEST.
NED, YOU DO NOT MAKE BEDS ON NED, BUT UNLESS YOU OPEN, IT HAS TO BE A LIKE, FREE AND FAIR MARKET.
SO WE WILL BREAK UNTIL WHAT? 1, 1 45? SAY ONE 40, AND THEN WE'LL ACTUALLY BE BACK AT 1 45.
LET'S SAY ONE 40 WITH THE HOPES THAT WE'RE ACTUALLY STARTING BY 1 45 OF
[03:56:14]
OKAY,[03:56:15]
LET'S[03:56:15]
GO[03:56:15]
AHEAD[03:56:16]
AND[03:56:16]
GET[03:56:16]
STARTED.UM, ALL RIGHT, I'LL DO MY SPIEL AGAIN.
[11. Batch Study Items (Waive Notice – Possible Vote)]
OPEN CONVERSATION ON, UH, PIGGER 1 45.AS WITH ANY OTHER VOTING ITEM, UM, A SEATED MEMBER CAN MAKE A MOTION WHENEVER THEY WANT.
ONCE A MOTION IS MADE, WE WILL CHECK FOR A SECOND AND THEN WE'LL CONTINUE WITH THE QUEUE.
MY REQUEST, IT'S A REQUEST, IS THAT WE ALLOW PARTIES WHO FILED COMMENTS TO GET THROUGH COMMENTS BEFORE WE ACTUALLY TAKE THE VOTE.
BUT AGAIN, YOU KNOW, IF YOU'RE A SEATED MEMBER, YOU CAN MAKE A MOTION WHENEVER YOU WANT, INCLUDING A MOTION TO CALL THE QUESTION.
UM, BUT I'D LIKE TO GET THROUGH COMMENTS BECAUSE WE HAD A LOT OF INTERESTED PARTIES WHO FILED COMMENTS ON THIS, AND, YOU KNOW, WE'D LIKE THEM ALL TO GET CLOSURE.
AGAIN, I'D LIKE TO TAKE COMMENTS UP BY TOPIC INSTEAD OF PURELY SEQUENTIALLY.
I CAN REPEAT THAT ORDER AGAIN FOR YOU.
UM, GROUP ONE WILL BE THE GROUP OF ONE ERCOT.
THEY HAVE MAY 15TH COMMENTS, MAY 19TH COMMENTS, AND, UH, MAY 18TH REVISED IMPACT ANALYSIS.
I BELIEVE THEY ALSO HAVE A PRESENTATION, SHORT PRESENTATION.
THEN WE'LL, WE'LL GO TO GROUP TWO, WHICH IS REALLY TWO ISSUES.
THE STUDY SUBMISSION DATE AND THE INCLUSION OF RPG PROJECTS.
THAT GROUP IS RELIANT WISE ENERGY, CHOA, TBA, AND THEN SAILFISH GROUP THREE, WE'LL DO NET METERING.
THAT GROUP IS RA DATA CENTER COALITION.
AND THEN WE'LL TAKE THE ELI COMMENTS UP AT THE END OF THAT.
THEY'RE SORT OF COMPREHENSIVE GROUP FOUR.
THE, UM, PCLR ISSUE WILL DO AG AGENTIC AND LUMINARY GROUP FIVE.
THE WL PEN ISSUE WILL DO CYPRESS CREEK.
AND THEN GROUP SIX, THE COMMENTS ON CRITERIA.
AND WE'LL TRY TO FIVE MINUTES OR LESS.
UM, BUT ERCOT, YOU CAN TAKE LONGER THAN FIVE MINUTES.
JEFF, JEFF LOOKED LIKE EXCITED BY, BY A LIMIT.
BUT JEFF, PLEASE TAKE AS LONG AS YOU NEED.
UM, AND WE WILL SEE WHERE WE ARE.
UM, IT, IT, I WILL, UH, START OFF, AND AGAIN, THIS IS A, UH, SHORT PRESENTATION, BUT I'M HAPPY TO ANSWER ANY QUESTIONS THAT WE HAVE, UH, OR FOLKS HAVE.
UM, GO, I'LL GO THROUGH THE PRESENTATION AND THEN I'LL GO THROUGH THE, UH, COMMENTS THAT WE FILED, UM, UH, BOTH THE MAY 15TH AND THE COMMENTS WE FILED LAST NIGHT.
UH, JUST WANNA START OFF WITH A QUICK REMINDER OF WHERE WE HAVE BEEN, UH, WHERE WE STARTED THIS PROCESS.
REALLY, IT STARTED WITH, UH, PABLO'S PRESENTATION TO THE COMMISSION IN DECEMBER.
UH, AND, UH, STARTING IN FEBRUARY, WE HAD A SERIES OF WORKSHOPS.
UH, WE'VE HAD SPECIAL PRS MEETING SPECIAL, UM, ROS MEETING SPECIAL T.
AND, UH, I'LL SAY I, I REALLY APPRECIATE, UH, THE, UH, COMMENTS AND THE FEEDBACK THAT WE'VE
[04:00:01]
GOTTEN FROM STAKEHOLDERS, THE WORK THAT STAKEHOLDERS HAVE PUT INTO THIS.UH, I ALSO APPRECIATE THAT WE HAVE DROP COMMENTS, UH, MULTIPLE TIMES ON FRIDAYS AND SATURDAYS, AND YOUR COMPANIES ASK YOU TO REVIEW THOSE OVER THE WEEKEND.
AND I, I KNOW THAT, THAT, YOU KNOW, I, I KNOW WHAT THAT MEANS FOR Y'ALL.
AND, AND SO, SO I JUST START OFF BY SAYING, UH, I, I APPRECIATE ALL THAT AND APPRECIATE THE FEEDBACK.
AND I, I ALSO, UM, YOU KNOW, YOU MAY HEAR ME PUSH BACK AT TIMES TODAY ON SOME STAKEHOLDER FEEDBACK.
AND, AND I ALSO UNDERSTAND THAT, YOU KNOW, WE, WE HAVE OVER 400 GIGAWATTS OF LARGE LOADS THAT HAVE REQUESTED INTERCONNECT.
AND, UH, PROBABLY, UH, THE MAJORITY OF THAT, UH, MORE THAN HALF OF THOSE ARE NOT GOING TO BE INCLUDED IN THE BATCH ZERO STUDY.
AND, AND ALSO UN UNDERSTAND THAT, YOU KNOW, EVERYBODY WANTS THEIR PROJECT IN, AND, YOU KNOW, WE WE'RE NOT GOING TO ACCOMMODATE THAT, UH, JUST BECAUSE WE CAN'T.
BUT, YOU KNOW, I, I APPRECIATE WHERE STAKEHOLDERS ARE COMING FROM WHEN THEY'RE SUBMITTING THEIR COMMENTS AND THEY'RE ADVOCATING FOR THEIR PROJECTS AND THEIR POSITIONS.
SO, UM, MENTIONED, WE FILED COMMENTS ON, UH, MAY 15TH.
UM, I'LL, I'LL WALK THROUGH THOSE IN A MINUTE.
WE ALSO UPDATED THE IMPACT ANALYSIS, UM, ON MAY 18TH.
AND THEN LAST NIGHT WE FILED SOME, UH, ADDITIONAL, UH, JUST SOME MINOR CLARIFICATION, UH, COMMENTS.
UM, AND JUST AT A HIGH LEVEL, THE COMMENTS THAT WE, UH, FILED BOTH ON THE 15TH AND, UH, LAST NIGHT, NOT REALLY ANY MAJOR CHANGES, UH, THAT WE'VE INCORPORATED SINCE THE LAST SET OF COMMENTS THAT WE FOUND.
UM, BUT AGAIN, I'LL, I'LL WALK THROUGH KIND OF WHAT THE COMMENTS WERE AND, AND, AND WHY WE FILED THEM.
UH, I DID WANT TO TAKE JUST A, A BRIEF MINUTE TO GIVE SOME BACKGROUND ON SOME OF THE, UM, DISCUSSIONS THAT WE HAD AT LAST WEEK'S, UH, TECH MEETING AND KIND WHY
UH, SO ON, ON THE LEFT, WE PUT TOGETHER, UH, THIS IS THE LOAD THAT IS INCLUDED IN, UM, UH, OR ELIGIBLE TO BE INCLUDED IN, IN BATCH ZERO AS IT IS.
SO WE HAVE OUR, OUR BASE FORECAST, WHICH IS JUST THE, WHAT, WHAT'S EXISTING ON THE GRID, PLUS THE NORMAL ECONOMETRIC, UH, FORECAST WITH ELECTRIC VEHICLE GROWTH WITH ROOFTOP SOLAR AND ALL THAT.
UM, WE'VE HAD A NUMBER OF QUESTIONS THAT PREVIOUS WORKSHOPS AROUND THE QUOTE UNQUOTE MEDIUM LOADS, THE 25 TO 74.9 MEGAWATT LOADS.
UM, THE TSPS, UH, GIVE US, UM, I'M NOT SURE IF IT'S AN ATTESTATION, IS, I DON'T THINK THAT'S THE RIGHT WORD, BUT THE TSPS TELL US WHAT ADDITIONAL, UM, OF THOSE MEDIUM LOADS NEED TO BE INCLUDED.
THERE'S, UH, ABOUT 14 GIGAWATTS OF THE MEDIUM LOADS THAT, THAT, UM, WILL BE ADDED.
THIS IS A 2032 LOAD, BY THE WAY.
UM, AND THEN RIGHT NOW, UH, AS DRAFTED IN PAYER 1 45, UH, THERE IS ANOTHER 79 GIGAWATTS OF LOAD THAT IS ELIGIBLE TO BE EITHER BASE LOAD OR STUDY LOAD BASED ON THEIR STUDY.
THE STUDY VALIDITY CHECK, WHICH WE'LL WE'LL TALK ABOUT IN A MINUTE.
UM, AND THEN THERE'S THE PERMIAN BASIN LOAD, WHICH IS, UM, UH, PER THE LOAD THAT WAS IN THE PERMIT BASIN AND RELIABILITY PLAN, THAT'S ANOTHER 13 GIGAWATTS.
SOME OF THAT MAY ALSO BE IN THE 79 GIGAWATT.
UM, AND THEN THERE'S ADDITIONAL RPG LOAD, UH, THAT AL ALSO COULD ALSO BE IN PART OF THAT 79, SO THERE COULD BE SOME OVERLAP THERE.
UM, AND THEN THE, UM, I REFERRED TO IT AS THE AP COMMENTS, WHICH IS, UM, UH, I DON'T REMEMBER THE EXACT DATES THAT THEY HAD IN THERE, BUT ESSENTIALLY LOADS THAT WERE, UH, SUBMITTED, UH, AS PART OF AN RPG STUDY AFTER THE, THE, UH, DECEMBER 15TH CUTOFF, THAT THAT WOULD ADD ANOTHER, UH, ABOUT 35 GIGAWATTS.
UH, AND THAT LOAD IS NOT, UH, DOUBLE COUNTED TO THE QUESTION LAST WEEK IN THE 79, UM, BUT COULD BE DOUBLE COUNTED IN THE 38.
UM, SO THAT'S KINDA ON THE LOAD SIDE.
AND THEN ON THE GENERATION SIDE, I, I THINK IDEALLY WE WOULD LIKE TO RUN A TRANSMISSION PLAN BASED ON JUST THOSE FIRST TWO CATEGORIES, THE, WHAT'S OPERATIONAL GENERATION, AS WELL AS WHAT HAS MET 6.9 PARAGRAPH ONE, SO TRADITIONALLY AND TRANSMISSION PLANNING, THAT THAT'S WHAT WE WOULD LIKE TO DO.
UH, BUT AS WE ADD MORE LOADS ONTO THE SYSTEM, WE KNOW THAT THERE WILL BE ADDITIONAL GENERATION THAT WILL BE, UH, ADDED TO THE SYSTEM.
UM, AND, AND SO THE FIGURE 1 27 LAID OUT A SERIES OF STEPS WHERE WE COULD ADD ADDITIONAL GENERATION INTO LOAD OR INTO THE BASE CASES.
AND, AND SO YOU CAN KIND OF SEE HOW THAT STACKS UP, UM, FOR THAT, UH, AS YOU GO FURTHER UP, IT'S LESS AND
[04:05:01]
LESS CERTAINTY, UH, THEORETICALLY ON THOSE GENERATIONS.SO WE WANTED TO PROVIDE THAT INFORMATION TO ADDRESS SOME OF THOSE COMMENTS AND QUESTIONS.
UM, AND, AND THEN ALSO WANTED TO TALK THROUGH THE, UM, THE STUDY VALIDITY CHECK, UH, AND, AND JUST PUT TOGETHER THIS, UM, THIS SLIDE JUST TO GIVE SOME BACKGROUND, UH, FOR TECH MEMBERS, UH, THAT MAY, MAY OR MAY NOT BE AS FAMILIAR WITH THE PROCESS.
SO, UM, PRIOR TO BIGGER ONE FIFTEEN'S IMPLEMENTATION IN DECEMBER OF LAST YEAR, UH, LARGE LOADS THAT WERE INCLUDED IN AN RPG TRANSMISSION PROJECT REVIEW COULD USE THOSE STUDIES AS THEIR INTERCONNECTION STUDY.
UM, AND IF THEIR IN SERVICE, IF THEIR INTERATION DATES, THEIR INSERVICE STATE WAS MORE THAN TWO YEARS IN THE FUTURE.
UH, THE LARGE LOADS WITH THE INTERIM PROCESS IN 2022, LARGE LOADS THAT WERE REQUIRED, UH, THAT WERE REQUIRED TO FOLLOW IF THEIR IN-SERVICE STATE WAS LESS THAN TWO YEARS, BUT THEY HAD OPTIONALITY TO USE THE LOWEST PROCESS IF IT WAS, UH, MORE THAN TWO YEARS.
AND JUST, YOU KNOW, A SIDE NOTE ON THAT, YOU KNOW, AGAIN, THE RPG PROCESS IS ABOUT TRANSMISSION PROJECT AND GETTING TRANSMISSION PROJECTS APPROVED.
UM, YOU KNOW, THIS IS A, IT'S PROBABLY THE BEST TRANSMISSION PLANNING PROCESS IN THE COUNTRY, IF NOT THE WORLD.
UH, AND, AND IT, SO IT IS A FANTASTIC PROCESS FOR APPROVING TRANSMISSION PROJECTS.
UM, YOU KNOW, IT REALLY, I THINK WAS NOT INTENDED TO BE THE LARGELY LINEAR CONNECTION, UH, PROCESS THAT THAT WASN'T WHAT IT WAS INTENDED TO DO.
BUT, YOU KNOW, WE, WE FOR A TIME USED IT THAT TIME IS NOW PASSED.
UM, UH, SO, UM, RPG PROJECTS THAT WERE SUBMITTED PRIOR TO APRIL 1ST, THIS TIES TO THE 58 4 80